Citation : 2026 Latest Caselaw 1366 Cal/2
Judgement Date : 24 February, 2026
ORDER OCD - 22
IN THE HIGH COURT AT CALCUTTA
COMMERCIAL DIVISION
ORIGINAL SIDE
AP-COM/119/2026 M/S.
RAJ CONSTRUCTION AND CO
VS
GARRISON ENGINEER (CENTRAL) AND ANR.
BEFORE:
The Hon'ble JUSTICE SHAMPA SARKAR
Date: 24th February 2026
Appearance:-
Mr. Tanmoy Sett, Advocate
Mr. Pran Gopal Das, Advocate
... for the petitioner.
Mr. Sunil Singhania, Advocate
Ms. Priti Jain, Advocate
... for the respondents.
1. The petitioner is a proprietorship concern. The notice inviting tender was
issued by the respondent no.1 on February 16, 2024. The petitioner
participated and emerged as the successful bidder. The petitioner was
issued a letter of acceptance on March 9, 2024. Formal contract was
executed. The date of handing over the possession of the site was
scheduled on April 8, 2024 and the actual date of completion was
scheduled on January 2, 2025. The GCC (IAFW-2249) along with its
subsequent amendments were made applicable to the subject contract.
The work related to Periodical Services Plastering ATT and Miscellaneous
Works at MAP PH-II under GE(C) Kolkata. According to the petitioner, the
work site was not handed over within the stipulated time. The buildings
were occupied by residents. As such, the maintenance work could not
commence on time. The samples of the materials were sent to the
respondents, but the respondents did not approve the same. The
petitioner commenced work later but contends to have performed some
extra work. However, on account of non-approval of the samples, the
petitioner could not execute the work in the mode and manner provided in
the tender document. Show-cause notice was issued to the petitioner.
The petitioner replied to the show-cause notice. By a notice dated
January 23, 2025, time for completion was extended.
2. Disputes arose between the parties on various issues and the parties had
several meetings to resolve them. According to the petitioner, 12% of the
work had been completed. The work of plastering and macro concrete of
the external side of the Block-1 and Block-2 had been successfully
completed by the petitioner. The external weather coating was completed
in respect of Block-1. Rest of the work could not be completed, inter alia,
on account of non-availability of the site. To the utter shock and surprise
of the petitioner, by a letter dated February 12, 2025, the respondent no.1
cancelled and terminated the agreement with effect from February 14,
2025. The petitioner found that another notice inviting tender was floated
for the subject contract. The petitioner moved an application under
Section 9 of the Arbitration and Conciliation Act, 1996 before the
competent civil court and an injunction was granted, restraining the
respondents from branding the work of the petitioner as 'slow progress' or
that the "petitioner was not entitled to more workload" and/or that the
petitioner be 'removed from the approved list'. The respondent no.1 was
also restrained from preventing the petitioner from taking part in future
tenders.
3. Thus, disputes which arose between the parties.
4. The petitioner has claimed unpaid bills, has challenged the cancellation
and also has claims in damages for the loss of profit, cost of idle labour,
non-refund of performance guarantee and security deposit etc. The
petitioner contends that the claim of the petitioner came to more than
Rs.20 lakh. Reliance has been placed on clause 70 of the GCC which
provides for settlement of disputes by arbitration. It also provides that in
case of cancellation, reference cannot be made till alternative arrangement
has been made by the government. It is contended that, alternative
arrangement has been made by the government and another contractor
has been engaged to complete the work. Notice invoking arbitration was
issued on August 19, 2025. The respondent asked the petitioner to sign
an agreement and waive the applicability of section 12(5) of the Arbitration
and Conciliation Act, 1996. The GCC provides for appointment of an
Arbitrator from amongst serving officers.
5. Mr. Singhania, learned advocate for the respondents, submits that the
claims of the petitioner are not arbitrable. The claims are not admissible.
The petitioner did not execute the work and was very slow in its progress.
Thus, the respondents had invoked their right under the concerned GCC
to terminate the contract. The respondents deny each and every
allegation of the petitioner.
6. Under such circumstances, it appears to this Court that there is a
subsisting dispute.The GCC which contains an arbitration clause which
was made applicable to the concerned tender process and as such the
dispute is referred to arbitration.Unilateral appointment of an Arbitrator
from an employee of the respondents is not legally permissible.
7. This application is allowed by appointing Mr. Debasish Roy, Senior
Advocate [9831173923], as the sole arbitrator, to arbitrate upon the
disputes between the parties. The learned Arbitrator shall comply with the
provisions of Section 12 of the Arbitration and Conciliation Act, 1996. The
learned Arbitrator shall be at liberty to fix his remuneration as per the
schedule of the Arbitration and Conciliation Act, 1996.
8. All questions as to the arbitrability of the issues, admissibility of the
claims, limitation etc, shall be decided by the learned arbitrator, if so
raised.
9. AP-COM 119 of 2026 is disposed of accordingly.
(SHAMPA SARKAR, J.)
S. Kumar
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!