Citation : 2026 Latest Caselaw 204 Cal/2
Judgement Date : 22 January, 2026
2026:CHC-OS:16-DB
IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
(COMMERCIAL DIVISION)
ORIGINAL SIDE
Present:
The Hon'ble Justice Debangsu Basak
And
The Hon'ble Justice Md. Shabbar Rashidi
AD-COM 1 of 2024
With
CS 103 of 1999
M/s A.K. Ghosh & Sons
Vs.
The State of West Bengal
For the appellant : Mr. Pranit Bag, Adv.
Mr. Ashis Kumar Mukherjee, Adv.
Mr. Sourabh Prasad, Adv.
Mr. Akash Munshi, Adv.
For the respondent : Mr. Dhruba Ghosh, Sr. Adv.
Ms. Nilanjana Adhya, Adv.
Mr. Paritosh Sinha, Adv.
Mr. Arindam Mondal, Adv.
Mr. Altamas Alim, Adv.
Ms. Swagata Ghosh, Adv.
Hearing concluded on : 16.12.2025
Judgment on : 22.01.2026
2026:CHC-OS:16-DB
Md. Shabbar Rashidi, J.:-
1. The appeal is directed against the impugned judgment and
decree dated October 10, 2023 corrected by order dated October 12,
2023 passed in C.S. No. 103 of 1999.
2. By the impugned judgment and decree, the original suit being
C.S. No. 103 of 1999 filed at behest of the appellant herein, was
dismissed.
3. Learned advocate for the appellant submitted that the learned
Trial Judge misconstrued the facts as well as legal propositions and
came to an erroneous finding. The learned trial court also failed to
appreciate the evidence adduced leading to dismissal of the suit.
4. Learned advocate for the appellant further submitted that the
learned Trial Judge did not consider that the delay in the completion
of the project awarded to the appellant was attributable to the
respondent as the respondent delayed handing over the drawing
layout of the building. They also did not respond to the
communications made to them and convey their decisions on issues
raised by the appellant in time and delayed the release of payment
towards the running bills raised.
2026:CHC-OS:16-DB
5. Learned advocate for the appellant further submitted that
while dismissing the suit, learned Trial Judge completely overlooked
the fact that the delay in completion of the project was solely due to
the acts and omissions on the part of the respondent, which resulted
in increase in the cost of the project including overhead costs and
labour costs for the additional timeline of 19½ months.
6. Learned advocate for the appellant further submitted that the
learned Trial Judge failed to appreciate that the respondent did not
disclose the Joint Measurement Book despite of notice in this regard
by the appellant. Learned Single Judge ought to have drawn an
adverse inference against the respondent on account of non-disclosure
of Joint Measurement Book as the onus to prove such evidence was on
the respondent/defendant. According to learned advocate for the
appellant, the respondent acted in breach of contract between the two
parties. Since the delay was caused due to breach by the respondent,
the respondent was to bear the overheads and escalated costs of the
project. Learned advocate for the appellant also submitted that the
respondent had accepted the works beyond the contractual terms and
as such, was liable to pay for the same.
7. Learned advocate for the appellant further submitted that the
learned Trial Judge erred in holding that consumption statement was
2026:CHC-OS:16-DB
not provided by the appellant to the respondent. In fact, such
statement was neither demanded by the respondent nor such point
was raised and argued in the suit. Necessary building materials were
supplied to the appellant with considerable delay and extensions were
granted without imposing any conditions upon the appellant.
8. Learned Senior Advocate appeared for the respondent
submitted that the appellant was awarded a work contract in
pursuance of a tender. The appellant delayed the completion of the
work. The work was scheduled to begin from 16th January, 1989 and
was to be concluded by 15th April, 1990. However, owing to alleged
delays, the appellant sought extension of time by letter dated 28th
June, 1990. The contract period was extended up to 30th September
1990. The work was ultimately completed on 29th November 1991,
resulting in a delay of approximately 19 months and 14 days beyond
the stipulated completion period.
9. It was further contended by learned Senior Advocate that
upon completion of the work, the appellant raised bills which were
paid by the respondent. Appellant had accepted full and final payment
without any protest or reservation, and was therefore estopped from
raising any further claim.
2026:CHC-OS:16-DB
10. Learned Senior Advocate also submitted that the delay in the
completion of the project was attributable solely to the laches and
inability of the Appellant. In particular, it was contended that the
Appellant failed to construct the two masonary wells during the dry
season, which rendered the adopted construction method unsuitable
and resulted in avoidable delay. In addition, Learned Senior Advocate
also submitted that the appellant was duly provided with necessary
materials for construction, including 15 metric tonnes of cement. The
appellant never provided a consumption letter regarding timely
consumption of the building materials supplied to the appellant.
11. According to the plaint case, the appellant participated in a
tender process. He submitted the tender in response to an invitation to
tender from the Superintendent Engineer, Project Circle, P.W.(CB)
Directorate, Burdwan for construction of new Primary Healthcare
(P.H.C) with staff quarters including Sanitation & Plumbing works
along with two masonry wells at Udoypur under Rampurhat - I Block,
District Birbhum.
12. The tender submitted by the Appellant was accepted by the
Superintending Engineer by letter dated 20th December 1988. The
tender was quoted at 4.85% above the departmental schedule of rates,
and the total tender value was assessed at ₹22,77,981/-. Pursuant to
2026:CHC-OS:16-DB
such acceptance, a work order dated 30 December 1988 was issued in
favour of the Appellant by the Executive Engineer, Birbhum Division-I,
P.W. (CB) Directorate. A formal agreement was executed by and
between the parties bearing contract number 29/SE, PCE of 1988 -
89/41/Birbhum Division - I of 1988 -89.
13. It was the further case that according to the contract, the
work was scheduled to begin from 16th January, 1989 and was to be
concluded by 15th April, 1990. Owing to alleged delays, the Appellant
sought extension from time to time lastly by letter dated 28th June,
1990. The contract period was extended up to 30th September, 1990.
The work was ultimately completed on 29th November 1991, resulting
in a delay of approximately 19 months and 14 days beyond the
stipulated completion period. Such delay, according to the appellant,
was mainly on account of the following grounds, namely:
i. Delayed handing over of site for the construction work. ii. Delay in finalising and handing over approved designs and drawings, and failure to take timely decisions in respect thereof;
iii. Failure in furnishing of required supply of specified store materials such as cement and steel which was the obligation of the Respondent to supply; iv. Additional expenditure incurred due to delay in and carriage of departmental materials;
2026:CHC-OS:16-DB
v. Delay due to monetary constraint placed on the Appellant because of non-release of funds as per Running Account (RA) bills on time.
14. Upon completion of work, the Respondent had prepared the
final bill, to which the Appellant had raised objections. According to
the appellant, a sum of ₹32,56,903/- was due and payable. The
respondent having failed and denied to pay the legal dues, the
Appellant instituted the suit claiming recovery of the said amount
along with interest at the rate of 22% per annum from January 1,
1992 to February 29, 1996, aggregating to a total claim of
₹83,74,613/-.
15. The Respondent/State contested the suit by filing a written
statement denying all material allegations contained in the plaint. It
was contended that the Appellant had accepted full and final payment
without any protest or reservation, and was therefore estopped from
raising any further claim.
16. It was the case of the respondent that upon completion of the
project, the appellant received full and final payment of their bill raised
towards the project work without any demur and as such, the
appellants were estopped from claiming any amount of alleged unpaid
bills or any damages. Moreover, according to the terms of the tender,
the work was to commence by January 16, 1989 and it was supposed
2026:CHC-OS:16-DB
to be complete by April 15, 1990. The appellant failed to commence the
work in time inspite of all possible cooperation rendered on the part of
the respondent. By reason of delay which was solely attributable to
inaction on the part of the appellant, the appellant sought for
extension of time. The respondent accepted the request for extension of
time and the time of completion of project was extended by the
respondent on condition that such extension would not entitle the
appellant/plaintiff for any compensation on account of delay. The
project work was completed on November 29, 1991 after a delay of 19
months and 14 days.
17. Although, the respondent/defendant suffered loss and
damages due to delay in completion of the project owing to inaction of
the appellant/plaintiff, nevertheless, the respondent made full
payment to the plaintiff/appellant by the 11th and final bill being
Voucher No. 7 dated February 29, 1996 amounting to ₹31,61,721/-.
The full and final payment of all supplementary items of works
approved by the superintending Engineer, Project Construction Circle
was also made to the appellant by Voucher No. 8 dated February 29,
1996. Such payments were made as per the bills duly made out on the
basis of mutually recorded measurements and the payment was made
by the respondent and accepted by the appellant without any
2026:CHC-OS:16-DB
reservation. According to the case made out by the respondent, the
appellant was required to submit a bill every month in terms of Clause
8 of the contract, however, the appellant failed to submit bills month
by month. For such reason, the respondent department prepared the
bills on the basis of recorded measurements and payments were made
to the appellant on the basis of such bills. In such fashion, 11 bills for
the contractual works and one bill for supplementary work, was
approved by the superintending engineer in terms of Clause 12 of the
agreement and was paid to the appellant.
18. On the basis of the pleadings put in by the parties, the learned
Trial Judge framed as many as 8 issues in order to adjudicate the
disputes in the proceeding, namely:
1. Was the execution on completion of the work under the contract between the plaintiff and the defendant delayed due to the fall or default on the part of the defendant or by reason of the latches and inability of the plaintiff?
2. Was there any agreement between the plaintiff and the defendant to pay at different rates for additional items of works done by the plaintiff?
3. Did the defendant make payment for all items under the contract in question including additional items of work not mentioned in the contract?
2026:CHC-OS:16-DB
4. Is the plaintiff entitled to the claims preferred in respect of execution of extra item of works as mentioned in paragraph 11 of the plaint?
5. Did the plaintiff suffer any loss due to default on the part of the defendant for prolongation of work beyond the date for completion of work mentioned in the contract in question?
6. If so is the defendant liable to compensate the plaintiff on account thereof as claimed by the plaintiff?
7. Is the suit barred by limitation?
8. So what relief the plaintiff is entitled?
19. Issue No.7 was decided by the learned Single Judge in favour
of the appellant/plaintiff. No arguments were advanced by the parties
at the time of hearing of the instant appeal in relation to such issue.
On perusal of the materials placed before us, we also find nothing to
differ with the findings of learned Trial Judge. So far as Issue No.1
with regard to delay in completion of project work is concerned, it
transpires that the learned Single Judge came to a conclusion that the
delay in the completion work was not attributable to the respondent.
The learned Judge also held that the deficiencies on the part of the
appellant itself were actually responsible for delayed completion of
project. While deciding the issue, learned Single Judge noted that by a
letter dated January 4, 1989, the appellant informed the assistant
engineer that the plaintiff had received the work order and was in a
2026:CHC-OS:16-DB
position to start work at an early date. On the same day, the assistant
engineer wrote a letter to the plaintiff with a request to start work. The
date of completion of work was fixed on April 15, 1990. Learned Single
Judge also noted that by a letter dated May 4, 1989 the assistant
engineer intimated the appellant that upon inspection of the work on
March 9, 1989, March 20, 1989, April 11, 1989, April 17, 1989, April
21, 1989, April 24, 1989 and May 3, 1989 it was observed that no
work of masonary well was done by the appellant although, site
representative of the plaintiff was requested several times in this
regard. The letter also stated that the appellant had wasted the dry
season which was the best time for digging masonary well. Such
allegation was also not denied on the part of the appellant.
20. Learned Trial Judge also noted in the impugned judgement
that while seeking extension of time by its letter dated June 28, 1990,
it was stated that segment was not available for two months from the
end of March 1990. However, learned Single Judge was of the opinion
that non-availability of cement for a limited period of two months can
be taken as a ground causing delay of the entire project. The learned
Single Judge also took note of an explanation sought to be given on the
part of the appellant that much time was consumed in the
construction of masonary well by sinking method and in doing so
2026:CHC-OS:16-DB
considerable quantity of material had to be carried by head load from
about a distance of half a kilometer as the road became un-motorable
for some months.
21. By a letter dated February 12, 1990, the plaintiff informed the
assistant engineer that the plaintiff had taken up construction of one
Masonary well at the site shown by the assistant engineer. The said
letter was responded by the assistant engineer by a letter dated
February 26, 1990 wherein it was stated that the plaintiff started
construction of the Masonary well on February 20, 1990 only when the
assistant engineer was inspecting the site. The appellant/plaintiff
wanted to know the exact location of the second Masonary well and it
was shown to him on such date. The appellant or his representative
never asked for identification of the location earlier. Learned trial judge
also noted that by its letter dated June 29, 1990, the appellant
informed the executive engineer to the effect that much time was
consumed in constructing Masonary well by the method of sinking.
Building materials had to be taken overhead for 1/2 kilometers as the
road had gone un-motorable.
22. The learned Single Judge also noted in the impugned order
that an instant report was supposed to be submitted by the contractor
if he was not able to execute the work due to unavoidable
2026:CHC-OS:16-DB
circumstances. However, in the case at hand, an extension of time was
sought by the appellant without assigning any specific reason, merely
citing 'reasons beyond control'. A second extension of time was sought
by a letter dated June 28, 1990 on the ground of non-availability of
cement for two months from March 1990. On this score, the learned
Single Judge observed that the project work was hampered for a
limited period of two months for non-availability of cement. It did not
cover the entire project timeline and did not accept the same as a
ground for delay in completion of the project. The learned Single Judge
also noted that by a letter dated April 13, 1990, the assistant engineer
wrote to the appellant that whitewash, paint and other works were yet
to be executed. The letter also stated that the appellant/plaintiff was
not executing the tender project earnestly.
23. The materials on record reveals that the appellant was
requested to start the construction work by a letter from the Assistant
Engineer on the very date when the appellant intimated the
respondent, after acceptance of his tender, that it was ready to
undertake the project. Therefore, the case of the appellant that there
was considerable delay in the delivery of the site, ready for the work
does not stand.
2026:CHC-OS:16-DB
24. The respondent has come up with a case that the appellant
was provided all cooperation and supply of building materials at
relevant time. The appellant has not been able to provide the details of
such delayed supply of building materials. On the contrary, evidence
led at the trial demonstrates that a considerable amount of cement etc.
was lying with the appellant, supplied by the respondent. In fact, the
appellant, in its letter, cited the reason for delayed execution of work
as non-motorable condition of road which obliged the appellant to
carry head loads to the project site for about ½ km. In such letter by
the appellant, there is no whisper of delayed supply of building
materials. Not only that, the appellant was obliged to submit
consumption reports of such articles. Our attention was not drawn to
any evidence which established that such report was submitted by the
appellant at any point of time.
25. According to the terms of the contract, the contractor was
under obligation to instantly intimate respondent of any circumstances
which hindered the execution of the project. However, no such report
appears to have been submitted by the appellant. The appellant
ventilated its inability at the time when it sought for extension of time.
His request for such extension also did not disclose any specific reason
of delay save and except 'reasons beyond control'. The evidence led at
2026:CHC-OS:16-DB
the trial also does not disclose that the appellants ever endeavored to
refute the allegation of the respondent to the effect that the appellant
lost the dry seasons without any reason in digging up the masonary
well. At the time of inspection of the first masonary well, the appellant
allegedly asked the Assistant Engineer for the location of second
masonary well which, of course, was shown to them. However, it
remains a mystery as to how the appellant agreed to execute the work
when the construction site was not known to him and as to what
prevented the appellant from taking instructions beforehand.
26. The evidence on record also shows that after the award of
contract work, the respondent conducted survey of the ongoing project
on several dates i.e. on March 9, 1989, March 20, 1989, April 11,
1989, April 17, 1989, April 21, 1989, April 24, 1989 and May 3, 1989.
By a letter dated May 4, 1989 the assistant engineer intimated the
appellant that upon inspection of the work it was observed that no
work of masonary well was done by the appellant although, site
representative of the plaintiff was requested several times in this
regard. Later, by a letter dated April 13, 1990, the assistant engineer
wrote to the appellant that whitewash, paint and other works were yet
to be executed by the appellant. We have noted hereinbefore that
project was to commence with January 16, 1989 and it was supposed
2026:CHC-OS:16-DB
to be complete by April 15, 1990. Extension of time was sought twice
by the appellant and was granted by the respondent.
27. So far as the case made out by the appellant is concerned,
according to them the delay was caused on account of belated
approval of construction drawings, delay in supply of building
materials, stale decision on the issues raised by the appellant.
However, at the time of hearing, the appellant did not draw our
attention to any specific act or omission on the part of the respondent
which could be accepted as genuine cause of delay. The appellant did
not point out the specific drawing which was provided to the appellant
belatedly. On the contrary, it appeared from evidence that the day
appellant intimated its readiness to execute the job, on the selfsame
day, by a letter from Assistant Engineer; he was requested to execute
the same. We have already noted that cement etc. was duly supplied to
the appellant and in fact, at the time of inspection, it was found that
considerable amount of cement was still lying with the appellant. The
appellant also did not refute the case of the respondent to the effect
that the appellant failed and neglected in submitting the consumption
statement of the building materials as required in compliance to the
terms of the contract.
2026:CHC-OS:16-DB
28. In such inspection, it was duly intimated to the appellant that
the project work was not being carried out with required speed. There
were several works to be accomplished. While asking for extension of
time, the appellant pleaded un-motorable condition of road where
building materials had to be taken as manually. According to the
terms and conditions of the contract, the appellant was supposed to
intimate the authorities about any circumstances hindering the
completion of project but our attention was not drawn to any such
communication on the part of the appellant/plaintiff. In view of the
aforesaid facts and circumstances, we find no reason to differ with the
findings of the learned Single Judge that the appellant was not able to
prove that delay in completion of the project work was attributable to
the respondent.
29. Issue nos. 3 to 6 were taken up and decided together. The
learned Trial Judge considered the evidence adduced on behalf of the
parties and observed that in accordance with the terms and conditions
of the contract more specifically Clause 12, the decision of the
Superintending Engineer of the circle was to be final. The learned
Single Judge also noted that after completion of the work, meetings
were convened. The minutes of the meeting disclosed that the
appellant participated in such meetings with regard to claim for
2026:CHC-OS:16-DB
carriage of departmental materials for distance beyond initial 20 km.
The claim of the appellant was considered and discussed in the first
meeting held on June 27, 1995. It was further discussed in the second
meeting dated July 14, 1995 and a final order was issued on August
28, 1995 by the Superintending Engineer. Learned Trial Court also
observed that the plaint filed on behalf of the appellant did not contain
any statement to the effect that the order dated August 28, 1995 was
not accepted by the appellant or it was passed in violation of any term
of the contract.
30. According to Clause 18 of the contract, the appellant was not
entitled to claim transportation cost of the building materials. It was to
be borne by the appellant himself. By a letter dated December 13,
1991, the appellant intimated the respondent that the work had been
completed and asked for a refund of the security deposit. By another
letter dated January 1, 1992, the appellant claimed reimbursement for
extra expenditure. The appellant also disputed the measurements of
different items of work recorded in the measurement book by a letter
dated March 2, 1992. By another letter dated March 16, 1992, the
appellant withdrawn his protest noted on the final bill prepared on the
basis of measurements dated February 21, 1992. It was observed by
learned Trial Judge that after withdrawing his protest, the appellant
2026:CHC-OS:16-DB
was estopped from raising any dispute in connection with the
measurements.
31. Evidence on record goes to show that final bill was made ready
and it was communicated to the appellant by a letter dated February
7, 1994 by the Executive Engineer. The appellant raises claim by a
letter dated November 22, 1993 addressed to the Chief Engineer which
was relegated to the Executive Engineer in terms of clause 12 of the
contract, with intimation to the appellant. It transpires that in terms of
letter dated June 15, 1998 issue by the Executive Engineer; all the
claims raised by the appellant were paid by voucher No. 8 dated
February 29, 1996, in terms of an order passed by the Superintending
Engineer, Project Construction Circle. The final bill of the appellant
was paid by T. O. Voucher No. Seven dated February 29, 1996. In such
fashion, the claims raised on the part of the appellant were finally
decided by the authorities. Nothing has been placed before us, at the
time of hearing, that the appellant was entitled for any claim other
than that was decided and paid to the appellant after affording due
opportunity to the appellant of hearing, in accordance with the terms
and conditions of the contract between the parties. In such view of the
facts, we are of the opinion that the learned Trial Court was quite
justified in deciding issue Nos. 3 to 6 against the appellant/plaintiff.
2026:CHC-OS:16-DB
32. Since, on the basis of evidence led at the trial, we are of the
opinion that the appellant has not been able to justify that the delay
caused in the completion of the project work was attributable to the
respondent/defendant. We have also come to a conclusion that the
appellant was paid all his bills including the final bill as well as the bill
raised for the additional works upon affording the appellant a
reasonable opportunity of hearing, we find no materials to hold that
the appellant is entitled for any damages.
33. In the light of discussions made hereinbefore, we find no
reason to interfere with the impugned judgment and decree. We affirm
the same.
34. Consequently, the instant appeal being AD-COM 1 of 2024
and CS 103 of 1999 along with all connected applications, if any, are
hereby dismissed however without any order as to costs.
35. Urgent photostat certified copy of this judgment, if applied for,
be supplied to the parties on priority basis upon compliance of all
formalities.
[MD. SHABBAR RASHIDI, J.]
36. I agree.
[DEBANGSU BASAK, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!