Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Union Of India vs Senbo Engineering Limited
2024 Latest Caselaw 2492 Cal/2

Citation : 2024 Latest Caselaw 2492 Cal/2
Judgement Date : 5 August, 2024

Calcutta High Court

Union Of India vs Senbo Engineering Limited on 5 August, 2024

Author: Sabyasachi Bhattacharyya

Bench: Sabyasachi Bhattacharyya

                      In the High Court at Calcutta
                        Original Civil Jurisdiction
                           Commercial Division

The Hon'ble Justice Sabyasachi Bhattacharyya

                        AP-COM No. 208 of 2024
                   [Old Case No. AP No. 245 of 2021]

                                Union of India
                                     Vs
                          Senbo Engineering Limited

     For the petitioner        :     Mr. Satyendra Agarwal, Adv.
                                     Mr. Subhankar Chakraborty, Adv.
                                     Ms.Ruchira Manna, Adv.


     For the respondent        :     Mr. Dhruba Ghosh, Sr. Adv.

Mr. Nilay Sengupta, Adv.

Mr. Sujit Banerjee, Adv.

Mr. Altamash Alim, Adv.

Ms. Ananya Barik, Adv.

     Hearing concluded on      :     15.07.2024

     Judgment on               :     05.08.2024

     Sabyasachi Bhattacharyya, J:-


1. The Union of India, through the General Manager of the Metro

Railway, has filed the present challenge under Section 34 of the

Arbitration and Conciliation Act, 1996 (hereinafter referred to as "the

1996 Act‟‟) against an award whereby several monetary claims of the

claimant/respondent were allowed.

2. Learned counsel for the petitioner argues that the three-member

Arbitral Tribunal decided on the validity of termination of the contract

of the claimant despite such relief having not been sought by the

claimant in its statement of claim. That apart, termination falls under

the „excepted clauses‟ of the contract and thus, could not have been

adjudicated upon by the Tribunal.

3. Claims 1, 2, 3, 7 and 8, which were all allowed, are excepted matters

as per Clause 63 of the General Conditions of Contract (GCC). While

determining claim no.1, the Tribunal went into the veracity of

measurements and based its award on the basis of such

measurements, which falls within the excepted clauses as well.

4. The contract between the parties specifically states that no interest is

payable, despite which, under claim no.11, the Tribunal granted

interest to the claimant. It is argued that, as per Section 31(7) of the

1996 Act, interest cannot be granted unless agreed upon, which

agreement is absent in the present case.

5. The matter of measurement with regard to the bills/termination owing

to default of contractor falls under Clause 62, which is also one of the

excepted matters under Clause 63 as per learned counsel for the

Railways.

6. Despite there being disputes regarding payment of bills, the claimant

could simultaneously have continued the work within the provisions

of the contract between the parties. Clauses 39(1) and 39(2)

contemplate rates for extra items of work and Clause 43(1) deals with

monthly statement of claims. However, without availing of the same

and despite being given repeated opportunities, the claimant

abandoned the work midway, for which the termination took effect in

accordance with law and the contract.

7. Although there were no monthly claims under Clause 43(i), the

Tribunal went on to allow the claims of the claimant.

8. Despite it being indicated in the award that there was some

duplication, the Tribunal went ahead to pass the award in favour of

the claimant. It was recorded by the Tribunal in paragraph no. 8.3.2

of the award that work was abandoned by the contractor.

9. It is next argued that new claims, which were not part of the original

claim, were allowed, which was contrary to the contract between the

parties. Whereas claims 1, 2, 3, 11 and 12 were not part of the

original claims, claim nos. 5, 6, 8, 10 were increased.

10. Clause 46(3) contemplates that on-account payments do not prejudice

the final settlement.

11. The Tribunal, while deciding the counterclaim of Railways, re-wrote

the contract between the parties contrary to the order passed on

November 17, 2017 in APO No. 507 of 2017 arising out of AP No.934

of 2017, an application under Section 9 of the 1996 Act. Vide order

dated January 15, 2020 passed in AP No. 491 of 2019, costs were

awarded, to be paid by the petitioner to the State Legal Services

Authority. However, the Tribunal adjusted the cost amount with the

counterclaim which, according to the petitioner, was illegal.

12. Learned senior counsel appearing for the claimant/respondent

submits that the Arbitral Tribunal interpreted the terms of the

contract which was within its domain and not susceptible to

challenge. Moreover, the views taken by the Tribunal were plausible

views and, merely because another view is possible, cannot be

substituted by such alternative view by this Court.

13. It is argued by the respondent that the claims allowed by the Arbitral

Tribunal do not fall within the „excepted‟ matters under Clause 63 of

the GCC.

14. The amounts awarded by way of compensation for wrongful

encashment of the Bank Guarantees are not „interest‟ within the

meaning of Clause 64(1)(iii).

15. Thus, it is argued that the present challenge ought to be dismissed.

16. The respondent argues that the impugned award was passed upon

hearing both parties and taking into consideration all the evidence

and arguments made by the parties.

17. Para 3.4 of the award records that both the claimant and respondent

presented themselves for the meeting and had stated that they were

satisfied with the full opportunity given to them to present their cases.

Hence, they cannot have anything further to stay. It is pointed out

that no application under Section 18 of the 1996 Act has been filed by

the petitioner alleging lack of proper opportunity being given to

present its case. Thus, such ground taken in the application under

Section 34 is an afterthought.

18. The pleadings in the Section 34 application, it is argued, are bald

allegations without any particulars. The tests of Section 34 are not

met, it is argued.

19. Learned senior counsel for the claimant/respondent cites Food

Corporation of India vs. Forbesganj Jagdish Mills Ltd. reported at

(2000) SCC OnLine Cal 612. In support of the proposition that the

Court, under Section 34 of the 1996 Act, is not sitting in appeal until

and unless the award is bad on the face of it and that the Arbitrator is

the best judge.

20. Learned senior counsel also cites National Highway Authority of India

vs. Gammon India Ltd. reported at (2014) SCC OnLine Cal 17407 for

the proposition that the Court cannot have a re-look into the

conclusion arrived at by the Arbitrator. If the Arbitrator interprets a

clause in a particular manner, the Court would not interfere with the

same, since it is not sitting in appeal.

21. It is not permissible for the Court to interfere with the Arbitrator‟s

view merely because another view would be possible. The Arbitrator, it

is argued, is the best judge of quality as well as quantity of evidence,

particularly since each of the three members of the Tribunal were well

experienced in such matters and were chosen by the parties

consciously due to their special knowledge in resolving disputes.

22. Again, it is argued that interpretation of contract is for the arbitrator

to decide and under law, the arbitrator is made the final arbiter

of disputes between the parties.

23. Learned senior counsel for the claimant/respondent next relies on

Sutlej Construction Ltd. v. State (UT of Chandigarh) reported at(2018) 1

SCC 718 for the proposition that the Court ought not re-appreciate

evidence as long it is not a case that the award is completely without

reason. The Court, in the said case, referred to Associate Builders v.

Delhi Development Authority reported at (2015) 3 SCC 49 in holding

that an award can be set aside if it shocks the conscience of the Court

and not when the Court things it to be unjust on the facts of the case.

24. The arguments regarding the claims falling within excepted matters, it

is contended, is baseless and speculative.

25. Learned senior counsel for the respondent next cites H.L. Batra and

Company vs. State of Haryana and another reported at(1999) 9 SCC

188 in support of the contention that additional claims filed by the

claimant pertaining to the contract do not enlarge the award contrary

to law and are within the terms of reference.

26. The Arbitral Tribunal, in paragraph 8.3.1 of the award, has rightly

decided regarding the ground qua termination of contract raised by

the petitioner in the present application under Section 34. It was

correctly observed by the Tribunal in paragraph 8.3.3 to 8.3.4 that the

Railways themselves seemingly created the circumstances for making

the contractor unable to perform; hence, the termination of the

contract was held to be without merit.

27. The Security Deposit was submitted by the respondent as a security

for the completion of work and since the contract was rendered

impossible to perform due to laches of the petitioner, there is no

reason why the said amount should not be released in favour of the

claimant/respondent.

28. Since the work could not be done owing to the petitioner‟s failure in

not handing over the encumbrance free site, delay in the execution of

the project is attributable to the petitioner and, as such, interest on

mobilization advanced was rightly directed to be paid in favour of the

claimant. The claimant/respondent cannot be made to suffer due to

laches of the petitioner.

29. Owing to massive delays caused by the petitioner, the Bank

Guarantees were extended, for which huge amount was incurred every

time by the petitioner. Had the Arbitral Tribunal acted reasonably and

unjustifiably, it could have allowed the claim of the respondent in

respect of the Bank Guarantees in its entirety. However, the Tribunal,

on proper evaluation of proof placed before it, allowed only such sums

as it deemed fit and proper.

30. Claim no.1(i) was allowed on admission of the Railways and claim

no.1(ii) is also based on statements of Railways regarding the

admitted Escalation Bill. Claim no.3 was for the principal amount of

Bank Guarantees which were illegally encashed after termination of

the contract and claim no.7 is in respect of interest wrongfully

charged by the petitioner on mobilization advance even after original

tenure of the contract, although the contract was not terminated due

to any fault of the respondent. It is thus, submitted that the present

challenge ought to be dismissed on merits.

31. Upon hearing learned counsel for the parties, the Court comes to its

conclusions as follows:

32. The Supreme Court, in Sutlej Constructionltd (supra), has amply laid

down the contours of interference under Section 34 of the 1996 Act. In

such a challenge, there cannot be any interference when the award is

reasonable and on the basis of a plausible view. Re-appreciation of

evidence cannot normally be done and when it comes to setting aside

of an award under the public policy ground, the award should shock

the conscience of the Court. Merely because the Court thinks it unjust

on the facts of the case, it cannot substitute its view for that of the

Arbitrator to do what it considers to be justice.

33. In H.L. Batra (supra), the Supreme Court also laid down the scope of

arbitration where an award is set aside and a new arbitrator is

appointed for settling of disputes. In such circumstances, it was held

that the second Arbitrator‟s scope was not confined only to those

claims which have been originally filed before the first Arbitrator.

34. Although the ratio of Sutlej Construction ltd (supra) is applicable, H.L.

Batra (supra) has no application since in the present case, the

question is not merely whether new claims can be made but whether

there was a bar in making such new claims under the contract.

35. Clause 64(1)(ii) of the agreement between the parties provides that the

demand for Arbitration has specified the matters which are in

question or subjected to the dispute or difference as also the amount

of claim item wise. Only such disputes or differences in respect of

which the demand has been made, together with counter claims or

set-off, shall be referred to arbitration and other matters shall not be

included in the reference.

36. Thus, it is not a general case, as was being considered in H.L. Batra

(supra), where additional claims can always be incorporated later on.

The very Arbitration Clause on the strength of which the disputes

between the parties was referred in the instant case to arbitration,

that is, Clause 64, in sub-clause(ii), restricts additional claims to be

made later on. If the Arbitral Tribunal derives powers from the self-

same contract, it was not for the Tribunal to go beyond the agreement

itself, as the parties themselves have chosen the procedure to be

followed. Under Section 19(2) of the 1996 Act, the parties are free to

agree on the procedure to be followed by the Arbitral Tribunal in

conducting its proceedings. Since the parties chose to exclude

subsequent additional claims, the tribunal was bound by the same.

37. In the present context, insofar as claim no.1(iv), claim no.4, claim

no.5, claim no.6 , claim no.9 and claim no.10 are concerned, since the

Arbitral Tribunal did not grant any award to the claimant/respondent,

the said claims are not being dealt with, being beyond the subject-

matter of the present challenge.

38. Claim no.1(i) was granted by the Tribunal. In paragraph 9.1.1.4 of the

award, the respondent/present petitioner was directed to release an

amount of Rs. 1,20,09,342-/ to the claimant under the head of

amount withheld on CC/30th/Account Bill. Although disputes as to

measurement are precluded from arbitration, falling within Clause

22(5), which is one of the excepted clauses, while granting claim 1(i),

the Tribunal based its award on the measurements of the petitioner-

Railway itself. As such, there could not be any fault found with such

adjudication, as the Tribunal did not enter into the merits of the

measurements but relied on the measurements of the Railway itself.

39. Insofar as the award on claim 1(ii), as incorporated in paragraph

9.1.2.3 of the award is concerned, the same was on the basis of the

admitted 7th(final) Escalation Bill. It being an admitted position and

no adjudication on merits being entered into, the premise of the said

component of the award cannot be faulted either on the same logic.

40. Under claim 1(iii) of the claimant relating to the CC/31stOn Account

Bill, the Tribunal observed that an amount of Rs 1,12,69,519/-was

recoverable from the claimant against the final bill. Apart from the

said verdict going against the claimant/respondent, the same was

based on detailed calculations, a summary of which was given in the

award. Hence, the said component of the award cannot be interfered

with at all at the instance of the respondent-Railway.

41. Coming to claim 2, the same pertained to recovery of Security Deposit,

as retention money from the claimant's On Account Bills, for

Rs. 10,48,723/-.The entire claim was granted by the Tribunal. The

logic behind the same was furnished in paragraphs 8.3.1-8.3.4 of the

award. In the said paragraphs, the tribunal categorically entered into

the question whether the termination of the contract was proper and

justified. While holding so, the Tribunal observed that the Railways

themselves "seemingly created the circumstances" for making the

contractor unable to perform. Solely on such premise, the Tribunal

proceeded to declare the termination of contract to be without merit.

However, it is well-settled that the Arbitral Tribunal is a creature of

the contract between the parties. An arbitral tribunal is clothed with

its powers by virtue of the agreement between the parties and, thus,

cannot go beyond its charter as vested by the agreement, which is the

source of its powers.

42. The disputes and differences which can be referred to arbitration is

governed by Clause 63 of the agreement between the parties in the

present case, which specifically provides that the matters coming

within the ambit of exception clauses as mentioned therein would not

be arbitrable between the parties.

43. Such "excepted matters" include Clause 61(1) and Clause 61 (2), the

first of which pertains to the entitlement of the Railways to determine

and terminate the contract at any time should, in its opinion, the

cessation of work becomes necessary owing to the grounds mentioned

therein.

44. Sub-Clause (2) of Clause 61 provides for determination of contract

under sub-clause (1), in which case if the contractor claims payments

for expenditure incurred by him in the expectation of completing the

whole work, the Railways are to admit and consider the same.

45. However, the relevant clause here is Clause 62, which relates to

determination of contract owing to default of contractor. The said

clause also comes within the purview of "excepted matters". Under

sub-clause (vi) of Clause 62, abandonment of the contract is one of the

grounds of determination. Such determination falls within Clause 62,

which is an excepted matter in terms of Clause 63 which governs the

disputes arbitrable between the parties. More importantly, the

claimant never made any specific claim in the arbitral proceeding

challenging the termination itself.

46. The premise of the Railway retaining the security or retention money

was the termination of contract, upon which the Railway is entitled as

per the contract itself to retain the Security Deposit. Without

challenging the termination and despite the termination falling within

the cloak of protection of excepted matters under Clause 62 of the

agreement, the Arbitral Tribunal traversed palpably beyond its powers

in adjudicating on such issue.

47. Section 34 (2)(a)(iv) of the 1996 Act provides that an arbitral award

may be set aside by the Court if the award deals with a dispute not

contemplated by or not falling within the terms of the submission to

arbitration or if it contains decisions on matters beyond the scope of

the submission to arbitration. The proviso thereto stipulates that if the

decisions on matters submitted to arbitration can be separated from

those not so submitted, only that part of the arbitral award which

contains decisions on matters not submitted to arbitration may be set

aside.

48. Following such principle, the award on claim 2 is liable to be set aside.

49. The Railway has also challenged the award on claim 3, regarding

refund of Bank Guarantee, which has been dealt with by the Arbitral

Tribunal inparagraph9.3.7 of the award.

50. The Railway/petitioner argues that the same is a new claim, beyond

the purview of the original demand and, thus, falling beyond the scope

of arbitration under Clause 64(1)(iii). However, this Court fails to

satisfy itself on such count. The Bank Guarantees were by nature

performance guarantees and mobilization advance guarantees. The

furnishing of such Bank Guarantees was inextricably connected with

performance guarantee and mobilization advance, which directly

emanate from the dues of the claimant on the bills for work done.

They are not related to termination, since no clause in the agreement

links the retention of Bank Guarantee with termination. As such,

adjudication on such claim does not touch on the termination of

contract, which is an excepted matter.

51. Hence, the refund of the Bank Guarantees invoked by the

respondent/petitioner cannot be seen as a new claim but comes

squarely within the ambit of the original reference which touches

upon non-payment on bills raised by the claimant for work done.

Clause 61,sub-clauses (1) and (2) do not envisage forfeiture of Bank

Guarantee amounts in excess of Security Deposit on termination. The

Bank Guarantee amounts are not included within the Security

Deposit, forfeiture of which is linked with termination; thus, the

Arbitral Tribunal acted well within the confines of its jurisdiction in

awarding such amount. Since this Court is not sitting in a regular

appeal over the same, the factual adjudication of the Tribunal on

claim 3 cannot be interfered with even if a different view were to be

possible on the materials on record.

52. The next disputed question which arises is the award on claim 7,as

granted in paragraph 9.7.6 of the award.

53. The Railway/petitioner takes an objection on the ground that Clause

64(5) of the agreement between the parties provides that were the

arbitral award is for the payment of money, no interest shall be

payable on whole or any part of the money for any period till the date

on which the award is made. The Railway seeks to confuse the award

component on claim 7 with „interest‟.

54. However, the interest on mobilization advances which were sought to

be refunded under claim 7 were payments which had already been

made by the claimant to the Railways. The Arbitral Tribunal held that

the 12% interest already charged by the Railways beyond the original

completion date was without Authority and reduced the same to 5%

interest. The effect thereof was that the Railways had to refund the

balance amount after deduction of interest already paid to the

Railways at the rate of 12% from interest calculated at 5%.The net

effect of the said award-component is that an amount already

deducted in excess by the Railways was directed to be partially

refunded to the claimant.

55. As opposed to the interest envisaged in Clause 64(5) which is an

additional component of interest payable on an awarded amount,

claim 7 comprised itself of an award for payment of money, being

refund of excess interest already deducted from the claimant. Thus,

there is a clear distinction between claim 7, which comprises of a

direction to refund an amount already withheld by the Railway, from

an additional component of interest imposed on an awarded amount

by the Tribunal. In the present case, claim 7 did not comprise of any

additional interest component of an award granted by the Tribunal

but was itself a part of the principal arbitral award. Hence, such

objection of the Railway is specious and hereby turned down.

56. However, as far as claim 8 is concerned, as awarded in

paragraph9.8.4 of the award, the same is directly contrary to Clause

17A, sub-clauses (ii) and (iii) of the GCC. The said sub-clauses clearly

provide that no other compensation, apart from necessary extension of

time, shall be payable for works carried forward to the extended period

and that even if there was a failure or delay on the part of the Railway

to handover to the contractor possession of the lands necessary for

execution of the works, such failure/delay shall in no way affect or

vitiate the contract or entitle the contractor to damages or

compensation therefor, but in any such case, the Railway was to grant

such extension of the completion date as may be considered

reasonable.

57. Even in the teeth of such specific bar to extra compensation, the

Tribunal, under claim 8, precisely granted such compensation. Claim

8 was refund of commission paid to its bank by the claimant for

extension of Bank Guarantees from time to time beyond the original

contractual period.

58. It is to be considered that the extension beyond the original

contractual period was sought by the claimant itself and accordingly

granted by the Railway Authorities. After having asked for such

extensions and being granted the same, the claimant is squarely

covered by the bar under Clause 17A, sub-clauses (ii) and (iii) and

cannot be held to be entitled to further damages or compensation

therefor. The commission paid to the bank for extension of Bank

Guarantee was willingly paid by the claimant for seeking the

extensions and if such commission is also directed to be borne by the

Railway, the same would tantamount to additional damage or

compensation for such extension, which is palpably barred under

Clause 17A as discussed above.

59. In such view of the matter, the said component of the award is also hit

by Section 34(2)(a)(iv) of the 1996 Act, and thus ought to be set aside.

60. Lastly, claim 11 pertained to interest on the awarded amounts which

was granted by the Tribunal in paragraph 9.11.4 of the award.

However, Clause 64(5) of the GCC is a clear bar to grant of interest,

since it stipulates that where the arbitral award is for the payment of

money, no interest shall be payable on whole or any part of the money

for any period till the date on which the award is made. Hence, the

said component of the award is also vitiated by Section 34(2)(a)(iv) of

the 1996 Act. The claim of interest being barred by the same

agreement which clothes the Arbitral Tribunal with the power to

adjudicate, the said bar had to be adhered to by the Tribunal. The

interest component granted in the teeth of the bar was clearly violative

of the contract between the parties and, being covered by the „excepted

matters‟, was beyond the scope of arbitrable disputes as envisaged by

the agreement between the parties.

61. In view of the above, insofar as the awards pertaining to claim nos.2,8

and11 are concerned, those being beyond the scope of submission to

arbitration and containing decisions on matters beyond such scope,

are palpably violative of Section 34(2)(a)(iv) of the 1996 Act. Since

those parts can be clearly segregable from the rest of the award in

terms of the proviso to Section 34(2)(a)(iv), those components of the

award are liable to be set aside.

62. Accordingly, AP-COM No. 208 of 2024 [Old Case No. AP No. 245 of

2021] is allowed in part on contest, thereby setting aside the

impugned award of the Arbitral Tribunal insofar as is it relates to

claim nos. 2, 8, 11.

63. There will be no order as to costs.

64. Urgent certified server copies, if applied for, be issued to the parties

upon compliance of due formalities.

( Sabyasachi Bhattacharyya, J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter