Citation : 2022 Latest Caselaw 8618 Cal
Judgement Date : 22 December, 2022
IN THE HIGH COURT AT CALCUTTA
Constitutional Writ Jurisdiction
Appellate Side
Present :-
The Hon'ble Justice Moushumi Bhattacharya.
W.P.A 21100 of 2022
Chandras' Green Project Limited & Ors.
Vs.
Rail Vikas Nigam Limited & Ors.
For the petitioners : Mr. Kishore Datta, Sr. Adv.
Mr. Dwaipayan Basu Mallick, Adv.
Ms. Sreya Basu Mallick, Adv.
Mr. Anik Dey, Adv.
For the KMDA : Mr. Satyajit Talukdar, Adv.
For the KMC : Mr. Biswajit Mukherjee, Adv.
Mr. Dipankar Ghosh, Adv.
For the respondent nos. 1-3 : Mr. Shankar Ranjan Sen, Adv.
Ms. Chandrani Bhattacharyya, Adv
Last Heard on : 19.12.2022
Delivered on : 22.12.2022.
2
Moushumi Bhattacharya, J.
1. The first petitioner was leased 25 acres of land under the Kolkata
Municipal Corporation in October, 1996 in an area on the Eastern
Metropolitan Bypass. The petitioner developed the land by expanding
substantial resources. Part of this property is led out for marriage and other
ceremonial purposes and is known as the "P.C. Chandra Garden". The
petitioners were subsequently made aware that an elevated Metro Railway
track would pass in front of the leasehold premises of the petitioners and
that Rail Vikas Nigam Limited (RVNL) / respondent nos. 1-3 would execute
the project. The Kolkata Municipal Corporation (KMC) granted an NOC to
RVNL for using KMC land for construction of the Metro Railway from New
Garia to Airport. RVNL was required to excavate a portion of the slope of the
leasehold premises of the petitioners adjoining the EM Bypass and
accordingly approached the petitioners for permission to excavate the land
partition for constructing the piers and viaducts for the Metro Railway.
2. The petitioners seek a direction on RVNL to restore the slopes in the
petitioners leasehold property to its original condition at RVNL's costs or
through the respondent no. 4/Gammon India Limited, who was given the
task of executing the project for RVNL.
3. The urgent need for restoration of the slopes of the petitioners'
property is reflected from the photographs annexed to the writ petition.
Photographs taken of the slopes prior to commencement of the construction
work show un-damaged slopes with trees and plants beautifying the area.
Photographs taken after commencement of the construction work portray a
different picture. The slopes have been excavated with the under laying
black soil being exposed to public view. The aesthetics of the green slopes
with plants has been replaced by broken and corrugated slopes.
4. The only question before the Court is whether RVNL through Gammon
can be called upon to restore the slopes to their original condition.
5. By a letter dated 18th February, 2013, RVNL brought the inevitable
consequences of cutting of the slopes to the notice of the petitioners. The
last paragraph of the letter shows that RVNL assured that the cutting of the
P.C. Chandra Green Project area will be protected by subsequent pitching
work by RVNL. The intention of RVNL to do the pitching work is reiterated in
a mail dated 20th January, 2014 where the necessary protection was also
assured in the cutting zone. The stand taken by RVNL in terms of protecting
the land which was cut-away for construction of Metro Railway, also
appears from other correspondences between the parties from October, 2013
to January, 2014. The attachments in the mail of 20th January, 2014
showing cross-section of piers and proposed diversion in front of P.C.
Chandra Garden also contains a note with a written undertaking for
temporary protection of the area by sand bag pitching and permanent
protection by boulder pitching.
6. The material before this Court reflects that RVNL gave several
assurances, through written documents, that it would undertake necessary
protection for the cutting zone of both temporary and permanent nature in
the form of sand bag and boulder pitching.
7. The subsequent work undertaken by RVNL however resulted in
extensive damage to the slopes of the petitioner's land along the service road
off EM Bypass which is evident from the photographs annexed to the writ
petition. Admittedly, the work of laying piers and viaduct was completed in
2020. RVNL did not however undertake any temporary or permanent
pitching work as promised in its letters.
8. The defence taken by RVNL of disputed question of facts and the
petitioners' encroachment on public land cannot be countenanced since
RVNL did not raise these issues to the petitioners at the relevant point of
time. The submission of learned counsel appearing for RVNL that the
petitioners have encroached on the land or have failed to produce any plan
of the land to ascertain the elevation of the slope is not relevant to the issue
at hand. These points can at best be taken by KMC since the land was
leased by KMC to the petitioners. Contrary to the submissions made on
behalf of the RVNL, counsel appearing for KMC and KMDA have submitted
before the Court that they have nothing to do with the dispute between the
petitioners and RVNL. Significantly, KMC has not alleged any encroachment
by the petitioners on KMC land.
9. Further, the letter relied on by RVNL of 16th September, 2013 from
RVNL to the petitioners deals with the allegation of the petitioner dumping
additional earth over the concerned land and the consequent issue of
ingress and egress of the petitioners. The letter does not deal with any
impediment on RVNL for executing the restoration work as promised by
RVNL in letters to the petitioners.
10. The issue is simply a matter of holding RVNL to its promise and
undertaking to make good the loss and damage suffered by the petitioners.
The extent of damage is clearly visible from the photographs annexed to the
writ petition and reflects a striking difference in the visible appearance of the
slopes before and after construction work undertaken by RVNL. RVNL has
admittedly not kept its promise of pitching work for restoring the slopes with
the help of sand bags and boulders. RVNL cannot be permitted to resile from
its position through technical pleas like disputed question of facts.
11. This Court is of the view that the express promise and undertaking
given by RVNL in several letters resolves the issue of facts allegedly being
disputed. In any event, there is no absolute bar on a Writ Court dealing with
contested factual issues if the circumstances call for interference.
12. Being of the view that RVNL cannot be permitted to change its
position after completing the construction work in 2020 and taking
advantage of the fact that the petitioners did not object to such construction
work being for the larger public benefit, WPA 21100 of 2022 is disposed of
with a direction on RVNL and Gammon to restore the slopes in the property
of the petitioners to its original condition at RVNL's cost either by itself or
through Gammon. RVNL is directed to start the restoration work within
eight weeks from today and restore the area to its earlier visibly aesthetic
shape and form.
Urgent Photostat certified copies of this judgment, if applied for be
supplied to the parties upon fulfillment of requisite formalities.
(Moushumi Bhattacharya, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!