Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mintech Global Private Limited vs Kesoram Industries Limited - ...
2024 Latest Caselaw 3180 Cal/2

Citation : 2024 Latest Caselaw 3180 Cal/2
Judgement Date : 8 November, 2024

Calcutta High Court

Mintech Global Private Limited vs Kesoram Industries Limited - ... on 8 November, 2024

Author: Sabyasachi Bhattacharyya

Bench: Sabyasachi Bhattacharyya

                      In the High Court at Calcutta
                   Ordinary Original Civil Jurisdiction
                              Original Side
                          (Commercial Division)

The Hon'ble Justice Sabyasachi Bhattacharyya

                       EC 335 of 2023
                   IA NO: GA-COM/2/2024
              MINTECH GLOBAL PRIVATE LIMITED
                             VS
        KESORAM INDUSTRIES LIMITED - CEMENTDIVISION

                                    With

                        AP-COM 334 of 2024
                    KESORAM INDUSTRIES LIMITED
                               VS
                  MINTECH GLOBAL PRIVATE LIMITED

                                    With

                    AP-COM 335 of 2024
              MINTECH GLOBAL PRIVATE LIMITED
                            VS
        KESORAM INDUSTRIES LIMITED -CEMENT DIVISION

                                    With

                        AP-COM 563 of 2024
                    KESORAM INDUSTRIES LIMITED
                               VS
                  MINTECH GLOBAL PRIVATE LIMITED

    For the claimant/award-holder   :      Mr. Kalyan Bandopadhyaya, Sr. Adv.,
                                           Mr. Sirsanya Bandopahyaya, Adv.,
                                           Mr. Avishek Guha, Adv.,
                                           Mr. Rahul Kr. Singh, Adv.,
                                           Mr. Subhajit Das, Adv.

    For the
    award-debtor/
    Kesoram Industries Ltd.         :      Mr. S. N. Mookherjee, Sr. Adv.,
                                           Mr. Mainak Bose, Adv.,
                                           Mr. Arvind Jhunjhunwala, Adv.,
                                           Mr. Debjyoti Saha, Adv.,
                                           Mr. Anirud Goyal, Adv.,
                                           Mr. S. J. Mookherjee, Adv

    Hearing concluded on            :      05.10.2024

    Judgment on                     :      08.11.2024
                                     2




     Sabyasachi Bhattacharyya, J:-



1.   AP-COM No. 334 of 2024 has been filed under Section 34 of the

     Arbitration and Conciliation Act, 1996 (for short "the 1996 Act"), by

     Kesoram Industry Limited, the respondent in the Arbitral Proceedings

(hereinafter referred to as the "respondent") whereas Mintech Global

Private Limited has filed AP-COM No.335 of 2024 challenging a

different portion of the same award, being the claimant in the Arbitral

Proceeding (hereinafter referred to as the "claimant"). Both the said

challenges have been preferred against the same award whereby some

of the claims and counter claims have been allowed by the Arbitral

Tribunal (AT) comprised of three members.

2. The short backdrop of the case is that an agreement was entered into

in writing on January 27, 2016 between the parties, whereby the

claimant was to set up and commission a manufacturing unit to make

and produce the end products of cement ready mix mortar, AAC

blocks, fly ash bricks and allied products as per requirement of the

respondent and to manufacture, make and deliver such end products

to the respondent.

3. A dispute having arisen between the parties following the issuance of

two letters dated March 7, 2017 and March 8, 2017 by the respondent

to the claimant asking the latter to stop further manufacture and

production of the end products, the arbitral proceeding was initiated

by the claimant alleging that the termination was invalid and making

several claims, inter alia towards outstanding sum and interest, future

commitment charges, loss of future earning and ancillary reliefs. The

respondent, on the other hand, took out a counter claim with the

statement of defence, praying for recovery of mobilization advance and

interests, damage to reputation, recovery of commitment charges

allegedly paid under mistaken belief and fraudulent inducement and

damages due to breach.

4. By the impugned arbitral award dated March 20, 2023, the majority

members of the AT granted the claims towards outstanding sum and

interest at the rate of 9 per cent per annum from March 2017 till the

date of the award, future commitment charges and costs to the tune of

Rs.3.50 Crore. On the other hand, the counter claims of recovery of

mobilisation advance and interest thereon at the same rate of 9 per

cent per annum were also granted. Being aggrieved by the respective

portions of the award affecting them, both the parties have preferred

the present challenges.

5. Learned senior counsel for the respondent seeks to defend the

termination of contract on the ground that the AT failed to advert to

several subsequent communications between the parties dated April

24, 2017, May 10, 2017 and August 7, 2017, which according to the

respondent disclosed the discussions between the parties regarding

the terms of exiting the contract in terms of the contractual clauses.

The AT placed stressed only on the March 7, 2017 communication

and held that the termination was invalid. It is argued that the

clauses of the agreement indicate that the same could be determined

at will with prior six months‟ notice. It is contended that the

communications between the parties clearly show that the parties

chose to exit the contract, rendering the requirement of prior notice

academic.

6. Secondly, it is argued that the commitment charges could at best be

granted till the expiry of six months after the notice since the contract,

by its very nature, was determinable at will. The AT went beyond its

jurisdiction and re-wrote the contract by granting future commitment

charges for a period of ten years from the respective dates of

commencement in respect of the different end products which, in any

event, would take such award beyond the date of expiry of the

agreement itself.

7. It is further argued that the claimant failed to produce sufficient

documents in support of its claim of damages and in the absence of

any proof in that regard, the provisions of Sections 73 and 74 of the

Contract Act come into play and the claim ought to have been

dismissed.

8. Further, learned senior counsel appearing for the respondent submits

that it was the claimant‟s duty to mitigate the loss. In the absence of

any pleading of proof as to mitigation of loss by the claimant, no

compensation could be granted under any of the heads of claims.

9. It is next argued by the respondent that the Minimum Assured

Production (MAP) as per Clause 1.7 of the contract was not met by the

claimant and as such, there was no scope of the claimant seeking

future commitment charges. The commitment charges would be

conditional upon the claimant producing the minimum assured

quantity and making the same available for consumption by the

respondent. Having not done so and having not proved the

commencement date of commercial production, none of the claims in

that regard ought to have been granted.

10. Learned senior counsel for the respondent further argues that the

contractual rate on interest on mobilisation advance was 14.50 per

cent per annum but only 9 per cent was granted, which is also

contrary to the agreement between the parties.

11. Moreover, since both the parties‟ claims were partially granted, the

burden of entire costs ought not to have been imposed on the

respondent alone.

12. Learned senior counsel cites Associate Builders v. Delhi Development

Authority reported at (2015) 3 SCC 49 and Ssangyong Engineering and

Construction Co. Ltd. v. National Highway Authority of India (NHAI)

reported at (2019) 15 SCC 131 in support of the proposition that an

unreasoned award violates the fundamental policy of Indian law and

amounts to patent illegality under Section 34 of the 1996 Act. Non

consideration of vital evidence tantamounts to perversity, on which

ground the award ought to be set aside insofar as the claimant‟s

claims are concerned.

13. Learned senior counsel next cites Kailash Nath Associates v. Delhi

Development Authority and another reported at (2015) 4 SCC 136 for

the proposition that if the contract specifies a sum for the breach or as

a penalty clause, reasonable compensation can be granted,

irrespective of actual damage, not exceeding the stipulated amount.

14. Mahanagar Telephone Nigam Limited v. Tata Communications Ltd.,

reported at (2019) 5 SCC 341, is next cited for the contention that

under Section 74 of the Contract Act, compensation for breach is

limited to liquidated amount or stipulated penalty and genuine pre-

estimate of damages with proof of actual damage is required for grant

of such damage, unless such proof is difficult or impossible. Here, the

clauses of the contract specifies liquidated damages for delays in

delivery, installation and commissioning with penalties, which ought

to have been adhered to by the AT.

15. Learned senior counsel cites Unibros v. All India Radio reported at

(2023) SCC OnLine SC 1366 where the Supreme Court laid down the

requirements for grant of claims relating to profit, opportunities and

the like. Delay in completion of contract which is not attributable to

the claimant, the claimant‟s status as an established contractor

handling substantial projects and credible evidence to substantiate

the claim of loss of profitability are prerequisites for such ground.

16. Learned counsel next cites Cargill International SA v. Bangladesh

Sugar and Food Industries Corp., a Queen‟s Bench decision of England

reported at (1996) 4 AllER 563, and the judgment of the court of

appeal from the same, reported at (1998) 1 WLR 461, for the

proposition that performance bonds in contracts do not represent

estimate of damages; rather, those guarantee due performance.

Additional damages beyond the bond cannot be granted. Additional

damages, if any, in respect of recovery of overpayments can be

pursued separately.

17. Learned senior counsel also relies on Murlidhar Chiranjilal v.

Harishchandra Dwarkadas and another reported at (1961) SCC OnLine

SC 100 and argues that the damages for breach place the injured

party in a position as if the contract was performed. However, the

injured party must also mitigate its losses. In a Bombay High Court

decision in the matter of M/s Auto Craft Engineers v. Akshar

Automobiles Agencies Private Limited, it was also reiterated that

mitigation efforts are to be demonstrated by the claimant.

18. In Indian Oil Corporation Ltd. v. Amritsar Gas Service and others,

reported at (1991) 1 SCC 533, it was held by the Supreme Court that if

the agreement is revocable, the only relief if there is an invalid

termination is compensation for the period of notice.

19. Dakshin Haryana Bijli Vitran Nigam Ltd. v. Navigant Technologies

Private Limited reported at (2021) 7 SCC 657 is cited for the

proposition that the grounds in a dissenting opinion can be set up as

good grounds for challenging an award.

20. Learned counsel next cites Union of India v. Bright Power Projects

(India) Pvt. Ltd. reported at (2015) 9 SCC 695 and argues that the AT

may award interest from the date of cause of action commencement

till the date of award, subject only to agreement by parties. Delhi

Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation reported

at (2022) 9 SCC 286 is relied on to argue that it is the discretion of the

AT under Section 31(7) of the 1996 Act whether to grant interest or

not and, if so, for what period and what amount, subject to the

agreement.

21. Learned counsel next argues that the proposition that the AT cannot

re-write a contract is a fundamental principle of justice and the AT

cannot interpret beyond the scope of the contract. In support of such

contention, the following judgments are cited:

i) PSA SICAL Terminals Private Limited v. Board of Trustees of V.O.

Chidambranar Port Trust Tuticorin and Others), reported at 2021

SCC OnLine SC 508;

ii) South East Asia Marine Engineering & Constructions Limited

(SEAMEC LTD.) v. Oil India Limited, reported at (2020) 5 SCC

164;

iii) Indian Oil Corporation Limited v. Shree Ganesh Petroleum,

reported at (2022) 4 SCC 463.

22. Refuting the arguments of the respondent, learned senior counsel

appearing for the claimant contends that the termination itself being

invalid, the provision in the contract for repayment of mobilisation

advance and interest thereon were automatically scrapped and hence,

unlawfully granted in the award.

23. It is contended that the claimant was in no way responsible for less

production, if any, as the respondent could not market the minimum

assured quantity in terms of contract. It is argued that the respondent

paid the commitment charges without demur till June, 2017 without

any denial of liability and as such, cannot now claim a refund of the

same.

24. Learned senior counsel relies on the views of the third Arbitrator, who

authored the dissenting opinion, to argue that there were sufficient

materials on record to grant future earnings as claimed by the

claimant.

25. It is argued that the termination being illegal, the claimant was very

much entitled to future commitment charges as well.

26. Learned senior counsel for the claimant then takes the court

elaborately through the materials on record and the evidence in

support of his contention that there was strong material basis to

justify the grant of future commitment charges and the outstanding

payments as well as the interest claims of the claimant.

27. It is contended that there were four components of commitment

charges, being salary and wages, interest on capital (including

working capital), depreciation and sixteen per cent of franchise

manufacture‟s margin, all of which were quantifiable amounts and

sufficiently substantiated by evidence. The commitment charges were

granted on the basis of the revised cost sheets for calculation provided

by the respondent itself to the claimant on May 5, 2017 post-

termination of the contract and were granted on the basis of the input

of material consumption as stated by the respondent‟s witness no.1

(RW1).

28. No reason was attributed by the respondent at any point of time for

asking the claimant to stop production, nor was any clear termination

intended to be conveyed.

29. Learned senior counsel appearing for the claimant cites UHL Power

Company Ltd. v. State of Himachal Pradesh reported at (2022) 4 SCC

116 and Associate Builders v. Delhi Development Authority reported at

(2015) 3 SCC 49 for the proposition that the AT is the final authority

to interpret a contract.

30. Konkan Railway Corporation Ltd. v. Chenab Bridge Project undertaking

reported at (2023) 9 SCC 85 and Parsa Kente Collieries Ltd. v.

Rajasthan Rajya Vidyut Utpadan Nigam Ltd. reported at (2019) 7 SCC

236 are relied on for the proposition that a possible view of the AT in

respect of quantity and quality of evidence cannot be interfered with

under Section 34 of the 1996 Act.

31. It is argued that if compensation is not by way of penalty or

unreasonable, the same can be awarded if there is a genuine pre-

estimate by the parties, for which contention learned senior counsel

cites Oil & Natural Gas Corporation Limited v. Saw Pipes Ltd., reported

at (2003) 5 SCC 705.

32. In Tarapore & Company v. Cochin Shipyard Ltd., Cochin and Another

reported at (1984) 2 SCC 680, the Supreme Court held that if an

agreement is predicated upon an agreed fact situation, it becomes

irrelevant or otiose to the extent that it ceases.

33. The claimant cites A.T. Brij Paul Singh and others v. State of Gujarat,

reported at (1984) 4 SCC 59 in support of the contention that the

expectation of profit is implicit in works contracts and the margin of

profits depends on facts. In the present case, Annexure-I to the

agreement stipulates 16% as the manufacturer‟s margin and thus,

future earnings ought to have been granted.

34. Mitigation of loss is a question of fact and was not raised before the

AT. Hence, the same cannot be raised for the first time in the present

challenge under Section 34, for which proposition learned senior

counsel cites MMTC Ltd. v. H.J. Baker& Bros. Inc., reported at 2009

SCC OnLine Del 2143.

35. Learned senior counsel for the claimant also relies on Bombay

Housing Board (Now The Maharashtra Housing Board) v. Karbhase

Naik & Co., Sholapur, reported at (1975) 1 SCC 828 for the argument

that if a written notice is agreed upon for the purpose of termination,

failure to issue the same entitles the other party to compensation.

36. Radhey Shyam Pandey v. Union of India, reported at 2022 SCC OnLine

Cal 683 is cited for the contention that if a notice is required by the

agreement, non-service of the same renders the letter of termination

fall foul of the contract.

37. The claimant relies on Delhi Metro Rail Corporation Limited v. Delhi

Airport Metro Express Private Limited, reported at (2024) 6 SCC 357 for

the proposition that conclusions based on no evidence or ignoring vital

evidence are perverse, amounting to patent illegality under Section

34(2)(b)(ii) and violate Section 28(3) of the 1996 Act.

38. Ssangyong Engineering (supra) is also relied on for the proposition that

an addition or alteration of contract cannot be imposed on an

unwilling party by the AT; if so, it would be contrary to fundamental

principles of justice as understood in India and would shock the

conscience of the court.

39. Patel Engg. Ltd. v. North Eastern Electric Power Corpn. Ltd., reported at

(2020) 7 SCC 167 is relied on by the claimant for the proposition that

if the respondent is held liable to pay commitment charges, future

commitment charges cannot also be refused.

40. It is, thus, argued that the award should be set aside to the extent

that future earnings were not awarded to the claimant and sustained

in respect of the rest.

41. Having heard the parties, the court comes to the following

conclusions:

42. The scope of interference under Section 34 of the 1996 Act has been

quite clearly settled by the Supreme Court, as also reflected in the

judgments cited by both parties. Associate Builders (supra) and UHL

Power Co. Ltd. (supra) make it abundantly clear that the AT is the final

authority to interpret a contract and Konkan Railway Corpn. Ltd.

(supra) and Parsa Kante (supra) also lay down that a possible view of

the AT regarding quantity and quality of evidence cannot be interfered

with.

43. Ssangyong Engineering (supra) and Associate Builders (supra) have

been relied on by both parties. In fact, there cannot be any quarrel

with the proposition that if there is a perversity in the award insofar

as the non-consideration of vital evidence is concerned, the same

tantamounts to violation of the fundamental policy of Indian Law as

well as gives rise to a patent illegality, which is a sufficient ground for

interference under Section 34 of the 1996 Act.

44. Considered in the above backdrop, certain crucial aspects emerge as

determinants in the present case, the first of which is whether the

termination of contract was valid. Although Clause 5 of the agreement

has been relied on by the claimant, the same merely provides that the

respondent could not have the right to the manufacturing unit or

material stock, etc., in the event of termination. The said clause, thus,

has no bearing on the actual termination or its pre-conditions.

45. Rather, Clause 1.11 of the agreement is the exit clause which provides

that whichever party withdraws from its respective contractual

obligations under the agreement within the lock-in period [10+6 years,

as provided in Clause 1.10(A)], such party shall fully indemnify the

other party as per the considerations set out in Annexure-III to the

agreement. Thus, Clause 1.11 permits both parties to withdraw from

the agreement at will, which overrides the default tenure of 10 years

(with a possible extension of another 6 years, if agreed mutually).

46. However, Clause 1.11 subjects such exit to the conditions stipulated

in Annexure-III to the agreement. Annexure-III provides two separate

situations, respectively where the first and the second party to the

contract so exits.

47. In the present case, since the respondent (first party) chose to

withdraw from the contract, Clause 2 of Annexure-III applies. Sub-

clause (a) of Clause 2 provides that if the second party (here, the

claimant) agrees to retain manufacturing facility, it will have to return

the balance mobilization advances along with any pending interest

within 1 month from the end of the notice period. Sub-clause (b)

stipulates that if it does not so wish, the facility shall be dispose of

and the mobilization advance settled as per the illustrations therein.

48. Since the claimant opted for the first option of retaining the

manufacturing facility, which is abundantly clear from the materials

on record, there cannot arise any question of disposal of the facility.

49. The exit mechanism and compensation scheme in Annexure-III also

stipulates that if any party wishes to terminate the contract during its

pendency, it has to give the other party six months‟ notice in writing.

The notice period would be deemed to start from the date of

acknowledgment.

50. Thus, it is seen that a prior notice of six months is a mandate

qualifying the determination of contract at will by either party.

Admittedly, there has not been issued any such prior notice, since the

respondent proceeds on the premise that the communication dated

March 7, 2017, asking the claimant to stop production was the

termination notice.

51. Although the AT has observed that the communications dated March

7, 2017 and March 8, 2017 do not clearly disclose the intention to

terminate, the subsequent discussions between the parties, as elicited

from the subsequent correspondence between the parties which are

also part of the record, go on to show that both parties proceeded on

the premise that it was a termination nonetheless.

52. Also, the AT itself directed refund of mobilization advance and interest

thereon, thereby assuming that the agreement between the parties

stood terminated.

53. However, although the modalities of the exit process might have been

discussed between the parties, the claimant, at no point of time,

waived the mandatory contractual requirement of a prior notice of six

months. Hence, it cannot but be said that the termination of the

agreement, in the absence of such a prior notice, was invalid to such

extent.

54. The next question which follows necessarily is whether future

commitment charges could be granted beyond the six months‟ notice

period.

55. Such aspect has been discussed elaborately by the Supreme Court in

the Amritsar Gas case. As per the said judgment, if an agreement is

otherwise revocable, in the event of an invalid termination, the

compensation can be granted only for the period of notice.

56. Such logic is self-evident in the context of the instant lis, since it was

always open for both parties to exit from the contract at will by issuing

a termination letter at any point of time during the pendency of the

contract. No separate reasons were to be assigned for doing so,

making the contract determinable at will. The only rider was to issue

a six months‟ prior notice, which has not been done by the respondent

in the present case. The AT could not look beyond the said mandatory

notice period to assess any entitlement of the claimant beyond the

said period since in any event, it was always open for the respondent

to exit the contract at will.

57. Even if a prior notice was given, the agreement would come to an end

within six months from the same. In the present case, such six

months commenced from March 7, 2017, which was the date

construed to be the date of stoppage of production, never to be

resumed again. In fact the parties, by their subsequent conduct,

made it evident that both of them proceeded on the premise that the

March 7, 2017 communication tantamounted to the expression of

interest by the respondent to exit the contract in terms of Clause 1.11.

58. Even if a notice was given on the date of termination, after the lapse of

six months therefrom, the claimant could not have any further

entitlement on the strength of the contract since all contractual rights

would have come to a dead-end then.

59. Hence, the AT committed patent illegality in acting contrary to the

proposition laid down in Amritsar Gas (supra) to grant future

commitment charges much beyond the said six-months period.

60. The proposition of Patel Engineering (supra) is not applicable in the

present case in view of the agreement here being determinable at will

by either of the parties. Thus, although the respondent could be held

liable for commitment charges during the six months‟ notice period

subsequent to the termination, there was no scope of grant of future

earning or future commitment charges.

61. The Supreme Court has repeatedly held, as reflected in Ssangyong

Engineering (supra) as well, that the AT cannot deviate from the terms

of the contract. In fact, such proposition is premised on Section 28(3)

of the 1996 Act which provides that while deciding and making an

award, the Arbitral Tribunal shall, in all cases, take into account the

terms of the contract and trade usages applicable to the transactions.

62. Moving on to the issue of refund of mobilization advance, the same is

clearly governed by Annexure-III of the agreement.

63. Annexure-II clearly provides in respect of all the end products that

interest would be charged on the mobilization advance repayment at

the rate of 14.50% on the reducing balance of the principal. Notably,

the Tribunal held at Page No.120 of the award that the claimant was

contractually liable to return the mobilization advance to the

respondent with interest at the rate of 14.50% on reducing balance on

principal and further concluded that accordingly, the claimant was

held liable to pay to the respondent the said amount on account of

mobilization advance with interest "at the said rate" from March 7,

2017 till repayment. However, all on a sudden the AT deviated from

its own finding in the concluding portion and granted interest at the

rate of 9% per annum on the outstanding amount awarded from

March, 2017 till the date of award. The direction to pay interest till

the date of the award and not till the repayment, however, is

understandable, since it is covered by Section 31(7), sub-clauses (a)

and (b) of the 1996 Act.

64. The AT, under Sections 31(7)(a), has the discretion to impose interest

at such rate as it deems reasonable only when there is no agreement

otherwise between the parties. Hence, in the present case, the AT was

denuded of such discretion to reduce the rate interest to 9% per

annum on mobilization advance in the teeth of the specific agreement

between the parties, as evidenced in Annexure-III, stipulating the rate

of interest to be 14.5% per annum. Thus, the same tantamounted to

a deviation from the contract, which is violative of the principle laid

down in Ssangyong Engineering (supra) as well as Section 28(3) of the

1996 Act. In addition, the said reduction is also contrary to Section

31(7)(a) of the 1996 Act, thus, rendering such reduction patently

illegal on the face of it and accordingly amenable to interference under

Section 34 of the 1996 Act.

65. Additionally, the conclusion of 9% rate of interest is contrary to the

A.T.‟s own immediately earlier finding that the claimant was liable to

pay interest at the contractual rate of 14.50% per annum. This

amounts to perversity, which comes within the purview of „patent

illegality‟, amenable to interference under Section 34 of the 1996 Act

as well.

66. Insofar as the commitment charges already paid by the respondent

are concerned, the Tribunal did not direct refund of the same. Such

decision on the part of the AT was justified. The respondent based its

claim of refund on alleged mistaken belief and fraudulent inducement,

none of which were specifically pleaded or proved by the respondent.

That apart, the respondent, with its eyes open, participated in the

business transaction and paid commitment charges during the notice

period upon bills being raised by the claimant, much after the

termination, and is thus estopped from challenging the same, having

not raised any demur at the relevant point of time.

67. Insofar as the allegations and counter allegations regarding not

meeting the Minimum Assured Production is concerned, Clause 1.7 of

the agreement has to be looked into. Notably, the caption of the said

Clause is "Minimum Assured Production" and not „Minimum Assured

Consumption/Purchase‟. Thus, the minimum assured production is

seen from the end of the manufacturer/claimant, who has to meet the

said requirement, and not the respondent.

68. Also, the language of Clause 1.5 defines the scope of work as

"manufacture, making and delivering the end products" to the

respondent as per the latter‟s requirement. Since Clause 1.7 defines

minimum assured production as the minimum assured quantity of

end products, such assurance is not linked to the consumption by the

respondent but to the manufacture and delivery of the end product.

69. Hence, it was incumbent upon the claimant to meet the minimum

assured production. The claimant, however, has virtually admitted

that such requirement was not met, although seeking to shift the

blame to the respondent.

70. Seen from the opposite perspective, as per Clause 1.10(B) of the

contract, the respondent, in order to be liable to pay commitment

charges, must utilize the claimant‟s manufacturing unit capacity to

100% before looking at third parties for the same or similar products.

71. Hence, the "commitment", which is the essential component and pre-

requisite of "commitment charges", can arise only when the Minimum

Assured Production is met by the claimant and made available for

being utilized by the respondent. Hence, there was no scope of grant

of future commitment charges, since no present basis for enforcing

such commitment on the part of the respondent and the associated

charges has been made out by the claimant at any point of time.

72. Accordingly, there was no conceivable reason for the AT to grant

future commitment charges.

73. On such count, the decision of the AT is perverse, having overlooked

the lack of evidence in that regard, the composite effect of the clauses

of the contract insofar as the MAP is concerned (from which

contractual clauses the AT thus deviated), as well as the factor that no

future commitment charges or future earnings could be granted at all

beyond the notice period.

74. In addition, mitigation of loss, contrary to the argument of the

claimant, need not have been pleaded or proved by the respondent in

the first place. A composite reading of Sections 73 and 74 of the

Contract Act implicitly imposes the burden of proof on the claimant in

respect of mitigation of loss, making it a pre-requisite and an

inseparable component of a claim for damages. In the present case,

the claimant has not pleaded any such mitigation of loss, nor is there

any clear finding in the impugned award to that extent. In fact, for a

prolonged period, by virtue of the interim order passed by the Court,

the claimant was permitted to sell its end products without using the

brand name of the respondent, thus impliedly releasing the

respondent from the reciprocal commitment to be bound to the

products manufactured by the claimant. The principle laid down by

the Supreme Court in M/s Murlidhar Chiranjilal (supra) and the

Bombay High Court in M/s Auto Craft Engineers (supra) are thus fully

applicable in such context.

75. Hence, in the absence of consideration of such factors, the grant of

future commitment charges by the AT was patently illegal and ought

to be set aside as well.

76. Insofar as future earnings is concerned, the same logic as that which

applies to future commitment charges is applicable, and the AT was

justified in not granting future earnings to the claimant.

77. The Supreme Court has clearly set out the contours of interference

with an arbitral award, holding time and again that the AT cannot

lend an interpretation beyond the scope of the contract and cannot re-

write the contract itself. In PAC SICAL Terminals (supra), South-East

Asia Marine Engineering (supra) and M/s Shree Ganesh Petroleum

(supra), such proposition has been reiterated repeatedly, apart from

the same proposition being echoed in Ssangyong Engineering (supra).

78. Lastly, insofar as the grant of costs is concerned, the AT has reduced

the claim of the claimant in that regard and granted Rs.3.50 crore

instead of Rs.4,38,12,647/- as claimed originally, which claim was

based on a schedule of costs, which the respondent failed to offer.

Such reduction itself shifts the cost partially to the claimant. In any

event, it was well within the discretion of the AT to grant costs and no

patent illegality or element sufficient to shock the conscience of court

is found in such imposition of costs. As such, the cost component

ought not to be interfered with under Section 34 of the 1996 Act

merely because a different view than that of the AT is possible.

79. In view of the above discussions, the impugned award is liable to be

set aside partially.

80. Accordingly, AP-COM 334 of 2024, AP-COM 335 of 2024 and AP-COM

563 of 2024 are disposed of, thereby setting aside the impugned

award to the extent of Claim No.(iii) to the tune of Rs. 127,12,64,892/-

towards future commitment charges and also modifying the award to

the extent of Counter Claim No.(ii) inasmuch as the interest payable

on the mobilization advance from March, 2017 till the date of award is

to be calculated not at the rate of 9% per annum but at the rate of

14.50% per annum. The said award accordingly stands modified to

such extent.

81. EC No.335 of 2023 along with GA-COM 2 of 2024 shall now be placed

before the regular Bench having determination to take up such

matters. Liberty is granted to the parties to mention the matter before

such Bench.

82. There will be no order as to costs.

83. Urgent certified server copies, if applied for, be issued to the parties

upon compliance of due formalities.

( Sabyasachi Bhattacharyya, J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter