Citation : 2024 Latest Caselaw 2236 Cal/2
Judgement Date : 2 July, 2024
IN THE HIGH COURT AT CALCUTTA
ORIGINAL CIVIL JURISDICTION
ORIGINAL SIDE
The Hon'ble Justice Sabyasachi Bhattacharyya
A.P. NO. 152 of 2021
Mala Roy & Others
-Vs-
M/s. Jai Balaji Industries Limited
For the petitioners : Mr. Meghajit Mukerjee, Adv.
Ms. Sonia Das, Adv.
For the respondent : Mr. Abhrajit Mitra, Sr. Adv.
Mr. Sarvapriya Mukherjee, Adv.
Mr. Uttam Sharma, Adv.
Hearing concluded on : 25.06.2024
Judgment on : 02.07.2024
Sabyasachi Bhattacharyya, J:-
1. The present application under Section 11(6) of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as, "the 1996 Act")
arises out of the disputes between the parties in connection with an
Agreement for Settlement dated May 12, 2013. The
petitioners/creditors, pursuant to purchase orders of iron-ore and
fines placed by the respondent/debtor, had sold such materials to the
respondent. Subsequently, an amount became due by way of sale
price. The parties decided to resolve the issues by adjustment of the
debts and agreed to a repayment schedule by the Agreement-in-
question for realization of dues of the petitioner to the tune of Rs.
1,90,36,023/-.
2. Clause 9 of the Agreement contains the repayment schedule which
has five (05) components.
3. In sub-clause (a), the debtor/respondent was to pay an amount of Rs.
25,00,000/- at the time of signing of the agreement.
4. In sub-clause (b), it was stipulated that post-dated account payee
cheques of Rs. 20,00,000/- each would be handed over by the debtor
to the creditor.
5. As per Clause (c), five separate purchase orders of one rake each of a
particular size of iron-ore would be placed to the creditor/petitioner by
the debtor/respondent.
6. In sub-clause (d), it was provided that the said five cheques would be
presented to the Bank one by one by the creditor, each on the date of
actual loading of each rake.
7. Sub-clause (e) mentions that a sum of Rs. 50,10,171/- payable by one
M/s. Emars Mining and Construction Pvt. Ltd. to the
respondent/debtor would be adjusted by the debtor against the dues
payable to the creditor in terms of the agreement to be entered into
between M/s. Emars Mining and Construction Pvt. Ltd. and the
debtor/respondent.
8. The petitioners claim that due to closure of mining operations during
the period between May 16, 2013 (soon after the agreement) and the
later part of the year 2019, in view of the prevalent Government
Orders and restrictions regarding direct purchase which were beyond
the control of the petitioner, iron-ore could not be supplied by the
petitioners in terms of the agreement.
9. On December 7, 2019, the petitioner requested the respondent to
issue purchase orders as per the agreement and make payment of the
balance amount by issuing post-dated cheques. The respondent
refused to do so, thereby giving rise to the dispute between the
parties.
10. On July 15, 2020, the petitioners communicated in writing to the
respondent for a mutual discussion to resolve the disputes in terms of
the agreement. The same having failed even after repeated
correspondence, the petitioner invoked the Arbitration Clause in the
Agreement vide a Notice under Section 21 of the 1996 Act dated May
12, 2013, naming an Arbitrator.
11. The respondent denied the allegations and disputed that any
arbitrable dispute exists between the parties by replies dated
September 8, 2020 and September 30, 2020, sent in response to the
petitioners' letters dated July 15, 2020 and August 17, 2020 as well
as September 9, 2020.
12. Learned counsel for the petitioners submits that in the agreement, in
Clause 12, a force majeure provision was included, which, inter alia,
stated that neither party would be liable for any breach of the
agreement for reasons beyond the control and capacity of the
creditor/petitioner if the production and/or despatch would have been
sustained, delayed and/or not enforced in time due to the bar or rules
or act of any regulatory bodies/Government Authorities, etc. The
petitioner seeks to take advantage of the said clause and contend that
it was not possible for the petitioner to act on the agreement before
December, 2019.
13. It is next argued that although there might have been a minor error in
the Arbitration Clause, that is, Clause 13 inasmuch as it referred to
the validity of the agreement as the subject-matter of the probable
dispute, the language of the same, if read comprehensively, indicates
that any dispute or difference between the parties arising out of or in
relation to the agreement would be the subject-matter of arbitration.
As such, an Arbitrator ought to be appointed. In support of his
contentions, learned counsel cites several judgments which will be
considered at the appropriate time below.
14. Learned senior counsel for the respondent/debtor argues that the
subject-matter of the dispute relates to performance of the agreement
and does not touch the validity of the same, such validity being
undisputed. Hence, the dispute having not touched the validity,
which furnishes the only scope of arbitration as per Clause 13 of the
Agreement, the present application ought to be dismissed and the
parties are required to resolve the disputes not by way of an arbitral
proceeding but before a regular court of law/ forum.
15. Learned senior counsel next argues that the subject-matter of the
dispute is "dead wood". It is argued that the dispute sought to be
raised afresh by the petitioner has lost relevance long back and is
palpably barred by limitation, since the agreement was entered into as
long back as on May 12, 2013 and the first claim was made only in
December, 2019.
16. Secondly, in view of the respondent having not placed any purchase
order in terms of Clause 9(c) with the petitioner, no dispute has arisen
at all within the contemplation of the agreement.
17. It is argued that the force majeure clause is not applicable in the
present case at all. It is argued that the contention made at the bar
cannot be a relevant consideration for reading the force majeure clause
into the acts of the petitioner.
18. It is also contended that the Arbitration Clause in an agreement must
be strictly construed and the presumption would be that the relief of
the parties lies before a regular Civil Court and not before the Arbitral
Tribunal. It is argued that presumption lies in favour of the civil
court's jurisdiction and not the ouster of the same.
19. Learned senior counsel also cites several judgments which will also be
considered at the relevant juncture while deciding the issues.
20. To adjudicate the matter, the following issues fall for consideration:-
(i) Whether the present dispute falls within the ambit of the
Arbitration Clause;
(ii) Whether the claim is ex facie time-barred;
(iii) Whether the petitioner has any cause of action to refer to
arbitration.
21. The above issues are decided as follows:
Issue:
(i) Whether the present dispute falls within the ambit of the
Arbitration Clause.
22. To decide this issue, the Arbitration Clause (Clause 13) and the Forum
Selection Clause (Clause 14) in the Agreement itself are to be
considered. The said Clauses are set out below:
"13. AND WHEREAS in case of any dispute or any different between the parties arising out of or in relation to the Agreement as to the validity of this Agreement the same shall be resolved by mutual discussion. It both the parties fail to do so then the matter shall be referred to the „Arbitration‟ as per the "Arbitration and Conciliation Act, 1996". The cost of „Arbitration‟ shall be borne by both the parties equally and the place of „Arbitration‟ will be in Kolkata.
14. AND WHEREAS in case of any dispute or any difference between the parties arising out of or in relation to the Agreement shall be subject to the exclusive jurisdiction of the Courts in Calcutta."
23. The scope of reference to arbitration as per Clause 13 is in respect of
any dispute or difference between the parties "arising out of or in
relation to the Agreement". Immediately thereafter, the expression
used is "as to the validity of this Agreement". The respondent argues
that the scope of reference is restricted to the validity of the agreement
only and the previous words in the said Clause only qualify the same.
On a plain reading of the Clause, undoubtedly, it is seen that the
expression "arising out of or in relation to the Agreement" is suffixed
by the term "as to the validity...". However, on a closer scrutiny, it
becomes obvious that in the event the intention of the parties was only
to cover disputes relating to validity, the previous expression "arising
out of or in relation to" would be completely superfluous, since, in
such event, the expression "and whereas in case of any dispute or any
difference between the parties to the validity of this Agreement" would
suffice. However, it is a cardinal rule of construction to avoid
attributing redundancy to any of the expressions used in a document.
Purposive interpretation is a recognized principle of construction
where there is an iota of ambiguity. The courts, while construing a
provision, are to endeavour to give effect to all the words used in the
relevant clauses of the agreement if possible, unless such provisions
are otherwise completely unworkable.
24. Read in such context, the expressions "arising out of" and "in relation
to" are considerably wide in amplitude, encompassing disputes not
merely regarding interpretation of the different clauses of the
Agreement and issues arising directly from the Agreement but also all
issues arising incidentally, touching the Agreement. There may very
well be disputes which, although not directly relatable to the
Agreement, may arise out of it or in relation to it, covering necessary
implications and effects of the clauses in the Agreement and the rights
and liabilities of parties which can be reasonably deduced therefrom.
Issues emanating incidentally from the Agreement are also covered by
the said expressions. As such, the said phrases cannot be confined
merely to the validity of the Agreement. Such a restriction would be a
contradiction in terms, since validity of the agreement directly affects
the Agreement and cannot extend to issues otherwise arising out of it
or in relation to it, whether incidentally or whether relating to the
effects which can be inferred from the clauses thereof.
25. Thus, if the phrases "arising out of" and "in relation to" are read in
conjunction with "as to the validity", it would be an absurdity to
confine the scope of reference merely to validity of the Agreement,
which would have the necessary effect of entirely discarding the above
two expressions which have been deliberately used by the parties in
Clause 13.
26. Seen from another perspective, Clause 14, which is the Forum
Selection Clause, cannot be divorced from the Arbitration Clause so as
to stand on an entirely independent footing. The selection of a forum
cannot exist in thin air but is directly relatable to the dispute which is
to be decided by such forum. Hence, an indication of the scope of
disputes to be decided before the forum can also be derived from a
Forum Selection Clause. Conspicuously, Clause 14, which confers
exclusive jurisdiction on the courts in Calcutta, uses the expression
"in case of any dispute or any difference between the parties arising
out of or in relation to the agreement", entirely omitting the term
"validity". The Forum Selection Clause has to be read along with the
Arbitration Clause, since it does not supplant but supplements the
Arbitration Clause and qualifies the same, providing merely the forum
for redressal of the disputes which are indicated there. Hence, there
must be an identity in the ambit of disputes covered by the arbitration
clause and the forum selection clause. Otherwise, it would be absurd
and unworkable if the forum selection clause covers wider disputes
than the principal arbitration clause. Hence, Clauses 13 and 14 are
to be read together to impart meaning to each other.
27. Seen from such perspective, the obvious conclusion befitting a
reasonable mind would be that the parties deliberately agreed to refer
all disputes arising out of or in relation to the Agreement, including
those regarding validity of the Agreement, to arbitration, which would
be adjudicable by courts in Calcutta.
28. The expression "courts" has been sought to be explained by the
respondent to mean only regarding suits and not arbitration.
However, in such event, Clauses 13 and 14 would be mutually
exclusive, leading to the impossible conclusion that in the same
breath, the parties choose to refer disputes to arbitration but at the
same time provide for civil suits in the Forum Selection Clause.
Notably, the expression "court" has also been defined in the
Arbitration and Conciliation Act, 1996 and as such, may very well
mean the adjudication by courts in Calcutta in respect of the matters
referable in connection with the arbitral proceeding, where
intervention of courts is permitted under the 1996 Act, such as
Sections 9, 11, 34, 36 and 37 of the 1996 Act.
29. The respondent has cited the decision of a learned Single Judge of the
Madras High Court in the matter of H.G. Oomar Sait and another Vs.
O. Aslam Sait, reported at 2001 SCC OnLine Mad 465, where the court
quoted a judgment of 1993 where the Supreme Court observed that
honest men dread arbitration more than they dread law suits.
However, such premise itself has become obsolete upon the enactment
of the 1996 Act, in consonance with the UNCITRAL Model Code. It
has been consistently held in recent times that the endeavour of the
courts would be to interfere with an arbitral proceeding as little as
possible and to relegate all disputes to arbitration if an intention is
expressed by the parties to go for arbitration, which is a well
recognized mode of ADR (Alternative Dispute Resolution).
30. Thus, the views of courts have undergone a sea-change over the years
and the current endeavour of courts is to construe arbitration clauses
in favour of reference to arbitration where the parties have mutually
agreed to do so, rather than stultify such recourse by unnecessary
court interference. Even otherwise, the said judgment is
distinguishable on facts since there the parties had agreed to refer the
matter to arbitration during subsistence of the partnership agreement
but the court held that the same had been done only upon
dissolution, thereby traversing beyond the arbitration clause itself.
31. The respondent also cites Oriental Insurance Company Limited Vs.
Narbheram Power and Steel Private Limited, reported at (2018) 6 SCC
534. There, the court held that an arbitration clause is required to be
strictly construed and any expression of the clause must
unequivocally express the intent of arbitration. In the present case,
the unequivocal intention to refer the dispute to arbitration is not in
question but the issue is as to whether the subject-matter of dispute
falls within the scope of the arbitration clause.
32. In the said case, it was held that if a clause stipulates that under
certain circumstances there can be no arbitration and they are
demonstrably clear, then the controversy pertaining to appointment of
Arbitrator has to be put to rest. In the said case, as evidenced from
Paragraph 7 thereof, the arbitration clause had a clear negative
provision that it is clearly agreed and understood that no difference or
dispute shall be referable to arbitration as thereinbefore provided, if
the company has disputed or not accepted liability under or in respect
of the policy. The said circumstance cannot be equated with the
present case, since there is no such negative clause in the arbitration
clause herein.
33. The respondent also cites United India Insurance Company Limited
and Another Vs. Hyudai Engineering and Construction Company
Limited, reported at (2018) 7 SCC 607, where there was also a similar
clause restricting reference to arbitration if the company has disputed
or not accepted liability under or in respect of the policy. In the said
case, it was clearly agreed between the parties that the matter shall be
referred to arbitration only if the quantum was disputed, thereby
confining the reference in specific terms to disputes as to quantum
alone. In such context, the strict construction of the clause was
mandated by the Supreme Court. In the present case, however, there
is no such negative clause specifically providing in negative terms that
there would be no reference if the company has disputed or not
accepted liability in respect of the policy.
34. It is also required to be kept in mind that both the above judgments
were rendered in the context of insurance contracts where the well-
settled principle is that only disputes as to quantum are arbitrable.
Moreover, the lop-sided and unequal bargaining powers of the insurer
and an ordinary insured is also an underlying consideration in such
cases.
35. In Vidya Drolia and Others Vs. Durga Trading Company, reported at
(2021) 2 SCC 1, the Supreme Court recognized the principle of
kompetenz-kompetenz, which was left to the discretion of the court to
decide. It was observed that validity of the agreement was a sine qua
non and the court is to see whether the underlying contract contains
an arbitration clause for disputes arising between the parties, for
which it was necessary to enquire into the purpose of the arbitration
clause. In Paragraph No. 150 of the said judgment, the strict principle
rule of interpretation was reiterated, but in case of insurance
contracts.
36. It is well-settled that in case of insurance contracts, almost in all
cases, a dispute is arbitrable only if the quantum is refuted and not
otherwise. No parallel can be drawn between the principles applicable
to the present case and such proposition.
37. Again in Life Insurance Corporation of India and Another Vs. Dharam
Vir Chand, reported at (1998) 7 SCC 348, the strict rule of
interpretation in respect of an insurance contract was being
considered by the Supreme Court. A mistake of drafting was under
scrutiny there. In the present case, however, if we read the arbitration
clause by adopting purposive interpretation, even without reading into
it any mistake of drafting, all disputes or differences arising out of or
in relation to the contract, including validity, is to be inferred as the
subject-matter of arbitration.
38. The respondent also cites Indore Development Authority Vs. Shailendra
(Dead) through legal representatives and Others, reported at (2018) 3
SCC 412. The consideration therein was regarding two expressions
used in two statutes which were being interpreted by the Supreme
Court. The intendment of beneficial legislations and the effect thereof
on interpretation of statutes were being considered. As such, the
proposition laid down therein is completely irrelevant for the present
purpose.
39. On the other hand, the petitioner cites Enercon (India) Limited and
Others Vs. Enercon GMBH and another, reported at (2014) 5 SCC 1
where, in Paragraph 88, it was observed that the courts have to adopt
a pragmatic approach and not a pedantic or technical approach while
interpreting or construing an arbitration agreement or arbitration
clause. Therefore, when faced with a seemingly unworkable
arbitration clause, it is the duty of the court to make the same
workable within the permissible limits of the law, without stretching it
beyond the boundaries of recognition. A common sense approach was
preferred by the Supreme Court to give effect to the intention to the
parties to arbitrate. The arbitration clause, it was held, cannot be
construed with a purely legalistic mindset as if one is construing a
provision in a statute. Quoting Lord Diplock, it was observed that if
detailed semantic and syntactical analysis of words in a commercial
contract is going to lead to a conclusion that flouts business
commonsense, it must be made to yield to business commonsense.
40. It is to be kept in mind that the respondent was already a debtor to
the petitioner at the juncture when the agreement-in-question was
entered into between the parties. The agreement itself contemplates a
settlement of the dues by incorporating modalities for discharge of the
liability of the respondent to the petitioner, thus making it a purely
commercial agreement. Hence, commercial prudence would only be
subserved if effect is given to the intention of the parties to arbitrate,
which is evident from the Clauses 13 and 14 of the agreement
between the parties. The effort would be to facilitate resolution of the
dispute by the alternative dispute redressal mode of arbitration rather
than putting a spanner in the wheels of such resolution.
41. Also, in Visa International Ltd. Vs. Continental Resources (USA) Ltd.,
reported at (2009) 2 SCC 55, the Supreme Court observed that if there
is a clear intention of parties to go for arbitration, the matter is to be
referred to arbitration and that no party can be allowed to take
advantage of "inartistic drafting" of arbitration clause as long as such
clear intention of parties to go for arbitration in case of future disputes
is evidenced from the agreement and materials on record including
surrounding circumstances.
42. Seen from such perspective, the inevitable conclusion is that Clauses
13 and 14, read in proper perspective, takes within their fold all
disputes and differences between the parties arising out of or in
relation to the agreement including the validity of the agreement.
Hence, the first issue is decided in favour of the petitioners.
Issue:
(ii) Whether the claim is ex facie time-barred.
43. To consider the question of limitation, the case of the parties is to be
considered. The petitioners' contention is that the agreement-in-
question, which is an admitted document, was entered into on May
12, 2013. From May 16, 2013 onwards, the mines were closed,
apparently due to coal auction Circulars and Government decisions
prevailing at that juncture, which ultimately led to modalities being
set out for e-auction in respect of coal. The embargo was lifted in or
about the end of the year 2019. The petitioner, accordingly, requested
purchase orders to be issued and balance cheques to be given by the
respondent in terms of Clause 9 of the Agreement in a written
communication dated December 7, 2019, on resumption of mining
activities.
44. In order to bolster its case, the petitioner has relied on Clause 12 of
the Agreement which incorporates a force majeure provision. As per
the said Clause, neither party shall be liable for any breach of the
agreement caused by force majeure which is not in control and beyond
the capacity of the creditor (the present petitioner) if the production
and/or dispatch would have been sustained, denied and/or not
enforced in time, inter alia due to the bar or rules or act of any
regulatory bodies/Government Authorities, etc.
45. The actual facts of the case are based precisely on the said provision,
as according to the petitioner, the mining activities were stopped
between May 16, 2013 and the later part of 2019, precluding the
petitioner from giving effect to supply of iron ore as per the terms of
Clause 9 of the Agreement during the said period.
46. The veracity of such case is definitely required to be decided before the
Arbitral Tribunal on merits when the claim is ultimately filed.
However, the very arguability of the said issue justifies a reference to
arbitration, since it is well-settled that while deciding an application
under Section 11 of the 1996 Act, the court cannot enter into the
merits of the case. Even if there is an iota of doubt on the issue of
limitation, it cannot be said that the claim is ex facie barred by
limitation. In the present case, the issue of limitation is very much
arguable and requires evidence to be led and an adjudication on
merits.
47. Moreover, since there was no time-line in the Agreement, time could
not be said to be the essence of the contract, which could time-bar the
claim of the petitioner. Rather, as per the petitioners' case, the cause
of action froze by the operation of the force majeure clause till
resumption of mining activity in 2019, immediately after which the
dispute was raised and ultimately the matter was referred to
arbitration by issuing a notice under Section 21 of the 1996 Act.
48. There is nothing on record to show that the respondent ever refused to
perform its part of the Agreement. Sub-clauses (b) and (c) of Clause 9
of the Agreement cast a liability on the respondent as well, to hand
over five post-dated account payee cheques to the petitioners and also
to place five separate purchase orders of one rake each of the specified
size of iron ores to the petitioners. Hence, the liability was on both
sides and in the absence of anything to show at this stage that the
respondent completed its part of the Agreement or refused to comply
with the Agreement, it cannot be said that the cause of action arose at
any time before December, 2019.
49. Hence, this Court does not find any ex facie bar of limitation apparent
on the face of the materials before the court and, as such, even the
issue of limitation is required to be decided on merits by the
Arbitrator. Hence, this issue is also decided in favour of the
petitioners and against the respondent.
Issue:
(ii) Whether the petitioner has any cause of action to refer to
arbitration.
50. The respondent raises a question as to the cause of action having not
yet arisen at all in view of no purchase order being placed by the
respondent. The respondent argues that as such, the question of the
petitioner not being in a position to dispatch materials never arose.
51. However, it was not an available option for the respondent not to place
the purchase orders. If such an option was available in the facts of
the case, it might still have been argued that the cause of action
would arise in future and no claim arose for such future cause of
action. However, the Agreement itself, as evidenced from the different
clauses of the same, was the culmination of a previous debt of the
respondent to the petitioners. The Agreement is also captioned as an
"Agreement for Settlement" and clearly enumerates and admits the
previous dues of the respondent/debtor to the petitioner/creditor,
which were sought to be settled between the parties at an agreed
amount of Rs. 1,90,36,023/-. Thus, the Agreement itself arose from a
previous liability of the respondent towards the petitioners by way of a
modality being fixed for repayment of the debt. Clause 9 provides the
different components of such repayment schedule. However, the sub-
clauses of Clause 9 are not in chronological order, for one to happen
in order for the next to arise. Those were rather overlapping in respect
of time.
52. Sub-clause (9), regarding payment of Rs. 25,00,000/- by the debtor to
the creditor, was admittedly satisfied by such payment being made.
Sub-clauses (b) and (c) cast liability on the respondent to issue five
post-dated account payee cheques and place purchase orders for iron
ore as specified therein. A reciprocal obligation of the petitioner was
to supply such materials and to encash the cheques each on the dates
of actual loading of the rakes. Although the petitioner could not
perform its part by supplying such rakes of iron ore, at the same time,
at this stage it cannot not be ascertained whether the respondent also
complied with its part of the Agreement by issuing the cheques,
placing the purchase orders as well as adjusting the amount of Rs.
50,10,171/- due to the respondent from one M/s Emars Mining and
Construction Pvt. Ltd. with the dues payable to the
petitioner/creditor.
53. Thus, the cause of action for the present claim did not ripen, at least
prima facie, before 2019. Hence, the mere non-placement of purchase
orders by the respondent cannot entitle the respondent to take
advantage of its own wrong in non-compliance of its part of the
Agreement. Since the Agreement itself was a continuation of the
previous liability of the respondent to the petitioner, it cannot be said
that the cause of action for the claim had not fructified as no
purchase order was placed by the respondent. By doing so, the
respondent cannot take advantage of its own wrong and negate the
agreed mode of resolution of dispute, that is, arbitration, which was
clearly intended between the parties.
54. The respondent cites the judgment of Bengal Chamber of Commerce
and Industry and Others Vs. State of West Bengal and Others, reported
at (2010) SCC OnLine Cal 2553, where it was held that there cannot be
any deposition contrary to pleadings and that of The Assam Company
(India) Limited Vs. Numazar Dorab Mehta & Ors., reported at (2014) 2
CHN 200 also on the proposition that arguments from the Bar
contrary to pleadings cannot be accepted.
55. Such propositions have apparently been cited to controvert the
petitioners' plea that it was prevented by the force majeure clause from
performing its part of the agreement and consequently, invoking the
Arbitration Clause. However, at this stage, it would be premature to
decide such issue conclusively. Moreover, it is not a mere submission
from the Bar but a part of the pleadings of the petitioners in their
application as well as affidavit-in-reply which bear testimony to the
stand of the petitioners that the claim is not palpably barred by
limitation. Thus, the aforesaid judgments cited by the respondent are
entirely besides the point.
56. The line of judgments cited by the respondent regarding a new case
not being permitted to be made out in affidavit-in-reply have no direct
bearing in the present context since the "case" of the petitioners has
not yet been made out at all.
57. In an application under Section 11 of the 1996 Act and/or the
affidavits filed in connection therewith, the petitioner is not making its
claim, but only prima facie seeks to satisfy the court that a dispute
falling within the purview of the arbitration clause exists, that there is
a valid arbitration clause and the dispute is otherwise arbitrable.
58. It is beyond the competence of the court taking up an application
under Section 11 to enter into the merits of the claims at all. The
actual claim of the petitioners shall only be reflected in its statement
of claims filed before the Arbitrator and as such, at this stage it
cannot be said that the pleadings made in the affidavits of the parties
can either be believed or disbelieved or even be treated to be
comprehensive, comprising the entire case of the parties.
59. Pleadings in a proceeding under Section 11 of the 1996 Act are
intended only for the limited purpose of satisfying the court as to
existence of its essential ingredients and are not meant to be the
actual statements of claim or defence of the parties.
60. Seen in such context, the petitioners have definitely made out a prima
facie case sufficient for the purpose of Section 11 of the 1996 Act to
convince the court that there is a live cause of action which cannot be
labelled in any manner as "dead wood". Thus, the present issue is
decided in favour of the petitioners and against the respondent as
well.
61. In view of the above, all the objections taken to the application filed
under Section 11 of the Arbitration and Conciliation Act, 1996 are
turned down. The application is held to be very much maintainable.
The agreement containing the arbitration clause is admittedly valid.
An arbitration clause exists between the parties and the dispute
raised by the petitioners is covered by the said clause as well as the
forum selection clause. The dispute being otherwise arbitrable as
well, the matter is required to be referred to arbitration.
62. Accordingly, A.P. No. 152 of 2021 is allowed on contest, thereby
appointing Sri Krishnaraj Thakker, Advocate (Mobile No. -
9830116355) as the sole Arbitrator to resolve the disputes between
the parties, subject to a declaration being obtained from him under
Section 12 of the Arbitration and Conciliation Act, 1996.
63. The learned Arbitrator shall fix his remuneration in terms of the 1996
Act, read with its Schedules. It is made clear that all questions
between the parties are left open to be urged before the learned
Arbitrator.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!