Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Debaprasad Das vs West Bengal State Electricity ...
2022 Latest Caselaw 143 Cal

Citation : 2022 Latest Caselaw 143 Cal
Judgement Date : 20 January, 2022

Calcutta High Court (Appellete Side)
Debaprasad Das vs West Bengal State Electricity ... on 20 January, 2022
               IN THE HIGH COURT AT CALCUTTA
                 CIVIL APPELLATE JURISDICTION
                          (Appellate Side)


                                           Reserved on: 13.01.2022
                                           Pronounced on: 20.01.2022

                                             FMA 102 of 2017
                                                  With
                                              CAN 1 of 2017
                                       (Old No. CAN 6634 of 2017)

                                        (Through Video Conference)


Debaprasad Das
                                                               ...Appellants
                                    -Vs-
West Bengal State Electricity Distribution Company Limited and Others
                                                         ...Respondents

Present:-

Mr. Ram Mohan Pal, Advocate ... for the appellant

Mr. Sujit Sankar Koley, Advocate ... for the WBSEDCL

Coram: THE HON'BLE JUSTICE PRAKASH SHRIVASTAVA, CHIEF JUSTICE THE HON'BLE JUSTICE AJOY KUMAR MUKHERJEE, JUDGE

Ajoy Kumar Mukherjee, J:

1. Being aggrieved by and dissatisfied with the order dated 7th June,

2016 passed by a Single Bench in W.P. 21706 (W) of 2015 (Debaprasad

Das vs West Bengal State Electricity Distribution Company Limited and

others), present appellant Debaprasad Das preferred this mandamus appeal

on the grounds inter alia that the learned Single Bench ought to have

considered that the respondent Electricity Board admitted that high-

tension electric post has been installed at the petitioner's plot No. 929 and

he ought to have considered that in the reply notice dated 05.06.2015, the 2 FMA 102 of 2017

electricity authority agreed to remove the high-tension electric line from

the said plot No. 929, if the writ petitioner agreed to pay shifting charges .

Learned Single Bench also failed to consider that the initial report filed by

respondents No. 9 reveals that two naked electric poles are erected at plot

No. 929 just at the verge of Panchayat Road. Learned Single Bench ought

to have make direction to the electric authority for removal of electric

posts and electric line from the property of the petitioner and instead of

that he is erred in holding that the electricity authority did not install

naked electric poles at the aforesaid property of the writ petitioner.

2. Petitioners case in a nutshell is that by a registered deed dated

18.09.1984, petitioners became absolute owner and occupier of plot No.

929 and his name has also been duly recorded in LR Record of Rights. On

04.07.2014 petitioner filed written objection to the respondent/electricity

authority for removing the electric posts from the private property of the

writ petitioner at plot No. 929 installed by the respondents /electricity

authority, forcibly and illegally and also for illegally passing electric wire

through the property of the petitioner causing damage and obstruction to

build dwelling house in the petitioners own property at plot No. 929. On

12.09.2014 petitioners filed another written objection to the

respondents/electric supply authority, for not installing new electric posts

at the plot No. 929, owned by writ petitioner. On 13.02.2015 the petitioner

again issued and served notice to the respondents/ electricity authority not

to install further new transformer at the property of the writ petitioner at

plot No. 929. The respondent electricity authority have no right to install

electric posts or electric transformer at private absolute property of the writ

petitioner, but inspite of the objection raised by petitioner, they are

illegally and forcibly passing high voltage electricity line through installed 3 FMA 102 of 2017

electric posts and transformer at the private property of the petitioner.

Actually they have trespassed into the private property of the writ

petitioners at suit plot No. 929 and installed high voltage electric line

and thereafter again installed 3 (three) naked cemented electric posts,

trespassing into the petitioner's property with a motive to install new

electric transformer. In the above background writ petitioner moved

present writ petition under Article 226 of the Constitution of the India

with a prayer for issuing rule, commanding the electricity authority to

remove the electric posts and electric line from the private property of the

writ petitioner at plot No. 929 and also to issue rule of prohibition

restraining respondents electricity authority not to install further electric

posts and/or electric transformer and / or electric line at the private

property of the writ petitioner .

3. Learned Single Bench called for a report from concerned BLLRO,

whether any pole has been erected on the plot of land of the petitioner

and BLLRO filed affidavit which provides complete and specific answer

to the dispute on 05.04.2016 stating, two naked poles have been erected

in plot No. 289 which are piece of land belonging to the State. Learned

Single Bench after being satisfied that said naked poles have not been

erected on land of petitioner, as reported by BLLRO and also finding

no substance in petitioners contention that he is willing to make residential

house on plot No. 929 after complying formalities regarding conversion,

was pleased to dismiss the writ petition.

4. We have carefully considered the documents available on record.

From the report dated 17.11.2015 filed by S.E. & Project Manager

WBSEDCL, it appears that one spot verification was carried out on

03.11.2015 by the representative of their office in presence of the 4 FMA 102 of 2017

petitioner. Said inspection reveals that only two naked poles were erected

under BRGF scheme beside village morum road but no transformer was

installed due to objection raised by the petitioner. It further reveals from

the said report that another existing 11 k.v. electric line is passing through

the petitioner's plot no. 929 and two H.T. poles attached to this existing

line were erected on the petitioners plot No. 929 at least 20 years back.

Said statement by WBSEDCL also finds support in the report of BLLRO

dated 05.04.2016, which says that high tension electric line are present

since past above the LR plot No.929 from South West to North East

direction and a pole exists therein which was erected earlier in the land of

the petitioner.

5. Accordingly position in the present case is that a separate high

tension line of 11 k.v. and two H.T. poles exists over petitioner's plot No.

929 for at least 20 years as a feeder line, so that the villagers can avail

electricity. It is true that in the present case a serious dispute has been

raised as to whether two new naked poles having no transformer, installed

recently on writ petitioner's plot No. 929 or on government plot No. 289.

In this context it is also to be mentioned that admittedly writ petitioner

raised objection only on 04.07.2014 for removal of existing electric posts

with high tension line from the private property of the writ petitioners at

plot No. 929 installed by the respondents and regarding erection of new

electric poles, he had raised further objection on 12.09.2014 when two

new naked electric poles were erected therein for installation of new

transformer. There is also nothing in the record to show that petitioner

raised any objection about existence of said 11 k.v. high tension line over

his said land of 929 which was erected and installed about 20 years back.

Though petitioner stated that the electricity authority forcible and illegally 5 FMA 102 of 2017

erected those poles and /or passed high voltage electric line over the

property of the writ petitioners, but we do not find any document in

support of the same. Presently when two naked poles are erected in that

of place for installation of a new transformer, only then petitioner has

come up before the writ court, for not only shifting those two naked

poles from his land but also the previously installed aforesaid 11k.v.

high tension line which was installed over his land at least 20 years

back.

6. Learned counsel for the respondents in this context have drawn

our attention to section 164 of The Electricity Act, 2003, which provides

that the licensee can exercise power of telegraph authority in certain cases.

Section 68 of said Act deals with the provisions for installation of over

head 11 k.v. lines and section 168 of the Act gives protection for action

taken by the said authority in good faith.

7. Having regard to the said fact and in the absence of any objection

or litigation , we have sufficient reason to believe that at least 20 years

back when aforesaid 11 k.v. high tension line and two H.T. poles

attached to that existing line were erected on petitioner's plot No. 929, it

was erected and installed in accordance with law, in order to distribute

electricity to the villagers. Present two naked poles are erected recently

under BRGF scheme for installation of new transformer and being

aggrieved by such act of the respondents/electric authority, petitioner has

filed the writ petition with a prayer for shifting not only said two naked

poles which are installed recently but also prayed for shifting of over head

11 k.v. line which exists in the plot No. 929 for at least 20 years.

8. While this controversy going on between the parties the

divisional Engineer , (Tech-1) WBSEDCL vide his letter dated 23.03.2021 6 FMA 102 of 2017

appraised writ petitioner that upon inspection, they have observed that

shifting of 11 k.v. line from the plot of petitioner as claimed by him may

be possible by erection of two new 4 pole structure along with the other

allied works, on condition that the writ petitioner will have to bear whole

costs of the scheme for the said shifting work and if any problem arises

petitioner will have to sort it out.

9. Having regard to the above facts and circumstances of the case,

we dispose of this appeal with a direction upon respondents /electricity

authority to submit an estimated cost of shifting works in terms of their

letter dated 23.03.2021 to the petitioner within four weeks of the order

and petitioner will be at liberty to deposit that estimated costs of shifting

work to the respondents /electricity authority. On being such deposit made

by the petitioner Debaprasad Das, the respondent/electricity authority shall

carry out the shifting of newly erected naked poles as well as shifting of

11 k.v. high voltage line from the petitioners plot No. 929 in terms of

their letter dated 23.03.2021 within a period of 4 weeks.

10. FMA 102 of 2017 is accordingly disposed of.

11. There will be no order as to costs.

12. Urgent photostat certified copy of this judgment, if applied for, be

supplied to the parties upon compliance with all requisite formalities.

(PRAKASH SHRIVASTAVA) CHIEF JUSTICE

(AJOY KUMAR MUKHERJEE) JUDGE Kolkata 20.01.2022

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter