Citation : 2022 Latest Caselaw 221 Cal/2
Judgement Date : 28 January, 2022
IN THE HIGH COURT AT CALCUTTA
ORIGINAL CIVIL JURISDICTION
(Original Side)
A.P. No. 374 of 2020
(Through Video Conference)
Reserved on: 24.12.2021
Pronounced on: 28.01.2022
M/S. HINDUSTHAN BUILDERS
...Applicant
-Vs-
IRCON INTERNATIONAL LIMITED
...Respondent
Present:-
Mr. Sauvik Nandy, Mr. S. Saha, Advocates ... for the applicant
Mr. Raghunath Ghose, Ms. Sevanti Roy, Advocates ... for the respondent
Coram: THE HON'BLE JUSTICE PRAKASH SHRIVASTAVA, CHIEF JUSTICE
Prakash Shrivastava, CJ:
1. This application under Section 11(6) of the Arbitration and
Conciliation Act has been filed by the applicant for appointment of
arbitrator to resolve the dispute between the parties.
2. The case of the applicant is that in response to the e-tender,
applicant had given the offer and letter of acceptance dated
29.01.2016 was issued to the applicant by the respondent for
construction of 750m approx. concrete road as per technical and
MORTH Specifications. The formal agreement was executed on
14.03.2016. The work was to be completed within 9 months, but there
was some delay in completion. The extension of time was granted by
the respondent by their letter dated 05.06.2017. Ultimately, the work
was completed on 15.12.2017. The allegation of the applicant is that
the work was delayed due to the default on the part of the respondent.
According to the applicant the payment was also delayed and was
made only after 05.03.2019 that too on submission of No Claim
Certificate which was submitted under economic duress. Applicant
had issued the letter dated 02.09.2019 for appointment of arbitrator.
Applicant thereafter had sent the notice for conciliation dated
19.06.2020 which was replied by the respondent stating that the full
payment was made in March, 2019 and No Claim Certificate was
submitted by the applicant in January, 2019, hence, the contract was
discharged, therefore, the prayer for conciliation could not be
accepted. The applicant thereafter had sent the communication dated
01.10.2020 for appointment of arbitrator which was replied by the
respondent on 27.10.2020 taking the stand that after acceptance of the
final bill of payment on 05.03.2019 and on submission of No Claim
Certificate the contract stood discharged, therefore, the applicant
could not invoke the mutual settlement, conciliation or arbitration
clause.
3. The submission of the learned Counsel for the applicant is
that the No Claim Certificate was issued by the applicant under
economic duress as the payment was delayed by the respondent,
therefore, on the basis of such No Claim Certificate, the remedy of
arbitration cannot be denied.
4. Submission of the learned Counsel for the respondent is that
the applicant had submitted No Claim Certificate voluntarily and there
is no material on record to show that it was submitted in duress, hence
he cannot invoke the arbitration clause after receiving full payment.
5. Having heard the learned Counsel for the parties and on the
perusal of the record, it is noticed that the arbitration agreement is
undisputed which provides for the following conciliation/arbitration
clause:
"45.2 Conciliation/Arbitration
45.2.1 It is a term of this contract that
Conciliation/Arbitration of disputes shall not be commenced unless an attempt has first been made by the parties to settle such disputes within 120 days of submission of monthly statement of such claim, through mutual settlement.
45.2.2 In the event of failure to resolve and dispute or differences between the parties hereto as to the construction or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, dispute or difference on any account or as to the withholding by the Employer of any certificate to which the Contractor may claim to be entitled to, through mutual settlement, the Contractor may refer such matters to the Chairman & Managing Director in writing within 60 days from the date of failure of amicable settlement of such disputes or differences for settlement through Conciliation. 45.2.3 If the effort to resolve all or any of the disputes through Conciliation fails, the Contractor may refer to the Chairman & Managing Director of the Employer for settlement of such disputes or differences through arbitration. No disputes or
differences shall be referred to arbitration after expiry of 60 days from the date of notification of the failure of Conciliation."
6. The record further reflects that in January, 2019 the
applicant had undisputedly submitted the No Claim Certificate stating
as under:
"1. I/We, engaged in carrying on business under the name and style "M/s HINDUSTHAN BUILDERS" certify and confirm in full belief & knowledge that we have worked for M/s Ircon International Limited under the contractual obligations under contract agreement/Letter Acceptance bearing No. IRCON/2053/SHM/CON.ROAD/HB/AGMT/2, Dated 14.03.2016 and Agreement dated. NIL. After completion of the above stated works, we have reconciled all account statement jointly with M/s. Ircon International Limited, and we have scrutinized all our payments with respect to actual quantity of works executed and payments thereof in accordance with contract provisions including all claims, contentions, disputes, issue whatsoever in respect of this contract jointly with Ircon International Limited and we declare that the measurement and the payments thereof are in complete satisfaction and shall be extinguished in full on payment as stated in the following paragraph.
2. I/we confirm that I/We entitled to 53,45,578.37 (Rupees fifty three lacs forty five thousand five hundred seventy eight and thirty seven paisa only), in full and final settlement of all my Bills, claims, issues, disputes if any and contentions from M/s. Ircon International Limited. I also confirm and declare that with the receipt of aforesaid amount/costs, my/our all claims, disputes, differences if any, between my above said Contract and M/s Ircon International Limited, under and with reference to above said Agreement / Letter of Acceptance No. IRCON/ 2053/ SHM/
CON.ROAD/HB/AGMT/2, Dated 14.03.2016 shall stand full and finally settled and extinguished."
7. It is also not in dispute that thereafter final payment was
made to the applicant on 05.03.2019 which was duly accepted by him.
There is no material placed on record by the applicant to show that the
final bill was accepted under protest. Even after submitting the No
Claim Certificate and accepting the final bill payment on 05.03.2019,
the applicant remained silent for about 6 months when on 02.09.2019
it had issued the notice raising the plea that No Due Certificate was
obtained under duress and making a prayer for arbitration. No prima
facie material is placed on record indicating that the No Claim
Certificate was obtained from the applicant on dotted line or under
any coercion. Clause 44.2 of the contract in clear terms provides that:
"44.2 Signing of "No Claim" Certificate:
The Contractor shall not be entitled to make any claim whatsoever against IRCON under or by virtue of or arising out of this contract, nor shall IRCON entertain or consider any such claim, if made by the Contractor, after he shall have signed a "No Claim" Certificate in favour of IRCON in such form as shall be required by IRCON after the works are finally measured up. The Contractor shall be debarred from disputing the correctness of the items covered by "No Claims" certificate or demanding a clearance for arbitration in respect thereof."
8. Considering the similar issue in the matter of United India
Insurance Co. Ltd. vs. Antique Art Exports Pvt. Ltd. reported in
(2019) 5 SCC 362 in a case where 11 weeks after issuance of the
discharge voucher, for the first time a plea was raised that the
discharge voucher was signed under undue influence and coercion and
no prima facie evidence was filed in support thereof, it has been held
that claim was settled with accord and satisfaction leaving no arbitral
dispute subsisting under agreement to be referred to arbitrator for
adjudication. In that case the decision of the High Court to appoint the
arbitrator in spite of the signing of the discharge voucher has been set
aside by holding that:
"21. In the instant case, prima facie no dispute subsisted after the discharge voucher being signed by the Respondent without any demur or protest and claim being finally settled with accord and satisfaction and after 11 weeks of the settlement of claim a letter was sent on 27th July, 2016 for the first time raising a voice in the form of protest that the discharge voucher was signed under undue influence and coercion with no supportive prima facie evidence being placed on record in absence thereof, it must follow that the claim had been settled with accord and satisfaction leaving no arbitral dispute subsisting under the agreement to be referred to the Arbitrator for adjudication."
9. It is also settled that each case in which such a plea is raised
is required to be decided on its own facts and that mere allegation that
the discharge voucher or No Claim Certificate was obtained by fraud
coercion or undue influence is not sufficient to accept the plea for
appointment of arbitrator, but the party seeking appointment of
arbitrator is required to produce prima facie evidence to substantiate
plea of fraud coercion or undue influence. In the present case no such
prima facie evidence has been produced.
10. Learned Counsel for the applicant has placed reliance upon
the judgment of the Hon'ble Supreme Court in the matter of R.L.
Kalathia & Co. vs. State of Gujarat reported in (2011) 2 SCC 400
but that is a judgment by Hon'ble Single Judge of the Supreme Court
whereas the judgment in the case of Antique Art Exports Pvt. Ltd.
(supra) is a judgment by two Hon'ble Judges of the Hon'ble Supreme
Court. Moreover, the view taken in the case of Antique Art Exports
Pvt. Ltd. (supra) is also supported by the earlier judgment in the
matter of Union of India and Ors. vs. Master Construction Co.,
(2011) 12 SCC 349.
11. In view of the above legal and factual position, I am of the
opinion that after submission of No Claim Certificate and receipt of
full and final payment without any protest and keeping silent for about
6 months, in the facts of the present case, the applicant is not entitled
to dispute the No Claim Certificate at this stage and invoke the
arbitration clause. Hence, the A.P. is accordingly dismissed.
(PRAKASH SHRIVASTAVA) CHIEF JUSTICE
Kolkata 28.01.2022 ___________ PA(SS)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!