Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Zulfequar Ali vs The Kolkata Municipal ...
2023 Latest Caselaw 4883 Cal

Citation : 2023 Latest Caselaw 4883 Cal
Judgement Date : 9 August, 2023

Calcutta High Court (Appellete Side)
Zulfequar Ali vs The Kolkata Municipal ... on 9 August, 2023
03.    09.08.2023
       Court No.6
      Tanmoy Ghosh


                                         MAT 876 of 2023

                                        Zulfequar Ali
                                          -Versus-
                           The Kolkata Municipal Corporation & Ors.

                                                With
                                        IA No: CAN/1/2023

                          Mr. Mansoor Alam, Adv.
                                              ...for the appellant/
                                               writ petitioner.

                          Mr. Dilip Chatterjee, Adv.,
                          Mr. Mihir Kundu, Adv.,
                          Ms. Manisha Nath, Adv.
                                              ...for the Kolkata Municipal
                                               Corporation.


                          Affidavit of service filed in Court today be kept with

                     the records.

                          By consent of the appearing parties, the appeal and

                     the connected application are taken up together for

                     hearing.

                          A judgment and order dated April 4, 2023, whereby

                     the appellant's writ petition being WPA 25820 of 2022

                     was disposed of by a learned Single Judge of this Court,

                     is under challenge in this appeal at the instance of the

                     writ petitioner.

                          The    appellant/writ   petitioner   approached   the

                     learned Single Judge with the case that unauthorized

                     construction has been put up at premises no. 1/4/1D,

                     Jiban Krishna Ghosh Road, Kolkata - 700037.
                               2




     The learned Judge noted that a demolition case had

been initiated in respect of certain portions of the

building at the concerned premises in the year 1975-76.

An order was passed by the Special Officer (Buildings) I

on August 19, 1983 for demolition of the first floor of the

said building.

     The grievance of the writ petitioner is that the order

of   demolition    has     not    yet   been     implemented.        A

representation dated November 4, 2022, has been made

by the writ petitioner, addressed to the Municipal

Commissioner, the D.G. Building and the Executive

Engineer    Building      Department,        Borough-I,        Kolkata

Municipal Corporation. However, such representation

has not yet been considered. The writ petitioner further

alleged that the unauthorized portion of the concerned

premises is being used for commercial purpose without

requisite permission having been obtained in that regard

from the Corporation Authorities.

     The learned Judge disposed of the writ petition with

the following observations and directions:-

           "There is nothing on record to suggest that in the
     interregnum, that is, after the passing of the order in 1983 till
     the filing of the representation in November 2022, the petitioner
     took any step for implementing the order of demolition.
           The Executive Engineer (Civil) of the concerned authority
     has forwarded instruction that the premises was inspected and
     it was found that there is an existing two storied old brick built
     building with tin shed supported by bamboo structure at the
     subject premises. The age of the building is more than forty
     years and no new construction has been found.
                                  3




            The petitioner has not been able to show that any new
      construction has been made which is not in accordance with the
      Municipal Building laws.
            The alleged unauthorised construction is in existence
      from 1973-74.
            At this stage it will not be proper to direct the Corporation
      to initiate any proceeding for demolition of the unauthorised
      construction in respect of a two storied brick built tin shed
      structure constructed approximately forty years back.
            As regards use of the premises for commercial purpose
      without obtaining any permission, it will be open for the
      petitioner to raise appropriate objection before the concerned
      authority.
            In the event such representation is filed, the same shall
      be taken up for consideration by the concerned authority in
      accordance with law after giving reasonable opportunity of
      hearing to all the necessary parties ."


      Being aggrieved, the writ petitioner is before us by

way of this appeal.

      We have heard learned Counsel for the appellant as

well as learned Counsel for the Corporation. From the

affidavit of service filed in Court today, we find that the

private respondent has been served but he has chosen

not to appear.

The learned Judge was justified in observing that

the appellant/writ petitioner or his predecessor-in-

interest slept tight over the matter from 1973-74, when

the alleged unauthorized construction was made.

However, we are unable to agree with the learned Single

Judge that only because considerable time has passed

since the alleged unauthorized construction was made,

no action should be taken against the same. An illegal

construction cannot become legal merely by passage of

time, however lengthy the time period be. The

Corporation's own Officer passed a demolition order. It

was found that the entire structure is unauthorized.

However, considering the facts and circumstances of the

case, the Special Officer (Building) directed demolition of

only the first floor along with the staircase and permitted

retention of the remaining portion upon payment of

applicable charges. To our mind, the Corporation ought

to have implemented its own demolition order without

any delay at all.

However, it appears that 40 years have passed by

after the demolition order was passed and the order

remains on paper only. It has not been executed.

Learned Advocate for the Corporation says that he

has no instruction as to why the order could not be

implemented. He has no instructions if there were

restraint orders of any competent forum in that regard.

The case is 50 years old. It may not be possible to trace

out all necessary documents.

We appreciate the practical difficulty. This difficulty

could have been avoided had the writ petitioner or his

predecessor been more diligent in the matter of

approaching Court for implementation of the demolition

order.

Be that as it may, a representation has been made

by the appellant/writ petitioner to the Corporation, as

indicated above. In the representation dated November

4, 2022, the writ petitioner/appellant herein has

expressed his apprehension that the unauthorized

structure may be in such a condition so as to pose a real

threat to the safety and security of the people in

occupation thereof or the people in its vicinity. We are of

the considered opinion that the Corporation should

apply its mind and consider such representation and

take a decision thereon. After all, it is the statutory duty

of the Corporation to ensure that illegal/unauthorized

buildings/structures are removed in public interest. It is

also the duty of the Corporation to ensure that if for

unavoidable reasons, an unauthorized construction

cannot be demolished, the same is at least in a condition

so as not to jeopardize the safety and security of people

in or around such construction. The Corporation should

revisit the issue of the impugned construction being an

unauthorized one. An appropriate reasoned decision

should be taken by the Corporation in the matter, after

granting an opportunity of hearing to the appellant

herein, the private respondent and the occupiers of the

premises in question or their authorized representatives.

Let the entire exercise be completed within eight weeks

from the date of communication of this order by the

appellant to the respondent no.4, being the Executive

Engineer (Building), Borough-I, Kolkata Municipal

Corporation. The respondent no.4 shall take an informed

and reasoned decision in the matter, in accordance with

law, keeping public interest in mind.

The order of the learned Single Judge stands

modified to the above extent.

Since we have not called for affidavits, the

allegations in the stay petition shall be deemed not to

have been admitted by the respondents.

The appeal being MAT 876 of 2023 and the

connected application being IA No: CAN/1/2023 are

accordingly disposed of.

Let urgent photostat certified copy of this order, if

applied for, be made available to the parties upon

compliance with all requisite formalities.

(Arijit Banerjee, J.)

(Apurba Sinha Ray, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter