Citation : 2023 Latest Caselaw 3721 Cal
Judgement Date : 8 June, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.10028 of 2023
Shapoorji Pallonji and Company
Vs.
The West Bengal Power Development Corporation Ltd. and others
For the petitioner : Mr. Sakya Sen,
Mr. Asif Hussain,
Ms. Labani Pan
For the WBPDCL : Mr. Abhrajit Mitra,
Mr. Jishnu Chowdhury,
Mr. Debanjan Mandal,
Mr. Chayan Gupta,
Mr. Sandip Dasgupta,
Mr. Aviroop Mitra,
Ms. Mahima Choura
Hearing concluded on : 10.05.2023
Judgment on : 08.06.2023
Sabyasachi Bhattacharyya, J:-
1. The petitioner has challenged a Tender cum Reverse Auction floated
by the respondents in respect of Flue Gas De-sulphurisation (FGD)
Package in respect of four units of the Sagardighi Thermal Power
Project (2x300 MW + 2x500 MW). The specific premise of the
challenge is Clause 26.0 of the Notice Inviting Tender (NIT). The
petitioner has also challenged the rejection of the petitioner's bid at
the technical stage.
2. Learned counsel for the petitioner argues that there is inherent
discrepancy between the different sub-clauses of Clause 26.0, which
comprise the 'Must Conditions'. Whereas for Phase-I units, Limestone
Consumption of FGD System shall not exceed 3.68 T/hr. at 100 per
cent unit MCR with SO2 removal efficiency of 80 per cent, such
consumption for Phase-II units, as per the NIT, are not to exceed 7.61
T/hr. at 100 per cent unit MCR with SO2 removal efficiency of 96 per
cent.
3. However, in spite of such provisions in paragraphs 3 and 4 of sub-
clause 26.1, in paragraph 5 of the same sub-clause, the maximum
Total Auxiliary Power Consumption for Phase-I units is 5900 KW with
both units operating at 100 per cent TMCR whereas for Phase-II, such
consumption shall not exceed 4800 KW operating also at 100 per cent
TMCR condition.
4. It is submitted that such inherent discrepancy governing Phase-I and
Phase-II units vitiates the clause. Whereas Limestone Consumption
would be less with worst coal firing and SO2 removal efficiency at 80
per cent for Phase-I units, while the maximum Total Auxiliary Power
Consumption for FGD System for such units is 5900 KW, for Phase-II
units, the Limestone Consumption shall not exceed 7.61 T/hr. with
worst coal firing and SO2 removal efficiency of as high as 96 per cent,
while the Total Auxiliary Power consumption for such units cannot
exceed 4800 KW.
5. It is further argued that such clause is not only arbitrary, such
conditions are technically impossible for any operator to meet.
6. Moreover, it is contended that the criteria stipulated in such clause do
not have any correlation with the purpose of the Tender and the
product sought.
7. Learned counsel for the petitioner next argues that the said clause is
contrary to the Notification dated March 7, 2019 issued by the Central
Electricity Regulatory Commission (CERC), in particular Regulation
No.49 thereof (amended on August 25, 2020 and further amended on
February 2, 2021).
8. It is also pointed out that whereas Phase-I units contemplate 300 MW,
Phase-II units are intended for 500 MW, which does not tally with the
converse ratio of power consumption as per the impugned Clause
26.1.
9. Moreover, learned counsel for the petitioner submits that the rejection
of the petitioner's bid was bad even in terms of the NIT provisions.
Clause 24.2 of the same provides that a substantially responsive bid is
one that meets the requirement of the Bidding Document without
material deviation, reservation or omission. Such terms, if accepted,
are defined to be ones which:
i) affect in any substantial way the scope, quality or performance
of the plant and installation services specified in the contract; or
ii) limit in any substantial way, inconsistent with the Bidding
Document, the Employer's right or the Public's obligations
under the proposed contract.
10. Thus, the petitioner also challenges the rejection of the petitioner's bid
at the technical stage.
11. Learned counsel for the respondents, at the outset, argues that the
impugned tender has already reached its culmination, upon the price
bids being opened and the L-I and L-II bidders being declared.
12. Hence, the clock ought not to be set back to the stage of inception of
the writ petition.
13. Next, it is argued, the petitioner fully participated in the tender
process and thereafter, subsequent to the rejection of its technical bid,
has come up with the present challenge, by taking a chance in respect
of the outcome of the auction. Moreover, the delay in preferring the
present challenge is inordinate. Hence, the writ petition ought to be
dismissed, if not for any other reason, on the grounds of delay and
mala fides.
14. With regard to the amendment of Regulation 49 of the relevant
Notification, learned counsel argues that there was no material
alteration therein of the impugned clause. For such purpose, learned
counsel for the respondents places the exact amendment and the
Gazette Notification thereof. Hence, the petitioner's argument that the
impugned clause was contrary to such Regulation/Notification is not
tenable in the eye of law.
15. That apart, it is argued that the application of cap at the rate of 1 per
cent both for Phase-I and Phase-II units is absolutely reasonable and
not, in any manner, arbitrary.
16. The respondents cite an unreported judgment dated February 11,
2022 passed by the Supreme Court in Balaji Ventures Private Limited
Vs. Maharashtra State Power Generation Company Ltd. and another for
the proposition that unless a clause was tailor-made to suit a
particular bidder, the owner should always have the freedom to
provide the eligibility criteria in a tender and a challenge on the
ground that the bid condition/clause might not suit a particular
bidder cannot be any ground for challenge.
17. Next citing a Division Bench judgment of this Court reported at 2020
SCC OnLine Cal 2213 [Subir Ghosh Vs. State of West Bengal and
others], it is argued that the challenge to a tender has to be before the
time to put in the bids is closed. If a bid is made and is thrown out on
an illegal or unfair condition in the tender document, even then, a
challenge can be fashioned.
18. Learned counsel for the respondents also places reliance on Greentech
Environ Management Pvt. Ltd. and others Vs. the Union of India and
others, reported at MANU/WB/0054/2021, where it was held by this
Court that it did not lie in the mouth of the petitioners therein to
challenge the tender process after having participated in the same and
having turned out to be unsuccessful.
19. Learned counsel for the respondents next cites National High Speed
Rail Corporation Limited Vs. Monte Carlo Limited and another, reported
at (2022) 6 SCC 401, to indicate the limited grounds on which there
can be interference under Article 226. Such criteria having not been
satisfied in the present case, it is submitted, the writ petition ought to
be dismissed.
20. From the cited judgments, certain principles can be elicited.
21. The limited scope of challenge to a tender process, according to the
Supreme Court [in Balaji Ventures (supra)], is that a particular clause
or condition of a tender is tailor-made to suit a particular bidder or is
arbitrary. Otherwise, the owner/employer should always have the
freedom to provide the eligibility criteria and the terms and conditions
of the bid, unless those are mala fide.
22. The bidder cannot be permitted to challenge a clause merely because
it does not suit him and/or is inconvenient to him.
23. It has further been observed by courts that a challenge to tender
documents on the ground of being unfair or illegal has to be thrown
before the time to put in the bids is closed.
24. In the event the bidder participates and awaits the outcome of the
bids, a challenge at the behest of such bidder ought not to be allowed.
25. In National High Speed Rail Corporation (supra), the Supreme Court
stipulated specific grounds of interference under Article 226. The
grounds were, whether the process or decision made by the authority
is mala fide or intended to favour someone, or is so arbitrary and
irrational that no responsible authority acting reasonably and in
accordance with relevant law could have reached it; also, whether the
public interest is affected.
26. In the present case, the challenge to the impugned Clause of the NIT
is three-fold. As to the first limb of the challenge, the petitioner
argues that the conditions stipulated therein are technically
impossible to meet. However, the petitioner has failed to establish
such ground in any cogent manner. Moreover, in the meantime, the
financial bids have been opened and two bidders have already come
out successful, being declared as L-I and L-II, which itself demolishes
the myth that the tender conditions could not be fulfilled.
27. The next challenge is that Clause 26.1 is arbitrary.
28. However, a bare perusal of the same clearly shows that the same
specifies certain technical requirements. Not only is the court or any
other authority than the authority floating the tender technically
incompetent to decide the legitimacy of such requirement, it is well-
settled that the tender-issuing authority reserves absolute right in
specifying its requirements.
29. The purpose for which tender was floated in the present case was
technically very specific. The thermal power project was to get four
units of a Flue Gas De-sulphurisation Package, two of 300 MW and
other two of 500 MW.
30. There is parity between Paragraphs 3 and 4 of Clause 26.1, insofar as
both have been capped at One per cent in terms of the relevant
Notification.
31. The requirements of Phase-I and Phase-II units are entirely different,
for which the Limestone Consumption of FGD System vary in respect
of both, as well as the worst coal firing and SO2 removal efficiency.
32. The Total Auxiliary Power consumption for the FGD System,
accordingly, varies as per the need of the respondent-Authorities for
the particular project.
33. Nothing has been shown by the petitioner to indicate that the said
conditions are patently arbitrary or mala fide and/or tailor-made to
suit the particular purpose of any particular bidder or a small section
of bidders.
34. The question of arbitrariness does not arise, insofar as the authorities
have ample jurisdiction to determine their own criteria for a particular
project for which the tender is floated.
35. It is not for the court or any other authority to decide whether the
criteria are not co-related with the purpose of the tender.
36. Moreover, nothing has been established by the petitioner to rebut the
presumption that the tender issuing authorities had cut their coat
according to their own cloth.
37. Even otherwise, the petitioner waited for the outcome of the technical
bid, after having fully participated in the tender process, and only
after having lost in the technical bid, has preferred the present
challenge.
38. Certain time-lines are important in this context. The tender was
floated on September 30, 2021 and a pre-bid meeting was scheduled
in the month of November, 2021. Thus, there was ample scope for the
petitioner, along with other bidders, to clarify their queries and doubts
and, if dissatisfied, to challenge the clauses of the tender. However,
instead of choosing to do so, the petitioner awaited the result of the
tender process, having participated therein till its technical bid was
rejected as late as in the month of July, 2022.
39. Such conduct of the petitioner itself is mala fide and reeks of
opportunism.
40. Insofar as Regulation 49 of the relevant Notification is concerned, it is
clear from the February, 2021 amendment thereto that the relevant
provisions of Regulation 49 remained unaltered even after such
amendment was effected.
41. Regulation 49, as it stood originally, provided certain norms of
operation for thermal generating stations.
42. By the amendment, sub-sub-clause (iv) of sub-clause (d) of Clause (E)
of Regulation 49 was omitted and a new sub-clause (f) was inserted
after sub-clause (e) of Clause (E) of the said Regulation. The norms of
Auxiliary Energy Consumption for Emission Control System with
regard to reduction of emission of sulphur dioxide for Wet Limestone
based FGD systems was capped at 1.0 per cent, which has not been
shown to be arbitrary or unreasonable in any manner, to require
interference under Article 226 of the Constitution of India.
43. Thus by applying the tests as provided by the Supreme Court in the
cited judgments, there is no reason why the impugned clause ought to
be set aside.
44. Regarding the question as to whether the petitioner's technical bid
comprised of a material deviation, reservation or omission as defined
in Paragraph 24.2 of Clause 24.0 of the NIT, the same is entirely
subjective. Unless that much discretion is left with the authority
issuing the tender, no technical tender could be floated by any
authority. Such technical considerations, which have not been shown
to be mala fide or arbitrary in any manner, are best left to the
judgment of the respondent-Authorities issuing the tender. The
process by which the decision to reject the petitioner's technical bid
was reached has not been shown to be flawed or irregular in any
manner.
45. That apart, it is too late in the day to permit the petitioner to have the
tender process recalled, after having participated in the same and
having been unsuccessful.
46. Hence, there is no scope of interference either with the rejection of the
petitioner's technical bid or the impugned Clause and sub-clauses of
the NIT.
47. Accordingly, WPA No.10028 of 2023 is dismissed on contest, without
any order as to costs.
48. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!