Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Dbar Code Restro Bar & Club Llp And ... vs Cesc Limited And Others
2022 Latest Caselaw 548 Cal

Citation : 2022 Latest Caselaw 548 Cal
Judgement Date : 15 February, 2022

Calcutta High Court (Appellete Side)
Dbar Code Restro Bar & Club Llp And ... vs Cesc Limited And Others on 15 February, 2022
                      In the High Court at Calcutta
                     Constitutional Writ Jurisdiction
                              Appellate Side

The Hon'ble Justice Sabyasachi Bhattacharyya



                       W.P. No. 23338 (W) of 2019
                                  With
                             CAN 1 of 2021

             DBar Code Restro Bar & Club LLP and another
                                 Vs.
                      CESC Limited and others



     For the petitioners     :     Mr. Sarvesh Chandra Shrivastava,

     For the CESC Limited    :     Mr. Debanjan Mukherjee,

     For the
     private respondents     :     Mr. Krishnakant Thaker,

Mr. Chayan Gupta, Mr. Rajesh Upadhyay

For the State : Mr. Sudipto Panda, Ms. Munmun Tiwary, Mr. Debasish Mondal

Hearing concluded on : 04.02.2022

Judgment on : 15.02.2022

Sabyasachi Bhattacharyya, J:-

1. The petitioners, being the lessees in respect of the disputed premises

under the private respondent nos. 6 and 7, have filed the present writ

petition on the allegation that the lessors/respondent nos. 6 and 7

are disrupting electric supply to the tenanted premises regularly. The

petitioners are running a bar and restaurant as well as a club from

the said premises and are, thus, suffering serious loss of business

and goodwill due to such alleged disruptions.

2. It is contended by the petitioner that the petitioner entered into a

lease agreement dated July 19, 2016, wherein the lease rent was fixed

at Rs.16,00,000/- per month, for user of a commercial space.

3. However, due to alleged disruption of power supply by the lessors, the

petitioners were constrained to apply for fresh electric connection in

their own name. However, when the CESC personnel came for

inspection for the purpose of giving such new connection in the name

of the petitioners, they were raised by the private respondents and

their men and agents, thereby preventing the CESC personnel from

giving such electric connection to the petitioner and/or holding

inspection in that regard.

4. Learned counsel appearing for the private respondents submits that

the writ petitioners have suppressed relevant facts. As such, the writ

petition ought to be dismissed since the petitioners have approached

the writ court with unclean hands.

5. It is submitted that the lessors and the petitioners entered into not

one but as many as three agreements, all dated July 19, 2016. As

per the lease deed disclosed in the writ petition, the commercial space

was to be enjoyed at a lease rent of Rs.60,000/-. It is further pointed

out that the said deed entitled the petitioners to enjoy power load

capacity of 2 kVA only from one electric meter.

6. The second deed entered into between the private parties on the same

date as the first provided that, for scheduled maintenance, amenities,

utilities and other purposes in respect of the said commercial space,

the petitioners would be entitled to 60 kVA power load capacity, also

to be provided by the lessors. The total rent payable as per the said

agreement was Rs.1,90,000/- per month.

7. The third agreement between he lessors and the lessees provided

that, for signboard display, the petitioner would pay a monthly

amount of Rs.1,20,000/-.

8. Hence, it is argued by the respondent nos.6 and 7 that the entire

lease agreement between the lessors and the lessees comprised of not

only the agreement disclosed in the writ petition but all the three

agreements, referred to above, dated July 19, 2016. Learned counsel

for the private respondents places reliance on photocopies of the said

documents, annexed to their pleadings by way of the application for

dismissal of the writ petition as well as exception to the report filed by

the CESC Limited in the present writ petition.

9. It is further argued by learned counsel for the respondent nos.6 and 7

that, in terms of the first two agreements, the petitioners are already

enjoying 62 kVA power load capacity, upon payment of the composite

monthly amount of Rs.2,50,000/- (60,000/-+1,90,000/-).That apart,

for display of the signboard of petitioner no.1, the petitioners are to

pay Rs.1,20,000/- per month.

10. Thus, it is submitted that the petitioners are already entitled to

62 kVA power load capacity as per the three subsisting agreements

between the private parties, but are using a lesser load at present.

11. Moreover, it is contended that the petitioners have even applied for a

power load capacity less than that actually used at present by the

petitioners and much less than 62 kVA which they are entitled to use

as per the first two agreements.

12. It is further submitted that the entire rent of the premises is

comprised of the composite monthly amount of Rs.3,70,000/-

(60,000/- + 1,90,000/- + 1,20,000/-).

13. It is argued that the lessee is seeking to modify the terms of the three

agreements by obtaining an order from the writ court. It is further

insinuated that the CESC Limited is acting hand-in-glove with the

petitioners in suppressing the bar to the petitioners in taking another

electric connection at the premises-in-question, since a new electric

connection, if given to the petitioners at the same premises, would not

be feasible and would definitely amount to splitting of loads, which

would ultimately reduce the revenue of the CESC Limited itself.

14. Learned counsel for the respondent nos. 6 and 7 argues that such

oblique attempt of the petitioners ought not to be encouraged by

permitting the petitioners to take a new electric connection at the

premises of the private respondents de hors the law and in gross and

unlawful modification of the subsisting three agreements between the

parties.

15. The plinth of the submissions of the petitioners is the right of a

person to get electric supply, as embedded in Section 43 of the

Electricity Act, 2003 (hereinafter referred to as "the 2003 Act").

However, such right is not unfettered and has to be exercised in such

a manner which does not violate the rights of others and/or defies

any law or legal contract entered into by the prospective consumer.

16. The CESC, in its report dated February 8, 2021 filed in the writ

petition, stated that previously the writ petitioner used to enjoy

electric supply for Meter No. 4716700 under Consumer No.

20033120041 (standing in the name of Respondent no. 6 Amitabh

Kejriwal) and Meter No. 5005940 under Consumer No. 85202008064

(standing in the name of Accuphase Property Development Pvt. Ltd.).

However, the former, that is, Meter No. 4716700 got burnt the year

before, that is, in 2020 which was reported to the CESC Ltd. On June

26, 2020. The burnt meter, according to the CESC, lay

disconnectedand the petitioner was enjoying electric supply from the

latter, that is, Meter No. 5005940 as on the date of the report, that is,

February 8, 2021.

17. In the application taking exception to the said report, respondent nos.

6 and 7 allege that the functional meter, that is, Meter No. 5005940 is

providing uninterrupted and sufficient electric supply to the entire

second floor, occupied by the writ petitioner no. 1-bar and that the

meter load of the same is 58.8 kVA. It is also alleged that the said

meter is a Current Transformer (CT) meter, which is installed only

where there is a high demand of electricity load, and is a dedicated,

exclusive electricity cable line from the CESC junction box on the

public road to the meter.

18. In its affidavit-in-opposition to the exception, the CESC takes a stand

that the meter of Amitabh Kejriwal has a sanctioned load of

24.29 kW, but that the said meter was found burnt and disconnected

at the time of inspection. The CESC does not deny the allegation in

the exception that the meter in the name of Accuphase was dedicated

exclusively to the petitioner no. 1. Rather, it is admitted by the CESC

that the sanctioned load for supply to the Accuphase meter is 50kW.

19. However, respondent nos. 6 and 7, in their reply to the CESC

opposition, avers that the burnt meter had already been replaced

before the opposition was affirmed.

20. It is conspicuous from the affidavit-in-opposition of the CESC Limited

itself that the writ petitioner DBar Code Restro Bar & Club has

applied for a separate meter connection against a connected load of

40 kW.

21. Thus, the following relevant details are borne out by the agreements

and the CESC pleadings :

(i) The comprehensive lease agreement between the parties is

comprised of the three agreements, all dated July 19, 2016.

(ii) As per the three agreements, the petitioners are entitled, upon

a monthly payment of Rs.3,70,000/- (including signboard) in

total and at least 2,50,000/-, to have 2kVA power load capacity

plus an additional 60 kVA from a sub-meter, totalling 62 kVA.

(iii) The petitioners, however, applied to CESC for a new connection

having sanctioned supply load of 40 kW only. [It is relevant that

Real Power (in kW = kiloWatts) is expressed as the Apparent Power (in

kVA = kiloVolt-Amps) multiplied by the Power Factor]

(iv) CESC version : Accuphase meter, dedicated to petitioner no.1-

bar, has a meter load of 58.8 kVA and Respondent No. 6's

meter has a sanctioned load of 24.29 kW.

22. Thus, the petitioners are already enjoying electric supply having a

meter load of about 58.8 kVA (as per CESC's admission) from a

dedicated meter at the premises-in-question, whereas they are

entitled, only upon payment of Rs.3,70,000/- per month, to have 62

kVA. Over and above such existing supply, the since-repaired electric

meter of the respondent no. 6 has a sanctioned load of 24.29 kW.

23. Hence, Section 43 of the 2003 Act is not violated at all in the present

case, since, as per the three agreements themselves, the petitioners

are entitled, upon payment of a monthly contractual amount of Rs.

3,70,000/-, to more power than they are currently using. Such power

is being supplied by none other than the private respondent nos. 6

and 7 from at least two electric meters, one which stands in the name

of the respondent no. 6 and the other in the name of Accuphase, a

company owned and controlled by the private respondents.

24. Moreover, the other meter standing in the name of the respondent no.

6, from which the petitioner no. 1-bar also enjoys electricity, has an

additional sanctioned load of 24.29 kW.

25. Hence, there is no scope of the petitioners suffering from any dearth

of electricity at the premises-in-question. One meter is exclusively

dedicated to the petitioner no. 1, thus ruling out any disruption to

electric supply therefrom by the respondent nos. 6 and 7. The other

meter is also available, if required.

26. Thus, as borne out by the records, in the name of infraction of

Section 43 of the 2003 Act, the petitioners seek the blessings of a

court order to modify the terms of the existing agreements between

the parties as well as to avoid paying the substantial electric charges

which are ex facie components of the total lease rent, that is, the total

amount payable by the lessees/petitioners for enjoyment of the

property and its amenities in the capacity of lessees.

27. Such an effort ought not to be sanctioned by the writ court,

particularly, in view of the current pendency of a civil suit instituted

by the petitioners themselves claiming similar reliefs, including a

relief protecting the enjoyment of essential services, including

electricity, by the petitioners, to be provided by the respondent nos. 6

and 7.

28. Moreover, the private respondents are justified in arguing that the

petitioners have suppressed vital and relevant facts, particularly, in

respect of the other two agreements subsisting between the parties,

apart from the only agreement disclosed in the writ petition, the

substantial amounts of money payable by the petitioners to the

private respondents in view of the other two agreements and the

power load capacity of 62 kVA being sanctioned by the terms of the

three agreements, in respect of which already a civil suit is pending at

the behest of the petitioners.

29. In such view of the matter, the petitioners are not entitled to the

reliefs as claimed in the writ petition.

30. Accordingly, W.P. No.23338 (W) of 2019 is dismissed on contest,

without, however, any order as to costs. CAN 1 of 2021 also stands

disposed of accordingly.

31. However, this order will not prevent the petitioners from approaching

the civil court in the suit pending between the parties for pursuing

the relief in respect of the petitioners' contractual rights to enjoy

62 kVA power load capacity upon payment of the contractual dues, or

as per direction of the civil court, to the respondent nos. 6 and 7. The

civil court shall independently decide such questions without being

influenced in any manner by any of the observations made herein.

32. Urgent certified copies of this order shall be supplied to the parties

applying for the same, upon due compliance of all requisite

formalities.

( Sabyasachi Bhattacharyya, J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter