Citation : 2023 Latest Caselaw 2054 Cal
Judgement Date : 28 March, 2023
AD-03
Ct No.09
28.03.2023
TN
WPA No. 23359 of 2022
Sanjoy Paul
Vs.
Calcutta Electric Supply Corporation Ltd.
(CESC) and others
Mr. Rajendra Banerjee,
Mr. Dip Jyoti Chakraborty
.... for the petitioner
Mr. Debanjan Mukherji
.... for the CESC Limited
Mr. Ayan Banerjee,
Mr. Surajit Biswas,
Mr. Arijeet Bera,
Mr. Aqsa Khan
.... for the private respondent no.6
Learned counsel for the petitioner contends that
the private respondent has no locus standi to object to
the petitioner's application for shifting of an existing
electricity service connection and increase in load.
It is contended by the petitioner that initially a
demolition notice was issued by the Howrah Municipal
Corporation to the petitioner in respect of the
concerned premises. Subsequently, the previous
construction was demolished and upon obtaining a
valid sanction plan, the present petitioner is
constructing a new building. For such purpose, the
shifting of the service connection and the increase in
load have been applied for.
The CESC Limited, it is contended, does not
have any objection otherwise to give such connection
apart from obstruction being raised by the private
respondent.
Learned counsel for the CESC Limited submits
on instruction that, in principle, the CESC Limited
has no objection to shift the electricity connection and
increase the load as sought by the petitioner upon the
petitioner complying with all formalities. However, it
is submitted that the private respondent is objecting
to the same.
Learned counsel appearing for the petitioner, at
this juncture, places reliance on a full Bench
judgment of this court reported at AIR 2011 Calcutta
64 [Abhimanyu Mazumdar vs. Superintending Engineer
and another] for the proposition that if any person is
in settled possession of a property, irrespective of the
lawfulness of his title, the person is entitled to get an
electricity connection independently within the
contemplation of Section 43 of the Electricity Act,
2003 (hereinafter referred to as "the 2003 Act").
Learned counsel appearing for the petitioner
further submits that the private respondent is
objecting to the electricity connection shifting because
of personal grudge, since a previous illegal activity of
the private respondent was challenged by the
petitioner by way of another writ petition.
Learned counsel appearing for the private
respondent controverts the contentions of the
petitioner. It is submitted that the petitioner was
previously served with a 'stop work' notice and a
subsequent demolition notice. Thereafter, the
petitioner has been making a new construction, again
in deviation from the Municipal Laws.
As such, the Howrah Municipal Corporation has
issued a fresh 'stop work' notice to the petitioner. It is
submitted that under Section 178(2) of the Howrah
Municipal Corporation Act, 1980 (hereinafter referred
to as "the 1980 Act"), no person shall occupy or
permit to be occupied any such building or use or
permit to be used any building or a part thereof
affected by any work until permission has been
granted by the Commissioner, in the event no
completion certificate has been issued.
In the present case, it is argued, the said
provision is a clear bar to the petitioner making the
construction. Hence, the shifting of electricity and
increase in load, if granted, will be in direct
contravention of Section 178(2) of the 1980 Act. It is
further apprehended by the private respondent that in
the event the load is allowed to be increased, the
petitioner shall induct third parties and create third
party rights in respect of the building, despite the
same being an illegal construction.
In the present case, the dispute raised by the
private respondent is regarding the legality of the
construction being made by the petitioner.
However, even within the contemplation of
Municipal Law, mere issuance of a stop work notice
itself does not taint a building to be illegal, unless a
demolition notice is served.
There is a clear provision even under the
Howrah Municipal Corporation Act, 1980 for an
opportunity being given to the accused person to
represent himself on the question of whether the
construction is being made illegal.
Hence, at this juncture, it cannot be said
beyond doubt that the petitioner is making
unauthorized construction. Insofar as Section 178(2)
of the 1980 Act is concerned, the petitioner has
argued that, as envisaged in Article 254 of the
Constitution of India, the State Legislation has to give
way to a special Statute enacted by the Parliament.
The Electricity Act, 2003, being an Act of the
Legislature, while the Howrah Municipal Corporation
Act, 1980 is a State statute, the said proposition
would otherwise be applicable. However, in the
present case, as rightly submitted by the private
respondent, there is no clear conflict between Section
43 of the 2003 Act and Section 178(2) of the 1980 Act,
since the two provisions are not mutually exclusive
and can operate harmoniously.
However, at the present juncture, it would be
premature to say that if an existing electricity
connection at the same premises is merely shifted to
some other place and the load is permitted to be
increased, the same will amount to permitting the
petitioner to occupy a building which is without
completion certificate.
The shifting and increase of load sought is not a
new instance of grant of fresh electricity connection to
the petitioner, which would attract the provisions of
Section 178(2) of the 1980 Act, since no new
permission or occupation is being created by virtue of
shifting and/or increase in load.
By the same logic, Section 43 of the 2003 Act is
also not applicable as the petitioner is not seeking a
new and independent electricity connection.
Whatever may be the fate of the proceeding
going on before the Howrah Municipal Corporation
regarding the legality or otherwise of the construction
made by the petitioner, the same cannot be a
deterrent at the present moment to permitting the
petitioner to shift his existing electricity connection to
a different place within his own premises and to
increase the load thereof.
Hence, WPA No. 23359 of 2022 is allowed,
thereby directing the CESC Limited to shift the
existing electricity service connection of the petitioner
as sought by the petitioner and to ensure that the
increased load is given, of course, subject to feasibility
and compliance of all formalities by the petitioner in
that regard. It is, however, made clear that such
shifting and/or increase in load of the electricity meter
shall not ipso facto create any special equity or right in
favour of the petitioner, which the petitioner otherwise
does not have in law, and shall abide by the outcome
of the proceeding before the Howrah Municipal
Corporation with regard to the legality or otherwise of
the construction being made by the petitioner.
In the event the CESC personnel are obstructed
by the private respondent and/or his men and agents
in shifting such connection and/or increasing the
load, it will be open to the CESC personnel to
approach respondent no.5, the Officer-in-Charge,
Acharya Jagadish Chandra Bose Botanical Garden
Police Station for police assistance. If so approached,
such assistance shall be given at the cost of the
petitioner by respondent no.5 by acting on a server
coy of this order.
It is further reiterated that the shifting of
electricity connection and/or increase in load shall
not in any manner prejudice the rights of the Howrah
Municipal Corporation or the private respondent to
object to any illegality, if committed by the petitioner
in making the construction.
There will be no order as to costs.
Urgent photostat certified copies of this order, if
applied for, be made available to the parties upon
compliance with the requisite formalities.
(Sabyasachi Bhattacharyya, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!