Citation : 2022 Latest Caselaw 3785 Cal
Judgement Date : 30 June, 2022
10 30.6.2022
Sc Ct. no.8
FA 108 OF 2008
--------------
National Projects Construction Corporation Limited Vs.
M/S. United Construction Company
Ms. Rakhi Shroff ... For the Appellant
The appeal is directed against a judgment and
decree dated 15th December, 2006 in a money suit filed
by one M/S. United Construction Company against the
present appellant.
We have heard learned counsel appearing for the
appellant. We feel that the suit could have been decreed
only on the basis of Ext.7. The said letter was issued by a
responsible officer of the defendant/appellant to the
plaintiff/respondent in reply to a demand made by the
plaintiff in its letter dated 7th February, 2002. For better
appreciation, we reproduce the said letter in full.
"To M/s. United Construction Co. Babupara, PO: Falakata, Dist. Jalpaiguri.
Sub : - Your outstanding due payment as on 31.03.2001 Ref : - Your letter No.Nil dt.7.02.2002.
Dear Sir,
With reference to your aforesaid letter this is to inform you that an outstanding amount due to your favour is as detailed below :
Sl Name of work Bill Amount T.D.S. Payment of bill Balance payment No Rs. (Rs) .
1. Supply of Bed 9,383.00 Nil Nil 9383/-
2. Supply of Aggre-
Gate (Pakur variety) 20mm & down size 1,82,750.00 Nil Nil 1,82,750/-
3. Supply of bouldor and placing of the same in crates 4,24,395.00 2395.00 2,39,580.00 1,82,815/-
4. Pouring of M-15 grade concreting 2,95,496.00 1564.00 1,56,420.00 1,37,512/-
5. Supply of boulder stone metal and sand 1,20,800.00 Nil Nil 1,20,800/- Total Rs. 10,32,824.00 3959.00 3,96,000.00 6,33,260/-
Thanking you,
Yours faithfully,
(M.N. Tiu) Unit Officer"
The said letter has taken into consideration all
relevant facts that are required to be considered for the
purpose of determining the amount due and payable to
the plaintiff/decree holder for the works done. The
evidence was to show that the plaintiff/respondent has
performed their obligation but were not paid certain
amount.
There is a dispute with regard to the claim of
amount payable for the works done. According to the
Ext.7, the letter dated 8th April, 2002 conclusively shows
that the appellant/defendant has taken into
consideration all the relevant factors to determine the
sum of Rs.6,33,260/- as the amount due and payable to
the plaintiff/respondent for the works done. The refusal
to make such payment was financial crunch.
Learned counsel for the appellant has admitted that
the said letter was issued under coercion or by unfair
means.
However, we could not find from the pleadings that
any such defence was raised in the pleading or before the
trial court.
The author of the said Ext.7 is a B.S.C. Engineer
(Civil) and was working in the office of the
appellant/defendant for the last 26 years and was looking
after civil works. During cross-examination he has
admitted that the respondent/plaintiff was entrusted with
the job of - i) M-15 Grade Concrete Pitching work in
aperon and in slops, ii). Supply and placing of boulders in
crates, iii). Supply of pakur varieties and iv) supply of bed
materials for roads.
He has not stated that the signature was obtained
on the said letter by coercion or by unfair means. On the
basis of such testimony read with other evidence on
record we are of the view that the learned trial court was
justified in decreeing the suit for a sum of Rs.6,33,260/-
along with interest.
The appellant at the time of admission of appeal
admitted that a sum of Rs.3,57,190/- is due and payable
to the plaintiff/respondent and in fact, has paid the same
amount to the decree holder in the execution proceeding.
The balance amount of Rs.3,89,258/- with accrued
interest thereon shall be paid to the plaintiff/respondent
company by the learned Registrar General of this Court
by a bank draft.
Since the respondent is not represented, we direct
the office of the learned Registrar (Administration, L &
OM) to communicate this order to the decree holder at the
address mentioned in the causetitle within a week from
date and the decree holder is directed to realize the said
amount from the office of the learned Registrar General.
If an approach is made with a certified copy of this
order, the Registrar General shall expedite such release.
The appeal accordingly fails. The suit is decreed in
full.
Photostat certified copy of this order, if applied for,
be furnished expeditiously.
(Soumen Sen, J.)
(Siddhartha Roy Chowdhury, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!