Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Orissa Metaliks Private Limited vs Shenyang Casting And Forging ...
2023 Latest Caselaw 2101 Cal/2

Citation : 2023 Latest Caselaw 2101 Cal/2
Judgement Date : 18 August, 2023

Calcutta High Court
Orissa Metaliks Private Limited vs Shenyang Casting And Forging ... on 18 August, 2023
                   IN THE HIGH COURT AT CALCUTTA
                   (Ordinary Original Civil Jurisdiction)
                          COMMERCIAL DIVISION


Present:

The Hon'ble Justice Krishna Rao



                               CS 279 of 2019


                      Orissa Metaliks Private Limited
                                   Versus
                Shenyang Casting and Forging Industries
                             Company Limited.



            Mr. Jishnu Chowdhury
            Mr. Debdut Mukherjee
            Ms. Priyanka Sharma
                                            ... for the plaintiff.



Hearing Concluded On : 24.07.2023

Judgment on              : 18.08.2023

Krishna Rao, J.:


1.

Plaintiff has filed the present suit against the defendant for recovery of

an amount of Rs. 2,20,46,576.27/- with interest.

2. The plaintiff is engaged in the business of manufacturing of iron and

steel and has a manufacturing unit at Kharagpur, Midnapore, West

Bengal. The defendant is engaged in the business of design,

manufacturing and supply of major equipment for pellet plant.

3. After discussion and negotiation between the parties two agreements

were entered on 19th February 2017 and 17th March, 2017 for design,

manufacturing and supply of major equipments for a 6,00,000 TPA

Grade Kiln Pellet Plant Line - 4 and 6,00,000 TPA Grade Kiln Pellet

Plant Line -5. The total value of the contract is USD 3.00 Million of

each contract. As per Clause 3.10 of the contract, the plaintiff is

required to pay USD 50,000 as advance by way of Letter of Credit and

10% of the total value is to be paid by way of bank guarantee. As per

clause 5.00 of the contract, the defendant is required to supply the

parts and accessories within a maximum period of 180 days from the

date of token advance.

4. The defendant raised two invoices of each agreement dated 12th March

2017 and 17th March 2017. The plaintiff has paid the token advance of

USD 50,000 each to the defendant on 20th March, 2017 and 22nd

March, 2017. The payment made by the plaintiff on 20th March, 2017

which was equivalent to Rs. 32,72,240.58/- and payment made on 22nd

March, 2017 was equivalent to Rs. 32,74,740.95/- due to the foreign

exchange fluctuation.

5. The plaintiff and the defendant have agreed that the zero date from

which the 180 days within which delivery had to be effected would be

counted from 30th March, 2017. By e-mails dated 31st March, 2017, 3rd

April, 2017 and 7th April 2017, the terms of payments were modified. In

the meeting held on 10th April, 2017, it was mutually agreed between

the parties that the second contract would be cancelled and the

payment made thereunder shall be adjusted in the first contract. In the

meeting held on 21st September, 2017 and 22nd September, 2017, the

zero date was again modified to 10th July 2017.

6. The first Letter of Credit was opened on 10th July, 2017 with HDFC

Bank for a value of USD 12,07,000 by incurring cost of Rs.

1,01,824.74/- in favour of the defendant. Due to the difficulties

expressed by the defendant, the plaintiff has closed the Letter of Credit

by a letter dated 23rd November, 2017 and a fresh Letter of Credit was

issued by the plaintiff through the State Bank of India on 29th

November, 2017. Various meetings between the parties were held and it

transpired that defendant was not in a position to perform the contract.

7. On 22nd February, 2018, the plaintiff had sent a notice though the

learned Advocate calling upon the defendant for immediate

performance and also indicated that the plaintiff will also claim

damages for non-performance of contract. The notice issued by the

plaintiff was duly delivered to the defendant but inspite of receipt of the

notice, the defendant failed to perform the contract.

8. It transpired from the records that after filing of the suit, writ of

summons were served upon the defendant but inspite of receipt of writ

of summons of this case, the defendant has not entered in the suit and

accordingly on receipt of report from the department, by an order dated

25th November 2022 the present suit was placed in the list of

"undefended suit".

9. The plaintiff has examined one witness in support of his case by filing

examination-in-chief on affidavit along with all documents and the

same was marked as Exhibit A collectively.

10. Clause 3.10 d of the agreement provides payments terms which reads

as follows:

"3.10 PAYMENT TERMS

Payment will be released as per the terms specified herein, Billing schedule document No: OMPL-II/16- 17/P7162-00019 (BS), attached to this contract is part of this contract.

             1.    Token      advance             USD 50,000.00
                   along with order by
                   TT.

             2.    90% (USD 2650000)              LC to be opened for
                   of order value less            100% of order value
                   token       advance,           less token advance
                   Prorate        basis           (USD 2950000)
                   against           the
                   dispatch, as per the
                   billing schedule, LC
                   to    be   enchased
                   against           the
                   submission         of
                   documents,

                   Dually         signed          LC shall be opened
                   commercial invoice,            within 30 days from
                   Test Certificate (In           date of receipt of
                    triplicate)                   first payment
                    Bill of Lading,
                    Inspection     report
                   dually signed and
                   stamped by Buyer



                    Packing     List   (In
                    Triplicate)

               3.   USD           300000             10% of order value
                    Against submission
                    the      Performance
                    bank Guarantee of
                    10% of order value
                    which shall remain
                    valid for the period
                    of Guarantee at
                    least for 18 months.
                    Refer clause 10.00,
                    must be submitted
                    along     with   last
                    supply     of   good
                    equivalent to 10 of
                    order value."



11. Clause 5.00 of the agreement provides delivery period which reads as

follows:

"5.00 DELIVERY PERIOD

All the equipment shall be delivered at CIF-Haldia/Kolkata within 105- 180 days from date of token advance of order without any failure, (latest by 20th October, 2017). Part shipment is allowed however all the goods must be delivered in three consignment as specified herein,

A. First consignment Material will be of steel parts of delivered within 105 the equipment, days at Indian port stationary parts of the equipment

B. Second Material will be consignment delivered within 150 inclusive of days at Indian Port Rotating parts of the equipment

C. Third consignment Material will be inclusive of drive delivered within 180 Gear box, motor, days at Indian Port electrical panel, control panel, etc.

However, Purchase requested seller to deliver the goods in 150 days from date of signing of contract.

You shall provide all the engineering drawings scoped in, within 30 days from date of contract, Equipment drawings must be submitted immediate on signing the contract so as OMPL can extend their approval immediate to commence the manufacturing of the equipments by seller.

Delivery is linked only to first payment, not to drawings approval, this please be noted, however any delay in opening the LC will have impact on delivery period correspondingly.

Kindly note that the maintenance of delivery schedule is of paramount importance and is a vital consideration for the placement of order with you. We shall tolerate no delay in the delivery of the items on any grounds whatsoever."

12. Clause 18.00 of the agreements provides for termination which reads as

follows :

"18.00 TERMINATION

We reserve the right to terminate the contract in the event of :

1. Non fulfilment of supply after a maximum delay of one month.

2. Non fulfilment of quality and workmanship standards as mentioned in this contract, inclusive of this contract."

13. As per invoices raised by the defendant, the plaintiff in terms of the

agreement has paid USD 50,000 each on 20th March, 2017 and 22nd

March, 2017. As on 20th March, 2017, the value of USD 50,000 was

equivalent to Indian Rupees 32,72,240.58/- and on 22nd March, 2017

the value of USD 50,000 was equivalent to Indian Rupees

32,74,740.95/-. The delivery period was 180 days from 30th March,

2017 and subsequent the date of delivery period was modified to 10th

July, 2017.

14. Initially, the plaintiff has opened the Letter of Credit on 10th July, 2017

in the HDFC Bank for a value of USD 12,07,000 by incurring cost of

Rs. 1,01,824.74/- but subsequently on the request of the defendant,

the plaintiff has closed the said Letter of Credit and opened a new

Letter of Credit through the State Bank of India on 29th November,

2017 for value of USD 12,07,000 by incurring cost of Rs. 50,936.00/-

15. Even after completion of all formalities and payment of token advance

as per the contract, the defendant failed to perform its obligations by

supplying the materials to the plaintiff as agreed by the defendant. The

defendant even after receipt of the legal notice has not come forward to

comply with the terms of the contract.

16. The Agreements dated 19th February, 2017, 17th March, 2017, two

invoices date 12th March, 2017 and 17th March, 2017, the bank

transaction of USD 50,000 each dated 20th March, 2017 and 22nd

March, 2017, the emails dated 31st March, 2017, 3rd April, 2017 and 7th

April, 2017, the letter dated 20th April, 2017 wherein the second

contract was cancelled, Letter of Credit dated 10th July, 2017 with the

HDFC Bank, Letter of Credit with the State Bank of India dated 29th

November, 2017, Minutes of the Meetings dated 24th July, 2017 to 27th

July, 2017, 21st September, 2017 to 22nd September, 2017, 12th

November, 2017 and 10th May, 2018, Advocate notice dated 22nd

February, 2018 and the track reports are exhibited as Exhibit A

collectively.

17. Considered the submissions made by the learned Counsel for the

plaintiff, perused the plaint, examination in chief on affidavit of the

plaintiff's witness and the documents exhibited during the evidence of

the plaintiff's witness. This court finds that the plaintiff in compliance

of the contracts entered between the parties and in terms of invoices

raised by the defendant, the plaintiff has paid token advance of USD

50,000 each on 20th March, 2017 and 22nd March, 2017 and

subsequently on the request of the defendant, first Letter of Credit was

closed and a fresh Letter of Credit was opened with the State Bank of

India by incurring expenditure of Rs. 1,01,824.74/-.

The defendant has received the total amount of Rs.

65,46,981.23/- from the plaintiff and the plaintiff has also incurred

an amount of Rs. 1,01,824.74/- for opening of fresh Letter of Credit

by closing earlier Letter of Credit. The defendant has neither supplied

materials in terms of contract nor has refunded the amount, thus the

plaintiff is entitled to get the amount incurred by the plaintiff along

with interest as well as damages.

18. In view of the above, the plaintiff do get a decree for Rs.

2,20,46,576.27/- against the defendant with interest at the rate of 18%

per annum from the date of filing of the suit till the realisation of the

decretal amount.

19. C.S No. 279 of 2019 is thus disposed of. Decree be drawn

accordingly.

(Krishna Rao, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter