Citation : 2023 Latest Caselaw 2539 Cal/2
Judgement Date : 6 September, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Original Side
The Hon'ble Justice Sabyasachi Bhattacharyya
WPO No. 1434 of 2023
Reliable Facility Services Private Limited and Another
Vs.
Government of West Bengal and Others
For the petitioners : Mr. Suddhasatva Banerjee, Adv.
Mr. Pushan Kar, Adv.,
Mr. Sagnik Majumdar, Adv.,
Mr. Abhidipto Tarafdar, Adv.
For the State : Mr. Sirsanya Bandopadhyay, Adv,
Mr. Arka Kr. Nag, Adv.
Hearing concluded on : 21.08.2023
Judgment on : 06.09.2023
Sabyasachi Bhattacharyya, J:-
1. The petitioner-Company is engaged in the business of providing
housekeeping and maintenance services. It participated in a tender
dated March 3, 2023 floated by the respondent-Authorities and
emerged as the L-1 bidder. The respondents sought a justification of
the prices submitted by the petitioners in terms of the Clause 8.9.5 of
the tender document on the ground that the petitioners‟ bid was much
less than the quoted price of the bid items.
2. The petitioners provided justification by citing efficient operation and
bulk purchase of material, resulting in significant discounts enjoyed
by the petitioners. However, such justification was rejected by the
respondents and the petitioners were required to perform a
demonstration of the proposed work at the premises of Khadyashree
Bhawan. Although it is argued that such demonstration was not part
of the conditions of the tender, the petitioner participated to secure
and perform the contract.
3. It is argued by the petitioners that subsequently the respondents
imposed additional obligations in the form of new conditions, which
were foreign to the tender, including use of a particular brand of glass
cleaning material, enhanced rate of security deposit and additional
security deposit, if the Letter of Acceptance was to be awarded to the
petitioners. Such conditions were communicated to the petitioners
vide letter dated April 25, 2023, which also mentioned that the
petitioners‟ failure to perform the said conditions would lead to
forfeiture of the earnest money deposit and/or cancellation of the
petitioners‟ bid.
4. It is argued that the said conditions were arbitrary and imposed
subsequent to the bidding process.
5. The petitioners‟ wrote an advocate‟s letter dated April 28, 2023
expressing such grievances. The respondent invited the petitioners to
a meeting by dint of a letter dated May 16, 2023, which was to be held
on May 24, 2023 for settling disputes.
6. However, subsequently, by a letter dated May 30, 2023, the
respondents cancelled the entire tender process and forfeited the
earnest money deposited by the petitioners, in the process debarring
the petitioners from participating in future bids for a period of five
years.
7. It is argued that the bid prices of the four participants in the tender
were similar and there was hardly any difference in the quoted prices
between the petitioners and the L-2 bidder.
8. The present writ petition, thus, has been preferred challenging the
order of blacklisting dated June 30, 2023 and seeking refund of the
earnest money deposited by the petitioners.
9. Learned counsel for the petitioner argues that the blacklisting of the
petitioner no.1 was done for five years without a prior show-cause
notice or opportunity of hearing being given to the petitioners. An
order of blacklisting has severe civil consequences and such action on
the part of the respondents amounts to violation of principles of
natural justice.
10. In support of such contention, learned counsel for the petitioners cites
UMC Technologies Private Limited Vs. Food Corporation of India and
others, reported at (2021) 2 SCC 551, as well as an unreported
judgment dated June 26, 2023 passed in WPO No.1317 of 2023 [HI
Speed Logistic Pvt. Ltd. and Another Vs. Food Corporation of India and
others] and the judgment dated June 13, 2023 in WPO No.742 of 2023
[Pranab Bose Vs. Union of India and Others].
11. Learned counsel next argues that no loss or damage was suffered by
the respondents in the tender process and as a result, the earnest
money could not be forfeited. No party can stand to gain from a
situation when no work order has been placed and no loss has been
suffered. It is argued that in the absence of proof of actual loss, the
respondents acted illegally in insisting upon forfeiture of the earnest
money.
12. In such context, learned counsel cites Kailash Nath Associates Vs.
Delhi Development Authority and Another, reported at (2015) 4 SCC
136.
13. The petitioners next argue that a State or a statutory body is expected
to act reasonably and rationally and cannot be permitted to enrich
itself in an unjust manner. In support of such contention, learned
counsel cites MBL Infrastructure Limited Vs. Rites Limited and Others,
reported at 2020 SCC OnLine Cal 478.
14. Learned counsel next contends that even in a case where the party if
aware of the consequences of blacklisting, which is to take place if
certain conditions prescribed are not met, the blacklisting authority
must issue a show-cause notice, provide a hearing, and observe the
principles of natural justice. The show-cause notice must mention
blacklisting as one of the consequences, which was entirely absent in
the present case.
15. In support of such proposition, learned counsel cites Gorkha Security
Services Vs. Government (NCT of Delhi) and Others, reported at (2014)
9 SCC 105.
16. It is further argued by learned counsel for the petitioners that the
existence of an arbitration clause is not an absolute bar to maintain
an application under Article 226 of the Constitution of India. For
such proposition, learned counsel cites Prabir Kumar Bidya Vs. The
Union of India and Others [WPA No.10713 of 2018].
17. Lastly, it is contended that the clause of the contract referred to in the
impugned decision does not authorise forfeiture of earnest money
deposit. The clauses authorising forfeiture coupled with power of
blacklisting had not admittedly been invoked and are also completely
inapplicable to the facts of the case as the bid of the petitioners has
not been cancelled but the petitioners have withdrawn their bid. Only
if the bid is cancelled, the same "may" draw the consequences of
forfeiture and blacklisting. Learned counsel, in the context of
interpretation of the word "may", cites Bhikhubhai Vithlabhai Patel and
Others Vs. State of Gujarat and Another, reported at (2008) 4 SCC 144.
18. Learned counsel also places reliance on certain relevant clauses of the
tender document.
19. Learned counsel appearing for the respondent nos.1 to 4 submits that
in view of the existence of an arbitration clause (Clause 10.1.1) in the
Notice Inviting Tender (NIT), which covers any dispute between the
parties, the petitioners had an alternative efficacious remedy in the
form of arbitration. Hence, the present writ petition ought not to be
entertained.
20. It is argued that vide a letter April 10, 2023, the Deputy Secretary,
Government of West Bengal sought justification from the petitioners
for the violation of Clause 8.9.5 specified in the tender document, as
the petitioners, in every item of the bid, quoted much less price. It is
argued that the power to call for an explanation is contained in Clause
8.9.5.
21. The petitioners insinuate that the representative of the L-2 bidder was
present on the date that is April 19, 2023, before the tender committee
when the petitioners attended that meeting. It is clarified by the
respondents that so far as the L-1 bidder is concerned, they have
quoted a rate which is more than 20% less than the expected price,
whereas the L-2 bidder also quoted a price less than 20% in some of
the items apart from four. That is the reason why the L-2 bidder was
also called along with the L-1 bidder for providing justification to their
quotations.
22. The petitioners have argued on the forfeiture of EMD without any
proper reason, but the respondents contend that Clause 6.5.1of the
NIT specifies that EMD can be forfeited in the following circumstances:
i) Withdrawal of bid;
ii) False or faulty documentation,
iii) Any unilateral revision made by the bidder during the valid
period of offer.
23. Clause 8.9.5 also says that the tenderer has a right to forfeit the EMD
amount if the contractor quotes a price below 80% of the estimated
price of the items other than the manpower price, which was
applicable in the present case.
24. Even assuming that a wrong provision or clause was quoted in the
impugned order dated June 30, 2023, such error is inconsequential.If
the authority has the power, quoting a wrong clause would not nullify
the findings.
25. With regard to the requirement of notice, learned counsel for the
respondent nos.1 to 4 argues that the petitioners were already aware
of the consequence and had replied through their advocate‟s letter
annexed at page 94, paragraph (e) of the writ petition. Hence, the
action taken by the respondents was not a surprise for the petitioners.
The purpose of notice of prior hearing is that no action for which civil
consequences follow is be intended to be a surprise. In the present
case, there was no surprise element at all.
26. Learned counsel for the respondent nos. 1 to 4 next argues that the
mere participation and offering of bid price less than 80% do not
accrue any vested right in favour of the petitioners, even if they were
an L-1 bidder. Learned counsel submits that the facts of MBL
Infrastructure Limited (supra) were different and hence not applicable
to the present case.
27. Insofar as Gorkha Security Service (supra) is concerned, paragraph 25
thereof states the clause considered by the Supreme Court, which is
significantly different from the present case. In the present case, the
phrase "if so warranted" is absent, which phrase, in the said case,
compelled the Supreme Court to come to the finding in paragraphs 26
and 27 of the judgment.
28. Shanti Sports Club (supra) is distinguishable on facts as well. Kailash
Nath Associates (supra), interpreted with MBL Infrastructure Limited
(supra), cannot be applicable at all when the bid is cancelled and after
participation in the tender process. The petitioners cannot now say
that the clause specified for forfeiture of the EMD in the NIT is
outrageous and against the law, it is argued.
29. Heard learned counsel for the parties.
30. A perusal of the tender document reveals that Clause 10.1 contains
an arbitration clause. However, the nature of the allegations in the
present writ petition is gross violation of principles of natural justice
and patent arbitrariness. Thus, if the said allegations are established,
the present case would fall within the window stipulated by the
Supreme Court time and again for interference under Article 226 of
the Constitution of India, which principle has also been reiterated in
Prabir Kumar Bidya (supra), cited by the petitioners. Hence, the
objection as to availability of arbitration as an alternative recourse is
turned down and the writ petition is entertained.
31. In order to examine on merits whether the petitioners are entitled to
the reliefs sought, the relevant clauses of the tender document are of
utmost importance.
32. With regard to forfeiture of earnest money, two clauses are of
importance. The first Clause, referred to by both sides, is Clause
8.9.5 of the tender document. As per the said provision, if the
contractor quotes price below 80% of the estimated price of the items
other than manpower, the contractor/agency will have to submit
justification mathematically along with authenticated documents to
support the low bid price along with supportive documents, otherwise
the authorities reserve the right that the bid may be cancelled and it
may draw the forfeiture of the EMD amount along with other
conditions to bar the said low bidder to take part in the future tender
process of the Food and Supplies Department.
33. The other provision is Clause 6.5.1 which provides that the Food and
Supplies Department reserves the right to forfeit the earnest money
deposit (EMD) of any bidder in certain circumstances. The first
ground enumerated there is withdrawal of bid, while bids are under
consideration during the tender period. The bid was withdrawn by the
present petitioner by citing certain reasons. However, it is required to
be ascertained whether such withdrawal was "while bids are under
consideration during the tender period".
34. The next sub-clause relates to false or faulty documentation,
fabricated information and documentation and failure to execute the
work or part thereof, as stated in the terms and conditions. There is
no specific allegation that any of the documentations were faulty. The
information supplied by the petitioners was not alleged to be
fabricated as such, nor could there be any failure to execute the work
or part thereof on the part of the petitioners, since the work was not
awarded to them at all. Unilateral revision made by the bidder, in
terms of the third sub-clause, is also not applicable, as is sub-clause
(iv), which is failure to accept the work order for executing the
document or submit security deposit, which was not be present case,
since no work order was issued at all.
35. Certain facts are to be ascertained from the correspondence annexed
to the writ petition. Upon the petitioner no.1 turning out to be the
successful bidder, the respondent-Authorities communicated in
writing to the petitioners on April 10, 2023 clarifying that the
petitioners had submitted a much „less‟ quoted price of the bid items,
for which a hearing was given to the petitioners.
36. Two days thereafter on April 12, 2023, the petitioner no.1 wrote a
reply thereto to the authorities, where they gave certain explanations
including that the petitioner no.1 was a leading organization providing
such facilities across West Bengal and that the petitioners get bulk
discounts on their purchases and also control the material
misutilization and wastage.
37. In any event, as admitted by the petitioners, the hearing and
demonstration asked from the petitioners was within the authority of
the tender-issuing authorities as per the tender document and cannot
be faulted on such score.
38. Interestingly, from the documents annexed at pages 83 and 84 of the
writ petition, which was an annexure to the reply of the petitioners
dated April 12, 2023, it is seen that in the projected monthly materials
required for facility management services for the Khadyashree Bhawan
tentatively disclosed by the petitioners to clarify the doubt regarding
quotation of less price, they mentioned certain particular brand
names of products, including the brand name of a particular product
which was apparently to be used as a glass cleaner. Serial No.4 of the
said material list furnished by the petitioners themselves named a
particular brand of glass cleaner. It was claimed in the same row of
the list that five litres of the said brand name of glass cleaner would
require an expenditure of Rs.1265/-.
39. In continuance of the tentative monthly calculation for facade cleaning
for facility management of the Khadyashree Bhawan, the petitioners
quoted a price of Rs.620/- for five litre of the same brand name of
glass cleaner.
40. Again, in another sub-list annexed with the communication of the
petitioners dated April 12, 2023, it was mentioned that three litres of
the same glass cleaner would require Rs.450/-.
41. Hence, the insistence in the further reply of the respondents in their
communication dated April 25, 2023 that the said particular brand
name of glass cleaner be used by the petitioners for giving the
demonstration, was not at all unjust but, rather, in consonance with
the claim made by the petitioners. It is obvious that if the petitioners
did the job during demonstration with some other brand, the costs
would vary considerably, thereby leaving no scope for the authorities
to ascertain the veracity of the demonstratively low price quoted by the
petitioners.
42. In the communication dated April 25, 2023, certain "additional"
Clauses were allegedly mentioned. The petitioners have vociferously
argued that such introduction of new clauses at a belated stage was
beyond the scope of the tender and the petitioners could not be
penalized on such ground.
43. A scrutiny of the so called „additional‟ clauses shows that the first of
those specified that only glass cleaning product of the brand name
suggested by the petitioners should be used for the purpose of glass
cleaning and the other named products, as mentioned by the
petitioners themselves, should be used accordingly for the cleaning
operation and other services. Such clause was not an „additional‟
clause as such, but only a reiteration of the original clauses of the
tender document, read in conjunction with the claims made by the
petitioners themselves.
44. There has to be a transparency in the bidding process, both from the
end of the tender-issuing authority and the bidders. Clarity and
transparency are not a one-way traffic.
45. In the present case, particular criteria were mentioned in the tender
document, pursuant to which specific bids were made by the
petitioners. At the clarification stage which was allowed by the tender
document, the petitioners quoted specific prices in reply to the charge
of the petitioners having quoted demonstratively less prices, referring
to particular brands for particular components of the job envisaged
under the contract.
46. Hence, the insistence of the authorities that in order to achieve
compliance and adherence to the prices actually quoted by the
petitioners, the same brands were to be used during the work, was
neither unjust nor arbitrary.
47. Clause (ii) of the „additional‟ clauses stipulated that cleaning and other
operations shall have to be performed as per the scope of the work of
the NIT and as per the declaration given by the petitioners in their
letter dated April 12, 2023, failure or shortfall to provide satisfactory
service in which regard would entail imposition of penalty as per the
terms and conditions of the NIT. As Clause (i), Clause (ii) is also not a
new clause sought to be introduced later.
48. Clause (iii) stipulated that in terms of the Memo dated February 25,
2022, as the reduced rate of security deposit at 3% ends on March 31,
2023, Rs.14,14,854/- (10% of the total amount of Rs.1,41,48,540/-
that is 10% of the tender value) would be the security deposit
including the EMD amount. The said clause was not de hors the
contemplation of the NIT; rather, was provided for in the tender
document itself.
49. The same logic applies to Clause (iv) which stipulates that additional
performance security of 10% of the tendered value as per the Memo
dated July 18, 2018 would have to be submitted if the tender inviting
authority decided to offer Letter of Acceptance of the tender.
Manpower utilisation, Clause (iv) provide, would also require that
payment should be as per NIT. Thus, the warning of cancellation of
the petitioners‟ bid and forfeiture of EMD was clearly issued in the
communication dated April 25, 2023.
50. In their advocate‟s letter dated April 28, 2023, the petitioners raised
several objections. One of the grounds of challenge by the petitioners
was that the expression "may" was mentioned in Clause 8.9.5 of the
NIT. The said phrase is sought to be interpreted by the petitioners to
mean that there cannot be any automatic forfeiture or that the
forfeiture clause cannot be absolute.
51. Such argument cannot be accepted in the present case, since Clause
8.9.5 clearly stipulates that if the contractor quotes prices below 80%
of the estimated price, the contractor/agency would have to submit
justification mathematically along with authenticated documents to
support the low bid price and supportive documents. Otherwise, it is
stipulated, the respondents reserves the right that the bid may be
cancelled and it may draw the forfeiture of the EMD amount along
with other conditions to bar the said low bidder to take part in the
future process of the Food and Supplies Department.
52. Clause 8.9.5 is composite, contemplating cancellation of the contract,
forfeiture of the EMD amount and debarment of the concerned bidder
in the same breath.
53. The interpretation sought to be lent by the petitioners to "may" is not
acceptable. The very construction of the sentence clearly indicates
that it is the respondents who reserved the right of cancellation,
forfeiture and debarring the bidder. Hence, the forfeiture comes into
operation the moment the respondents so choose subject, of course, to
the satisfaction of the earlier portion of Clause 8.9.5.
54. In the present case, the petitioners quoted price below 80% of the
estimated price and a justification was sought. In the clarificatory
meeting, the petitioners failed to satisfy the respondent-Authorities by
their demonstration. Having failed so, particularly in the perception of
the respondent-authorities, the petitioners cannot now resist the
exercise of due discretion by the respondent-Authorities in cancelling
the bid and forfeiture of the EMD amount as per the terms of the
tender document.
55. The communication dated May 16, 2023 by the respondents to the
petitioners was a notice for the petitioners to be present in the meeting
as per the financial bid in the NIT for the process of the financial bid
evaluation, settling disputes if any and selection of the bidder to serve
as agency for facility management for Khadyashree Bhawan.
56. Subsequently, vide notice dated June 30, 2023, which is impugned
herein, the petitioners were informed that upon clarification and
justification sought for the bid price quoted on different items of work
as per the scope of work and the demonstration of the petitioners on
April 17, 2023, in the perception of the respondents, the same clearly
established that the material quantity and expenses shown in the
mathematical justification are seemingly imaginary.
57. In fact, a hearing was given to the petitioners on May 24, 2023.
58. The petitioners had expressed their unwillingness to serve the
respondent, for which the petitioners were debarred from participating
in the future bids for five years.
59. Before going further, it is to be noticed that one of the objections taken
by the petitioners is that the L-2 bidder was also present at the
hearing.
60. In the present case, the tender process itself has been aborted in view
of both the L-1 and L-2 bidders having failed to satisfy the authorities
on mathematical justification on their significantly low bids, below
80%. Hence, nothing turns on the presence of the L-2 bidder who was
also rejected in the process. That apart, the respondents have
sufficiently justified the presence of the L-2 bidder in the meeting,
since both the L-1 bidder (petitioners) and the L-2 bidder had quoted
low bids, less than 80% of the estimated price.
61. Hence, the meeting and the exercise calling for demonstration cannot
be vitiated in any manner. In any event, the petitioners participated in
the same.
62. Interestingly, the petitioner, after being served with the notice dated
April 25, 2023 where the respondents insisted upon use of the
particular brand name cited by the petitioners themselves, shied away
from such proposal.
63. In fact, the respondents were gracious enough to give another
opportunity to the petitioners to stick to their own cited brand names,
to satisfy the prices quoted by the petitioners corresponding to such
brand name.
64. The result of the communication by the respondents dated April 25,
2023 was, however, a reply by the petitioners dated April 28, 2023,
which was an advocate‟s letter sent by the petitioners. Apart from
quoting certain provisions, the petitioners clearly and in no uncertain
terms requested the respondents to cancel the subject-tender and
refund the EMD money at the earliest within a period of seven days.
Legal action was also threatened by the petitioners.
65. Thus, in the letter dated April 28, 2023, the petitioners, instead of
sticking to their own quotations, expressed an unequivocal intention
to withdraw from the work, after turning out to be the successful
bidder.
66. Reverting back to the clauses of the contract, Clause 6.5, in sub-
clause (i), specifies, as a ground for forfeiture of EMD, the withdrawal
of bid while bids are under consideration during the tender period.
67. Although the parties were at a juncture when, strictly-speaking, the
tender process was over, no work order had yet been issued. The
hearing and demonstration sought by the respondents were also
broadly within the contemplation of the tender process, as evident in
the tender document. Hence, the withdrawal of the bid by the
petitioners was during the tender period. Thus, under 6.5.1, the
respondents had the right to forfeit the amount of EMD.
68. In any event, nothing remained to be cancelled, the since the
petitioners chose to withdraw from the tender process after having
turned out to be successful but having been exposed in the
demonstration and hearing before the respondent-Authorities.
69. Clause 8.9.5 further empowers the respondents, in the event the
contractor fails to justify mathematically along with authenticated
documents to support the low bid price if the prices quoted are below
80% of the estimated price, to cancel the bid and to exact forfeiture of
the EMD amount. Clause 8.9.5 also stipulates that the concerned
bidder may be restrained from taking part in future tender process of
the Food and Supplies Department.
70. Hence, there is no illegality or arbitrariness in the decision-making
process of the respondent-authorities in cancelling the bid of the
petitioners and forfeiting the EMD amount, strictly in terms of the NIT.
71. The next question which arises is whether the respondents blacklisted
the petitioners without a show-cause notice.
72. The requirement of a prior show-cause notice, to grant sufficient
opportunity of hearing to the concerned party, is an essential
component of natural justice, as laid down in UMC Technologies
Private Limited (supra), HI Speed Logistic Pvt. Ltd. (supra) as well as
Pranab Bose (supra), all cited by the petitioners.
73. The question which arises is whether the show-cause notice must
mention blacklisting as a consequence as well.
74. In Gorkha Security Services (supra), the question which came up for
consideration was the necessity of serving show-cause notice as a
requisite of the principles of natural justice. The effects of blacklisting
were discussed by the Supreme Court, as reiterated in several
judgments, and it was observed that a show-cause notice has to
precede a blacklisting.
75. A show-cause notice, as held by the Supreme Court, has to meet two
requirements, namely that the materials/grounds which according to
the department necessitate an action are to be stated, and the
particular penalty/action which is proposed to be taken is also
required to be mentioned.
76. The Supreme Court in the said case also reiterated that the purpose of
a show-cause notice is primarily to enable the noticee to the meet the
grounds on which the action is proposed against him.
77. In such context, let us consider the instant case. The first notice on
the part of the authorities was dated April 10, 2023 where the
authorities clearly mentioned that the price quoted by the petitioners
was less than 80% of the estimated prices, for which a hearing was
given to the petitioners.
78. The petitioners gave a reply to such notice on April 12, 2023
disclosing certain explanations for the meagre price. The petitioners
also cited tentative monthly materials required for the job
contemplated under the tender.
79. In fact, specific parameters were also mentioned by the petitioners in
their reply. Subsequently, on April 17, 2023, the petitioners gave a
demonstration. It is to be remembered that Clause 8.9.5 was well
within the knowledge of both the parties. In fact, the insistence of the
respondents for a mathematical justification and demonstration was
all along disclosed by the respondents to be due to the quotation of
the petitioners being less than 80% of the estimated price, within the
contemplation of Clause 8.9.5. Hence, the petitioners all along had a
clear idea as to the reason for which they were being given a hearing
and were required to give a demonstration as well.
80. The mere pretext that the petitioners were never given a show cause
notice indicating the exact ground of blacklisting or indicating the
consequences of blacklisting pales into insignificant, since the notice
dated April 10, 2023 issued by the respondents clearly mentioned that
failure on the part of the petitioners to submit proper justification as
well as dissatisfaction on the score of such justification would entail
that the respondents would take action "as appropriate as per the
NIT". Clause 8.9.5 was a part of the NIT and was specifically quoted
in the communication dated April 10, 2023. In the very second
sentence of the communication, it was mentioned that the tender
committee found that contrary to the Clause in the NIT at section
8.9.5, the petitioners had submitted much less as the quoted price of
the bid items.
81. Read in a composite manner, the entire text of the communication
dated April 10, 2023 was a clear show cause notice to the petitioners
regarding the alleged violation of clause 8.9.5 and the probable
consequence of implementation of Clause 8.9.5 "as appropriate, as per
the NIT".
82. In fact, the petitioners not only got an opportunity of hearing and gave
a reply on April 12, 2023, the petitioners actually participated in the
hearing and had an opportunity of dispelling the doubts in the minds
of the respondents. A demonstration was also sought from the
petitioners and was given by the petitioners, which resulted in
dissatisfaction of the authorities on the score of mathematical
justification as communicated in the letter dated April 25, 2023.
83. The respondent-Authorities, however, went one step further in fairly
granting a further opportunity to the petitioners to stick to the brands,
corroborating to the respective estimated prices, quoted by the
petitioners themselves, to do the work. It was also mentioned in the
said communication dated April 25, 2023 that failure and/or
dissatisfaction of the tender committee might lead to cancellation of
the petitioners‟ bid and forfeiture of the EMD, to be decided by the
authority of the department.
84. Clause 8.9.5 was all along implicit in the various opportunities of
hearing and demonstration given to the respondents and was the
premise of the replies given by the respondents, which also included
the repercussion of blacklisting.
85. Thus, the petitioners cannot now be permitted to argue that they were
not at notice of the consequence of blacklisting, which was implicit in
Clause 8.9.5, which was quoted by the authorities in their
communications, having got several opportunities of hearing,
representation and demonstration on such count.
86. What the petitioners did after that is also required to be factored in.
On April 28, 2023, instead of taking the opportunity given by the
respondents, the petitioners wrote an advocate‟s letter where they did
not limit themselves to disputing the stand taken by the respondents
but also went to the extent of requesting the respondents to cancel the
subject-tender and refund the EMD money at the earliest, failing
which the petitioners threatened legal action.
87. Such stand of the petitioners clearly comes within the purview of the
first sub-clause that is sub-clause (i) of Clause 6.5.1 of the tender
document, which stipulates that withdrawal of bid, while bids are
under consideration during the tender period, would entail forfeiture
of the EMD.
88. Clause 6.5.1, read in conjunction with Clause 8.9.5, clearly justifies
the respondents‟ impugned action.
89. Insofar as the allegation of imposition of additional conditions by the
respondents is concerned, the same is also incorrect on the score of
security deposit, since Clause 8.3.1 of the tender document provides
that the successful bidder shall furnish within a week of the
acceptance of the tender a security deposit of Rs.4,25,000/- (3% of the
annual contract value), on failure of which and not taking over the
work, the EMD amount would be forfeited and the bidder would be
debarred for a period years of future tender of the respondent-
Authorities, on which the decision of the authorities would be final
and binding to the bidder. Thus, there is no scope of attributing
erroneous imposition of additional costs on the respondents on such
count as well.
90. Apart from the arbitration clause, Clause 8.4 of the NIT stipulates that
in the event of any dispute between the respondents and the
petitioners, the Principal Secretary/Secretary and/or designated
officer on behalf of the respondent-Authorities reserves the sole
discretion to settle the disputes and his/her decision is final, with
which the contractor is to abide by.
91. The petitioners in the present case have not explored any of the said
options as well.
92. The last question which arises is whether the failure of the
respondents to quote the correct clauses in their impugned notice of
forfeiture and debarment if fatal. The respondents, in the said notice,
dated June 30, 2023, clearly speak about the clarification and
justification sought from the petitioners, the demonstration given by
the petitioners on April 17, 2023 and that it established that the
material quantity and expenses shown in the mathematical
justification are seemingly imaginary. It was further cited in the said
communication that the petitioners had expressed their unwillingness
to serve the respondents. Hence, there was a substantial reference to
the pith and substance of the relevant clauses as discussed above.
Clause 6.5.1(iv) was also quoted, which contemplates failure to accept
the work-order or execute the agreement or submit security deposit in
prescribed time as required as per the provision. In the present case,
the petitioners, indeed, failed to accept the work order or execute the
agreement or submit the security deposit in time, more so by their
specific refusal to participate in the work. Thus, Clauses 6.5.1, sub-
clauses (i) and (iv) as well as 8.9.5 of the tender were either quoted or
substantially mentioned, with clear reference to the content of the said
clauses in the impugned notice.
93. Thus, there was no illegality, arbitrariness or unreasonableness in the
decision-making process of the respondent-Authorities in forfeiting the
EMD amount of the petitioners as well as debarring the petitioners for
five years.
94. In such view of the matter, WPO No.1434 of 2023 is dismissed on
contest without any order as to costs.
95. Urgent certified server copies, if applied for, be issued upon
compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!