Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Dredging And Desiltation Company ... vs M/S. Mackintosh Burn & Northern ...
2023 Latest Caselaw 912 Cal/2

Citation : 2023 Latest Caselaw 912 Cal/2
Judgement Date : 11 April, 2023

Calcutta High Court
Dredging And Desiltation Company ... vs M/S. Mackintosh Burn & Northern ... on 11 April, 2023
                  IN THE HIGH COURT AT CALCUTTA
                 (Ordinary Original Civil Jurisdiction)
                       COMMERCIAL DIVISION


Present:

The Hon'ble Justice Krishna Rao



                           IA No: GA 8 of 2021

                           In CS 242 of 2018



           Dredging and Desiltation Company Private Limited
                                  Versus
              M/s. Mackintosh Burn & Northern Express
                           Consortium & Ors.



           Mr. Sakya Sen
           Mr. Sankarsan Sarkar
           Mr. Sunil Singhania
           Ms. Kalpana Singhania
                                                 ...for the plaintiff
           Mr. Ratul Das
           Mr. Subhrajyoti Das
           Mr. Sagnik Basu
           Mr. Dilawar Khan
           Mr. Mainak Biswas
                                                 ...for the defendant No. 3
           Mr. Arnab Chakraborty
           Mr. P. Bhowmick
                                           ...for the defendant Nos. 1 and 2


Hearing concluded on             : 23.02.2023
                                         2


Judgment on              : 11.04.2023

Krishna Rao, J.:


      Plaintiff has filed the instant application under Order XIIIA of the

Code of Civil Procedure, 1908 as amended by the Commercial Courts Act,

2015 praying for summary Judgment for a sum of Rs. 1,93,12,425/- as

admitted by the defendant no. 1 in its letter dated 16th August, 2017.


      In the month of November 2017, in view of ensuing Ganga Sagar Mela,

2017 and improve the navigability of certain channels in River Muriganga

for a smooth movement of cargo and passenger vessels for transportation of

cargo, bikers and pilgrims, Inland Waterways Authority of India, on behalf of

the government of West Bengal, the proforma defendant no. 5 invited online

tender having experience of using cutter suction dredgers in two cover

systems. The plaintiff and one M/s. RDL IDS PL JV were the only

contractors who have submitted tender in respect of the tender Notice. None

of the said two tenders were accepted and the tender notice was not

materialized.


      By a letter dated 7th December, 2016, the Inland Water Authority of

India issued a letter to the defendant No. 2 requested to make an offer for

carrying out dredging at the jetties at Lot No. 8 and Chemaguri Khal on

emergent basis by deploying cutter suction dredgers capable of dredging at

least 250 cubic meters of solid per hour within the aforesaid tender at the

rate of Rs. 230/- per cubic metre. On receipt of the said letter, the defendant

no. 2 had called the plaintiff to participate in a meeting held at the office of

Chief Secretary, Irrigation and Waterways Directorate at Jal Sampad
                                          3


Bhawan, Salt Lake City, Kolkata. In the meeting, the plaintiff was requested

by the defendant no. 2 to consider taking up the aforesaid dredging work

and to submit its offer.


          On 9th December, 2016, the plaintiff had submitted its offer to do the

job as per the terms and conditions mentioned in the said letter to the

defendant no. 2 by giving its willingness to undertake the said dredging

work. Following the offer of the plaintiff, the defendant no.1 by a letter dated

9th December, 2016, confirmed its willingness to the Inland Waterways

Authority of India to carry out the above-mentioned dredging work. By a

letter dated 14th December, 2016, the Government of West Bengal awarded

the work in favour of the defendant no. 2 as well as in favour of another

Company namely M/s. Reach Dredging Ltd.


          By letter dated 15th December, 2016, issued by the defendant no. 1 in

favour of the plaintiff requesting the plaintiff to take up the dredging work

with respect of Lot No. 8 : Area ABCDEFGH for an estimated quantity of

2,00,676 cubic metres on the terms and conditions as mentioned in the said

letter.


          Mr. Sakya Sen, Learned Counsel representing the plaintiff submits

that the defendant no. 5 by a letter dated 14th December, 2016 accepted the

offer of the defendant no.1 at the rate of Rs. 225/- per cubic metre for

completing the dredging and desilation work. The defendant no. 1 had

accepted the offer at the rate of Rs. 225/- per cubic metre and offered

plaintiff for the said work at the rate of Rs. 202.50/- per cubic metre. Mr.

Sen submits that as per clause 8 of the offer letter by and between the
                                       4


plaintiff and the defendant no.1, the defendant no.1 would give payment to

the plaintiff as soon as they receive the same from the defendant no. 5.


      Mr. Sen submits that defendant no. 1 along with its constituents,

being the defendant nos. 2 and 3 were only acting as commissioning agent

by delegating the allotted work issued by the defendant no. 5 to the plaintiff

herein. Mr. Sen submits that after completing of entire work, the plaintiff

had raised invoice for a total amount of Rs. 9,07,00,155/- dated 20th March,

2017 but in spite of several requests made by the plaintiff, the defendants

did not pay any amount to the plaintiff.


      Mr. Sen relied upon the letter dated 27th February, 2017 addressed to

the Additional District Magistrate, being the authority of defendant no. 5

and submits that the defendants have admitted the quantity dredged by the

plaintiff i.e. 3,88,656 cubic metre. He further submits that the defendant

No. 1 had admitted the value of the invoice that is amounting to Rs.

10,05,64,740/- calculating the quantity dredged multiplied by Rs. 225/- per

cubic metre. He further submits that the defendant no.1 further admitted

the number of daily hours dredging was continued by the plaintiff for the

period from 17th December, 2016 to 16th January, 2017 at Lot No. 8 Jetty to

passenger jetty no. 1 at Chemaguri Khal.


      Mr. Sen submits that the defendant no. 1 by a letter dated 16th

August, 2017 addressed to the District Magistrate being the Authority of the

defendant no. 5 admitted to work of dredging and disilation was successfully

completed by the defendant no. 1 in January, 2017 and the defendant no.1

had already forwarded the invoice raised by the plaintiff and is awaiting the
                                       5


full payment of the bill amounting to Rs. 10,05,64,740/- inclusive of service

tax. He submits that in the said letter, the defendant no.1 further admitted

that the plaintiff had completed 3,88,656 cubic metre of dredging work. Mr.

Sen submits that it was further admitted that the defendant no.1 that the

defendant no. 5 had already released payment of Rs. 2,14,58,250/- for the

quantity of 95,370 cubic metre dredged by the petitioner.


      Mr. Sen submits that defendant no. 5 had given a contract to the

defendant no.1 for dredging work at the rate of Rs. 225/- per cubic metre

and the defendant no.1 had sub contracted the said work to the plaintiff at

the rate of Rs. 202.50 per cubic metre and thus it is back-to-back contract

and the payment was supposed to be received by the plaintiff on a back-to-

back contract basis in terms of clause 8 of the contract by and between the

plaintiff and the defendant no.1 dated 15th December, 2016.


      Mr. Sen submits that defendant no.1 had admitted the quantity of silt

dredged by the petitioner being 388656 cubic metre and the defendant no.1

had forwarded the invoice raised by the plaintiff to the defendant no. 5 for

release of payment and the defendant no.1 had admitted that in lieu of bill

raised by the plaintiff on the defendant no.1, the defendant no.1 had

received a sum of Rs. 2,14,58,250/- for a quantity of 95370 cubic metre of

silt dredged.


      Mr. Sen submits that as per the admission, defendant nos. 1, 2 and 3

are liable to pay a sum of Rs. 1,93,12,425/- to the plaintiff in terms of the

agreement by and between the defendant no.1 and the plaintiff dated 15th
                                        6


December, 2016 is specifically in terms of clause 8 being 90% of the sum

already received by the defendant no.1 ie. Rs.1,93,12,425/-.


Mr. Sen relied upon the following judgments:


            i.      (2017) 1 SCC 568 (IDBI Trusteeship Services Ltd. -vs-
                    Hubtown).
            ii.     (2017) 8 SCC 237 (Kanchan Udyog Limited -vs- United
                    Sprits Limited).
            iii.    (1974) 2 SCC 729 (P. Dasa Muni Reddy -vs- P. Appa Rao).




      Mr. Debnath Ghosh, Learned Advocate representing the defendant

nos. 1 and 2 and submits that the plaintiff raised invoice dated 20th March,

2017 for Rs. 9.07 Crore under the cover of the letter dated 23rd March, 2017

but the bill has not been raised as per the terms of the Letter of Intent but

the bill has been raised on the basis of dredging hours and has not been

certified KoPT or the appropriate Authority.


      Mr. Ghosh submits that the plaintiff has to submit bills after being

satisfied by the proforma defendant no. 5 as per Letter of Intent. He submits

that the plaintiff has not submitted completion certificate for finalisation of

the bill. He submits that the invoice raised by the plaintiff is not acceptable

to the defendant no.1 since plaintiff had failed to submit bill as per certified

dredged quantity.


      Mr. Ghosh submits that there is no admission on the part of the

defendant that the payment would be released in favour of the plaintiff even

if the bills were raised on the basis of dredging hours and if such bills were
                                         7


not certified by the KoPT or the appropriate authority contrary to the

contract between plaintiff, the defendant no. 1 and the defendant no. 2. Mr.

Ghosh submits that the defendant nos. 1 and 2 have several time requested

the plaintiff to raise bills as per the terms of the contract between the parties

but that plaintiff failed to submit bill in terms of the contract.


      Mr. Ghosh submits that defendant no. 1 and 2 have rebutted the bills

submitted by the plaintiff vide email dated 13th February, 2018 informing

that the invoice dated 20th March, 2017 has not been accepted.


      Mr. Ghosh submits that admittedly no summon has been served upon

the defendant nos.1 and 2 after the transfer of suit before this Court and

thus the procedure contemplated under Order XIIIA, Rule 2 of the Code of

Civil Procedure, which directs that an application may apply for summary

judgment at any time after summons has been served on the defendant but

the plaintiff has not followed the procedure.


      Mr. Ghosh submits that the bills submitted by the plaintiff are neither

admitted documents nor any undisputed facts from which it can be inferred

that summary judgment can be passed. Mr. Ghosh submits that a definite

difference has been adopted by the defendant denying the authenticity and

veracity of the bills and highlighted the discrepancies between the bill raised

and the bill to have been raised in terms of the contract.


      Mr. Ghosh submits that the plaintiff has to prove the bills by

adducing evidence to satisfy this Court that the plaintiff has submitted the

bill in terms of the contract.
                                        8


Mr. Ghosh relied upon the following judgements:


            i.     2022 SCC Online Del 2862 (Interiors Products Private
                   Limited -vs- Rahul Bhandari)
            ii.    2021 SCC Online Cal 526 (MadhusriKonar -vs- New
                   Central Book Agency)
            iii.   (2011) 15 SCC 273 (Himani Alloys Ltd -vs- Tata Steel
                   Limited)
            iv.    (2010) 6 SCC 601 (Jeevan Diesels -vs- Jasbir Singh)
            v.     (2020) 13 SCC 564 (Shree Ambica Medical Stores -vs-Surat
                   Peoples Cooperative Bank Limited).



      Learned Counsel representing the defendant no. 3 submits that he

has adopted the submission made by the Counsel for the defendant nos. 1 &

2 and further submits that as per condition no. 3 of the contract, the work

completion or progress is to be certified by the competent authority; KoPT or

other nominated by the Administration.


      Counsel for the defendant no. 3 submits that the invoice was raised

on estimated calculation by the plaintiff taking into consideration of

operation of four numbers of machineries and minimal optimal output

quantity of the machines and not on actual quantity of Silt dredged which

requires certification by the KoPT.


      Learned Counsel for the defendant no. 3 submits that since the

certification had become available, the defendant no.1 called upon the

plaintiff to rectify its invoice and raise it in terms of the contract but the

plaintiff has not taken any steps and had filed the instant suit.
                                       9


      Learned Counsel for the defendant no. 3 submits that there is no

admission as claimed by the plaintiff. He submits that on 28th February,

2017, the defendant no.1 forwarded the invoice of the plaintiff because till

that time, there was no certified quantity of work was done certificate was

available with the defendant no.1. He submits that on the same day i.e. on

28th February, 2017, the defendant no.1 received the certified quantity when

KoPT submitted the documents by letter dated 27th February, 2017.


      Learned Counsel for the defendant no. 3 submits that there is a

difference between obligation to make payment and the mode and manner of

making payment.


      Counsel for the defendant no. 3 had relied upon the following

judgements:


         i.       (1911) 2 Ch 279 (Tewkesbury Gas Company, Tysoe -vs- The
                  Company).
         ii.      ILR (1964)1 P&H 143 (Mrs. I.K. Sohan Singh -vs- State Bank
                  of India).
         iii.     AIR 1956 Bom 151 (M/s. Navnital & Co. -vs- Kishanchand &
                  Co.).



      The work order issued by the proforma defendant no. 5 to the

defendant no. 1 on 14th December, 2016 reads as follows :


                      "GOVERNEMNT OF WEST BENGAL
                       Office Of The District Magistrate
                South 24-Parganas, Alipore, Kolkata - 700 027
                 (An ISO 9001 : 2008 Certified Organization)

      Memo No : 311(2)/CON/G                     Date : 14.12.2016
                                 10


To,

       1. M/s Mackintosh Burn Ltd, 8, N.S. Road, Kolkata- 700 001
       2. M/s Reach Dredging Ltd., 1, Garstin Place, Kolkata-700
001

            Sub   : Dredging for Ganga Sagar Mela-2017
Sir,

      With reference to letter No. IWAI/MD/247/2016-17 dated
09-12-16 and F. No. IWAI/MD/247/2016-17 dated 14-12-16, you
are requested to kindly take up dredging work as follows :-



       AREA    [REF         QUANTITY   TO          AGENCY
       KOPT                 BE DREDGED             WORKING
       HYDROGRAPH           (APPROX)               ON
       IC   SURVEY                                 NATIONAL
       AND     PWD                                 WATERWAYS
       MECH                                        UNDER IWAI
       ESTIMATES]                                  AND
                                                   REFERENCE
       Lot 8 - Area         3,13,676 Cubic         The
       ABCDEFGH             Metres          -      Mackintosh
                            1,13,000 Cubic         Burn Limited
                            Metres    earlier
                            assigned to [WAI
                            = 2,00,676 Cubic
                            Metres
       Lot 8 - Area         55,826     Cubic       Reach
       PQRS - Jetty 2       Metres                 Dredging
       Benuban      to      54,968     Cubic       Limited
       Mohana       in      Metres
       Chemaguri
       Creek


CONDITIONS :

1.     Payment will be made @ Rs. 225/- per cubic meter of actual
       quantity silt dredged, as approved by the State Government.

2.     Excavated silt should be deposited on the shore/ in the
       trenches provided by local administration to prevent back
       flow into river channel and enable measurement of quantity
       extracted.

3.     Work completion/progress is to be certified by the competent
       KoPT/Others nominated by the administration.
                                      11


     4.    Local officials will maintain liaison and guide on the
           channels to be dredged.

     5.    Large scale movement of pilgrims, visitors and vehicles will
           commence shortly. All effort should be made to complete
           dredging by 05-01-2017.

     6.    Each agency must mobilize at least two dredgers of at least
           400 m per hour of solids capacity and adequate pipelines to
           carry away silt.

     7.    The Mela Committee will periodically review progress of
           dredging and may re-assign the work among selected
           agencies in the interest of timely completion and safe transit.

                                                          Yours faithfully
                                 Additional District Magistrate (General),

                                                    South 24 Parganas."



     On receipt of work order dated 14th December, 2016, the defendant

no. 1 had back-to-back issued the work order to the plaintiff dated 15th

December, 2016.


     "Ref: MBANC/GSM2017/2016-17
     Dated: 15th December 2016

     To:

     Dredging & Desiltation Co Pvt Ltd
     167, Old China Bazar Street, 2nd Floor
     Kolkata 700001

     Sub: LOI for Dredging for Ganga Sagar Mela-2017
     Ref: Your Letter DDC/171/16-17 dated 9.12.2016


     With reference to the above you are requested to kindly take up
     dredging work as follows :

                                              QUANTITY   TO  BE
           AREA     (REF  KOPT                DREDGED (APPROX)
           HYDROGRAPHIC SURVEY
           AND     PWD    MECH
           ESTIMATES]
                                      12


           Lot 8 - Area ABCDEFGH            2,00,676 Cubic Meters



     CONDITIONS :

     1.    Payment will be made at Rs. 202.50 per Cubic Meter of
           actual quantity silt dredged, as approved by the State
           Government.

     2.    Excavated silt should be deposited on the shore/ in the
           trenches provided by local administration to prevent back
           flow into river channel and enable measurement of quantity
           extracted,

     3.    Work completion/ progress is to be certified by the competent
           authority : KoPT/Others nominated by the administration.

     4.    Local officials will maintain liaison and guide on the
           channels to be dredged.

     5.    Large scale movement of pilgrims, visitors and vehicles will
           commence shortly. All effort should be made to complete
           dredging by 05-01-2017.

     6.    You must mobilize at least two dredges at least 400 m per
           hour of solids capacity each and adequate pipelines to carry
           away silt.

     7.    The Mela Committee will periodically review progress of
           dredging and may re-assign the work among selected
           agencies in the interest of timely completion and safe transit.

     8.      Payment will be disbursed immediately as receive from
     client.

     9.    Taxes will be deducted as per govt rules from bills.
                                                         Yours faithfully,

                 For Mackintosh Burn and Northern express Consortium



                                                          Bireswar Saha
                                                   Dy General Manager."



     On 23rd March, 2017, the plaintiff has raised bill for an amount of Rs.

90700155/- to the defendant no. 1. Along with the bill, the plaintiff has
                                          13


informed the defendant no. 1 by a letter dated 23.03.2017 that the plaintiff

has already submitted copy of daily dredging log of all the dredgers along

with summary statement showing daily dredging hours for the entire period

of operation. The plaintiff also informed that the statement of dredging

hours will find that the plaintiff dredged work for 1065.30 hours at Lot No. 8

and 151.35 hours at Chemaguri Khal taking into consideration of minimum

optimum output of 320 cubic metre solids per hour and the total dredging

quantity comes to 340960 cubic metre for Lot No. 8 and 48520 cubic metre

for Chemaguri Khal.


        On 28th February, 2017, the defendant no. 1 had requested the

proforma defendant no. 5 regarding the details of the daily dredging hours

for the period from 17th December, 2016 to 16th January, 2017 at Lot No. 8

jetty   to   passenger   Jetty-1   and   Chemaguri   Khal   and   in   the   said

communication, the defendant no.1 had informed the defendant no. 5, the

quantity and value of the work as intimated by the plaintiff to the defendant

no.1.


        By a letter dated 16th August, 2017, the defendant no.1 has admitted

that the work has been completed in the month of January, 2017 but the

authorities have released the payment of Rs. 2,14,58,2504/- a quantity of

95,370 cubic metre approximately and requested the authorities to release

the balance payment of Rs. 7,91,06,709/-.


        Now, the question in the present application is whether the amount of

Rs. 2,41,50,250/- received by the defendant no.1, the plaintiff is entitled to

get 90% amount out of the same.
                                       14


      Admittedly the pro forma defendant No.5 issued work order to the

defendant no.1 to execute the work at the rate of Rs. 225/- per cubic metre

actual quantity silt as approved by the State government. The defendant

no.1 has authorised the plaintiff to execute the said work at the rate of Rs.

202.50 per cubic metre. The plaintiff had submitted bill for a total quantity

of 3,89,480 cubic metre for a total amount of Rs. 90700155/-. The

defendant no.1 has not disputed the quantity and the amount raised by the

plaintiff and accordingly the defendant no. 1 had requested the respondent

no. 5 for release of the amount as per the quantity claimed by the plaintiff

and the authorities have released only Rs. 2,14,58,250/- for a quantity of

95,370 cubic metre. Now the defendants have raised the issue though the

plaintiff had submitted the Bill but the plaintiff has not submitted any

certificate from the competent authority with regard to the completion of

work as per clause 3 of the terms and condition of the letter dated 14th

December, 2016.

Initially the respondent no. 5 had issued work order to the defendant

no.1 on 14th December, 2016 wherein the condition no. 3 reads as follows;

"work completion/progress to be certified by the competent authority KoPT/others nominated by the administration."

The similar condition was imposed upon the plaintiff when the

defendant no.1 has authorized the plaintiff to execute the said work at the

rate of Rs. 202.50 per cubic metre.

It is not the case of the defendants that the defendant no.1 had

submitted completion certificate in terms of clause 3 of the condition of the

letter dated 14th December, 2016. From record, it reveals that the details

submitted by the plaintiff was accepted by the defendant no.1 and on the

basis of the invoices raised by the plaintiff, the defendant no.1 had

requested the defendant no. 5 to release the amount. The defendant no. 5

had released only an amount of Rs. 2,14,58,250/- for a quantity of 95,370

cubic metre.

Clause 8 of the conditions of the letter dated 15th December, 2016,

wherein the defendant no.1 had given the sub-contract to the plaintiff, it is

mentioned that "payment will be disbursed immediately as received from

client".

In the present case, the defendant no. 5 has released an amount of

Rs. 2,14,58,250.00/- quantities of 95370 cubic metre in favour of the

defendant no.1. It is admitted that the defendant no.1 had not procured any

completion certificate from the competent authority as required in clause 3

of the work order dated 14th December, 2016 issued by the defendant no. 5

to the defendant no.1. The defendant no. 5 has released the amount in

favour of defendant no.1 without any completion certificate submitted by

defendant.

In the short notes of submission filed by the defendant no. 3, the

defendant no. 3 admitted that:

"m. Since the certificate had become available, the defendant no.1 called upon the plaintiff to rectify its

invoice and raise it in terms of the contract. The plaintiff has not taken any steps and/or refuse to do so and has filed the suit.

3(ii). There is no admission as incorrectly claimed by the plaintiff on the part of the defendant no.1. On 28th February ,2017, the defendant no.1 forwarded the invoice of the plaintiff because at that time, there was no certified quantity of work done available to the defendant no.1. On the same day, that is 28th February, 2017, the defendant no.1 had received the certified quantities that become available when KoPT submitted the document under the cover of letter dated 27th February, 2017. There is, therefore, no admission of the defendant no.1 to 3. Further the state of West Bengal has also rejected plaintiff's claim made in a different and inflated rate."

In the above paragraphs, the defendant no. 3 has admitted that

defendant no. 1 had the certificate and the said certificate was issued by

KoPT on 27th February, 2017.

Certificate issued by the Director Marine Department, KoPT dated 27th

February, 2017 reads as follows :

"No. Mrn/80/51 Date : February 27, 2017

Ms. Joyoshi Das Gupta, IAS Additional District Magistrate (General), South 24 Parganas, Alipore

Mela Officer, Ganga Sagar

Sub : Estimate of quantity of silt extracted during dredging

Madam,

Further to this office letter no. Mrn/80/18, dated 25th January, 2017 the detailed block wise difference of volume alongwith names of dredgers deployed therein enclosed.

                                                                Yours faithfully



                                                             (Capt. J. J. Biswas)
                                                   Director, Marine Department



      AREA        BAME OF     NAME       OF   PERIOD     DIFF.   IN   REMARKS
                  DREDGERS    PARTY           OF         QUANTITY
                                              DREDGING   BET.
                                                         SURVEY
                                                         DATED
                                                         15.12.2016
                                                         &
                                                         10.01.2017
      ABCD        TAPI        IWAI            04.12.16   1255 CU.M    This        is
                                              TO                      Considering
                                              15.12.16                the        re-
                                                                      siltation
                                                                      trend
                                                                      between
                                                                      the survey
                                                                      on        31st
                                                                      August
                                                                      2016 and
                                                                      15th
                                                                      December,
                                                                      2016.
      ABCD        TAPI        IWAI            15.12.16   9012 CU.M
                                              TO
                                              09.01.17
      CDEFG       TAPI        IWAI            15.12.16   7785 CU.M
                                              TO
                                              09.01.17
      CDEFG       NETAI   &   MACKINTOSH      17.12.16   7785 CU.M
                  SAI RAM                     TO
                                              09.01.17
      FIJG        SAI   RAM   MACKINTOSH      17.12.16   63513
                  KRISHNA,                    TO         CU.M
                  BADANI &                    09.01.17
                  NETAI
      OPQR        K2          REACH           22.12.16   9678 CU.M
                              DREDGING        TO
                                              06.01.17
      CHEMAGURI   SAI RAM     MACKINTOSH      04.01.17   24072
      CREEK                                   TO         CU.M
                                              10.01.17
                                              Total      1,23,100
                                                         CU.M




The certificate issued by KoPT dated 27th February, 2017, certified the

quantity of 95370 cubic metre on the basis of which the defendant no. 5 had

released the amount of Rs. 2,14,58,250/- in favour of the defendant no. 1. It

is crystal clear that the defendant no. 1 had the certificate and the

defendant no. 5 had released the amount in favour of defendant no.1 and

thus as per Clause 8 of the condition of the letter dated 15th December,

2016, the defendant no.1 is under the obligation to disburse the amount to

the plaintiff as claimed by the plaintiff.

In the case of IDBI Trusteeship Services Limited (Supra), Hon'ble

Supreme Court held that if any part of the amount claimed by the plaintiff is

admitted by the defendant to be due from him, leave to defend the suit (even

if triable issues or a substantial defence is raised), shall not be granted

unless the amount so admitted to be due is deposited by the defendant in

court.

In the case of Kanchan Udyog Limited (Supra), the Hon'ble Supreme

Court held that if a party entitled to a benefit under a contract is denied the

same, resulting in violation of legal right, and does not protest, foregoing its

legal right, and accepts compliance in another form and manner, issues will

arise with regard to waiver or acquiescence by conduct.

In the case of P. Dasa Muni Reddy (Supra), the Hon'ble Supreme

Court held that abandonment of right is much more than mere waiver

acquiescence or latches. The doctrine which the Courts of law will recognise

is a rule of judicial policy that a person will not be allowed to take

inconsistent position to gain advantage through the aid of courts. Waiver is

consensual in nature. It implies a meeting of the minds. It is a matter of

mutual intention. The doctrine which the courts of law will recognise is a

rule of judicial policy that a person will not be allowed to take inconsistent

position to gain advantage through the aid of courts. Waiver sometimes

partakes of the nature of an election.

The judgments relied by the defendants are distinguishable in the

facts and circumstances of the present case.

In the present case, the work order issued by the defendant no. 5 to

the defendant no. 1 and the work order issued by the defendant no.1 to the

plaintiff contains the clause that work completion/progress to be certified by

the competent authority i.e. KoPT/others nominated by the administration.

The defendants claim that the plaintiff has not submitted the above-

mentioned certificate and as such payment cannot be released without the

certificate. The said clause does not reveal that the bill submitted by the

plaintiff is to be accompanied with the completion certificate. Admittedly on

27th February, 2017, the competent authority had issued certificate and on

the basis of the certificate, the defendant No.5 had released an amount of

Rs. 2,14,58,250/- for the quantity of work of 95,370 cubic metre. It is not

the case of the defendant no. 1 that the defendant no. 1 had submitted

certificate. The certificate dated 27th February, 2017 issued by the Director,

Marie Department to the defendant no. 1 and accordingly payment was

released for the said quantity.

As per Clause 8 of the work order issued by the defendant no.1 to the

plaintiff payment is to be disbursed immediately after receipt of payment by

the defendant no.1. Admittedly, defendant no.1 had received the amount of

Rs. 2,14,58,250/- and thus the defendant no.1 cannot deny for the payment

to the plaintiff in terms of work order dated 15th December, 2016.

In view of the above prayer (a) of the Notice of Motion is allowed.

G.A. 8 of 2021 is thus disposed of.

(Krishna Rao, J.)

Later :

Counsel for the defendant nos. 1 and 2 prayed for stay of the

operation of the order. Counsel for the plaintiff raised objection. Considered

the submission made by the respective parties. Prayer is refused.

(Krishna Rao, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter