Citation : 2025 Latest Caselaw 868 Cal/2
Judgement Date : 14 January, 2025
IN THE HIGH COURT AT CALCUTTA
Ordinary Original Jurisdiction
ORIGINAL SIDE
(COMMERCIAL DIVISION)
AP-COM/577/2024
SRMB SRIJAN PVT. LTD.
VS.
AGGARWAL STEEL INDUSTRIES PVT. LTD. AND ANR.
BEFORE:
The Hon'ble JUSTICE SHAMPA SARKAR
For the petitioners ... Mr. Arnab Das, Adv.
Ms. Syeda Romana Sultan, Adv.
Mr. Vaibhav Sharma, Adv.
For the respondents ... Mr. S.N.Mitra, Sr. Adv.
Mr. Avra Mazumder, Adv.
Ms. Alisha Das, Adv.
Mr. Suman Bhowmik, Adv.
Mr. Samrat Das, Adv.
Ms. Elina Dey, Adv.
Mr. Sourendra Nath Banerjee, Adv.
Hearing concluded on: 02.01.2025 Judgment on: 14.01.2025
Shampa Sarkar, J.:-
1. This is an application under Section 11 (5) and (6) of the Arbitration
and Conciliation Act 1996, for appointment of an Arbitrator. The case of the
petitioner was that the respondent No.1 entered into a Unit Franchise
Agreement with the petitioner on January 1, 2022, which was valid for two
years from the effective date of the agreement, that is, January 1, 2022 or
from the day of commencement of business. The terms and conditions were
mutually agreed between the parties.
2. The said agreement was executed in the office of the petitioner within
the jurisdiction of this court. It was agreed that the respondent No.1 would
act as the franchisee of the petitioner in the States of Jammu and Kashmir,
Himachal Pradesh and Punjab and for the same purpose, it would make a
payment of royalty of Rs.300 per metric tonne along with applicable taxes
for the first four months and thereafter, would pay an amount of Rs.400 per
metric tonne on a monthly basis along with taxes.
3. On the request of the respondent No.1, the petitioner deployed its own
sales team in the States of Jammu and Kashmir, Himachal Pradesh and
Punjab and it was agreed between the parties that the cost for deployment of
the sales team would be borne by the respondent No.1. According to the
petitioner, it was obligatory on the part of the respondent No.1 to provide
proper report of the sales statement periodically. It was contended by the
petitioner that various discrepancies were detected by the petitioner with
regard to sale of the products. The respondent No.1 did not take any
consent or approval for relocating the manufacturing operations and the
unit was given on lease to a third party, which started that manufacturing
activity for the products at Bardi, Himachal Pradesh. This was in violation of
the terms and conditions of the agreement.
4. Accordingly, it is alleged that the manufacturing of the materials
abruptly stopped and the brand value and the reputation of the petitioner
suffered. According to the petitioner, it had incurred huge loss and damages
to the tune of 40 lakhs. When the petitioner confronted the respondent No.1
about the illegal activities, the respondent No.1 allegedly accepted the
breaches and requested the petitioner to permit the respondent No. 2, a
group company of the respondent No.1, having a common promoter to
discharge the obligations of the said agreement. By an email dated March
14, 2022, the respondent No.2 requested the petitioner to amend the
agreement and to incorporate the name of the respondent No.2 therein, and
also requested the petitioner to allow the operation of the manufacturing
unit at Bardi, Himachal Pradesh. The respondent No.2 assured to abide by
the terms and conditions and also proposed to execute a supplementary
agreement. It was proposed that the production of the materials would
commence immediately after the renewal of the said agreement.
5. Having no other alternative, the petitioner contended to have accepted
such proposition and a supplementary agreement was executed on April 25,
2022, between the parties, for a further period of two years on similar terms
and conditions. The supplementary agreement was made a part of the
original franchise agreement. According to the petitioner, the respondent
No.2 failed to perform its obligations and the entire production was stopped
till May 2022. This jeopardized the entire business cycle of the petitioner in
the said States. Due to non-performance on the part of the respondent No.2
as well, the petitioner suffered loss and damages, which led to loss of
distributors, dealers and customers.
6. The petitioner sent various emails, asking the respondents to release
the wages and salary of the sales team deployed by the petitioner, but the
respondents deliberately paid no heed to such request. Lastly, the petitioner
had no other alternative, but to terminate and revoke the franchise
agreement dated January 1, 2022, as well as the supplementary agreement
dated April 25, 2022.
7. By a letter dated December 5, 2022, the petitioner raised a demand of
Rs.3,11,29,747/- towards outstanding damages and losses suffered.
According to the petitioner, Article 26 of the Franchise Agreement dealt with
the law applicable and settlement of disputes. The Article provided that the
parties would attempt in good faith to resolve any dispute, difference or
claim arising out of or in relation to the agreement. The dispute must be
notified to the other party in writing and both parties would then try to
resolve the same through mutual discussion. In case the dispute was not
resolved within 30 days from receipt of the written communication by the
other party, the complaining party could issue a notice of reference,
invoking settlement of such dispute through arbitration. All disputes
between the parties would be subject to the exclusive jurisdiction of the
courts of Calcutta.
8. Article 26 of the Franchise Agreement was placed by the petitioner, in
support of such contentions. It was urged that once the parties failed to
resolve the dispute by negotiation and mutual discussion, the only other
mechanism for settlement of such unresolved disputes raised by the
petitioner, was arbitration by a sole arbitrator to be appointed by this court.
9. The supplementary agreement was referred to in support of the
contention that the said agreement was made a part of the original
agreement and the dispute resolution clause in the supplementary
agreement also provided that parties should attempt to settle the dispute by
negotiation and in the event the dispute could not be resolved by the parties
within 30 days, it would be referred to arbitration. The arbitration would be
held in Kolkata, in accordance with Arbitration and Conciliation Act, 1996.
10. According to the petitioner, although several requests and
representations were made to the respondents to release the amount
claimed, the respondents neglected to adhere to the terms and conditions of
the agreement. The petitioner invoked the arbitration clause under Section
21 of the Arbitration and Conciliation Act, 1996 and by the letter dated July
10, 2023, the petitioner nominated its own arbitrator, a former Judge of the
High Court at Calcutta.
11. According to the petitioner, upon receipt of the notice invoking
arbitration, the respondent No.2 by a letter dated August 2, 2023, refused to
settle the dispute through arbitration and proposed to settle the dispute by
negotiation. The respondent No.2 also rejected the claim with regard to
outstanding dues, losses suffered, damages, etc. By a letter dated August
11, 2023, the petitioner accepted the proposal for negotiation and proposed
to conduct a virtual meeting from its registered office, as mentioned in the
cause title of this application. The respondent No.2 refused to join the
virtual meeting and by a letter dated August 21, 2023, made certain
baseless and unfounded allegations against the petitioner.
12. The petitioner was for the first time informed that the respondents
had approached the High Court at Himachal Pradesh challenging the notice
invoking arbitration. The petitioner, thereafter, preferred an application
under Section 11 (5) and (6) of Arbitration and Conciliation Act, 1996, before
the High Court at Calcutta, which was registered as AP No.683 of 2023. The
respondents appeared in the proceeding and informed the court that an
application under Section 9 of the said Act had been filed before the High
Court at Himachal Pradesh and an order staying any proceeding on the
basis of the notice invoking arbitration had been passed. Accordingly, by an
order dated October 4, 2023, a learned Coordinate Bench disposed of AP
No.683 of 2023, by observing that, when the notice invoking arbitration had
been stayed by another High Court, the High Court at Calcutta could not
entertain the application and granted liberty to the petitioner to raise the
questions before the High Court at Himachal Pradesh, including the
question of lack of jurisdiction of the said court, in view of the seat chosen
by the parties as Kolkata. On the basis of the said order, the petitioner
appeared before the High Court at Himachal Pradesh and made
submissions.
13. It was contended by the learned Advocate for the petitioner that the
objection as to the jurisdiction of the High Court of Himachal Pradesh was
also urged and at that juncture, the parties decided to resolve the dispute
mutually, by negotiation. On the basis of such submission of the parties, the
application was disposed of and the question of jurisdiction was not decided.
14. It is the specific case of the petitioner that after the application filed
before the High Court of Himachal Pradesh, being Arb. Case No. 633 of 2023
was disposed of on March 1, 2024, the petitioner informed the respondents
about a virtual meeting to be held on March 8, 2024, at 5.30 pm. The
meeting link was also provided by the petitioner. The meeting was attended
by the respondents, but no fruitful result matured out of the meeting,
thereby, leaving the petitioner with no other alternative, but to invoke the
arbitration clause as per Article 26 of the Franchise Agreement dated
January 1, 2022 and Article V(v) of the supplementary agreement dated
April 25, 2022.
15. Accordingly, by a letter dated March 19, 2024, the petitioner again
invoked the arbitration clause proposing the name of a retired Judge of this
court to arbitrate upon the dispute between the parties. In reply to the said
notice, the respondent No.2 by a letter dated 19 April 2024, rejected the
proposal made by the petitioner and instead, suggested a few names of
learned Judges of Himachal Pradesh to be nominated as an arbitrator. The
petitioner refused to accept any of those names and thus this application
has been filed before the court seeking appointment of the sole arbitrator in
the facts and circumstances of the case.
16. Mr. Surojit Nath Mitra, learned Senior Advocate, submitted that the
address of the respondents as per the cause title would indicate that the
respondents were outside the Ordinary Original Civil Jurisdiction of the
High Court at Calcutta. The work was to be executed outside West Bengal.
The respondent No.1 was to act as the franchisee of the petitioner in the
States of Jammu and Kashmir, Himachal Pradesh and Punjab. Thus, the
State of West Bengal was in no way connected with the said agreement, out
of which the present dispute arose. This Court lacked the jurisdiction to
take up the matter.
17. Mr. Mitra further submitted that this was the second application for
appointment of the arbitrator and the application was not maintainable as it
was hit by the principles of res judicata. The first application for
appointment of an arbitrator being AP/683/2023, was rejected by a
Coordinate Bench by order dated October 4, 2023. The Coordinate Bench
directed that once the High Court of Himachal Pradesh had stayed the
notice invoking arbitration, the court was not inclined to appoint an
arbitrator on the basis of the said notice. Any order on the said application
would be in conflict with the decision of the said High Court. The petitioner
was granted liberty to take appropriate steps before the Himachal Pradesh
High Court, including the point of jurisdiction. According to Mr Mitra, such
liberty would mean that the petitioner should have approached the
Himachal Pradesh High Court for appointment of the sole arbitrator, once
the negotiations failed.
18. It was further submitted that the petitioner entered appearance in
Arb. Case No. 633 of 2023, by submitting to the jurisdiction of the High
Court of Himachal Pradesh and agreed before the said court to resolve the
dispute through negotiation. Reflection of such conduct of the petitioner was
available from the order dated March 1, 2024, passed in Arb. Case No. 633
of 2023 and the petitioner could not have come to this court after the
negotiations had failed.
19. Having heard the learned advocates for the respective parties, this
court finds that there is existence of an arbitration clause which provides for
settlement of disputes by arbitration, upon failure to resolve the dispute
amicably. Both the Franchise Agreement and the Supplementary Agreement
clearly indicate that the parties had agreed that the courts of Kolkata would
have exclusive jurisdiction. Article 26 further provided that the arbitral
award would be in writing and would be final and binding on each party and
would be enforceable in any competent court in respect of the applications
made. The supplementary agreement provided that all the clauses of the
principal agreement would remain the same and be in full force and effect
between the parties. The said agreement further provided that in the event,
the dispute was not resolved within 30 days, it would be referred to and
settled by arbitration. The arbitration would be held at Kolkata in
accordance with the Arbitration and Conciliation Act, 1996.
20. The parties thus agreed that the arbitration shall be held at Kolkata
and only the courts at Kolkata would have the jurisdiction to entertain any
application under the Arbitration and Conciliation Act. The order of the
Coordinate Bench dated October 4, 2024, recorded that it was arguable
whether the respondents could have filed any application before the
Himachal Pradesh High Court in view of the designated venue in the
arbitration agreement. The order dated August 4, 2023, passed in Arb. Case
No. 633 of 2023, records that the dispute resolution clause indicated that
the arbitral proceedings were contemplated to be held at Kolkata. However,
the ex parte order of stay was granted on the understanding of the court
that prior to resorting to the arbitration proceeding, the parties had agreed
to settle the dispute by negotiation and only if the negotiation failed, the
same could be referred to and settled by an arbitrator in arbitration
proceedings.
21. The court found that the petitioner, unilaterally and without resorting
to a negotiation to settle the dispute, had nominated an arbitrator. On this
ground, the interim order of stay was passed ex parte, restraining the
petitioner from acting in furtherance of the first notice invoking arbitration
dated July 10, 2023. When the petitioner approached this court for
appointment of an arbitrator, a Coordinate Bench observed that it was
arguable as it how the respondents could approach the Himachal Pradesh
High Court, when the designated venue as agreed between the parties was
Kolkata and the courts of Kolkata were to have exclusive jurisdiction in
respect of any application filed under the said Act. Her Lordship refrained
from passing any order for appointment of arbitrator on the basis of the said
notice under Section 21 of the said Act issued by the petitioner, as the said
notice had been stayed by another High Court.
22. Instead of appointing an arbitrator, Her Lordship directed the
petitioner to approach the Himachal Pradesh High Court and take all points
available, including the point of jurisdiction. Such direction does not
indicate that Her Lordship had rejected the application on the ground of
lack of jurisdiction, as the High Court at Himachal Pradesh had entertained
an application under Section 9 of the said Act. The relevant portion of the
order dated October 4, 2023 is quoted below:-
"Even though the dispute between the parties is evidence from the letters exchanged and appears also to have been admitted by the respondent (petitioner before the Himachal Pradesh High Court) in its affidavit-in-opposition, this Court is however not inclined to appoint an Arbitrator in terms of the very same notice which has been stayed by the Himachal Pradesh High Court. This would result in a conflict in the decisions of two High Courts.
The petitioner shall be at liberty of taking appropriate steps before the Himachal Pradesh High Court including the point of jurisdiction. It is also arguable whether the respondent could have filed any proceeding before the Himachal Pradesh High Court in view of the designated venue in the arbitration agreements."
23. The petitioner appeared before the Himachal Pradesh High Court.
Although, it is urged by the petitioner that the arguments on the point of
jurisdiction were advanced at length, it appears that the application was
disposed of when the parties agreed to once again try to mutually settle the
matter through negotiation. The jurisdiction of the said court was neither
decided nor discussed. It any event, appointment of Arbitrator will be in
accordance with the agreement. The Himachal Pradesh High Court would
not assume jurisdiction to exercise powers under Section 11 of the said Act,
on the ground that the application under Section 9 of the said Act was filed
before the said court. The seat of arbitration as agreed between the parties
was Kolkata.
24. While disposing of the said application, the High Court at Himachal
Pradesh recorded that the parties had mutually agreed that they would
initially hold one negotiation on March 8, 2024, and try to resolve the
dispute. Thereafter, unless the parties agreed to have further negotiations,
the parties were to proceed in accordance with the agreement entered into
between the parties. Accordingly, in view of such mutual agreement, the
arbitration case was disposed of along with all connected applications.
25. The agreement provides for an arbitration clause with the jurisdiction
of the courts at Kolkata in respect of all applications filed by the parties
under the said Act. The designated seat of arbitration as Kolkata has been
mentioned in the supplementary agreement, which was made a part of the
franchise agreement. The relevant clauses are quoted below for convenience.
26. Article 26 of the Franchise Agreement is quoted below:-
ARTICLE 26
APPLICABLE LAW AND SETTLEMENT OF DISPUTES i. This agreement and the rights and obligations of the parties hereunder shall be governed by and construed in accordance with the applicable laws of India.
ii. The Parties shall attempt in good faith to resolve any dispute, difference or claim arising out of or in relation to this Agreement:
Any dispute is to be notified to, the other party in writing setting out the dispute or claim which both the parties will then try to resolve through mutual discussions. In case it is not resolved within thirty (30) days from receipt of the written communication
by the other party, the complaining party may issue a notice of reference, invoking settlement of such dispute through Arbitration. iii. All disputes between parties shall be subject to exclusive jurisdiction of the courts of Kolkata only.
iv. Any and all disputes ("Disputes") arising out of or in relation to or in connection with this Agreement between the Parties or relating to the performance or non-performance of the rights and obligations set forth herein or the breach, termination, invalidity or interpretation thereof shall be referred for arbitration at Kolkata, India in accordance with the terms of Indian Arbitration and Conciliation Act, 1996 or any amendments thereof. The language used in the arbitral proceedings shall be English. The arbitral award shall be in writing and shall be final and binding on each party and shall be enforceable in any court of competent jurisdiction. In respect of application/s made under the Arbitration and Conciliation Act, 1996, the Courts at Kolkata, alone shall have the jurisdiction to entertain such application.
27. The dispute resolution clause from the supplementary agreement is
quoted below :-
V) Dispute Resolution -
Unless stated to the contrary in this Supplementary. Agreement, any dispute between the Parses at any time in regard to any matter arising from the Supplementary Agreement or its interpretation or rectification shall be submitted for settlement by negotiation by the each party. In the event that the dispute cannot be resolved by the Parties within thirty (30) days it shall be referred to and settled by arbitration proceeding.
The arbitration shall be held at Kolkata in accordance with the Arbitration and Conciliation Act, 1996 and any, subsequent amendment thereon.
28. Thus, the submissions of Mr. Mitra cannot be accepted. The order in
Arb. Case No. 633 of 2023, dated March 1, 2024, clearly records that the
parties had agreed before the said court to negotiate once and unless they
wanted further negotiations, they would proceed in respect of the dispute as
per the terms of the agreement and the terms of agreement have been
quoted hereinabove. The relevant portion of the order is quoted below:-
"Learned counsel for the parties mutually agree that in terms of Article V Clause (v) of the supplementary agreement, they will initially hold
only one negotiation on 08.03.2024 and try to resolve the dispute and thereafter unless mutually agreed to have further negotiations, the parties shall proceed in accordance with the agreement entered into between them.
In view of the agreement entered into between the parties, the instant petition is disposed of, so also all the pending applications.
29. Reference is made to the decision of Hon'ble Apex Court in the matter
of Arif Azim Co. Ltd. vs Micromax Informatics FZE reported in 2024 SCC
Online SC 3212, The relevant paragraphs is quoted below :-
71 (iv) The moment 'seat' is determined, it would be akin to an exclusive jurisdiction clause whereby only the jurisdictional courts of that seat alone will have the jurisdiction to regulate the arbitral proceedings. The notional doctrine of concurrent jurisdiction has been expressly rejected and overruled by this Court in its subsequent decisions.
30. Thus, the High Court at Calcutta has the jurisdiction to decide and
entertain this application and accordingly, this court allows the said
application by appointing Hon'ble Justice Siddhartha Roy Chowdhury
(retired), a former Judge of this court to arbitrate upon the disputes between
the parties. This appointment is subject to compliance of Section 12 of the
Arbitration Conciliation Act 1996.
31. The learned Arbitrator shall fix his own remuneration as per the
schedule of the said Act.
32. AP-COM 577 of 2024 is, accordingly, disposed of.
33. There will be no order as to cost.
34. Parties are directed to act on the server copy of this judgment.
(Shampa Sarkar, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!