Citation : 2022 Latest Caselaw 2519 Cal
Judgement Date : 5 May, 2022
IN THE HIGH COURT AT CALCUTTA
Civil Appellate Jurisdiction
(Appellate Side)
F.M.A 51 of 2022
With
I.A. No. C.A.N. 1 of 2021
M/s. Western Engineering Works.
Vs.
The State of West Bengal & Ors.
Before: The Hon'ble Justice Arijit Banerjee
&
The Hon'ble Justice Kausik Chanda
For the Appellants : Mr. Saktinath Mukherjee, Ld. Sr. Adv.
Mr. Aniruddha Chatterjee, Adv.
Mr. Rahul Karmakar, Adv.
Mr. Asif Sohail Tarafdar, Adv.
Mr. Sounak Mukherjee, Adv.
For the State : Mr. Amitesh Banerjee, Ld. Sr. Standing
Counsel
Ms. Ipsita Banerjee, Adv.
Mr. Suddhadev Adak, Adv.
Heard On : 21.01.2022, 31.01.2022, 23.02.2022,
28.02.2022, 03.03.2022, 07.03.2022
09.03.2022 & 14.03.2022
CAV On : 14.03.2022
Judgment On : 05.05.2022
Arijit Banerjee, J.:
1. The writ petitioner/appellant had approached the learned Single
Judge essentially challenging a notice dated 6/18 April, 2018 ( in short the
2
'Impugned Notice'), issued by the Joint Secretary to the Government of West
Bengal, the material portion whereof reads as follows:-
"Now, therefore, after careful consideration of this matter and in
terms of the Clause 4 of the Lease Deed, the Governor of the State
of West Bengal is pleased to determine the lease of Plot No. CN-3,
Sector - V, Salt Lake, Kolkata for violation of Clause 2(6) of the
lease deed and re-enter into possession of the demised land."
2. The other prayer in the writ petition was for a mandamus
commanding the respondent authorities to allow the writ petitioner's prayer
made vide letter dated December 15, 2015, for change of purpose of use of
the concerned land, from construction of a Motor Training School to a Hotel
with Banquet and Restaurant facility upon accepting fees in terms of the
Government Notification No. 4004-UD/M/SL(AL/NR)/8L-08/04 dated 8th
December, 2011. The learned Single Judge dismissed the writ petition.
Hence this appeal by the writ petitioner.
3. Before the learned Single Judge as also before us, the writ petitioner
submitted as follows:-
(a) An Indenture of lease dated July 24, 1985, was executed by
the Governor of the State of West Bengal in favour of the writ
petitioner in respect of land measuring approximately 10 katthas
in Block CH in Sector (v) of Bidhan Nagar, for a period of nine
hundred ninety nine years, for erection of a building thereon for
the purpose of setting up of a weigh bridge/Motor Training School.
The relevant clauses of the said deed of lease read as follows:-
"(i) To construct the building in conformity with such
building rules as may from time to time be framed by the
Government or other authority prescribed in that behalf and
according to plans, specifications, elevations, designs and
sections sanctioned by the government, or that authority
within three years from the date of possession of the demised
land or such extended time as may be allowed by the
Government in writing.
(ii) Not to use or allow to be used the land and/or the
structure thereon or any part thereof for any purpose other
than for the purpose as mentioned in para 1 without the prior
permission in writing of the Government or other authority
prescribed in that behalf.
(iii) Provided always that if there be any breach of any of
the terms and conditions and covenants herein on the part of
the lessee contained the lesser shall have the right to re-enter
into possession of the demised land or any part thereof in the
name of the whole and thereupon this demise shall forthwith
stand determined.
Provided nevertheless the lessor shall not exercise the
right without serving the lessee a notice in writing giving six
months' time to remedy the breach."
(b) Due to acute financial crisis, the writ petitioner could not
complete the proposed construction within the prescribed period of
time.
(c) In the year 2006, a notice was served on the writ petitioner
by the Government to show-cause as to why the lease in favour of
the writ petitioner should not be determined by reason of breach of
Clause 2(6) of the lease deed which required the lessee to complete
the proposed construction within 3 years from the date of
possession being made over to the lessee, or such extended time as
may be allowed by the Government in writing.
(d) Written explanations dated December 4, 2006, and
December 14, 2007, submitted by the writ petitioner, were found
to be unsatisfactory and unacceptable to the Government. A notice
dated February 19, 2010, was issued by the Government,
addressed to the writ petitioner, the material portion whereof reads
as follows:-
"And whereas the explanation dated 4th December, 2006
and subsequent explanation dated 14-12-2007 submitted by
the lessee have been found to be unsatisfactory and
unacceptable to the Government;
And whereas the Governor of the State of West Bengal was
pleased to serve upon him a final and peremptory notice
under proviso to Clause 4 of the aforesaid Indenture to
remedy the breach caused by violation of Clause 2(6) of the
lease deed within six months from the date of receipt of this
notice and if it fails/neglects to remedy the breach within the
stipulated period, the aforesaid lease granted by the
Government shall stand determined and the Government will
re-enter into possession of the aforesaid land in full or in part
thereof in the name of the whole after expiry of the aforesaid
period of six months in terms of Clause 4 of the aforesaid
Indenture;
And whereas the said M/s. Western Engineering Works
have failed and/or neglected to take any action substantial to
remedy the breach caused by violation of Clause 2(6) of the
aforesaid Indenture within the aforesaid notice period;
Therefore the Governor of the State of West Bengal has
already determined the lease granted in favour of M/s.
Western Engineering Works in respect of the Plot No. 3 in
Block - CN in Sector-V of Bidhannagar, District 24 Parganas
(North) and started process of resumption of the said plot of
land and re-enter into possession in part thereof in the name
of the whole."
(e) The said notice was challenged by the writ petitioner by filing
a writ petition being W.P. 6670 (W) of 2010. By an order dated
December 19, 2013, a learned Judge of this Court quashed the
said notice and directed that "provided the writ petitioners complete
the building by 31st March, 2015, the respondents are permanently
restrained from issuing any notice of termination of the lease on the
ground of Clause 2(6)."
(f) The writ petitioner filed CAN 11946 of 2014 praying for
modification of the aforesaid order dated December 19, 2013, by
extending the time to complete the proposed construction. It was
submitted that after the order dated December 19, 2013, was
passed, the sanctioned plan lapsed. Clearances from various
authorities were required in order to obtain a fresh sanction.
Necessary clearances had been obtained from the authorities
except from the Airport's Authority of India. The learned Judge
disposed of the application by an order dated December 19, 2014,
"directing the Airport Authority of India to process the application of
the writ petitioners and take a decision within 4 weeks from the
date of communication of this order. Thereafter, the writ petitioners
will apply before the respondent Nos. 7, 8 for sanction of the plan.
They will process the same, taking a decision within 8 weeks of
submission of the application. If the plan is sanctioned, the writ
petitioners will complete the building by 31st December, 2017."
(g) The writ petitioner has in fact constructed a G+1 storeyed
building on the concerned plot of land in terms of the sanctioned
plan of 2008 and has applied for issuance of Part Completion
Certificate before the concerned authorities.
(h) On July 18, 2015, the writ petitioner addressed a letter to
the Joint Secretary, Urban Development Department, Government
of West Bengal, essentially stating that keeping in mind the market
viability of a Motor Training School in the concerned area it is not
advisable to go for the same. Instead, a commercial building is
more viable in the location. The last two paragraphs of the said
letter read as follows:-
"Sir, as per the order of the Hon'ble High Court, Calcutta,
the deadline for completing construction of building is
31.12.2017 and accordingly we got all approvals from all the
concerned authorities required for construction. The building
plans and structural design from our architect is also ready.
Now "Nabadiganta Industrial Township Authority" is not
giving us approval of sanction plan till the time we obtain
permission from your department for change of use. Only
because of this we are unable to start construction.
Hence, we request you to grant us permission to change
the use of plot from "Motor Training School" to "Commercial
Building" at your earliest opportunity to enable us to complete
the construction as per the deadline given by High Court,
Calcutta."
(I) On December 15, 2015, the petitioner addressed a letter to
the principle Secretary, Urban Development Department,
requesting the latter to grant 5 years time "to Complete building of
the Hotel so that there is no deadline pressure of December 2017 as
granted to us by the Hon'ble High Court of Calcutta." This was
followed by a letter to the same effect written on February 13,
2017.
(j) Without responding to the writ petitioner's letters dated
December 15, 2015, or February 13, 2017, the Government of
West Bengal issued the impugned notice dated 6/18 April, 2018,
the operative portion whereof has been extracted in the first
paragraph of this judgment.
(k) In the aforesaid factual matrix, Mr. Mukherjee, learned Senior
Counsel appearing for the appellant, has made two-fold legal
submission.
(l) Firstly, he submitted that the respondent authorities by their
conduct have waived the forfeiture. He submitted that the right of
the respondents to enforce the forfeiture clause in the lease deed
arose long time back. However, the language of the notice
impugned in the present proceedings indicates that the
respondents treated the lease as subsisting till the date of the
impugned notice. He submitted that the very fact that the lease
was sought to be determined by the impugned notice goes to show
that the Government treated the lease to be subsisting and valid
till the date of that notice although the Government could have
terminated the lease much earlier by acting on the basis of the
forfeiture close in the lease deed. Thus, by their acts and conduct
the respondents, with the knowledge that forfeiture has been
incurred, have shown an intention to treat the lease as subsisting.
This amounted to waiver of forfeiture under Section 112 of the
Transfer of Property Act, 1882. In this connection learned Senior
Counsel relied on a decision of the Patna High Court in the case of
Shiv Prasad Singh v. Smt. Mandira Kumari Debi reported at
AIR 1940 Pat 478 and a decision of a coordinate Bench of this
Court in the case of M/s. Bungo Steel Furiture (Private) Ltd. v.
Pulin Chandra Daw reported at (1987) 1 CHN 116. We will
revert back to these decisions later in this judgment.
(m) The second point made by learned Senior Counsel was that the
lease has been determined without taking a decision on the
appellant's application for change of user. Clause 2(9) of the lease
deed permits the lessee to use the land for a purpose other than
the purpose for which it was leased out to the lessee with the prior
written permission of the Government or other authority
prescribed in that behalf. The appellant has made an application
for such permission. Without taking a decision on such
application, the lease has been sought to be determined. Mr.
Mukherjee referred to Notifications dated May 6, 2005, April 17,
2007, May 6, 2008 and December 8, 2011, issued by the Urban
Development Department of the Government of West Bengal,
copies whereof have been brought on record by way of a
supplementary affidavit affirmed on behalf of the appellant on
December 3, 2021. Relying on such Notifications, learned Senior
Counsel submitted that the Government, having noticed that a
good number of industrial and commercial plots are lying unused
in Bidhan Nagar, has taken a conscious decision which is reflected
in Paragraph 4 of the Notification dated May 6, 2005, which reads
as follows:-
"The lessee of a land or a transferee of leasehold right of a
land in Bidhannagar industrial and commercial plots, if they
intend to change the original purpose of allotment, shall have
to apply to the Government seeking such permission. The
Government of West Bengal in the Urban Development
Department shall examine the proposal and if it is found
suitable, shall allow such change of purpose subject to
payment of fees at the following rates and execution and
registration of a deed of rectification to the original lease-deed
following the usual rules of registration of the Government:
(i) Rs. 10.000/- (Rupees ten thousand) only per cottah if
an I.T. related project is proposed;
(ii) Rs. 20. 000/- (Rupees twenty thousand) only per
cottah for non-I.T. projects.
In no case any concession of registration fees shall be
allowed."
The subsequent notifications merely enhanced the fees payable for
obtaining permission for change of user. He said that in a plethora
of cases, this Court has directed the authorities to grant
permission for change of user upon payment of applicable fees.
The appellant's case stands on the same footing. The Government
should have allowed the appellant's application for change of user.
The Government sat tight on the application and suddenly
determined the lease. This was wholly unreasonable on the part of
the Government. The decisions of this Court relied upon by Mr.
Mukherjee were those rendered in W.P. No. 6858(W) of 2008
(Ashis Kumar ghosh v. The State of West Bengal & Ors.), W.P.
No. 16410 (w) of 2009 (Smt. Deepa Chakraborty & Ors v. The
State of West Bengal & Ors.), W.P. No 20739 (w) of 2010 (B.M.
Pal Chowdhury & Co. Pvt. Ltd. & Anr v. The State of West
Bengal & Ors.), W.P. No. 18668 (w) of 2012 (M/s. Din
Chemicals & Coatings Pvt. Ltd. & Anr v. The State of West
Bengal & Ors.), W.P. No. 19516(w) of 2012 (M/s. Seven Hill
Bytes Pvt. Ltd. & Anr v. The State of West Bengal & Ors). and
W.P. No. 12224 (w) of 2014 (GPT Health Care Private Limited
& Anr v. The State of West Bengal & Ors.).
4. Appearing for the State respondents, Mr Amitesh Banerjee, learned
Senior Standing Counsel, submitted as follows:-
(i) The terms and conditions of the lease deed imposed an
obligation on the appellant to construct the proposed building
on the concerned land within 3 years from the date of
possession of the demised land or such extended time as may be
allowed by the Government in writing, failing which the
Government could repossess the land in question whereupon
the demise would stand determined.
(ii) Possession of the land in question was taken over by the
appellant on September 5, 1985, as would be evident from a
possession certificate of that date. The first show-cause notice
was issued to the appellant on November 24, 2006, calling for
an explanation within 90 days as to why the concerned plot of
land shall not be resumed by the Government in view of the
appellant's failure to construct the proposed building on the
said plot of land.
(iii) Notice of resumption of the concerned land was issued on
February 19, 2010. This was challenged by the appellant before
the Writ Court. The notice was quashed. The appellant was
granted time till March 31, 2015 to complete the building. Such
time was extended by a subsequent order, till December 31,
2017.
(iv) The appellant applied for permission for change of user on July
18, 2015. Apart from writing a couple of letters after that, the
appellant did not take any step for ensuring that its application
is decided one way or the other. The appellant did not approach
the Court with a grievance that the Government was
unreasonably withholding permission for change of user. This
suited them. Land price was continuously increasing in the
meantime. The appellant cannot be permitted to put a premium
on the breach on its part.
(v) There was or is no act of waiver of forfeiture on the part of the
State.
(vi) There is no infirmity in the order of the learned Single Judge
which warrants inference. The appeal should be dismissed.
Court's View:-
5. I am unable to accept the first contention of the appellant that the
respondents had waived their right to forfeit the lease. Section 112 of the
Transfer of Property Act, 1882 (in short 'TPA'), insofar as the same is
relevant for the present purpose, reads as follows:-
"112. Waiver of forfeiture. - A forfeiture under Section 111,
clause (g), is waived by acceptance of rent which has become due
since the forfeiture, or by distress for such rent, or by any other
act on the part of the lessor showing an intention to treat the lease
as subsisting.
Provided that the lessor is aware that the forfeiture has been
incurred."
The argument of the appellant that by issuing the impugned
notice the respondents showed an intention to treat the lease as
subsisting even after right accrued in their favour to forfeit the lease,
is rather stretched. The respondents had initially issued a notice
dated February 19, 2010, to the appellant recording that the lease
granted in the latter's favour already stood determined and process
for resumption of the concerned plot of land had started. This notice
was set aside by a learned Single Judge by an order dated December
19, 2013 passed in W.P. 6670(W) of 2010. The learned Judge
restrained the respondents from issuing any notice of termination of
the lease on the ground of Clause 2(6) of the lease deed subject to the
writ petitioner/appellant completing the building by March 31, 2015.
6. On an application filed in connection with the said writ petition being
CAN 11946 of 2014, by an order dated December 19, 2014, the same
learned Judge extended the time for the appellant to complete the building
till December 31, 2017. Upon the appellant's failure to complete the building
even within such extended time period, the impugned notice dated
6/18.04.2018 was issued by the respondents, determining the lease and re-
entering into possession of the demised land. Learned Senior Counsel for the
appellant submitted that the language of the impugned notice shows that by
that notice the lease was determined. It follows that till such notice was
issued, the respondents had treated the lease as subsisting even after
forfeiture occurred. Hence, the respondents must be taken to have waived
the forfeiture. I am unable to agree. The earlier determination of the lease
was set aside by an order of this Court which, not having been challenged,
attained finality. Time was granted to the appellant to complete the building
initially by March 31, 2015, which was extended till December 31, 2017 and
in the meantime the respondents were restrained from issuing termination
notice on the ground of Clause 2(6) of the lease deed. Upon the appellant
failing to complete the building even by December 31, 2017, the impugned
notice was issued. The respondents had no option but to treat the lease as
subsisting at least till December 31, 2017, because of restraint orders of this
Court. Soon thereafter, in April 2018, upon the appellant's failure to take
advantage of this Court's order and complete the building by the end of
2017, the respondents issued the termination notice. I do not find any act
on the part of the respondents to voluntarily treat the lease as subsisting
even after forfeiture occurred.
7. A waiver is an intentional relinquishment of a known right. Blacks
Law dictionary, 11th Ed, defines waiver as the voluntary relinquishment or
abandonment - express or implied - of a legal right or advantage with
knowledge of such right. 'Implied waiver' is a waiver evidenced by a party's
decisive, unequivocal conduct reasonably inferring the intent to waive. An
implied waiver may arise where a person has pursued such a course of
conduct so as to evidence an intention to waive a right, or where his conduct
is inconsistent with any other intention than to waive it. Merely lying by and
witnessing the breach is no waiver. Some positive act must be done.
8. In the present case we do not find any express or implied waiver of
forfeiture on the part of the respondents. Initially the respondents had
exercised their right of forfeiture and had determined the lease that had
been granted in favour of the appellant. Such action of the respondents was
set aside. Due to interdiction of the Court the respondent's right to forfeit
stood suspended till the end of 2017, subject to the condition that the
appellant would complete construction of the building in question by that
time. Upon the appellant's failure to complete the building by the end of
2017, the right of the respondents to forfeit the lease relying on Clause 2(6)
of the lease deed, stood resurrected. The respondents exercised such right
and determined the lease by the notice impugned in the present litigation.
The respondents cannot be said to have waived the forfeiture whether within
the meaning of Section 112 of TPA or otherwise. The first contention of the
appellants therefore fails.
9. The two decisions relied upon by the appellant do not help the
appellant. In M/s. Bungo Steel Furniture (Private) Ltd. (supra), a notice of
forfeiture under Section 111(g) of the TPA was served by the lessor on the
lessee on 18-9-1971 which was received by the lessee on 23-9-1971. The
lessor issued another notice of forfeiture on November 8, 1971 which was
received by the lessee on November 10, 1971. In paragraph 13 of the plaint
of the suit filed by the lessor for evicting the lessee, the lessor/plaintiff
asserted that the lessee/defendant had become a trespasser, liable for
mesne profits and damages on and from 10-11-1971. In the plaint the
plaintiff categorically stated that "the defendant has not complied with the
said notice dated 8-11-1971 and is still continuing in unlawful occupation of
the lease hold premises as described in the Schedule below as a trespasser
making himself liable for mesne profits and damages @ Rs. 50 p.d. from 10-
11-1971 till eviction". In such factual background, a Division Bench of this
Court held that when the second notice of forfeiture was issued on 08-11-
1971 and when the plaint was filed in May, 1972, the lessor/plaintiff was
fully aware that forfeiture had been incurred by the lessee and that the first
notice dated 18-9-1971 was also issued for that purpose. If still, thereafter,
the lessor clearly manifested his intention to treat the lease as subsisting up
to 10-11-1971, the lessor must be taken to have waived the forfeiture for
which the first notice was issued on 18-9-1971 and for which the suit for
ejectment was eventually filed.
The facts of the present case are completely different. In the
above case, after occurrence of forfeiture, the lessor voluntarily
treated the lease as subsisting and thereby waived the forfeiture. In
the present case at hand, the lessor/respondent has not done
anything to evince such intention.
10. The decision in Shiva Prasad Singh, (Supra), was also rendered in
completely different set of facts. In that case, the plaintiff, with full
knowledge of the breach of a covenant in the lease deed, gave the defendant
notice to quit and thus recognised the existence of the tenancy. Further,
with full knowledge of the breach, the plaintiff had accepted rent. Still
further, in the plaint, the plaintiff had stated that if he was not given
possession of the property, he was willing to allow the defendant to remain
on the land in question at a certain rental per annum. In such factual
background it was held that if there had been a breach of covenant, the
plaintiff after knowledge of the same recognized the existence of the tenancy
and thereby waived any right which he might have had to forfeit the tenancy.
In our opinion, this decision does not advance the appellant's case to any
extent.
11. The other point urged on behalf of the appellant, in our view, has
substance. It is true that the lease was executed in favour of the appellant in
1985 and the appellant was put in possession of the land in question in the
same year. No doubt, the lease deed contained a covenant requiring the
appellant to complete the proposed construction on the leased out land
within 3 years from the date of possession of the demised land or such
extended time as may be allowed by the Government in writing. It is also not
in dispute that construction has not been completed by the appellant.
However, although the appellant was in breach of the aforesaid covenant
requiring it to complete construction within 3 years, i.e. by 1988, the
Government took no action for 18 long years. It was only in 2006 that the
Government issued a notice calling upon the appellant to show cause as to
why the concerned lease should not be determined by reason of breach of
the construction close in the lease deed. The appellant responded to such
notice by its letters dated December 4, 2006 and December 14, 2007. Again
there was a long silence on the part of the Government. By a notice dated
February 19, 2010 the Government recorded that the lease has been
determined. Such notice was set aside by a learned Single Judge of this
Court by order dated December 19, 2013 subject to the appellant completing
the building by March 31, 2015. Subsequently, the time for completing of
the building was extended till the end of December, 2017, by order dated
December 19, 2014. The aforesaid 2 orders attained finality, not having been
challenged before any higher forum. Consequently, the delay on the part of
the appellant in completing the building and resultant breach of the
construction clause in the lease deed stood condoned by orders of Court till
December 31, 2017.
12. In view of the appellant's failure or inability to complete construction
of the building even by the extended date i.e. December 31, 2017, the
Government issued the impugned notice dated 6/18 April, 2018, for
resumption of the land in question. However, in the meantime, in July,
2015, the appellant made an application to the competent authority for
granting permission for change of user of the land in question, from "Motor
Training School" to "Commercial Building". The application was followed up
by 2 letters dated December 15, 2015 and February 13, 2017. However,
without taking any decision on the appellant's application for permission to
change the user of the land in question, the impugned notice of resumption
was issued.
13. I am of the considered opinion that the Government should have
disposed of the appellant's application for permission to use the concerned
land for a purpose, other than what was originally contemplated, prior to
terminating the lease. Had the Government taken a prompt decision on the
appellant's said application and had the decision been a favourable one, may
be the appellant could have completed the requisite construction by the end
of December, 2017. We are inclined to give the appellant the benefit of doubt
on this ground.
14. Learned Senior Counsel for the appellant has drawn our attention to
several Notifications issued by the Urban Development of the Government of
West Bengal starting with the Notification dated May 6, 2005, which we have
referred to above. The said Notifications reflect a conscious policy decision
on the part of the State Government to allow change of user to the lessees
upon payment of prescribed fees if the proposed new user is found to be
suitable. Mr. Mukherjee, relying on several orders of learned Single Judges
of this Court, argued that the Competent Authority should be directed to
allow the appellant's application for change of user against payment of
requisite fees. I do not think that such a mandate should be issued since as
per the Notifications, the permission for change of user shall be granted if
the same was found to be suitable by the Competent Authority. However, I
am of the view that the State Government should take a decision on the
appellant's application for permission to put the land to a different use
before forfeiting the lease in question.
15. I accordingly direct that the notice impugned in the present
proceedings will be in abeyance till the time the Government takes a
decision on the appellant's application for change of user of the land in
question. The concerned authority in the State Government shall grant an
opportunity of hearing to the appellant's representatives and dispose of the
appellant's application for change of user in accordance with law within 3
months from the date of communication of this order. If the concerned
authority allows the appellant's application, the Government through its
Competent Officer shall grant reasonable extension of time to the appellant
to complete the requisite construction on the land in question. If the
appellant's application for change of user is rejected by the concerned
authority for reasons to be recorded in writing, the notice impugned in the
present proceedings shall stand resurrected and become operative after 7
days from the date of communication of the rejection order by the concerned
authority to the appellant.
16. The order under appeal is set aside. The appeal and the connected
applications are accordingly disposed of.
17. There will be no order as to costs.
18. Urgent certified website copies of this judgment, if applied for, be
supplied to the parties subject to compliance with all the requisite
formalities.
(KAUSIK CHANDA, J.) (ARIJIT BANERJEE, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!