Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Bengal Shelter Housing Development ... vs The Kolkata Municipal Corporation
2024 Latest Caselaw 2587 Cal/2

Citation : 2024 Latest Caselaw 2587 Cal/2
Judgement Date : 13 August, 2024

Calcutta High Court

Bengal Shelter Housing Development ... vs The Kolkata Municipal Corporation on 13 August, 2024

Author: Sabyasachi Bhattacharyya

Bench: Sabyasachi Bhattacharyya

OCD-2
                               ORDER SHEET

                             AP-COM/608/2024

                    IN THE HIGH COURT AT CALCUTTA
                     Ordinary Original Civil Jurisdiction
                              ORIGINAL SIDE
                           (Commercial Division)


           BENGAL SHELTER HOUSING DEVELOPMENT LIMITED
                               VS
               THE KOLKATA MUNICIPAL CORPORATION


  BEFORE:
  The Hon'ble JUSTICE SABYASACHI BHATTACHARYYA
  Date : 13th August, 2024.

                                                                      Appearance:
                                                            Mr. Joy Saha, Sr. Adv.
                                                        Mr. Reetobrata Mitra, Adv.
                                                      Ms. Jayati Chowdhury, Adv.
                                                       Ms. Rashhmi Singhee, Adv.
                                                           Ms. Sucheta Mitra, Adv.
                                                          Ms. Priya Malakar, Adv.
                                                                ...for the petitioner

                                                           Mr. Jaydip Kar, Sr. Adv.
                                                      Mr. Biswajit Mukherjee, Adv.
                                                           Mr. Altamash Alim, Adv.
                                                                        ...for KMC


        The Court: The petitioner Bengal Shelter Housing Development

Limited was incorporated on January 28, 2004 as a Joint Sector Company

between one Shelter Projects Limited and the West Bengal Housing Board

(WBHB).     In the said joint venture, the WBHB has 49.5 per cent share,

Shelter Projects has 49.5 per cent share and the rest 1 per cent is public.

        Pursuant to a tender floated by the respondent Kolkata Municipal

Corporation (KMC), the petitioner entered into a development agreement for

the purpose of developing the College Street Market premises for the

purpose of constructing a Book Mall where primarily book shops would be

rehabilitated. There would be other shops in the said premises as well. The

agreement for development was entered into between the parties on

February 24, 2006 and a supplementary agreement on June 12, 2006. The

development work was to be completed within 54 months which ended

roughly on December 26, 2010.

Thereafter the petitioner was permitted to continue the work and on

January 17, 2022, a termination letter was issued by the KMC to the

petitioner. On the self-same date, a letter of possession was also issued and

the KMC took possession of the market.

The petitioner, being aggrieved by the same, seeks to refer the matter

to arbitration pursuant to an arbitration clause in the agreement between

the parties.

The scope of the dispute in the arbitration would primarily be a

challenge to the termination and possession as well as allied reliefs.

The present application under Section 9 of the Arbitration and

Conciliation Act, 1996 (hereinafter referred to as "the 1996 Act") has been

filed in aid of the said intended arbitration, seeking injunction restraining

the respondent from transferring, alienating and/or dealing with the

subject-property in favour of third parties, injunction restraining the

respondent and its men and agents from entering into any agreement with

any other third party or developer or contractor for completion of the said

Mall as well as other consequential reliefs.

Learned senior counsel for the petitioner argues that the respondent

allowed the petitioner to work much beyond the contractual 54 months and

issued the notice of termination only on January 17, 2022, that is, after

about 12 years from the expiry of the stipulated time. Thus, time was never

intended to be the essence of the contract.

Learned senior counsel cites the judgment of Welspun Specialty

Solutions Limited Vs. Oil and natural Gas Corporation Limited, reported at

(2022) 2 SCC 382 for the proposition that whether time is of the essence in a

contract has to be culled out from a reading of the entire contract as well as

the surrounding circumstances. Merely having an explicit clause may not be

sufficient to make time the essence of the contract. In the said case, the

Supreme Court observed that as the contract was spread over a long tenure,

the intention of the parties to provide for extensions surely reinforced the

fact that timely performance was necessary. The fact that such extensions

were granted, it was held, indicated the efforts of the respondent therein to

uphold the integrity of the contract instead of repudiating the same.

Learned senior counsel appearing for the petitioner next argues that

as per Section 55 of the Contract Act, 1872, when a party to a contract

promises to do a certain thing but fails to do it before the specified time, the

contract becomes voidable at the option of the promisee if the intention of

the parties was that time should be of the essence of the contract. If it was

not the intention of the parties that time should be essence, the contract

does not become voidable for failure to do such thing at or before the

specified time, but the promisee is entitled to compensation from the

promisor. In case of a contract being voidable on account of the promisor‟s

failure to perform the promise at the time agreed, if the promisee accepts

performance, it cannot claim compensation for any loss occasioned by the

non-performance of the promise at the time agreed, unless at the time of

such acceptance, he gives notice to the promisor of his intention to do so.

In the present case, having not given any such notice despite

permitting the petitioner to exceed the initial 54 months by about 12 years,

it is argued that the respondent is not entitled either to compensation or to

termination.

Learned senior counsel appearing for the petitioner next contends that

there was no delay in performance due to the fault of the petitioner at any

point of time. Learned senior counsel relies on the averments made in the

application under Section 9 of the 1996 Act to argue that the work got

stalled at various stages due to rehabilitation of occupants, shifting of cable,

drainage, overhead lines, water supply/connection, shifting of a Mazar and

staff quarters.

It is argued that the petitioner has in fact handed over the entire

share of the respondent and has already delivered possession to 864 shops.

As per the agreement, the respondent was entitled only to 30 per cent share

in the developed property whereas the petitioner is entitled to 70 per cent.

Even out of the said 30 per cent, a substantial chunk was sold by the

respondent to the petitioner.

To support such contention, learned senior counsel appearing for the

petitioner places reliance on photocopies of two cheques of Rupees Five

Crore each, paid by the petitioner and its hundred per cent subsidiary, one

Barnaparichay Book Mall Private Limited ("Barnaparichay" for short). Thus,

it is argued that having allowed the petitioner to work so far and after the

petitioner having completed more than 90 per cent of the work and having

handed over the respondent‟s share, the termination was palpably mala fide

and illegal.

Learned senior counsel next argues that the second ground of

termination, apart from delay, was the alleged assignment to a third party.

It is argued that there was no assignment at any point of time.

Barnaparichay was incorporated on or about May 7, 2007 as a wholly

owned subsidiary of the petitioner-Company. The shareholding of the

petitioner-Company in Barnaparichay is 100 per cent. It is submitted that

the latter was formed merely as a Special Performance Vehicle (SPV) to carry

out the project of construction of the Book Mall. Hence, Barnaparichay is

not a third party as such. There was no assignment at any point of time.

The SPV was to complete the work for the petitioner-Company.

Secondly, the formation of Barnaparichay and entrustment of the

work to it was well within the knowledge of KMC, as a Director of WBHB has

been a nominee member in the Board of Directors of the petitioner-

company. The petitioner/Joint Sector Company is a conglomeration of the

WBHB and Shelter Projects Limited. Thus, every decision of the petitioner

was well within the knowledge of the WBHB, which is but another

instrumentality of the State as is the KMC/respondent. Hence, it is argued

that the KMC cannot feign ignorance of the formation of the SPV and the

entrustment of the work to it at the relevant point of time.

Learned senior counsel cites a Division Bench judgment of this Court

in the matter of Bajrang Prasad jalan and another Vs. Raigarh Jute and

Textile Mills Ltd. and others, reported at 1999 SCC OnLine Cal 534 as well as

an order of the Supreme Court in the matter of Shankar Sundaram Vs.

Amalgamations Ltd. & Ors. in support of the proposition that in petitions

under Sections 397/398 of the Companies Act, 1956, the corporate veil can

very well be lifted, upon which the holding and subsidiary companies should

be regarded as one and the same for the purpose of grant of relief.

Learned senior counsel for the petitioner argues that Rs. 237 Crore

has already been invested by the petitioner through Barnaparichay and the

project is on the verge of completion. Thus, the issuance of the termination

notice, simultaneously with possession notice, on the self-same date all on a

sudden was unwarranted and arbitrary; as such, de hors the law.

It is submitted that a Corporate Insolvency Resolution Process (CIRP)

was started in respect of Barnaparichay. The termination of the present

contract was challenged in connection therewith before the National

Company Law Tribunal (NCLT), which set aside the termination. Against

the same, the National Company Law Appellate Tribunal (NCLAT) was

moved, which set aside the order of the NCLT, holding that there was

assignment by the petitioner to Barnaparichay. The matter went up to the

Supreme Court which refused to interfere, however, with the observation

that the issue of termination was left open to be challenged before a civil

forum. Thus, the observations in the said proceeding are not germane in

the present context as the issues were kept open by the NCLAT and the

Supreme Court.

Lastly, it is argued that the availability of the relief of damages is not

an absolute bar to injunction.

Learned senior counsel appearing for the respondent commences with

the argument that the present application under Section 9 is not

maintainable, since the remedy of the petitioner lies at best in damages and

not in injunction. It is highlighted by learned senior counsel that the

petitioner seeks to stall a public infrastructure project, which would

adversely affect the public at large. It is argued that the petitioner has

taken different stances regarding completion of the work at different points

of time. In a prior application under Section 9, which was subsequently

withdrawn with leave to file afresh, the petitioner had contended that only

70 per cent of the work had been done, whereas now they argue that more

than 90 per cent has been completed. It is contended that the property is

spread over 13 bighas in a prime location of the city of Kolkata. It is further

submitted that all the vendors have not been rehabilitated in the developed

property and at least 5-10 per cent of them are still to be handed over

possession by the petitioner.

It is argued that Section 55 of the Contract Act does not prevent the

petitioner from terminating the contract if the petitioner commits inordinate

delay in completion of the project. It is argued that although the petitioner

was granted 10 years to complete the project even after the expiry of the

initially stipulated period, the petitioner having failed to substantially

complete the work even within such extended time, the termination notice

and consequential possession notice were justified.

It is argued that the respondent had issued a prior notice in the year

2020 under Clause 9(g) of the agreement, granting opportunity to the

petitioner to rectify the defects, which is annexed to the petition. Even

thereafter, the pre-termination show-cause notice was issued on November

12, 2021. Only after exhausting such prior procedure, a termination notice

and a notice of possession was issued on January 17, 2022. Thus, the

respondent fully complied with the provisions of the agreement before

issuing the termination notice. Despite getting opportunity for over a year

after the Clause 9 (g) notice, the petitioner failed to complete the work.

Clause 13 of the agreement, the respondent argues, precludes any

third party assignment, which was violated by the petitioner by assigning

the work to Barnaparichay. It is argued that Barnaparichay being a

different company and a separate juristic entity, the argument as to the said

company being an alter ego of the petitioner is not acceptable.

The NCLAT finally decided the issue of assignment having taken place

and only the question of termination was left open for being decided

separately. Thus, learned senior counsel for the respondent contends that

the issue of assignment cannot now be reopened in arbitration or otherwise.

It is argued that no notice of assignment was given at any point of

time by the petitioner to the respondent. It is submitted that the argument

regarding there being common Directors between WBHB and the petitioner

is specious, since the KMC is an entirely independent authority having no

connection with WBHB and in the absence of specific intimation of the

assignment to the respondent-KMC, the petitioner was liable to termination

in terms of Clause 13 of the agreement.

Apart from justifying the termination notice on the grounds of non-

performance and assignment, learned senior counsel for the respondent

hands over certain photographs to argue that the present state of the

property is undeveloped, seeking to destroy the argument of the petitioner

that the work has been substantially concluded.

It is reiterated that the petitioner was granted sufficient time over the

years but failed to avail of the opportunity to rectify its non-performance

despite a notice being given under Clause 9(g) of the agreement as long back

as in the year 2020. Thus, the injunction sought is intended to prevent a

public infrastructure project, which ought not to be permitted by the court.

Learned senior counsel appearing for the respondent next submits

that even the Supreme Court order from the decision of the NCLAT was

passed on March 4, 2024, whereas the present petition has been filed only

on May 16, 2024. Till date, no notice under Section 21 of the 1996 Act has

been issued by the petitioner. The above conduct, it is argued, makes it

explicit that the petitioner has not approached the court with clean hands,

having no intention to refer the matter to arbitration but merely to stall the

project by hook or by crook.

Learned senior counsel argues that Section 9 contemplates a 90 days‟

period for issuance of a notice under Section 21 of the 1996 Act in exigent

situations. In the present case, the facts and circumstances do not justify

the petitioner not having invoked the arbitration clause over such a long

period of time.

Thus, the respondent seeks dismissal of the application.

Upon hearing learned counsel for the parties on the question of grant

of ad interim orders, the Court comes to the following conclusions:

The first question which arises is whether a prima facie case has been

established by the petitioner with regard to the termination notice being

invalid or illegal. The notice is assailed inter alia on the strength of Section

55 of the Contract Act.

The petitioner has an arguable case on Section 55. The three courses

of action open in a case where the promisor fails to perform a promise

within the stipulated time as per Section 55 are:

i) For the promisee to terminate the contract, it being voidable due

to non-performance within the stipulated time where time is the

essence of the contract.

ii) If time is not the essence of the Contract, the contract does not

become voidable but the promisee is entitled to compensation

from the promisor for any loss occasioned by such failure.

iii) Even in case of the contract being voidable, if the promisee

accepts performance beyond the agreed time, it cannot claim

compensation for loss occasioned by the non-performance of the

promise within the agreed time unless at the time of acceptance,

the promisee gives a notice of the promisor of its intention to do

so.

In the present case, the promisee, that is the respondent, did not give

any notice to the promisor\petitioner as to its intention to claim

compensation, when permitting the petitioner to prolong the work well

beyond the stipulated time. By their mutual conduct, the parties have given

a go-bye to the 54 months‟ outer limit for completion of the project.

Instead of terminating the contract after the expiry of the 54 months

or claiming compensation at any time, the respondent has corresponded

with the petitioner all along, which goes on to show that the petitioner was

granted the liberty to extend the time for completion of the work. Before the

year 2020, there is nothing on record or argued by the parties which could

indicate the respondent‟s intention to terminate the contract or claim

compensation. By its very conduct, the respondent has acquiesced to the

extension of the time and thus it is, to say the least, arguable as to whether

the respondent is entitled to any compensation or to treat the contract as

voidable and terminate the contract.

The question is arguable since the respondent also has raised a

relevant question as the whether even if Section 55 of the Contract Act is

attracted, whether the respondent is required to wait indefinitely for a public

project to be completed. At this juncture, thus, at least an arguable case to

be referred to arbitration has been made out between the parties which itself

furnishes a prima facie triable case for the petitioner in the application

under Section 9.

Regarding delay, the petitioner has made elaborate pleadings and

annexed several documents to its application under Section 9 to prima facie

satisfy the court that the work was stalled not due to any fault of the

petitioner but due to unforeseen circumstances and that the delay is not

attributable solely to the petitioner. Rehabilitation of occupants, shifting of

cable, drainage, overhead lines and water supply, shifting of a Mazar and

staff quarters were some of the issue which cropped up on the way. Such

hindrances would be sufficient justification, at least prima facie, for the

delay in completion of the work.

The respondent, by permitting the work to be continued for 12 years

after the expiry of the original time-limit, has virtually acquiesced to such a

position. The numerous correspondences between the parties and by the

petitioner to different authorities also substantiate such claim.

Moreover, the petitioner has already handed over 864 shops in terms

of the agreements after development. Even as per the admission of the

respondent, since it argues that 5-10 per cent of the shops are yet to be

handed over, at least 90 per cent of the handing over is completed, which

goes on to show that a substantial part of the project has been done by the

petitioner.

Another valid argument of the petitioner is that it is entitled to 70 per

cent of the shares of the developed property and a further share out of the

30 per cent of the respondent has been transferred to the petitioner and

Barnaparichay subsequently. Thus, at this juncture, the petitioner would be

entitled to invoke Sections 202 and 204 of the Contract Act, since the

petitioner, as agent of the respondent for completion of the project, itself has

an interest in the property and the authority given under the development

agreement has been substantially exercised by the petitioner. The huge

investment of Rs. 237 Crore by the petitioner through Barnaparichay in the

project is also an important consideration to assess whether the termination

at this juncture is bona fide.

As regards the alleged assignment in favour of a third party, it is

arguable as to whether entrustment of the work by the petitioner-holding

company to a hundred per cent subsidiary in the capacity of SPV can

tantamount to an „assignment‟. Entrustment of work to a wholly owned

subsidiary is qualitatively different from an assignment to a third party.

Hence, the argument of the respondent that the termination was justified on

the ground of assignment for violation of Clause 13 of the agreement is

steeped in doubt, to say the least.

Hence, considerable doubt is cast on both the grounds of termination,

be it failure to perform the work or alleged assignment.

The argument of the respondent as to stalling of a public

infrastructure project is not applicable in terms. Although the project is

public in nature, the same cannot be strictly construed as an

„infrastructure‟ project, in respect of which the amended Specific Relief Act

has cast a bar to courts in granting injunction. The construction of a Book

Mall to rehabilitate local shopkeepers and book stalls is not exactly an

"infrastructure" project, although it has ramifications in the public domain.

That apart, the injunction now pressed for by the petitioner is to the

limited extent that the respondent should not transfer the property or create

a third party interest, which would not stall the development project in any

manner. In any event, a prima facie case has been made out by the

petitioner of having completed the work substantially.

It is also quiet arguable as to whether the respondent‟s portion, which

is now less than 30 per cent, has already been handed over by the

petitioner. Without an ascertainment as to the exact portion and extent of

the project which has been concluded, the respondent cannot be permitted

to frustrate the prospective arbitration by creating third party interest in the

entire property.

In the event the respondent is permitted to do so, the ultimate

reference to arbitration would be frustrated and nothing would remain for

the Arbitrator to adjudicate upon.

The delay on the part of the petitioner in preferring the present

application as argued by the respondent is also not tenable, since the matter

was sub judice up to the Supreme Court which passed its order only on

March 4, 2014. The very next month, an application under Section 9 of the

1996 Act was preferred by the petitioner but due to technical error the same

was withdrawn and re-filed in the present form on May 16, 2024. Also, there

is no legal bar in taking out a Section 9 proceeding prior to reference to

arbitration or invocation of the arbitration clause under Section 21 of the

1996 Act. Section 9 makes it amply clear that a reference may be made

within 90 days from an order passed therein.

As regards the conclusiveness of the NCLAT findings in respect of

assignment, the respondent‟s arguments cannot be accepted as well.

Despite having held that there was an assignment, even the NCLAT made it

clear that it did not have competence to decide on the issue of termination,

which view was explicitly upheld by the Supreme Court by leaving it open

for termination to be challenged before a competent civil forum/court. By

keeping the issue of termination open to challenge, the Supreme Court also,

by necessary implication, left it open for the grounds of termination

(including assignment) to be challenged before the appropriate forum. Since

the Arbitrator is the appropriate forum in the present case in view of the

existence of an arbitration clause, there cannot be any doubt that the issue

of assignment as well as alleged delay are amenable to the decision of the

Arbitral Tribunal.

Since Section 9 of the 1996 Act derives its colour in aid of and from

the subject-matter of the proposed arbitration, this Court has ample power

under Section 9 of the 1996 Act to grant the relief now prayed for by the

petitioner. In fact, the balance of convenience and inconvenience is squarely

in favour of grant of ad interim relief, since the petitioner not only claims a

right to complete the work but also argues that it has more than 70 per cent

right in the subject property. If third party rights are created at this

juncture on the entire property, of which possession has already been taken

by the respondent-KMC, the arbitral proceedings would be rendered

infructuous ab initio.

The urgency is also implicit, since the termination notice was coupled

with a possession notice and the respondent wasted no time in taking

possession of the property simultaneously with termination of contract at a

mature stage of development project. Hence, there is sufficient and justified

apprehension that if the rights of the petitioner are not protected from third

parties, the arbitral reference might be rendered irretrievably infructuous.

Although the arguments of the petitioner on the basis of the cited

judgments on assignment cannot be taken into contention, since in those

cases the Supreme Court and the Division Bench of this Court were looking

at a situation where the corporate veil was lifted on allegations of oppression

and mismanagement, which is distinct and different form the present case,

in principle, it is at least arguable as to whether a holding company and its

wholly owned subsidiary, entrusted as an SPV to complete the project, can

be distinguished for the purpose of completion of a project, so much so that

it can be said that there was an assignment violating the provisions of the

agreement.

Also, the ratio laid down in Welspun Specialty Solutions Limited (supra)

cannot be overlooked, where it has been held that whether time is the

essence of the contract can only be culled out from a composite reading of

the entire contract as well as surrounding circumstances (obviously

including the conduct of the parties) which in the present case, militates

against time being the essence of the contract.

Thus, the petitioner in entitled to ad interim injunction as prayed for

in prayers (a) and (c) of the present application. Accordingly, the respondent

and its men and agents are restrained by an order of ad interim injunction

from transferring, alienating, encumbering and/or parting with possession

of the subject-property situated at the College Street Market at premises No.

226, Bidhan Sarani, Kolkata - 700 007, as well as at 83, College Street,

Kolkata - 700 007 and 75, Madan Mohan Burman Street, Kolkata 700 007,

under Ward No. 39 under the Jorasanko Police Station, under the

jurisdiction of Borough No. IV of the Kolkata Municipal Corporation and/or

from entering into any agreement for development of the said property with

any third party/developer/contractor for completion of the said Mall till

disposal of the present application under Section 9 of the Arbitration and

Conciliation Act, 1996.

The respondent shall file its affidavit-in-opposition within 3 weeks

from date. Reply, if any, shall be filed within a week thereafter. The

application shall be listed for hearing on September 17, 2024.

(SABYASACHI BHATTACHARYYA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter