Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Oriental Insurance Company Limited vs The Reliance Jute Mills (International ...
2025 Latest Caselaw 1567 Cal/2

Citation : 2025 Latest Caselaw 1567 Cal/2
Judgement Date : 20 May, 2025

Calcutta High Court

The Oriental Insurance Company Limited vs The Reliance Jute Mills (International ... on 20 May, 2025

Author: Aniruddha Roy
Bench: Aniruddha Roy
                      IN THE HIGH COURT AT CALCUTTA
                    ORDINARY ORIGINAL CIVIL JURISDICTION
                           [COMMERCIAL DIVISION]
                               ORIGINAL SIDE
     Present:
     The Hon'ble Justice Aniruddha Roy

                                 AP-COM/186/2024
                             Old Case No. AP/322/2020

                    The Oriental Insurance Company Limited
                                       Vs.
                  The Reliance Jute Mills (International Limited)

     For the petitioner:                  Mr. Chayan Gupta, Adv.
                                          Mr. Sanjay Paul, Adv.
                                          Ms. Jaita Ghosh, Adv.

     For the respondent:                  Mr. Sabyasachi Chaudhury, Sr. Adv.
                                          Mr. Abhijit Guha Ray, Adv.
                                          Mr. S.E. Huda, Adv.
                                          Mr. Shounak Mukhopadhyay, Adv.
                                          Ms. Anwesha Guha, Ray, Adv.

     Reserved on:                         May 01, 2025

     Judgment on:                          May 20, 2025

     ANIRUDDHA ROY, J.:

Facts:

1. This is an assigned arbitration application.

2. This is an application filed under Section 34 of the Arbitration and

Conciliation Act, 1996 (for short, the said 1996 Act), inter alia, praying

for setting aside of an Arbitral Award dated March 2, 2020, at page 430,

Volume-IV of the application, passed by the Arbitral Tribunal.

3. The inescapable and inexorable facts are only stated which are required as a

prelude for the adjudication.

4. The applicant herein was the respondent Insurance Company (for short, the

Insurance Company) in the arbitral reference and the respondent herein

was the claimant (for short the claimant) in the reference.

5. The claimant was an insured with the Insurance Company. There was a

valid and existing insurance policy. On September 2, 2014 fire broke out at

the Jute Mill of the claimant. The policy was lawfully enhanced from Rs.22

crores to 32 crores. On September 3, 2014 the incident of fire was duly

notified to the Insurance Company with the substantial loss of finished

goods suffered by the claimant. One Dilip Kumar Saha was appointed as

preliminary surveyor who inspected the premises on September 4, 2014

and September 6, 2014. The preliminary surveyor also inspected both the

manual and computerised records, namely, the stock register of the

claimant. On September 8, 2014, one Sanjoy Dwivedi was appointed as

final surveyor by the respondent. On September 13, 2014 the preliminary

report was submitted by the preliminary surveyor. The time frame of 30

days under Sub-Regulation 2 to Regulation 9 of IRDA (Protection of

Policy Holders' Interest) Regulation, 2002 had expired on September 7,

2014. On October 17, 2014 the final surveyor caused advertisement to be

published in the newspapers to ascertain the salvage value of the salvages.

November 10, 2014 was fixed as the last date for receiving bids pursuant

to salvage process. Three bids were received. Two of which on November 7,

2014, and one was on November 10, 2014. On November 24, 2014

claimant wrote a letter to the Insurance Company claiming a part payment

for a sum of Rs. 10 Crores to enable it to carry on business. On December

3, 2014, the final surveyor sent an E-mail to the Insurance Company

informing of opening of bids received as part of salvage process and

requesting deputation of a responsible officer of the Insurance Company to

be present for the same day. However, none was present on behalf of the

Insurance Company. On December 5, 2014, a meeting was held when the

offers for salvage were opened and the highest bid received was for Rs.

1250/- per metric ton. The final surveyor persuaded the claimant to accept

salvage value at Rs. 1750/- per metric ton. On January 22, 2015

claimant wrote a letter to the Insurance Company requesting for part

payment as sought for in its said previous letter. On March 7, 2015, the

final surveyor sent an E-mail to the claimant urging to accept Rs. 12 crores

40 lakhs as full and final settlement and sent consent letter of the claimant

and the scanned copy was sent through E-mail. Claimant wrote on the said

consent letter subject to terms and condition contained in the Insurance

Policy. On the same day i.e. March 7, 2015, the six months period since

appointment of the surveyor had expired.

6. On March 21, 2015 the final surveyor submitted its survey report and the

report was submitted after expiry of six months period. On March 23, 2015,

claimant wrote a letter to the Insurance Company intimating that till then

the claim was not processed neither any payment was made nor any reply

was received by the claimant from the Insurance Company. The claimant

further raised its demand for payment with an interest. On April 19, 2015,

thirty days stipulated period to offer settlement of claim expired. On June

11, 2015 the claim was filed with the survey report prepared by the final

surveyor and was sent to the Head Office of the Insurance Company after

almost three months. The Divisional Office was sitting on the file without

any authority and jurisdiction as the claim exceeded Rs. 20 lakhs. On

August 18, 2015, internal E-mail of the Insurance Company was sent with

regard to two different rates of salvage in two claim files i.e. claimant and

Hooghly infrastructure, on the basis of which on October 6, 2015 E-mail

was sent to the claimant regarding acceptance of salvage values at

Rs.10,000/- per metric ton. On September 19, 2015, more than after one

year of the fire, supplementary report was filed by the final surveyor to the

Insurance Company without any intimation to the claimant. On September

24, 2015 at page 163 to the application the IRDA circular was published

regarding discharge voucher in settlement of claim, inter alia, directing the

Insurance Company shall not withhold claim amounts and execution of

discharge vouchers does not foreclose the rights of the policy holders to seek

higher compensation before judicial fora or any other fora established by

law. On October 6, 2015 an E-mail was issued by the Insurance Company

to the claimant to accept the salvage value at Rs.10,000/- per metric ton.

The said E-mail further mentioned otherwise the matter may drag and the

same shall attract audit scrutiny. On October 7, 2015, the claimant replied

to the said E-mail stating that increase salvage value of Rs.10,000/- per

metric ton was not acceptable on the basis for such overvaluation which

had no connection to the claimant's case. On October 10, 2015, claimant

wrote a letter to the Insurance Company requesting a judicious settlement of

its claim. On October 16, 2015 the claimant wrote a letter to IRDA

informing of the inordinate delay on the part of the Insurance Company in

settlement of the claim of the claimant. On November 13, 2015 claimant

wrote a letter to the Insurance Company informing about the inordinate

delay of more than one year on the part of the insurance company to settle

the claim of the claimant and the claimant was undergoing through

financial hardship. On March 10, 2016 the claimants agreed for appointing

another surveyor by the Insurance Company to further strengthen the cause

of fire especially as no action was being taken by the Insurance Company

otherwise. On March 15, 2016 the Insurance Company appointed another

surveyor, Mr. K.B. Kuri, the last surveyor for further strengthening the

cause of fire. On March 16, 2016 claimant wrote a letter to the Insurance

Company informing that more than a year had passed without settling the

claim of the claimant and the claimant requested the Insurance Company to

make a part payment of at least Rs. 8 crores, since the claimant was

suffering from financial stress to carry out its business. In April 2016, the

draft report was shared by the last surveyor with the claimant only with

regard to the cause of fire and without enclosure showing the assessment of

loss. On May 20, 2016, at page 191 Volume-II to the application, the

claimant received an E-mail from the said last surveyor containing a pre-

formatted letter of consent together with note of acceptance and instructions

to print both side on the letterhead of the claimant and to sign and stamp

the same. Claimant has been instructed, to get the said letter ready together

with the note of acceptance and the same was issued by the claimant. On

August 31, 2016 the claimant had signed the said pre-formatted discharge

voucher and sent it to the Insurance Company through E-mail. On

September 7, 2016, the Insurance Company credited the bank account of

the claimant to the extent of Rs. 11,17,81,171/-. On September 9, 2016

claimant by its letter written to the Insurance Company demanded the

remaining amount of Rs. 4,43,88,000/-. On September 19, 2016 the

claimant by its letter written to the respondent reiterated its demand to the

said extent of Rs. 4,43,88,000/- and requested the Insurance Company to

furnish the surveyors' reports submitted from time to time.

7. October 27, 2016, the claimant invoked the arbitration clause. Since the

Insurance Company did not accept the nomination of the claimant, an

application was moved under Section 11 of the 1996 Act and the Tribunal

was constituted. The reliefs claimed in the statement of claim by the

claimant is quoted below:-

"a) Declaration that all consent documents caused to be made by the claimant including letters dated 07.03.2015, 10.03.2016, 20.05.2016 and discharge voucher dated 31.08.2016 are vitiated by undue influence, coercion, misrepresentation and fraud and are liable to be adjudged void and all such consents/documents are liable to be delivered up and cancelled, if required

b) Award for Rs. 7,59,29,406.31 against the respondent;

c) Pendente lite interest and interest upon award at the rate of 15 percent per annum;

d) Costs;

e) Further and other reliefs;"

8. The statement of claim is available at page-53 at Volume-I of the

application. The statement of defence filed by the Insurance Company is

available at page-200, Volume-II of the application. The rejoinder of the

claimant is available at page 291, Volume-III of the application.

9. The award was made and published by the Arbitral Tribunal on March 2,

2020 at page 430, Volume-IV of the application allowing the claim of the

claimants for the balance sum with interest.

Submissions:

10. The principle ground taken by the Insurance Company that, since by

signing and executing the discharge voucher, the claimant had accepted the

settled amount consciously and after receiving the said settled amount, the

claimant could not have claimed the balance sum. Mr. Chayan Gupta,

learned counsel appearing for the Insurance Company, the applicant herein,

submits that the principle of accord and satisfaction would clearly operate

in the instant facts and circumstances.

11. Mr. Chayan Gupta, learned counsel appearing for the Insurance Company

while developing his points of argument has submitted that, it was not a

case of coercion or undue influence upon the claimant. When the claimant

had accepted its claim as full and final settlement by executing the

discharge voucher, the claimant could not have taken the plea that the

discharge voucher was executed by it under coercion and undue influence

practiced by the Insurance Company upon the claimant. He submits that

had there been any coercion or undue influence practiced upon the claimant

by the Insurance Company, then the claimant subsequently ought not to

have gone for new insurance policy which had been executed with the

Insurance Company. Even previous to this particular incident the claimant

was insured with the same Insurance Company and subsequent thereto

also.

12. Referring to the said IRDA circular dated September 24, 2015, Mr. Gupta

submits that the circular provides for that execution of voucher does not

foreclose the rights of the policy holder to seek higher compensation before

any judicial forum and/or any other fora established by law but in the facts

of the instant case, the claimant has voluntarily and wilfully executed the

discharge vouchers and accepted the payment without protest with the clear

understanding that it did not want to prolong the issue for settlement of its

claim. Therefore, in the facts of the instant case the claimant not only

executed the voucher but also accepted the payment without any protest.

Since the claimant has accepted the payment, the said IRDA circular would

not apply to support the case of the claimant.

13. Referring to pages 500 to 508 of Volume-III of the application and

specifically referring to Exhibit ADR-8 and Exhibit ADR-9 at pages 509 to

512, Volume-III of the application, learned counsel for the Insurance

Company submits that while assessing the value of salvage and the fixation

of its rate, all along the claimant was in communication with the surveyor

appointed by the Insurance Company and in consultation with the claimant

the surveyor has suggested the value for salvage. Therefore, series of

communication were there from time to time between the claimant and the

surveyor and some vital communication at pages 510 to 512 of the

application were not disclosed in the arbitral proceeding by the claimant and

suppressed. Such documents were disclosed by the Insurance Company in

the arbitral proceeding as a part of its counter statement of claim and the

learned Arbitral Tribunal has failed to assess the purport content and

evidential value of those documents. Had those documents been properly

assessed by the learned Arbitral Tribunal in accordance with law, then the

complexion of the award would have been changed and would have gone in

favour of the Insurance Company, that the claimant knowingly and wilfully

executed the discharge voucher after having consultation with the surveyors

and on the basis thereof the claim of the claimant was settled and the

payment was accepted by the claimant under such settlement of claim.

Learned counsel has specifically referred few paragraphs from the impugned

award which, inter alia, are paragraphs 13, 15, 19, 35, 39 and 68 and

submits that the learned Arbitral Tribunal did not consider the defence of

the Insurance Company taken before it, and ultimately no finding was

arrived at thereupon. He then refers to the notes submitted by the

Insurance Company at page 68 to the application and submits that the

same was not considered. Referring to Exhibits ADR- 1 to ADR-9 from the

application, he submits that the Arbitral Tribunal had not taken note of the

content of the same and there was no adjudication on the same.

14. Mr. Chayan Gupta, Learned Counsel for the award-debtor/Insurance

Company further submits that, the plea taken by the insured/award holder

for releasing money by signing the discharge voucher was that the insured

was undergoing a financial stringency at the relevant point of time. Referring

to Exhibit ADR-1, which are financial statement of the insured, Mr. Chayan

Gupta submits that the insured had not undergone through any financial

stress, as would be evident from their audited balance-sheet. There was no

economic duress. Referring to both pre and post Fire Insurance Policies,

Exhibit ADR-2, he submits that the insured even after the fire broke-out

continued with the Insurance Company and even after the disputes

occurred by and between the parties, the insured executed insurance policy.

This, according to him, shows that after executing the discharge voucher

and accepting the insurance claim on account of the subject fire

unconditionally, the insured proceeded for the further insurance policy with

the Insurance Company. Had there been any dispute in the mind of the

insured, it would not have proceeded with for further insurance with the

Insurance Company. He also refers to Exhibit ADR-7, which are the

discharge voucher post fire, to show that the insured all along aware of the

fact that to receive the insurance claim if any, the discharge voucher are

executed as and by way of full and final settlement of the claim and there

remained no further scope for raising any further claim. He also refers to the

Exhibit ADR-8 being the communication relating to disposal of salvage

along-with the communication between the insured and the third Surveyor

being Exhibit ADR-9. Referring to these Exhibits, Mr. Gupta submits that

the insured was all along with the touch of the third Surveyor and on the

basis of the mutual discussion and agreement between the insured and the

third Surveyor evaluation of salvage was done. Therefore, the insured had

no occasion to go beyond those claims on account of salvage as assessed by

the third Surveyor.

15. Mr. Chayan Gupta, Learned Counsel submits that from a close scrutiny of

the award, it would be evident that none of the above Exhibits being ADR-1

to ADR-9 was considered by the arbitral tribunal while adjudicating the

disputes between the parties and passing the award. The award is thus

perverse. He submits that the tribunal had based it's finding by excluding

the vital evidences and relevant materials without taking them into account.

In support, he has relied upon a Division Bench judgment of this Hon'ble

Court In the matter of: Collector of Customs, Calcutta and Ors. Vs.

Biswanath Mukherjee reported at 1974(1) CLJ 251.

16. Mr. Chayan Gupta further submits that, a perverse finding is one which is

on no evidence or one that no reasonable person would have arrived at. If it

is found that the relevant evidence was not considered, despite being there

before the tribunal, finding is of tribunal is perverse. In support, he has

relied upon a decision of the Hon'ble Supreme Court, In the matter of:

Sumitomo Heavy Industries Limited Vs. Oil and Natural Gas

Corporation Limited reported at (2010) 11 Supreme Court Cases 296.

17. Learned Counsel for the Insurance Company then submits that the subject

discharge voucher had not been accepted by the arbitral tribunal as full and

final settlement of the claim. The tribunal had proceeded in a manner which

is beyond the prescribed procedure under the law and thereby the award is

opposed to public policy and should be set-aside. In support, Learned

Counsel has relied upon a Supreme Court decision In the matter of:

Supermint Exports Pvt. Ltd. Vs. New India Assurance Co. Ltd. and

Others, reported at 2021 SCC OnLine Delhi 5237.

18. Mr. Chayan Gupta, Learned Counsel for the Insurance Company further

submits that, when the patent illegality is ex facie on the face of the arbitral

award, the award is liable to be set aside. In support, he has relied upon a

decision of the Hon'ble Supreme Court In the matter of Associate

Builders Vs. Delhi Development Authority reported at (2015) 3

Supreme Court Cases 49.

19. Mr. Chayan Gupta then submits that the finding of the Learned Arbitral

Tribunal, as in the instant case, since without considering the vital evidence

is perverse and liable to be set aside. In support, he has relied upon a

decision of the Hon'ble Supreme Court In the matter of: Ssangyong

Engineering And Construction Vs. National Highways Authority of

India (NHAI) reported at (2019)15 Supreme Court Cases 131.

20. In the light of the above, Mr. Chayan Gupta, Learned Counsel of the

Insurance Company submits that the instant award being perverse and also

being opposed public policy, is liable to be set aside.

21. Mr. Sabyasachi Chaudhury, Learned Senior Counsel appearing for the

insured award holder submits that, the principle challenge allegedly made,

as would be evident from the grounds taken by the Insurance Company in

the setting aside application are on counts:

(a) The award was opposed to public policy;

(b) The award is on the face of it perverse and

(c) Once the discharge voucher has been issued and accepted by the award holder, there was accord and satisfaction, hence, the award is bad in law and not sustainable beyond the said satisfied claim.

22. Mr. Chaudhury, Learned Senior Counsel submits that the claim arose

out of an Insurance Contract. There is no dispute between the parties

that the Insurance Contract was executed. In such case, if a claim is

raised arising out of such contract, such a claim has to be proved by the

claimant and the respondent would have to disprove and dislodge the

claim. It is not the case of the Insurance Company, in the facts of this

case that, the claimant has not proved its claim. The solitary plea of the

Insurance Company is that the claim allowed by the Learned Arbitral

Tribunal was beyond the alleged discharge voucher, under which the

claimant has accepted its claim as full and final settlement. The specific

case of the claimant was that the discharge voucher was signed by the

claimant under coercion and undue influence. The award shows that

such case of coercion and undue influence made out in the claim have

been specifically proved and only thereafter, the claim of the claimant was

allowed.

23. The Learned Senior Counsel for the claimant refers to the Arbitration

Clause from page 132 Volume-1 of the setting aside application. He

submits that the Arbitration Clause itself is clear and accepted by the

parties which, inter alia, provides that if any dispute or difference shall

arise as to the quantum to be paid under the policy liability being

otherwise admitted, such differences shall independently of all other

instances to be referred for decision of a sole arbitrator. Accepting the

said Arbitration Clause the parties herein participated and proceeded with

the arbitration reference. The parties are, now, debarred from raising any

dispute to the contrary.

24. Referring to the IRDA Circular dated September 24, 2015 at page

163, Volume- 2 of the setting aside application, Learned Senior Counsel

submits that the said Circular provides that the Insurance Company shall

not use the execution as of discharge voucher as a means of Estoppel

against the aggrieved policy holder when such policy holder approaches

any judicial forum. Execution of such discharge voucher does not

foreclose the rights of policy holder to seek Higher Compensation before

any judicial fora or any other fora established by law. All the Insurance

Companies were directed to comply with the said instruction. It is not the

case of the Insurance Company that the said Circular is not binding on

them. So long, the said Circular remains binding on the Insurance

Company, the alleged discharge voucher would not have been the plea of

the Insurance Company in support of their case for accord and

satisfaction.

25. Learned Senior Counsel then places the relevant averments made by

the Insurance Company from the statement of defence filed by it in the

arbitral reference. Referring to the pleadings, inter alia, at sub-paragraphs

(a) to (f) to paragraph 14 of the statement of defence, he submits that

the consistent stand of the Insurance Company in the arbitration was

that the insured was a loss making Company. In the notes of arguments

filed by the Insurance Company, the same stand continued. Section 34

application does not contain any pleading to that effect. Subsequently, in

course of the argument, at this stage, it has been urged from the bar

referring to the balance-sheet and financial statement of the Company

being Exhibit ADR-1, 2, 3, 4, 5 and 6 that the financial health of the

Insured was very strong. The Insured has not suffered any financial

duress, therefore, there was no reason for the Insured accept the said

discharge voucher under coercion and undue influence. The said

evidences were never vital evidence at all. He submits that if it is found

that a particular claim raised by the Insured under the Insurance

Contract is proved and found to be payable by the Insurance Company, it

is the obligation of the Insurance Company in law to pay such

compensation irrespective of the nature and character of the financial

health of the Insured.

26. Mr. Chaudhury, Learned Senior Counsel then refers to various

questions and answers from the record of the arbitral proceeding and

those which are quoted in the impugned award and submits that after

considering the entire witness action, Arbitral Tribunal has passed the

award. The award is detailed and well versed.

27. Learned Senior Counsel then submits that the scope of adjudication

under Section 34 of the Arbitration Act is very limited and narrow. On a

detail reading of the instant award it appears that the same is extremely

well versed and well-reasoned. The evidences referred to on behalf of the

Insurance Company being ADR-1, 2, 3, 4, 5, 6 and 7 are not at all vital

evidences. In the light of the scope of adjudication of the arbitral

reference, the evidences relating to financial health of the insured or the

pre and post fire Insurance Policies are not at all vital evidence. Once the

quantum of compensation is in dispute and the quantum claimed by the

claimant is proved in accordance with law and is found to be payable to

the claimant by the Insurance Company under the Insurance Contract, it

is sufficient to pass an award accordingly, for which all these evidences

are not at all material to be looked into as vital evidence. The discharge

voucher ADR-7 being pre and post fire issued by the Insurance Company

are also not vital evidence, as they are not relevant to be considered under

the specific Insurance Contract of which the arbitral reference arose.

Moreover, in view of the IRDA Circular dated September 24, 2015, the

discharge voucher had no relevance when the claim was for adjudication

before the Arbitral Tribunal. The communication being ADR-8 and ADR-9

are not at all vital evidence, as the Claimant/Insured has proved its case

for coercion and undue influence before the Arbitral Tribunal.

28. Mr. Sabyasachi Chaudhury, Learned Senior Counsel appearing for the

insured further submits that, a setting aside Court is not a court of

appeal and consequently errors of facts cannot be corrected by it. A

possible view by the arbitrator on the facts has necessarily to pass muster

as the arbitrator is the ultimate master of the quantity and quality of

evidence to be relied upon when he delivers his arbitral award. Thus, an

award based on little evidence or on evidence which does not measure up

in quality to a trained legal mind would not be held to be invalid on this

score. Once it is found that the approach of the arbitrator is not arbitrary

or capricious, then, he is the last word on facts. In support, he has relied

upon the decision of the Hon'ble Supreme Court In the matter of:

Associate Builders (supra).

29. Mr. Chaudhury further submits that the re-appreciation of evidence,

is permitted by the Appellate Court and cannot be permitted under the

ground of patent illegality appearing on the face of award as the setting

aside Court is not an Appellate Court. A mere contravent of a substantive

law, by itself is no longer a ground available to stay an arbitral award. If a

vital evidence being produced before the Arbitral Tribunal and the

Tribunal passing its award fails to look at it and to appreciate the same,

then the award becomes bad in law and against the fundamental policy of

Indian Law and award suffers from patent illegality. In the instant case,

all the vital evidences have been considered by the Arbitral Tribunal and

the evidences referred to on behalf of the Insurance Company which were

not at all vital, the same would have no bearing on the adjudication of the

issue before the Tribunal. Hence, he submits that, the award cannot be

said that it suffers from patent illegality. In support, he has relied upon

the decision of the Hon'ble Supreme Court, In the matter of: Ssangyong

Engineering And Construction (supra).

30. In the light of the above, Mr. Sabyasachi Chaudhury, Learned Senior

Counsel submits that the award does not suffer from any infirmity and

should not be interfered with. He prays for dismissal of Section 34

application.

31. In reply, Mr. Sanjay Paul, Learned Counsel appearing for the

applicant Insurance Company reiterates the earlier submissions and

submits that since Arbitral Tribunal has ignored the vital evidences,

patent illegality is apparent on the face of the impugned award and the

award is perverse and should be set aside. In support, at the reply stage,

Mr. Sanjay Paul has relied upon a decision of the Hon'ble Supreme Court,

In the matter of: Delhi Metro Rail Corporation Ltd. Vs. Delhi Airport

Metro Express Pvt. Ltd. reported at 2024 SCC OnLine SC 522.

32. He submits that the decision of the Hon'ble Supreme Court In the

matter of: Delhi Metro Rail Corporation (supra) was rendered after

considering the judgment cited by Mr. Chaudhury In the matter of:

Associate Builders (supra) and Ssangyong Engineering And

Construction (supra). He submits that since vital evidences were not

considered by the Learned Tribunal, the award is liable to be set aside.

33. Per contra, Mr. Sabyasachi Chaudhury, Learned Senior Counsel

submits that the evidences referred to by the Insurance Company are not

at all vital as already narrated above and therefore, even if those

evidences could be considered, would not have altered the award. He

submits that the setting aside application should be dismissed.

Decision :

34. After considering the rival contentions of the parties and upon perusal

of the materials on record, at the outset, the Arbitration Clause between

the parties and the provisions from the IRDA Circular dated September

24, 2015 are quoted below:

Arbitration Clause:

"If any dispute or difference shall arise as to the quantum to be paid under this policy (liability being otherwise admitted) such difference shall independently of all other questions be referred to the decision of a sole arbitrator to be appointed in writing by the parties to or if they cannot agree upon a single arbitrator within 30 days of any party invoking arbitration, the same shall be referred to a panel of three arbitrators, comprising of two arbitrators, one to be appointed by each of the parties to the dispute/difference and the third arbitrator to be appointed by such two arbitrators and arbitration shall be conducted under and in accordance with the provisions of the Arbitration and Conciliation Act, 1996.

It clearly agreed and understood that no difference or dispute shall be referable to arbitration as hereinbefore provided, if the Company has disputed or not accepted liability under or in respect of this policy.

It is hereby expressly stipulated and declared that it shall be a conditio0n precedent to any right of action or suit upon this policy that the award by such

arbitrator/arbitrators of the amount of the loss or damage shall be first obtained."

IRDA Circular:

"Reg: Discharge Voucher in settlement of claim *** The Insurance Companies are using 'discharge voucher' or "settlement intimation voucher" or in some other name, so that the claim is closed and does not remain outstanding in their books. However, of late, the Authority has been receiving complaints from aggrieved policyholders that the said instrument of discharge voucher is being used by the insurers in the judicial fora with the plea that the full and final discharge given by the policyholders extinguish their rights to contest the claim before the Courts.

While the Authority notes that the insurers need to keep their books of accounts in order, it is also necessary to note that insurers shall not use the instrument of discharge voucher as a means of estoppel against the aggrieved policy holders when such policy holder approaches judicial fora.

Accordingly insurers are hereby advised as under:

Where the liability and quantum of claim under a policy is established, the insurers shall not withhold claim amounts. However, it should be clearly understood that execution of such vouchers does not foreclose the rights of policy holder to seek higher compensation before any judicial fora or any other fora established by law.

All insurers are directed to comply with the above instructions."

35. On a meaningful reading of the Arbitration Clause this Court is of

the considered and firm view that if any dispute or difference shall arise

as to the quantum to be paid under the policy, liability being otherwise

admitted, such differences shall independently of all other questions be

referred to the decision of a sole arbitrator. The Insurance Company

participated in the arbitration reference without any objection as to its

maintainability. The jurisdiction of the Arbitral Tribunal was never

challenged. Therefore, the scope of reference between the participating

parties was limited only to the extent of determination of quantum of

compensation.

36. Next comes, the IRDA Circular dated September 24, 2015. The

Circular indisputably is binding upon the Insurance Company. There

was no challenge to the contrary by the Insurance Company. The

Circular unequivocally shows that Insurers/Insurance Company shall

not use the instrument of Discharge Voucher as a Means of Estoppel

against the Aggrieved Policy Holders, who approaches judicial forum.

The Circular further provides where the liability on quantum of claim

under a policy is established, the Insurers/Insurance Company shall

not withhold the claim. It should be clearly understood that Execution of

such vouchers does not foreclose the rights of policy holder to seek

Higher Compensation before any judicial fora or any other fora

established by law. The Circular was directed to be complied with by all

Insurers/ Insurance Companies. On a plain reading of the said

Circular, this Court is of the firm and considered view that, the execution

of discharge voucher would not amount to estoppel on the part of the

Insured, if such an Insured is aggrieved with the quantum of

compensation fixed by the Insurers/Insurance Company and

approaches a judicial forum and execution of such discharge voucher

also does not foreclose the rights of the Policy Holder/Insured to seek

Higher Compensation in accordance with law.

37. This Court is also of the firm view that, where the liability or quantum of the

claim under a policy is established, the Insurance Company shall not

withhold the claim amount and all Insurance Companies are directed to

comply with the provisions of the said Circular. The natural consequence of

the said IRDA Circular is that, if an Insured is aggrieved with the quantum

of claim allowed by the Insurance Company, it may approach the judicial

fora or any other fora established by law seeking Higher Compensation and

execution of the discharge voucher should not operate as an Estoppel on

the part of such Insured neither does it foreclose the rights of the Insured to

seek Higher Compensation.

38. The said Circular is binding upon the Insurance Company.

39. In the light of the above, the impugned award is required to be adjudicated

upon within the limited scope of Section 34 of the Arbitration Act.

40. In this backdrop, when the instant award has been read by this Court

meaningfully, it appears that the Learned Arbitral Tribunal has gone in

detail with regard to the plea of the Insured that the discharge voucher was

executed by it under coercion and undue influence. Apart from that the

Insured had proved its claim independent of execution of the discharge

voucher. In view of the provisions laid down in the said IRDA Circular

dated September 24, 2015, the plea taken by the Insurance Company for

Accord and Satisfaction on the basis of the execution of the discharge

voucher, in any event, would not stand in the eye of law.

41. The award further shows that upon detail witness action and upon

considering all the materials, the Ld. Arbitrator had arrived at its finding

that the insured being the claimant had proved its claim. When an

Insurance Contract is executed, it is the duty and legal obligation of the

Insurance Company to compensate the Insured by paying its claim, if the

Insured has proved its claim in accordance with law. When such a claim is

proved in the eye of law, the Insurance Company has no other alternative

but to pay the said claim to the insured. Unless otherwise agreed by and

between the parties to the relevant Insurance Contract, it is irrelevant and of

no consequence to consider the financial health of the insured or whether

any other Insurance Contract pre and post occurrence of fire was there, in

the facts of the instant case. The claim which is under adjudication allegedly

settled by and between the parties on the basis of any discharge voucher, as

pleaded by the insurance company is wholly irrelevant and immaterial

consideration, when the insured has claimed higher compensation.

42. The evidences as already referred to above, with regard to the financial

health of the Insured at any material point of time, would have no relevance

at all for adjudicating the claim of the insured in the facts and

circumstances of the instant case, therefore, any evidence with regard to the

financial health of the Insured would have no relevance or material bearing

on the adjudication and are not at all vital evidence. In absence of any

agreement by and between the parties that the insurance claim under the

Insurance Contract would depend upon the financial health of the Insured.

43. Similarly, arising out of a particular Insurance Contract, the Insured has

raised its claim in the arbitral reference. The adjudication of such claim

should be restricted only in respect of that particular Insurer/Insurance

Contract and not beyond, therefore, whether the parties have entered into

any previous Insurance Contract or future Insurance Contract and in claims

were raised and the fate of it are wholly irrelevant consideration while

adjudicating the claim raised by the Insured arising out of a particular

Insurance Company. Therefore, the evidence, as referred to above, with

regard to pre and post subject Insurance Contract, arising whereof the

arbitral reference arose, would have no relevance and material bearing in

the adjudication of the reference. Hence, all such evidences are not at all

vital and relevant for adjudication.

44. The objection raised by the Insurance Company that allegedly negotiation

took place by and between the Insured and the Surveyor appointed by the

Insurance Comp[any and the claimant allegedly was paid on the basis

thereof would amount to Accord and Satisfaction of the claim of the Insured

or waiver or estoppel on the part of the Insured, are not tenable in law as

provision under the said IRDA Circular dated September 24, 2015

provides that execution of discharge voucher will not operate as an estoppel

and the Insured can still claim Higher Compensation. Moreover, the

Surveyor did not file their report and settled the claim within the contractual

period and/or the statutory period fixed under the relevant guidelines and

the Insured has proved its claim beyond all reasonable doubt. Therefore, the

evidence, as referred to above according to the Insurance Company that on

the basis of a negotiation between the Insured and the Surveyor, the claim

was settled is not a tenable objection in the eye of law. Hence, the evidences,

as referred to above in this regard not at all vital or relevant for adjudication

of the claim of the Insured, in the facts of this case.

45. In the matter of: Associate Builders (supra) the Hon'ble Supreme Court

had observed as under:

"31.The third juristic principle is that a decision which is perverse or so irrational that no reasonable person would have arrived at the same is important and requires some degree of explanation. It is settled law that where:

                               i)      a finding is based on no evidence, or
                               ii)     an Arbitral Tribunal takes into account
                                       something irrelevant to the decision which
                                       it arrives at; or
                               iii)    ignores vital evidence in arriving at its
                                       decision,
                                    such decision would necessarily be perverse.

32. A good working test of perversity is contained in two judgments. In Excise and Taxation Officer- cum-Assessing Authority v. Gopi Nath & Sons, it was held:( SCC p. 317, para 7) "7....It is, no doubt, true that if a finding of fact is arrived at by ignoring or excluding relevant material or by taking into consideration irrelevant material or if the finding so outrageously defies logic as to suffer from the vice of irrationality incurring the blame of being perverse, then, the finding is rendered infirm in law."

In Kuldeep Singh v. Commr. of Police, it was held:

(SCC p.14, para 10)

"10. A broad distinction has, therefore, to be maintained between the decisions which are perverse and those which are not. If a decision is arrived at on no evidence or evidence which is thoroughly unreliable and no reasonable person would act upon it, the order would be perverse.

But if there is some evidence on record which is acceptable and which could be relied upon, howsoever compendious it may be, the conclusions would not be treated as perverse and the findings would not be interfered with."

33. It must clearly be understood that when a court is applying the "public policy" test to an arbitration award, it does not act as a court of appeal and consequently errors of fact cannot be corrected. A possible view by the arbitrator on facts has necessarily to pass muster as the arbitrator is the ultimate master of the quantity and quality of evidence to be relied upon when he delivers his arbitral award. Thus an award based on little evidence or on evidence which does not measure up in quality to a trained legal mind would not be held to be invalid on this score.

Once it is found that the arbitrators approach is not arbitrary or capricious, then he is the last word on facts. In P.R. Shah, Shares & Stock Brokers (P) Ltd. v. B.H.H. Securities (P) Ltd., this Court held : (SCC pp. 601-02, para 21)

"21. A court does not sit in appeal over the award of an Arbitral Tribunal by reassessing or re-

appreciating the evidence. An award can be challenged only under the grounds mentioned in Section 34(2) of the Act. The Arbitral Tribunal has examined the facts and held that both the second respondent and the appellant are liable. The case as put forward by the first respondent has been accepted. Even the minority view was that the second respondent was liable as claimed by the first respondent, but the appellant was not liable only on the ground that the arbitrators appointed by the Stock Exchange under Bye-law 248, in a claim against a non-member, had no jurisdiction to decide a claim against another member. The finding of the majority is that the appellant did the transaction in the name of the second respondent and is therefore, liable along with the second respondent. Therefore, in the absence of any ground under Section 34(2) of the Act, it is not possible to re-examine the facts to find out whether a different decision can be arrived at."

34. It is with this very important caveat that the two fundamental principles which form part of the fundamental policy of Indian law (that the arbitrator must have a judicial approach and that he must not act perversely) are to be understood."

46. In the matter of: Ssangyong Engineering And Construction

(supra) the Hon'ble Supreme Court had observed as under:

"34. What is clear, therefore, is that the expression "public policy of India", whether contained in Section 34 or in Section 48, would now mean the "fundamental policy of Indian law" as explained in para 18 and 27 of Associate Builders, i.e., the fundamental policy of Indian law would be relegated to the "Renusagar" understanding of this expression. This would necessarily mean that the Western Geco expansion has been done away with. In short, Western Geco, as explained in para 28 and 29 of Associate Builders, would no longer obtain, as under the guise of interfering with an award on the ground that the arbitrator has not adopted a judicial approach, the Court's intervention would be on the merits of the award, which cannot be permitted post amendment. However, insofar as principles of natural justice are concerned, as contained in Sections 18 and 34(2)(a)(iii) of the 1996 Act, these continue to be grounds of challenge of an award, as is contained in para 30 of Associate Builders.

37. Insofar as domestic awards made in India are concerned, an additional ground is now available under sub-section (2A), added by the Amendment Act, 2015, to Section 34. Here, there must be patent illegality appearing on the face of the award, which refers to such illegality as goes to the root of the matter but which does not amount to mere erroneous application of the law. In short, what is not subsumed within "the fundamental policy of Indian law", namely, the contravention of a statute not linked to public policy or public interest, cannot be brought in by the backdoor when it comes to setting aside an award on the ground of patent illegality.

38. Secondly, it is also made clear that re- appreciation of evidence, which is what an appellate court is permitted to do, cannot be permitted under the ground of patent illegality appearing on the face of the award."

47. In the matter of Delhi Metro Rail Corporation (supra), the Hon'ble

Supreme Court observed as under:

"40. In essence, the ground of patent illegality is available for setting aside a domestic award, if the decision of the arbitrator is found to be perverse, or so irrational that no reasonable person would have arrived at it; or the construction of the contract is such that no fair or reasonable person would take; or, that the view of the arbitrator is not even a possible view.24 A 'finding' based on no evidence at all or an award which ignores vital evidence in arriving at its decision would be perverse and liable to be set aside under the head of 'patent illegality'. An award without reasons would suffer from patent illegality. The arbitrator commits a patent illegality by deciding a matter not within his jurisdiction or violating a fundamental principle of natural justice."

48. Upon reading the provisions of Section 34 of the Arbitration Act and the

law laid down through various precedences, this Court, now, proceeds to

discuss power and authority of the Court under Section 34 of Arbitration

and Conciliation Act as follows:

(a) An award by an arbitrator can only be set aside on limited grounds and the supervisory role of the Court is limited to a narrow extent;

(b) The Court in exercise of its power under Section 34 of the Arbitration Act shall not exercise its appellate jurisdiction over the award while examining the correctness of the finding of the award. A Court while considering the objections under Section 34 of the Act shall not re-appreciate the fact finding enquiry, the evidence looked upon by the Arbitral Tribunal, the entire finding of the Tribunal and to reassess the evidence before the Arbitral Tribunal;

(c) When finding of the Arbitral Tribunal and its conclusion is based on a possible view on the basis of the records, Section 34 Court shall not interfere with the award. Section 34 Court shall not substitute its view when a possible and plausible view has already been taken by the Arbitral Tribunal on the basis of the existing materials before it.

(d) The finding of the Arbitral Tribunal with regard to construction of a contract is not to be interfered with, if there is a plausible view taken by the Arbitral Tribunal and even an error relating to interpretation of a contract or a document by an Arbitral Tribunal is regarded as an error within its jurisdiction and such an error is not amenable for correction by a Section 34 Court.

(e) While adjudicating the issue before the Arbitral Tribunal, if the Tribunal does not look into the evidence or consider the same, which is otherwise of no relevance or has no material barring in adjudication of the issue before the Arbitral Tribunal, such an evidence can and should not be construed to be a vital evidence before the Arbitral Tribunal. As such, non-consideration of such evidence would not render the award perverse.

(f) The important consideration by Section 34 Court would be whether an evidence, had it been considered by the Arbitral Tribunal would have altered the finding of the Arbitral Tribunal on the existing materials before it and in the event such is the case, then that particular evidence having a material bearing and relevance on the issue should be construed as a vital evidence and non-

consideration of the same would render the award perverse.

(g) A perverse finding is one which is based on no evidence or one that no reasonable person would have arrived at. In the event, it is found that some relevant and vital evidence had not been considered or that certain inadmissible evidence has been taken into consideration, the award may be perverse.

49. A close perusal of the impugned award would reveal that the Arbitral

Tribunal has dealt with the rival claims of the parties in detail. The

Tribunal has meticulously and meaningfully considered the evidence

before it. The Tribunal has analysed the evidence of the parties on proper

appreciation of their respective witness action. The Arbitral Tribunal has

dealt with the defence of the Insurance Company, in all respect. After all

these exercise the tribunal has come to its finding that the claimant has

proved its claim.

50. In the matter of: Collector of Customs, Calcutta and Ors. (supra)

the Hon'ble Division Bench of this Court had delivered the judgment in a

writ proceeding while examining the judgment of a Tribunal whether was

perverse or not. Firstly, the law applicable for judicial review in a writ

jurisdiction is not the same with regard to the application of law in the

arbitration proceeding. It was held that the decision of the Tribunal was

to be perverse if the Tribunal has given its finding on material not

admissible or has excluded the relevant materials. In the facts of this

case, it is not the case of the Insurance Company that the finding of the

arbitrator was based on such materials which were not admissible in

evidence. The plea taken by the Insurance Company that the Exhibits

ADR-1 to ADR-9 being material evidence were excluded to be looked into

by the Arbitral Tribunal. It has already been discussed above in detail

that had these Exhibits been considered by the Arbitral Tribunal, there

would have been no material alteration in the ultimate finding of the

Arbitral Tribunal in its award. The said Exhibits were not at all relevant

or vital evidence in the facts of this case. Hence, the ratio of the judgment

has no application and relevance in the facts and situation of the instant

case.

51. The ratio laid down In the matter of: Sumitomo Heavy Industries

Limited (supra) has also no application in the facts and situation of the

instant case. Since the Exhibits, as referred to above, were not at all vital

evidence, the consideration of the same was also irrelevant before the

Arbitral Tribunal. The award cannot said to be perverse in absence of

consideration of those evidences.

52. The ratio laid down In the matter of: Associate Builders (supra)

describes the scope and ambit of the authority of Section 34 Court and

the relevant portion have already been quoted above. Since the execution

of the discharge voucher was irrelevant and of no consequence while

considering enhancement of claim of the claimant before the Arbitral

Tribunal and the execution of other Insurance Contracts by and between

the parties had no relevance in the facts of this case and since the

evidence Exhibits being ADR-1 to ADR-9 not being vital evidence in the

facts of this case, it cannot be said that the award suffers from any

patent illegality.

53. In the matter of: Supermint Exports Pvt. Ltd. (supra), the Hon'ble

Supreme Court has held that the finding of the Tribunal which is

altogether against the evidence, it becomes perverse. This is not the case

here. The award shows that the same is a speaking award and was made

by the Tribunal on appreciation of the existing materials before it. The

evidence being Exhibits ADR-1 to ADR-9 were not at all relevant for

consideration. Hence, the award does not suffer from perversity in the

instant case. Thus, the ratio of the judgment has no application in the

facts of the instant case. The arbitrator throughout had a judicial

approach as would be evident on the face of the award and the arbitrator

has acted within the forecorner of law and no perversity is there on the

face of the award. Hence, the ratio laid down In the matter of: Delhi

Metro Rail Corporation Ltd. (supra) has no application in the facts of

this case. There is no patent illegality on the face of the award. There is

no violation of any substantive Indian Law which would be evident on the

face of the award. The award is not opposed to public policy of India at

all.

54. In view of the foregoing discussions and reasons, this Court is of the

considered and firm view that the Award does not warrant any

interference by this Court.

55. The Award dated March 2, 2020 stands.

56. Accordingly, the application being AP-COM/186/2024, Old Case No.

AP/322/2020 stands Dismissed, without any order as to costs.

57. The Learned Registrar, Original Side with whom the awarded amount

is lying secured in an interest bearing Fixed Deposit Account shall take

steps forthwith to encash the Fixed Deposit and pay the entire amount

with accrued interest thereupon, upon compliance of all formalities, in

favour of the respondent insured positively within a period of Four

Weeks from the date of communication of this judgment.

58. The concerned Bank shall also take all necessary steps accordingly.

(Aniruddha Roy, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter