Citation : 2023 Latest Caselaw 4960 Cal
Judgement Date : 11 August, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
WPA No. 17132 of 2023
India Power corporation Limited (IPCL)
Vs.
The State of West Bengal and others
For the petitioner : Mr. Saktinath Nath Mukherjee,
Mr. Surojit Nath Mitra,
Mr. S. Dutta,
Mr. Anindya Halder
For the
Respondent nos.1, 5 &6 : Mr. Somnath Ganguli,
Ms. Priyamvada Singh
For the Respondent nos.3 & 4 : Mr. Manoj Munshi, Ms. Usha Doshi, Ms. Priyanka Gope
For the respondent no.7 : Mr. Triptimoy Talukder, Mr. Shamba Chakraborty, Mrs. Chanchala Chatterjee
Hearing concluded on : 04.08.2023
Judgment on : 11.08.2023
Sabyasachi Bhattacharyya, J:-
1. The present challenge has been preferred against a cancellation of a
Letter of Award (LoA) and debarment of the petitioner-company. The
petitioner participated in a tender floated by the respondent no. 3 and
turned out the successful bidder. LoA was, accordingly, issued to the
petitioner on March 31, 2023. As per the terms of the tender
document, the successful bidder was to sign the AMISP Contract and
furnish the initial Performance Security within 14 days from the date
of issuance of the LoA. Failure to do so shall constitute "sufficient
grounds for the annulment of the award and forfeiture of the Bid
Security". In that event, the Utility may award the AMISP Contract to
the next lowest Bidder.
2. The petitioner allegedly engaged the respondent no. 7, a financial
service provider, to procure and to issue the performance bank
guarantee to the tendering authority on behalf of the petitioner.
However, on three successive occasions, the respondent no. 7 issued
fake bank guarantees, upon coming to know of which the petitioner
immediately lodged complaint with the police, giving rise to an F.I.R.
The petitioner ultimately furnished a proper and valid bank guarantee
on May 17, 2023. However, the same was not accepted and the LoA
was cancelled, and the petitioner debarred for three years from
participating in the tenders of the respondent no. 3. The writ petition
has been filed against such cancellation and debarment.
3. Learned Senior Advocate appearing for the petitioner submits that the
petitioner was not at fault for the issuance of fake bank guarantees.
The petitioner entrusted the respondent no. 7 with the task of
procuring and furnishing the same, as evident from an agreement
annexed to the writ petition. The petitioner also spent substantial
amounts on such contract.
4. Immediately upon learning of the forgery, the petitioner lodged
complaint with the police and also communicated with the respondent
authorities expressing its helplessness. Thus, the petitioner could not
be faulted.
5. It is submitted that the petitioner-company has been doing business
for over a century and have a formidable goodwill. It would not stoop
to so low levels as alleged, that too, after becoming successful in the
tender.
6. Learned Senior Advocate appearing for the petitioner next argues that
the respondent no. 3 had condoned the delay in issuing the
performance bank guarantee by accepting the late filing of the same
on May 17, 2023 as well as all prior bank guarantees. Before that, the
petitioner had put in the first bank guarantee in due time; however,
the same turned out to be fake, for which the petitioner was not
responsible in any manner.
7. It is next argued that, as per the conditions in the tender document,
delay in furnishing the bank guarantee would only furnish "sufficient
ground" for annulling the LoA, and not have the effect of automatically
annulling the LoA. Thus, there was sufficient discretion available to
the tendering authority to condone the same. The respondent nos. 3
and 4 accepted the bank guarantee much after the expiry of the
stipulated time and never tendered back the same. Thus, by its
conduct, the tender-issuing authority has accepted the delayed
submission of bank guarantee and condoned the delay in filing the
same.
8. Learned Senior Advocate, lastly, contends that the technical default
on the part of the petitioner, due to no fault of its own, does not justify
the cancellation of the LoA and debarment of the petitioner.
9. Before entering into the merits of the case, learned counsel appearing
for the respondent nos. 3 and 4 raises an objection as to
maintainability of the writ petitioner before the Calcutta High Court
on the ground of territorial jurisdiction.
10. It is argued that all the relevant transactions were performed in
Madhya Pradesh. Even the website portal of the respondent no.3 is
run and operated in Madhya Pradesh by the Government of Madhya
Pradesh. The bids in the tender process-in-question were all
evaluated in Madhya Pradesh. Even the decision to cancel the
petitioner‟s LoA was taken in Madhya Pradesh.
11. Thus, this Court does not have territorial jurisdiction to hear the
matter.
12. Learned counsel places reliance on Union of India and others Vs. Adani
Export Limited and another, reported at (2002) 1 SCC 567, where the
Supreme Court, while considering the scope of Article 226(2) of the
Constitution of India, observed that none of the facts therein were in
any way connected with the reliefs sought so as to constitute the
cause of action at Ahmedabad. Two of such facts were that the
respondents carried on their business from Ahmedabad and the
respondents had executed a bank guarantee through their bankers at
Ahmedabad as well as a bond at Ahmedabad. Similar to the present
case, it is argued, in the said case also the respondents had pleaded
jurisdiction of the Gujarat High Court in view of such facts having
occurred in Ahmedabad, which was turned down.
13. Learned counsel next cites Oil and Natural Gas Commission Vs. Utpal
Kumar Basu and others, reported at (1994) 4 SCC 711. In the said
case, a part of the cause of action was argued to arise within the
jurisdiction of the Calcutta High Court because the concerned party
became aware of the advertisement in Calcutta, submitted its bid from
Calcutta and made representations, demanding justice, from Calcutta
or learning about the rejection of the offer. However, it was held that
the Calcutta High Court did not have jurisdiction. The object
underlying the provision in Section 21 of the Code of Civil Procedure,
it was held, was not to encourage such litigants who deliberately
invoke the jurisdiction of a court having no jurisdiction for ulterior
motives, but to avoid harassment to litigants who had bona fide
commenced proceedings in a court which is later found to be wanting
in jurisdiction.
14. Learned counsel further cites South East Asia Shipping Co. Ltd. Vs.
Nav Bharat Enterprises Pvt. Ltd. and others, reported at (1996) 3 SCC
443, where the Supreme Court held, inter alia, that cause of action
consists of the bundle of facts which give cause to enforce the legal
injury for redress in a court of law and means every fact which, if
traversed, it would be necessary for the plaintiff to prove in order to
support his right to a judgment of the court. In other words, it is a
bundle of facts which, taken with the law applicable to them, gives the
plaintiff a right to claim relief against the defendant and must include
some act done by the defendant.
15. Learned counsel further cites a Division Bench judgment of this Court
in Utkarsh India Limited and Another Vs. Central Coalfields Limited
and Another, reported at 2021 SCC OnLine Cal 4259 where, in case of
an online transaction, the Court held that though appellants have
their place of business within the jurisdiction of this Court and had
received the notice of disqualification at their office at Kolkata, the
Jharkhand High Court had territorial jurisdiction since the integral
part of cause of action, that is, floating of tender, scrutiny of
documents and decision to disqualify the appellants and to impose
penalty was taken at Ranchi, Jharkhand.
16. Learned counsel for the respondent nos.3 and 4 then cites Aligarh
Muslim University and another Vs. Vinay Engineering Enterprises (P)
Ltd. And another, reported at (1994) 4 SCC 710, where the Supreme
Court had deprecated the assumption of jurisdiction by the High
Court by adopting a queer line of reasoning, although no cause of
action had arisen within its territorial jurisdiction.
17. The contesting respondents also place reliance on National Textile
Corpn. Ltd. And others Vs. Haribox Swalram and others, reported at
(2004) 9 SCC 786. The Supreme Court, while considering Article
226(2), turned down the claim that the Calcutta High Court had
jurisdiction because letters were sent by the writ petitioners from
Calcutta and replies had also been received at Calcutta and that the
petitioners were carrying on business at Calcutta, similar to the
present case.
18. The contesting respondents next rely on Alchemist Ltd. And another
vs. State Bank of Sikkim and others, reported at (2007) 11 SCC 335.
In the said case as well, the offer of the appellant-Company was
accepted and acceptance was communicated at Chandigarh. The
letter of revocation was received by the appellant-company at
Chandigarh. Consequences of the revocation ensued at Chandigarh.
However, on considering all the relevant judgments on the issue, it
was held that for the purpose of deciding whether the facts averred by
the appellant-petitioner would or would not constitute a part of the
cause of action, one has to consider whether such fact constitutes a
material, essential or integral part of the cause of action.
19. Thus, it is submitted that since the relevant decisions in the present
case were taken in Madhya Pradesh, including the cancellation of the
LoA and debarment of the petitioner, this Court does not have
territorial jurisdiction to entertain and decide the writ petition.
20. On merits, learned counsel for the respondent nos. 3 and 4, who are
the contesting respondents, submits that the furnishing of three fake
bank guarantees in quick succession was sufficient to debar the
petitioner from participating in future contracts with the respondent
no. 3 for three years. It is argued that the petitioner deliberately took a
chance by furnishing fake guarantees, hoping that the forgery would
be discovered only after the contract was awarded and at the stage of
invoking the same much later, when it would be too late.
21. It is argued that, in normal course of business, it is the bidder itself
which is to furnish a bank guarantee. It is unheard of that a third
party-financial service provider would furnish the bank guarantee on
behalf of the bidder. Even as per the contract, it is the successful
bidder who must furnish the same.
22. It is alleged by the contesting respondents that the petitioner
perpetrated the fraud and/or colluded in furnishing fake bank
guarantees. Thus, the respondent no. 3 was justified in its
apprehension of dubious credentials of the petitioner and rightly
annulled the LoA and debarred the petitioner from participating in
future tenders.
23. In any event, it is submitted, the petitioner was much beyond time in
submitting the performance guarantee.
24. Sufficient opportunity of reply and show cause was given to the
petitioner and, thereafter, the contesting respondents were compelled
to take the impugned action.
25. It is argued that there was no illegality, arbitrariness,
unreasonableness or mala fides in the impugned annulment and
debarment.
26. The respondent nos. 3 and 4, who are the contesting respondents,
submit that all relevant documents have been annexed to the writ
petition. As such, no affidavits are directed, and the matter is taken
up for adjudication on the issue of territorial jurisdiction as well as on
merits. For adjudication of the objection of territorial jurisdiction, the
nature of allegations made in the writ petition and certain aspects of
the factual disputes involved are required to be looked into. Hence, in
terms of the principle laid down in Order XIV Rule 2 of the Code of
Civil Procedure, all issues are taken up together for adjudication.
27. Since the question of territorial jurisdiction goes to the root of the
decision, the said issue is taken up for decision first.
28. In Alchemist (supra), the Supreme Court observed that, for the
purpose of deciding whether facts averred by the petitioner would or
would not constitute a part of cause of action, one has to consider
whether such fact constitutes a material, essential, or integral part of
the cause of action.
29. In Adani Exports (supra), the Supreme Court observed that each and
every fact pleaded does not give rise to a cause of action within the
court‟s territorial jurisdiction unless those facts are such which have a
nexus or relevance with the lis that is involved in the case. The Court,
in this context, relied on ONGC (supra), where the Supreme Court, in
the context of Article 226 of the Constitution, observed that the
expression „cause of action‟ means that bundle of facts which the
petitioner must prove, if traversed, to entitle him to a judgment in his
favour by the court. The Court further held that, in determining the
objection of lack of territorial jurisdiction, the court must take all the
facts pleaded in support of the cause of action into consideration
albeit without embarking upon an enquiry as to the correctness or
otherwise of the said facts. Thus, the question of territorial jurisdiction
must be decided on the facts pleaded in the petition.
30. Again, the Supreme Court, in South East Asia (supra), observed that
cause of action is a bundle of facts which, taken with the law
applicable to them, gives the plaintiff a right to claim relief against the
defendant. It must include some act done by the defendant, since, in
the absence of such an act, no cause of action would possibly accrue
or would arise.
31. Aligarh Muslim University, however, is a three-paragraph decision of
the Supreme Court, where no ratio can be said to have been laid
down. The same was apparently rendered in the context of a
proceeding under Section 31 of the Arbitration Act, 1940. The Court
held, in the facts of the case, that the arbitrator was from Aligarh and
was to adjudicate there; merely because the respondent was a
Calcutta-based firm, the High Court of Calcutta seemed to have
exercised jurisdiction where it had none by adopting a queer line of
reasoning.
32. However, the only common ingredients between the said case and the
present are that territorial jurisdiction was decided and the petitioners
are based in Calcutta (now Kolkata). It is rather obvious that where
the seat of arbitration is Aligarh, the Calcutta High Court does not
have jurisdiction under normal circumstances. No such issue is
involved in the case at hand. Hence, the said judgment is not a
germane precedent for the present consideration.
33. In National Textile Corporation (supra), the writ petitioner had claimed
delivery of certain goods upon adjustment of payment and for
injunction regarding the goods, which were to be supplied to mills at
Bombay (now Mumbai). The Supreme Court held that the mere fact
that the writ petitioner carries on business at Calcutta or that the
reply to the correspondence made by it was received at Calcutta is not
an integral part of the cause of action and therefore, the Calcutta High
Court had no jurisdiction to entertain the writ petition.
34. Thus, respondent nos. 3 and 4 in the present case seek to draw an
analogy with National Textile (supra) as, in the said case as well, it was
held that the mere fact that the writ petitioner carries on business at
Calcutta or that reply to correspondence made by it was received in
Calcutta is not an integral part of the cause of action.
35. In the same tune, respondent nos. 3 and 4 herein also cite Utkarsh
India Limited (supra), where a Division Bench of this court, in
connection with an online tendering process, held that this court had
no jurisdiction, although the petitioners in the said case deposited
earnest money from Kolkata and received all communication relating
to the impugned tender, including the disqualification letter, which
constituted cause of action, in Kolkata. There also, the Division Bench
recorded the petitioners‟ case that the impugned letter had cause
injury to their business and right to livelihood and thereby infringed
their right to trade and business guaranteed under Article 19 (1) (g) of
the Constitution. However, the Division Bench held that the entire
process of the impugned tender had emanated from the Head Office of
the Central Coalfields at Ranchi, Jharkhand, including the impugned
notice of disqualification and penalty, which formed the integral part
of cause of action for the lis.
36. However, on facts relevant to the ratio under discussion, there are
certain distinguishing features between the above cases and the
present lis. In paragraph no. 24 of Utkarsh India (supra), the Division
Bench held that Clause 32 of the General Conditions of Contract as
contained in the NIT clearly provided that in case of dispute arising
out of the contract entered into with suppliers, those will be subject to
the jurisdiction of the competent court of law. The courts in whose
territorial jurisdiction from where contract is being issued is located, it
was held, that is, Ranchi, Jharkhand, shall be competent to deal with
any matter arising out of the purchase order/contract. No similar
clause in the tender document has, however, been relied on in the
present case. Here, the entire gamut of facts pertaining to the
cancellation of LoA and debarment have to be looked into in the light
of Article 226 (2) of the Constitution.
37. Secondly, the cause of action in Utkarsh India (supra) was
disqualification of the petitioner in a tender simpliciter. In National
Textile Corporation (supra), there was a contractual dispute, which led
to withholding of goods.
38. In the present case, however, the bundle of facts comprising the cause
of action is not confined to the decisions taken in Madhya Pradesh by
the Respondent nos. 3 and 4 simpliciter. The petitioner has
specifically alleged that it had an arrangement with a financial service
provider (respondent no. 7), who duped the petitioner-company with
regard to the bank guarantees-in-issue. The petitioners also allege
that the said service provider not only procured the bank guarantees,
but also sent them to the respondent-authorities of its own, without
sanction from the petitioners, at least on the second or third occasion
after discovery of fraud.
39. Unlike Utkarsh's Case, here the dispute is not merely a bid being
turned down or disqualified on technical ground. The petitioner, in the
present case, was admittedly the successful bidder after the entire
tender process was over. It matter was at the stage of the petitioner
being awarded a contract, which was not done on the allegation that
the petitioner having failed to comply with the tender term of deposit
of bank guarantee within 14 days.
40. Again, in National Textile (supra), the dispute was contractual; the
goods, as per the contract, were to be supplied in Mumbai which,
having not been done, the case arose. Hence, the territorial
jurisdiction was held to lie in Mumbai.
41. In the case at hand, however, the dispute involves an alleged fraud
being perpetrated upon the petitioner as well in respect of the
particular bank guarantees which were the genesis of the refusal.
42. Hence, at least a part of the cause of action definitely arose within the
jurisdiction of this court.
43. Nawal Kishore Sharma (supra), cited by the petitioner, is apt in the
context. The Supreme Court, while considering the ambit of Article
226 (2) of the Constitution of India, was contemplating a situation
where the petitioner had been making all correspondence from his
native place in Bihar with regard to his disability compensation, the
rejection of which was the subject-matter of challenge.
44. Learned counsel for the Respondent nos. 3 and 4 seeks to distinguish
the ratio of Nawal Kishore's Case on the ground that there, the
Supreme Court had sympathised and taken into consideration the fact
that the petitioner was suffering from serious heart muscle disease
and breathing problem which forced him to stay in his native place.
However, such contention cannot be accepted, since the mention of
the disease by the Supreme Court was only in the context of
ascertaining territorial jurisdiction. In fact, immediately after such
finding in paragraph no. 17 of the judgment, the Supreme Court
proceeds to hold that "Prima facie, therefore, considering all the facts
together, a part or fraction of cause of action arose within the
jurisdiction of the Patna High Court where he received a letter of
refusal disentitling him from disability compensation."
45. Notably, the Supreme Court had considered, in Nawal Kishore Sharma
(supra), some of the decisions relied on by the respondent nos. 3 and
4, including ONGC's Case and Kusum Ingots as well as Election
Commission v. Saka Venkata Rao, which were considered by the
Supreme Court in Alchemist (supra).
46. The Division Bench of this Court, in State of Orissa V. Goenka
Investment and Mining Industries Pvt. Ltd., reported at AIR 1983 Cal
438, was considering as to whether a particular court had
jurisdiction. There, the primary consideration was where the notice of
termination was served, as there were two notices in contention. The
court observed that one of the notices was not a termination notice,
since not permitted as per the agreement and served on a non-
authorised person. The other notice, being free from such drawbacks,
was held to be a valid notice and thus accepted as the termination
notice which comprised of the cause of action. Having been served
within the territorial jurisdiction of the concerned court, it was held to
have jurisdiction. However, there the question was not whether the
place of issuance of notice or the place of receipt of the same has
jurisdiction.
47. Another factor to be considered here is that the present challenge is
not confined to the cancellation of work order to be issued to the
petitioner, but also extends to the debarment of three years, which
has both penal and civil consequences. Such consequences definitely
extend to the petitioner‟s business activities in West Bengal, which is
its base and where it is situated.
48. The factum of the petitioner running a business within the territory of
a court may be considered, under certain circumstances, irrelevant
and immaterial with regard to a dispute in respect of rejection of a bid;
but the said factor assumes major proportions when the challenge is
also to a debarment, which directly affects the business of the
petitioner everywhere, including in its seat of business, where it has
its head office. The impugned debarment, although on paper confined
only to tenders of the present respondent nos. 3 and 4, has larger and
adverse effect on the goodwill of the petitioner-company. Apart from
being a stigma against the petitioner in the sphere of its commercial
activities, a debarment in respect of one tendering authority generally
operates as a bar for others as well, since, almost in all tenders, there
is a restrictive clause regarding participation by bidders who are
suffering or have recently suffered debarment from any other
authority.
49. Thus, at least a part of the cause of action arises in West Bengal,
conferring territorial jurisdiction on this court, in the context of Article
226 (2) of the Constitution of India, to entertain and decide the writ
petition on merits.
50. In view of the above discussions, the objection regarding territorial
jurisdiction, raised by the respondent nos. 3 and 4, is turned down.
51. The main writ petition is now taken up for adjudication.
52. The petitioner has alleged that it is a century-old company with
impeccable goodwill and was in no way responsible for or connected
with the forgery committed in respect of the bank guarantees. It
alleges that the respondent no. 7 company, which was a financial
service provider appointed by the petitioner for procuring and
furnishing the bank guarantees, committed the forgery, may be in
collusion with the banks or others. In fact, it is the petitioner which
brought the forgery to the notice of the law enforcement authorities by
lodging complaints before the police. Even the second and third
fraudulent bank guarantees, it is contended, were sent by the
respondent no. 7 of its own, without intimating the petitioner.
53. Let us examine the turn of events.
54. The LOA was issued to the petitioner on March 31, 2023 and the e-
mail copy has well as signed copy of the bank guarantee worth Rs. 26
Crore 91 Lakh was sent from the petitioner‟s end on April 25, 2023.
The same, however, was notified to be fake by the concerned bank on
April 29, 2023.
55. The second bank guarantee was sent on May 3, 2023, which was also
fake. Now the respondent no. 3, vide letter dated May 10, 2023,
sought an explanation, as a prequel to the show cause.
56. However, a third fake bank guarantee was sent on May 16, 2023,
when the respondent no. 4 had also written to the petitioner.
57. At last, on May 17, 2023, a proper bank guarantee was issued by the
petitioner.
58. The petitioner, with more than a century‟s experience behind it, was
expected to be more cautious. It is rather incredible that as many as
three fake bank guarantees were sent by it, or on its behalf, on as
many as three successive occasions, be it through a „financial service
provider‟ or otherwise. The moment the first fraud was detected, the
petitioner ought to have taken corrective steps. Yet, two more similar
fake bank guarantees were sent on its behalf, from two different
banks.
59. The first fake bank guarantee was sent not by the service provider but
by the petitioner itself, as evident from the petitioner‟s email dated
April 25, 2023, annexed at page 192 of the writ petition. The
concerned bank, that is, the ICICI Bank, vide email dated April 29,
2023, informed the petitioner about the fraud.
60. Yet, the petitioner stuck to its blind faith on the perpetrator of the first
fraud, that is, the respondent no. 7. In the complaint lodged by the
petitioner, on the basis of which a First Information Report has been
registered (even as per the annexures to the writ petition), the
petitioner "believed" the respondent no. 7 after the discovery of the
first fraud and used the second fake bank guarantee provided by
respondent no. 7 dated May 3, 2023 and "waited for signing the
contract" with the M.P. Madhya Kshetra Vidyut Vitaran Co. Ltd., as
stated in paragraph no. 10 of the complaint, annexed to the writ
petition.
61. The petitioner alleges that thereafter, on May 16, 2023, the
respondent no. 7 issued a third fake bank guarantee, this time in the
name of the Federal Bank, without prior intimation to the petitioner.
62. However, there is nothing on record to show that the petitioner had
put any mechanism or instruction in place for the respondent no. 7 to
give prior intimation to the petitioner before sending another bank
guarantee. Rather, even till then, the petitioner was apparently sitting
tight over the repeated forgeries committed in its name, allegedly by
the respondent no. 7. The complaint against the alleged perpetrator
came long after, when the petitioner lodged complaint with the police
on May 23, 2023, which gave rise to a First Information Report.
63. Thus, the petitioner was guilty of utter negligence and was complacent
even after coming to know of the first instance of fraud, if not being in
connivance with the respondent no. 7 or other perpetrators of the
forgery.
64. Thus, there was sufficient reason for the respondent nos. 3 and 4 to
cancel the LOA issued to the petitioner.
65. Moreover, the outer limit of 14 days, as per the NIT, had long expired
on April 14, 2023. The first genuine bank guarantee was furnished by
the petitioner only on May 17, 2023, that is, more than one month
thereafter. There was no reason for the respondent authorities to
condone such delay, particularly in the context of the petitioner‟s
conduct of furnishing three fake bank guarantees in quick succession.
66. The Instructions to Bidders, which was admittedly a part of the tender
document, stipulated that the successful Bidder "shall" furnish the
initial Performance Security within 14 days of the receipt of
notification of award. The expression "shall" lends a mandatory tone
to the said clause.
67. The petitioner argues that the annulment of the award, on non-
compliance of the condition, was not automatic, since the language of
the relevant clause was that failure of the successful Bidder to submit
the initial Performance Security shall constitute "sufficient ground" for
the annulment and forfeiture of the Bid Security. However, the very
next sentence permits the Utility to award, in such case, the AMISP
Contract to the next lowest Bidder.
68. The conjunction of "shall" in furnishing the performance security in
time and the provision, on failure, to annul the LOA, forfeit security
and award the contract to the next lowest Bidder, does not leave any
doubt that the tenderers were at full liberty to do so, immediately
upon the delay having been committed. In fact, the respondent nos. 3
and 4 were rather charitable in issuing so many warnings and seeking
explanation from the petitioner in the present case.
69. The petitioner has next argued that the respondent nos. 3 and 4, by
their conduct of accepting the valid (fourth) bank guarantee as
Performance Guarantee, had condoned the delay. However, the said
argument is misconceived.
70. There was no instance, at any point of time, of the respondent nos. 3
and 4 acquiescing, „accepting‟ the bank guarantee or condoning the
considerable delay in submitting the same. Rather, by its several
communications, as referred to above, the respondent nos. 3 and 4
had been consistently intimating the petitioner that it was already out
of time in furnishing performance security after expiry of 14 days.
Explanations were also sought repeatedly, for the submission of fake
bank guarantees.
71. By its letters dated May 10 and May 16, 2023, the respondent no. 3
had repeatedly taken the stand that the petitioner‟s failure to submit
the bank guarantee on the due date had created an event of default;
consequently, the LoA issued on March 31, 2023 was liable to be
cancelled. Hence, at no point was there any „acceptance‟ or
„condonation‟ by the respondents.
72. In any event, furnishing three admittedly fake bank guarantees, even
though the first of which was furnished within the stipulated time, is
the very antithesis of bona fides on the part of the petitioner.
73. In R.K.Saxena V. Delhi Development Authority [ (2001) 4 SCC 137 ],
relied on by the petitioner, there was acceptance of several delayed
payments, which was deemed to be extension of time. Here, there is
no acceptance of any payment or interest thereon, since all the prior
bank guarantees submitted by the petitioner were fake. The only valid
one was furnished more than one month after the expiry of the last
date.
74. It does not lie in the mouth of the petitioner to place reliance of Poddar
Steel Corporation V. Ganesh Engineering Woks and Others, reported at
(1991) 3 SCC 273, which speaks about "minor technicality" being
waived. If furnishing three successive fake bank guarantees is termed
as a "minor technicality", this court is at a loss to assess what is a
major default.
75. In Miss Santosh Mehta V. Om Prakash and Others [ (1980) 3 SCC 610],
the context was judicial discretion to strike out the defence of a tenant
where the statutory provision was read in lenient perspective by the
Supreme Court. However, the protection given to a tenant by a
statute, that too in an era of beneficial legislation for the tenants,
which was read by the Supreme Court in advancing the intention of
the legislature, cannot be extended to the petitioner-company in the
present case, that too, in a fully commercial transaction.
76. Hence, none of the said reports have any relevance in the present
context.
77. Thus, the respondent nos. 3 and 4 were justified in cancelling the LoA,
in view of the delay of more than one month beyond the outer
stipulated limit occasioned by the petitioner in furnishing the
performance security bank guarantee.
78. Insofar as the debarment is concerned, there is also nothing illegal or
irregular there. The petitioner was given ample opportunity of showing
cause and explaining its conduct. In fact, the first three bank
guarantees being fake is an admitted position.
79. The reason behind such issuance of forged bank guarantees and the
role of the petitioner therein is, undoubtedly, a subject-matter of
criminal investigation. However, it cannot be denied that, from the
perspective of the tenderer, there were sufficient reasons to apprehend
foul play if work was awarded to the petitioner in the near future.
80. Moreover, vis-à-vis the tendering authority, the petitioner ought to
have been much more careful and cautious. It was negligent in
shifting the entire responsibility on the respondent no. 7, without
itself verifying the genuineness of the bank guarantee, which was an
essential component of getting the contract, on several occasions.
Such careless conduct on the part of the petitioner furnished
sufficient justifiable grounds to debar the petitioner for three years
from participating in the tenders of the respondent nos. 3 and 4.
81. Learned counsel for the respondent nos. 3 and 4 has rightly argued
that, there being no flaw in the decision-making process, the writ
court ought not to impose its own decision on the tendering
authorities.
82. Moreover, there was no instance of arbitrariness, mala fides or
unreasonableness in the impugned acts of the respondent-authorities.
Even applying the Wednesbury principle, there is no flaw in the
cancellation of the petitioner‟s LoA or debarment of the petitioner
worth interference by this court under the writ jurisdiction.
83. Before parting, the respondent nos. 3 and 4 have cited Dalip Singh V.
State of U.P. and Others, reported at (2010) 2 SCC 114 for the
proposition that a new creed of dishonest litigants, who are polluting
the stream of justice, ought to be strongly deprecated. However,
although the respondent nos.3 and 4 were undoubtedly negligent in
their over-reliance on respondent no. 7, which justifies the
cancellation and debarment impugned herein, it is too early yet, before
the conclusion of the criminal trial, to hold beyond doubt the
petitioner‟s direct involvement, perpetration of the offence and/or
collusion with the perpetrators thereof. Thus, labelling the petitioner a
"dishonest litigant" would probably be too harsh and premature at
this stage. In so far as the present writ petition is concerned, the
petitioner has not suppressed a single essential or relevant component
of the chain of events leading to the cause of action and, as such,
cannot be called an „unscrupulous‟ or a „dishonest litigant‟ at least for
the purpose of the present writ petition.
84. Learned counsel for the contesting respondents has also relied on N.G.
Projects Ltd. V. Vinod Kumar Jain and Others, reported at (2022) 6 SCC
127. There, the Supreme Court deprecated court interference in
tenders in respect of infrastructure projects or projects involving
public interest. The said proposition is applicable in the present case
too, as the project in question involves public interest. However, in
any event, the writ petitioner does not succeed in the present case on
other considerations, as spelt out above.
85. Hence, the writ petition fails. Accordingly, WPA 17132 of 2023 is
dismissed on contest without, however, any order as to costs.
86. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!