Citation : 2023 Latest Caselaw 7200 Cal
Judgement Date : 17 October, 2023
Form J(2) IN THE HIGH COURT AT CALCUTTA
Constitutional Writ Jurisdiction
Appellate Side
Present :
The Hon'ble Justice Bibek Chaudhuri
WPA 24344 of 2023
Timir Baran Pramanick
Vs.
The State of West Bengal and Ors.
For the petitioner : Ms. Reshmi Ghosh
Ms. Barnali Gantait
For the State : Mr. Chandi Charan De,
Addl. Govt. Pleader
Mr. Anirban Sarkar
Item No. 09
Heard & Judgement on : 17.10.2023
Bibek Chaudhuri, J.
Indisputably by an acquisition proceeding the land of the
predecessor-in-interest was acquired under the provision of the Act I
of 1894 sometimes in 1968-69 for Salt Lake Reclamation Project.
It is the case of the petitioner that a piece of land measuring
about 3.59 acres was not required in the said project. The said fact
was intimated by the Executive Engineer, Salt Lake Reclamation
Division to the Assistant Secretary, Government of West Bengal,
Metropolitan Development Department. It is clearly stated that the
land measuring about 3.59 acres situated in such a position where the
operation of reclamation work was difficult to proceed and also found
not necessary for the project. So, the said land was lying in
unclaimed position as before and it was kept outside the boundary of
the project. Subsequently, the Deputy Secretary, Land and Land
Reforms Department, Government of West Bengal issued a letter to
the L.A. Collector, North 24 Parganas to transfer process of the said
land in favour of the person from whom acquisition was made. It is
also stated by the petitioners that the acquisition was made only on
paper all along the petitioner and before him his predecessor-in-
interest was in physical possession of the said land. In spite of such
decision having been taken by the State Respondents and for
initiation of process of transferring his land in favour of the petitioner
the Collector directed the petitioner to deposit the compensation
amount which was actually paid and received by the L.A. Collector.
The State Respondents were delaying return of the said land in favour
of the petitioner. This led the petitioner to file WP No.21972(W) of
1999. The said writ petition was disposed of on 12 th September, 2005
by a Co-ordinate Bench holding, inter alia, that the acquisition
proceeding had terminated long ago and the acquired land stood
vested in the Government. Therefore, there is no scope for the
petitioner to get back said land which has been vested to the State by
acquisition process. Accordingly, the said writ petition was dismissed.
However, the Collector, North 24 Parganas was directed to refund
compensation amount of Rs.5616.37/- to the persons who deposited
such sum to the legal heirs and representatives as the case may be
with interest at the rate of 18 per cent per annum to be paid for the
period from December 21, 1994 to December 06, 1999. It is pointed
out by the learned advocate for the petitioner that though L.A.
Collector tendered the said amount, the petitioner did not receive it.
Subsequently, the petitioner preferred an appeal against the said
judgment of WP No.21972(W) of 1999. The said appeal was
registered as FMA 1882 of 2006. The Division Bench of this Court
dismissed the appeal on contest. Thus, the judgment in the above
numbered writ petition by a Single Bench was affirmed. Assailing the
said judgment the petitioner in Indore Development Authority versus
Manoharlal and Others filed an I.A. No. 170346 of 2019 before the
Hon'ble Supreme Court. Subsequently, the learned counsel sought for
permission to withdraw the said application with liberty to file an
appropriate application to initiate independent proceedings.
Accordingly, the said application was rejected giving liberty to the
petitioner to initiate independent proceedings with a direction that
when such an application is filed, it shall be considered in accordance
with law and on its own merits.
After disposal of IA No. 170346 of 2019 by the Hon'ble Supreme
Court, the petitioner has preferred the instant appeal with a prayer to
issue a writ in the nature of mandamus commanding the respondents
to release 3.59 acres of land immediately recorded in C.S. plot No.
4430/6284 at Mouza Krishnapur and Mahishbathan, North 24
Parganas. The petitioner has also prayed for cancellation and/or
recession of the letter dated 6th December, 1999 issued by the State
Respondents.
It is contended by the learned advocate for the petitioner that
as per the decision taken by the competent officers in the State
Government the land in question is required to be resettled and
relinquished in favour of the petitioner. Subsequently, the L.A.
Collector informed the petitioner that the subject land was acquired
and vested to the State and, therefore, the said land cannot be
resettled in favour of the petitioner. The learned advocate for the
petitioner submits that the subject land was not acquired in
accordance with the provision of Act I of 1894. Acquisition is complete
on declaration of award. In the instant case award was declared and
admittedly paid to the petitioner. Subsequently, L.A. Collector held
that the subject land is not required for any public purpose and it
would be resettled in favour of the petitioner. On this score, L.A.
Collector directed the petitioner to deposit the compensation amount
with the Collectorate. He deposited the entire compensation amount
in the treasury. Moreover, till date physical possession of the land has
not been taken by the acquiring authority. Thus, the petitioner is
entitled to get back the land in question. In the alternative he is
entitled to get fair compensation, rehabilitation and resettlement
under Section 24(2) of the Right to Fair Compensation and
Transparency in Land Acquisition Rehabilitation and Resettlement Act,
2013.
The learned Additional Government Pleader has opposed the
prayer made on behalf of the petitioner. It is submitted by him that
once a property vests in the State, it cannot be divested. There is no
provision in Act I of 1894 for relinquishment of vested land in favour
of the land owner. It appears from the order passed in WP 21972 (W)
of 1999 that a Co-ordinate Bench held that the petitioner is only
entitled to compensation and directed the State Respondents to repay
the compensation amount with interest at the rate of 18 per cent per
annum. Thus, this order was affirmed by the Division Bench. Thus,
the issue relating to vesting of subject land and question of payment
of compensation has been finally settled. Thus, question cannot be
reopened at this stage.
Having heard the learned advocates for the petitioner and the
State Respondents and on careful perusal of entire materials on
record I find that the acquisition proceeding in respect of subject land
was complete and the land was vested in the State. Therefore, there
is no scope for relinquishment of the subject land or any part thereof
specially when the acquisition proceeding was concluded by publishing
the award and payment made thereunder. This Court also finds that
Section 24(2) is not applicable under the facts and circumstances of
this case because of the fact that the subject land was vested to the
State and compensation has been paid. It is immaterial as to whether
the petitioner accepted the compensation or award once award is
published after vesting of land. Section 24(2) of the Right to Fair
Compensation and Transparency Act, 2013 has no manner of
application.
In view of the above discussion, I do not find any merit in the
instant writ petition. Accordingly, the instant writ petition is
dismissed.
However, there shall be no order as to costs.
(Bibek Chaudhuri, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!