Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Kakali Khasnobis vs Mrs Reeta Paul And Anr
2024 Latest Caselaw 2657 Cal/2

Citation : 2024 Latest Caselaw 2657 Cal/2
Judgement Date : 21 August, 2024

Calcutta High Court

Kakali Khasnobis vs Mrs Reeta Paul And Anr on 21 August, 2024

Author: Sabyasachi Bhattacharyya

Bench: Sabyasachi Bhattacharyya

OCD-11
                               ORDER SHEET

                             AP-COM/701/2024

                   IN THE HIGH COURT AT CALCUTTA
                 ORDINARY ORIGINAL CIVIL JURISDICTION
                        COMMERCIAL DIVISION


                           KAKALI KHASNOBIS
                                  VS
                        MRS REETA PAUL AND ANR.


  BEFORE:
  The Hon'ble JUSTICE SABYASACHI BHATTACHARYYA
  Date: 21st August, 2024.

                                                                       Appearance:
                                                            Mr. Aritra Basu, Adv.
                                                         Mr. Somnath Bose, Adv.
                                                        Mr. Shubham Khan, Adv.
                                                                ..for the petitioner

                                                      Mr. Sanjay Mukherjee, Adv.
                                                          Mr. Arghadip Das, Adv.
                                                             ..for the respondents

The Court: The present application under Section 11 of the Arbitration

and Conciliation Act, 1996 has been challenged on two-fold grounds. First, on

the ground that the same is barred by limitation and secondly, that the

petitioner did not comply with the mandatory provision of Section 11(5) and

Section 21 of the 1996 Act by issuing a prior notice to the respondents

requesting the appointment of an Arbitrator.

Insofar as the first issue is concerned, learned counsel for the

respondents places reliance on certain dates and points out that an application

under Section 9 of the 1996 Act was taken out by the petitioner on July 26,

2021 where an interim order was passed on July 27, 2021. Ultimately, the said

application was dismissed for not taking effective steps for appointment of

Arbitrator, on July 6, 2024. It is argued that the present application under

Section 11 has been filed only on July 16, 2024 and, as such, is hopelessly

time-barred.

On the issue of non-compliance of the pre-requisite of giving a notice to

the respondents for appointment of an Arbitrator, learned counsel for the

respondents cites a judgment of a learned Single Judge of the Delhi High Court

in the matter of Alupro Building Systems Pvt. Ltd. vs. Ozone Overseas Pvt. Ltd.

reported at 2017 SCC OnLine Del 7228. Learned counsel also cites a co-

ordinate Bench judgment of this Court in the matter of Sri Arun Kumar Bhunia

vs. Badal Midya reported at 2019 SCC OnLine Cal 9410.

In support of his contentions, learned counsel for the respondents also

relies on a judgment of another co-ordinate Bench of this Court in the matter

of West Bengal Power Development Corporation Limited vs. Sical Mining Limited

reported at 2022 SCC OnLine Cal 3036 and a judgment of the Bombay High

Court in Malvika Rajnikant Mehta and Others vs. JESS Constructions reported

at 2022 SCC OnLine Bom 920.

While controverting such arguments, learned counsel for the petitioner

points out that the petitioner would be entitled to the Covid-19 relaxations

granted by the Supreme Court in its judgments, which subsisted throughout

the period between March 15, 2020 and February 28, 2022.

Moreover, learned counsel points out that the non-compliance of the

provisions of Section 9 with regard to not referring the matter to arbitration

could only affect the outcome of the Section 9 application. However, insofar as

the present application is concerned, the same was filed on July 16, 2024

which in any event is before the expiry of three years from July 26, 2021, when

the Section 9 application was filed.

Insofar as the second objection is concerned, learned counsel, by placing

reliance on the invocation of arbitration clause by the petitioner dated July 20,

2021 and the reply thereto by the respondents dated August 16, 2021, submits

that the same comprised of sufficient compliance of Section 11(5) of the 1996

Act. It is argued that although the petitioner's letter dated July 20, 2021 was

addressed to the appointed Arbitrator, copies thereof were also forwarded to

the present respondents, which according to the petitioner comprised of

sufficient compliance of Section 11(5) and Section 21 of the 1996 Act.

The learned counsel for the petitioner also cites the stand taken by the

respondents in their written reply dated August 16, 2021, where the request of

the petitioner to appoint a particular person as an Arbitrator was clearly

repudiated.

Learned counsel for the petitioner relies, in turn, on a judgment of a

learned Single Judge of the Delhi High Court in the matter of De Lage Landen

Financial Services India Pvt. Ltd. vs. Parhit Diagnostic Private Limited and Others

reported at 2021 SCC OnLine Del 4160 and a coordinate Bench judgment of

this Court in Universal Consortium of Engineers Pvt. Ltd. vs. Kanak Mitra and

Another reported at AIR 2021 Cal 127.

Heard learned counsel.

Insofar as the first issue of limitation is concerned, it is evident from the

list of dates supplied by the respondents themselves that the application under

Section 9 of the 1996 Act was filed by the petitioner on July 26, 2021 on which

date, it may as such be construed, the cause of action for reference to

arbitration first arose. As the application under Section 11 has been filed on

July 16, 2024, just before the expiry of three years therefrom, it cannot be said

that the same is ex facie barred by limitation. It has been held time and again

by the Supreme Court and several High Courts that in the absence of any other

provision, the residual provision of Article 137 of the Schedule to the Limitation

Act is applicable to an application under Section 11 and as such, the period of

three years having not elapsed, it cannot be said that the present application is

time-barred.

That apart, the petitioner is also justified in arguing that the Pandemic

relaxations granted by the Supreme Court from the period between March 15,

2020 and February 28, 2022 are also applicable to the petitioner, upon which

the period in between has to be added to the limitation period. Thus, the first

objection raised by the respondents is turned down.

Insofar as the second issue is concerned, a perusal of the judgment of

the Delhi High Court in De Lage Landen (supra) shows that there were certain

other circumstances which also coloured the judgment of the Delhi High Court.

As for example, it has been narrated in the said judgment that the arbitration

clause in the said case, as worded, conferred complete discretion on the

petitioner-lender to make an appointment. The Court proceeded to observe

that in the light of the facts of the said case, it would be a non-issue as to

whether a notice under Section 21 was necessary in the said case. That apart,

the Court also took into consideration the fact that the petitioner had written to

the respondents therein independently of the unilateral invocation of

arbitration, by a communication/notice dated May 13, 2019, that it intended to

take recourse to legal proceedings under the agreement which was construed

by the learned Single Judge of the Delhi High Court as sufficient indication to

invoke the arbitration clause. Such considerations being absent here, it

cannot be said that the ratio laid down therein can be applied to the present

case in an undiluted form.

The learned coordinate Bench, in the matter of Universal Consortium of

Engineers Pvt. Ltd. (supra), had arrived at the finding that the Court was

unable to read into Section 21 any mandate to the effect that a Section 11

application will not be maintainable unless a notice under Section 21 has been

served by the petitioner on the respondent. The Court also placed reliance on

the judgment of Alupro Building Systems (Supra) in support of its observations.

Further, the learned Single Judge relied on a decision of the Apex Court in

State of Goa where it was held, according to the learned Single Judge, that an

application under Section 11 of the 1996 Act is itself a request by the petitioner

for arbitration.

However, with utmost respect, the ratio of Alupro Building Systems

appears to be a little bit different to me.

With regard to Section 21 not containing any provision that a Section 11

application will not be maintainable unless a notice under the said section was

served, the said logic does not, with utmost respect, appeal to me since

restriction, if any, in such context would be required to be embodied not in

Section 21 but in Section 11 itself.

Insofar as Alupro Building Systems (supra) is concerned, the same would

presently be dealt with here and I agree with the proposition that the decision

of the Delhi High Court in the said case does not squarely apply in the present

context.

In State of Goa (supra) as pointed by respondents' counsel in the present

case, the context was counter claims, where it was held that an application

under Section 11 of the 1996 Act is itself a request for arbitration.

It would be a circular logic and take us into infinite regress if such logic

is adopted in the present context. If adopted, it would mean that an

application under Section 11 should be construed as a notice for itself, which

is an absurd proposition. Moreover, the said observations were not only made

in the context of counter claim but also in the context of Section 21 of the 1996

Act, which commences an arbitral proceeding.

It would be apt to consider a different aspect of the matter at this

juncture. There is a difference between the requirements of Section 21 and

Section 11 as well as in the context in which the two Sections operate.

Whereas Section 21 is the commencement of the arbitral proceeding itself,

Section 11(5) contemplates a different requirement, being once step prior to the

commencement of the arbitral proceeding. Section 11(5) requires a request of

appointment of Arbitrator to be made whereas Section 21 requires such a

request to be made for the purpose of reference to arbitration.

Whereas the request under Section 11(5) is merely a precursor for the

actual appointment of Arbitrator by the Court, only upon which the arbitral

proceeding commences, the Section 21 operates as the commencement of the

arbitral proceeding itself.

Thus, there is no scope of confusing the requirements of Section 21 on

the one hand and Section 11 on the other, which operate in somewhat different

perspectives.

Seen in such perspective, the judgment rendered by the Delhi High Court

in Alupro Building Systems (Supra) might acquire some relevance.

However, a caveat ought to be entered at this stage. Alupro Building

Systems (supra) was not rendered in the context of Section 11 of the 1996 Act,

as correctly pointed out by learned counsel for the petitioner herein. The

context of the same was a challenge under Section 34 of the 1996 Act where

the Court was considering whether a notice under Section 21 is mandatory.

Since Section 21 is the commencement of the arbitral proceeding itself,

the rigours applicable to the same are of a much higher standard than a

request under Section 11(5) of the 1996 Act, since the latter is merely a prior

step intimating the intention to arbitrate and appoint an Arbitrator to the

respondents, which would indeed be followed by the actual appointment of

Arbitrator and the Arbitrator thereafter entering into the arbitral proceeding.

Thus, the tests applicable to Section 11(5) ought to be tested on a much

liberal anvil in favour of arbitration, as contemplated in the object and purpose

of the Arbitration Act, 1996, than that of Section 21, which is the actual

commencement of the arbitral proceeding itself and has its effect on nothing

less than the veracity and validity of the arbitral proceeding and the award.

While considering a challenge under Section 34, the Delhi High Court in

Alupro Building Systems (supra) held that a plain reading of Section 21

indicates that except where the parties have agreed to the contrary, the date of

commencement of arbitration proceedings would be the date on which the

recipient of the notice receives from the claimant a request for referring the

dispute to arbitration. The Court held that inherently the arbitration clauses

do not contemplate the unilateral appointment of an Arbitrator by one of the

parties and there has to be a consensus for which the notice under Section 21

serves an important purpose of facilitating a consensus on the appointment of

an arbitrator.

The Court also held that for the purposes of Section 11(6) of the 1996

Act, without the notice under Section 21 of the Act, a party seeking reference of

disputes to arbitration will be unable to demonstrate that there was a failure

by one party to adhere to the procedure and accede to the request for the

appointment of an arbitrator. The trigger for the Court's jurisdiction under

Section 11 of the Act is such failure by one party to respond.

However, with utmost respect to the erudition par excellence of the

learned judge who rendered the said judgment, being Justice Muralidhar, this

Court is of the clear and unambiguous opinion that the said observation vis-à-

vis Section 11(6) of the 1996 Act in the judgment was palpably obiter dictum,

since the entire context, as enumerated in the judgment itself, was an

application under Section 34 of the 1996 Act and not a Section 11 scenario.

That apart, the Court cannot read into the statute something which is

not intended by the Legislature itself. Section 11 nowhere stipulates that there

has to be a prior request of reference to arbitration under Section 21 of the

1996 Act. Section 11(5) clearly envisages a prior request for appointment of an

Arbitrator, which would necessarily be followed by the actual appointment and

thereafter commencement of the arbitral proceeding.

Seen in such context, Alupro Building Systems (supra) cannot be a

binding precedent in the present case.

In Sri Arun Kumar Bhunia (supra), a learned Single Judge of this Court,

inter alia, observed, although in a different context, that Section 11(6)(a) of the

1996 Act stipulates that when the procedure for appointment of the Arbitrator

has been agreed upon by the parties, the Chief Justice or his designate can

appoint an Arbitrator only when one of the parties fails to act as required

under the agreed procedure. In such light, it went on to observe that there

cannot be any doubt that issuance of a valid notice under Section 21 of the Act

of 1996 for referring the dispute between the parties to arbitration is a

condition precedent for commencement of a valid arbitral proceeding.

The context there was somewhat different than the present. Although

the incentive for the Court to embark on the judgment was an application

under Section 11(6) of the 1996 Act, in the said case, the parties had already

participated in an arbitral proceeding upon entering into a reference.

Thereafter, an issue was raised by the respondents therein to the effect that the

appointment of the Arbitrator was unilateral which, in the absence of a valid

notice under Section 21, was held by the learned Single Judge to be invalid. At

the risk of repetition, as discussed above, the context of commencement of an

arbitral proceeding being invalid in absence of a prior notice under Section 21

and in view of a unilateral appointment of Arbitrator is entirely different from a

Section 11(5) situation, where only a prior notice is required for the purpose of

appointment of an Arbitrator and not for the initiation of the proceeding itself.

In Malvika Rajnikant Mehta (supra) the Bombay High Court was

considering an application under Section 11(5) read with Section 15 of the

1996 Act. There it was observed that without a notice under Section 21 of the

Act, a party seeking reference of the disputes to arbitration would be unable to

demonstrate that there was a failure by one party to adhere to the procedure

and accede to the request for the appointment of an arbitrator. In the said

case, there was no dispute as to whether there was actually a prior request

under either Section 21 or Section 11(5) of the 1996 Act. The Court considered

that there were several correspondences between the parties which was

ultimately relegated to the arbitrator himself by the Court for consideration

whether there was a prior notice under Section 21 of the 1996 Act. Thus, I do

not find any reason to proceed on the premise that the ratio of the said

judgment is conclusive for the present purpose.

Coming back to the present case, we are to look into the documents

annexed to the present application to assess whether there was substantial

compliance with Section 11(5) of the 1996 Act. Section 11(5) does not

contemplate, under any stretch of imagination, the commencement of a valid

arbitral proceeding but is merely a precursor and the sine quo non for

appointment of an arbitrator which would then lead to commencement of the

proceeding subsequently and as such, has to be taken in much more liberal

context than Section 21, which itself marks the commencement of the arbitral

proceeding.

In the communication dated July 20, 2021 made by the petitioner to the

perceived Arbitrator, it was clearly indicated that the petitioner invokes the

arbitration clause and names the Arbitrator as the principal noticee to settle

the dispute as indicated in the said communication itself. There is no dispute

to the fact that copies thereof were forwarded to the present respondents as

well. The receipt of the said communication by the respondents is undisputed,

since the respondent chose the give a reply thereto in writing which is also

annexed the present application at page 43. In the reply dated August 16,

2021, the respondents, for all practical purposes, also construed the said

notice as one seeking invocation of the arbitration clause. However, what was

challenged by the respondents in the said reply was not that the said

communication of the petitioner was not a request under Section 11(5), being

addressed to the Arbitrator and not to the respondents, but that the said

unilateral appointment which was witnessed by the communication was not

valid in the eye of law.

Thus, the challenge in the reply of the respondents was confined to the

unilateral appointment of the Arbitrator himself, which has been obviated by

virtue of the petitioner seeking the appointment of an independent Arbitrator

by the present application under Section 11. Insofar as the last paragraph of

the reply of the respondent dated August 16, 2021 is concerned, the

respondents stated that question of acceptance of the alleged office of

arbitration and/or to initiate a proceeding as per provision of law with any

immediate effect by the unilateral named Arbitrator does not and/or cannot

arise at all. Further, the respondents stated that they denied and disputed the

same and as such the appointment of the particular learned advocate as

Arbitrator from the petitioner's side belonging to the same Bar Association was

not beyond question and the respondents did not accept the same since there

was every likelihood of manipulation and pressure on the mind of the said

learned advocate being the Arbitrator from the petitioner's side.

Thus, the matrix contemplated in Section 11(5) is fully satisfied in the

facts of the case. Section 11(5) envisages the failure of any agreement referred

to in sub-Section (2) and if the parties fail to agree on the Arbitrator within 30

days from receipt of a request by one party from the other party to so agree, for

the appointment to be made.

Here, the petitioner wrote a letter addressed in the first person to the

named Arbitrator but also addressed copies thereof to the respondents who

admittedly received the same and replied to the same. In the reply, apart from

challenging the unilateral appointment, the respondents made their intention

clear that they failed to agree on the Arbitrator, which is the specific language

and requirement of sub-Section (5) of Section 11 of the 1996 Act.

Thus, the respondents cannot now take the specious objection of non-

compliance of Section 11(5) at this stage and argue that the Section 11

application is premature.

Despite taking into consideration the ratio laid down in all the judgments

cited by the parties, we cannot lose sight of the object and purpose of the 1996

Act, in consonance with the contemplation of the UNCITRAL Model Law of

Arbitration. Such object and purpose, in no uncertain terms, encourages and

facilitates arbitration and seeks to make India an international hub for

alternative dispute resolution by the process of arbitration. The purpose of

Section 11(5) is not to throw a spanner in the wheels of arbitration but to

encourage and facilitate arbitration. As such, the interpretation of the said

section which would be congenial and conducive to arbitration can only be

accepted by the Court as valid.

In the context of the above discussions, I am of the clear opinion that the

requirements of Section 11(5) have been complied with in the present case and

the application is not premature.

Hence, both the objections taken by the respondents to the present

application are turned down.

A bare perusal of the arbitration clause indicates that the same covers

the dispute now sought to be raised between the parties and the dispute so

raised is otherwise arbitrable.

Accordingly, AP-COM/701/2024 is allowed, thereby appointing Mr.

Sagar Bandyopadhyay (Mob No. 9830068294), an Advocate practising in this

Court, as the sole Arbitrator to resolve the disputes between the parties,

subject to obtaining a disclosure under Section 12 of the Arbitration and

Conciliation Act, 1996 from the said Arbitrator. The learned Arbitrator shall, in

consultation with the parties and in consonance with the provisions of the

1996 Act and its Fourth Schedule, fix his own remuneration.

It is further made clear that all questions are kept open for being

adjudicated by the learned Arbitrator on merits and this Court has not entered

into the merits any of the issues involved, including any objection regarding

maintainability of the claims, if raised by the respondents, and all such issues

will be decidedly independently by the learned Arbitrator.

(SABYASACHI BHATTACHARYYAJ.)

bp/R Bhar/B.Pal

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter