Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Raj Construction And Co vs Garrison Engineer (Central) And Anr
2026 Latest Caselaw 1366 Cal/2

Citation : 2026 Latest Caselaw 1366 Cal/2
Judgement Date : 24 February, 2026

[Cites 4, Cited by 0]

Calcutta High Court

Raj Construction And Co vs Garrison Engineer (Central) And Anr on 24 February, 2026

Author: Shampa Sarkar
Bench: Shampa Sarkar
 ORDER                                                               OCD - 22
                     IN THE HIGH COURT AT CALCUTTA
                          COMMERCIAL DIVISION
                             ORIGINAL SIDE

                         AP-COM/119/2026 M/S.
                       RAJ CONSTRUCTION AND CO
                                 VS
                 GARRISON ENGINEER (CENTRAL) AND ANR.

BEFORE:
The Hon'ble JUSTICE SHAMPA SARKAR
Date: 24th February 2026
                                                                    Appearance:-
                                                      Mr. Tanmoy Sett, Advocate
                                                   Mr. Pran Gopal Das, Advocate
                                                            ... for the petitioner.
                                                   Mr. Sunil Singhania, Advocate
                                                         Ms. Priti Jain, Advocate
                                                          ... for the respondents.

1. The petitioner is a proprietorship concern. The notice inviting tender was

issued by the respondent no.1 on February 16, 2024. The petitioner

participated and emerged as the successful bidder. The petitioner was

issued a letter of acceptance on March 9, 2024. Formal contract was

executed. The date of handing over the possession of the site was

scheduled on April 8, 2024 and the actual date of completion was

scheduled on January 2, 2025. The GCC (IAFW-2249) along with its

subsequent amendments were made applicable to the subject contract.

The work related to Periodical Services Plastering ATT and Miscellaneous

Works at MAP PH-II under GE(C) Kolkata. According to the petitioner, the

work site was not handed over within the stipulated time. The buildings

were occupied by residents. As such, the maintenance work could not

commence on time. The samples of the materials were sent to the

respondents, but the respondents did not approve the same. The

petitioner commenced work later but contends to have performed some

extra work. However, on account of non-approval of the samples, the

petitioner could not execute the work in the mode and manner provided in

the tender document. Show-cause notice was issued to the petitioner.

The petitioner replied to the show-cause notice. By a notice dated

January 23, 2025, time for completion was extended.

2. Disputes arose between the parties on various issues and the parties had

several meetings to resolve them. According to the petitioner, 12% of the

work had been completed. The work of plastering and macro concrete of

the external side of the Block-1 and Block-2 had been successfully

completed by the petitioner. The external weather coating was completed

in respect of Block-1. Rest of the work could not be completed, inter alia,

on account of non-availability of the site. To the utter shock and surprise

of the petitioner, by a letter dated February 12, 2025, the respondent no.1

cancelled and terminated the agreement with effect from February 14,

2025. The petitioner found that another notice inviting tender was floated

for the subject contract. The petitioner moved an application under

Section 9 of the Arbitration and Conciliation Act, 1996 before the

competent civil court and an injunction was granted, restraining the

respondents from branding the work of the petitioner as 'slow progress' or

that the "petitioner was not entitled to more workload" and/or that the

petitioner be 'removed from the approved list'. The respondent no.1 was

also restrained from preventing the petitioner from taking part in future

tenders.

3. Thus, disputes which arose between the parties.

4. The petitioner has claimed unpaid bills, has challenged the cancellation

and also has claims in damages for the loss of profit, cost of idle labour,

non-refund of performance guarantee and security deposit etc. The

petitioner contends that the claim of the petitioner came to more than

Rs.20 lakh. Reliance has been placed on clause 70 of the GCC which

provides for settlement of disputes by arbitration. It also provides that in

case of cancellation, reference cannot be made till alternative arrangement

has been made by the government. It is contended that, alternative

arrangement has been made by the government and another contractor

has been engaged to complete the work. Notice invoking arbitration was

issued on August 19, 2025. The respondent asked the petitioner to sign

an agreement and waive the applicability of section 12(5) of the Arbitration

and Conciliation Act, 1996. The GCC provides for appointment of an

Arbitrator from amongst serving officers.

5. Mr. Singhania, learned advocate for the respondents, submits that the

claims of the petitioner are not arbitrable. The claims are not admissible.

The petitioner did not execute the work and was very slow in its progress.

Thus, the respondents had invoked their right under the concerned GCC

to terminate the contract. The respondents deny each and every

allegation of the petitioner.

6. Under such circumstances, it appears to this Court that there is a

subsisting dispute.The GCC which contains an arbitration clause which

was made applicable to the concerned tender process and as such the

dispute is referred to arbitration.Unilateral appointment of an Arbitrator

from an employee of the respondents is not legally permissible.

7. This application is allowed by appointing Mr. Debasish Roy, Senior

Advocate [9831173923], as the sole arbitrator, to arbitrate upon the

disputes between the parties. The learned Arbitrator shall comply with the

provisions of Section 12 of the Arbitration and Conciliation Act, 1996. The

learned Arbitrator shall be at liberty to fix his remuneration as per the

schedule of the Arbitration and Conciliation Act, 1996.

8. All questions as to the arbitrability of the issues, admissibility of the

claims, limitation etc, shall be decided by the learned arbitrator, if so

raised.

9. AP-COM 119 of 2026 is disposed of accordingly.

(SHAMPA SARKAR, J.)

S. Kumar

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter