Citation : 2022 Latest Caselaw 5936 Cal
Judgement Date : 26 August, 2022
26th August,
2022
(AK)
17
W.P.A 19015 of 2022
Modern Construction
Vs.
The State of West Bengal and others
Mr. Ayan Banerjee
Mr. Pralay Kar
Mr. Soumo Chaudhury
...for the petitioner.
Mr. Sirsanya Bandyopadhyay
Mr. Arka Kumar Nag
...for the respondent nos.2 to 4.
Learned counsel for the petitioner has raised an
issue as to whether there was any termination of the
contract entered into by the respondent authorities with
the petitioner at any point of time.
Learned counsel submits that, by virtue of a
communication dated June 14, 2021 (page-93 of the writ
petition), it was intimated to the petitioner that the
respondent authorities have no other option but to
"recommend for termination of the contract" as per
provision of SBD Clause no.52.
It is submitted that subsequently, however, there
was a request from the end of the respondent authorities
on September 3, 2021 for renewal of the Bank guarantee
earlier granted by the petitioner "for further one year for
the above-mentioned work".
Learned counsel contends that in view of the vague
language of recommendation in the communication dated
June 14, 2021, read in conjunction with the request for
further renewal of the bank guarantee on September 3,
2021, that is, after the expiry of the contract period and
also after the alleged recommendation of termination,
indicates that there was no termination in fact at all.
Hence, the invocation of the Bank Guarantee by the
respondent authorities on June 13, 2022, which has been
challenged in the present writ petition, was bad in law.
It is submitted that if there is patent fraud, the
invocation of bank guarantee can also be restrained by a
court.
Learned counsel appearing for the respondent
authorities, by pointing out to Clause 25 of the contract
between the parties, submits that there was a two-tier
alternative remedy available to the petitioner.
First, the said clause envisages that the concerned
engineer had to be approached with the dispute.
Secondly, the matter was to be referred to arbitration.
As such, the remedy, if at all, of the petitioner lay
before the concerned court having jurisdiction to take up
matters under Section 9 of the Arbitration and
Conciliation Act, 1996.
Learned counsel cites the judgment of a Supreme
Court reported at (2016) 10 SCC 46 (Gujarat Maritime
Board vs. Larsen and Toubro Infrastructure Development
Projects Limited and another), in support of the
proposition that between the appellant and the Bank, the
decision of the appellant therein as to the breach shall be
absolute and binding on the Bank.
It was observed that an injunction against the
invocation of an absolute and unconditional bank
guarantee cannot be granted except in situations of
egregious fraud or irretrievable injury to one of the parties
concerned.
The Supreme Court went on to hold that on being
satisfied that the first respondent had failed to perform
his obligations as covenanted, the appellant therein
cancelled the LoI and resultantly invoked the bank
guarantee.
Whether the cancellation was legal and proper and
whether, on such cancellation, the bank guarantee could
have been invoked on the extreme situation of the first
respondent justifying its inability to perform its
obligations under the LoI, etc. are not within the purview
of an inquiry under Article 226 of the Constitution of
India.
Learned counsel next contends that in any event,
the best allegation of the petitioner in the writ petition
could be that the termination of the agreement was not in
terms of the contract between the parties.
Even if such an allegation is made, the appropriate
forum for the petitioner would be the competent civil
court, with a claim for damages.
Hence, the writ petition ought to be dismissed, it is
argued.
A perusal of the documents annexed to the writ
petition, prima facie, shows that the respondent
authorities sought a renewal of the bank guarantee from
the petitioner on September 3, 2021 (annexure-P10 at
page-95 of the writ petition).
Such request was made subsequent to the expiry of
the original tenure of the agreement and also subsequent
to the termination being purportedly recommended vide a
communication dated June 14, 2021 (at page-93 of the
writ petition), hence, a doubt arises as to whether there
was any termination in the present case at all of the
contract between the parties.
Hence, the ratio as laid down by the Supreme Court
in the cited judgment does not squarely apply, since it is
argued in the writ petition as to whether there was
egregious fraud in the present case on the part of the
respondent authorities insofar as invocation of the bank
guarantee prematurely, before actual termination, is
concerned.
The argument of the respondent authorities to the
effect that the termination was decided upon finally by
the respondent cannot help the respondent authorities
much on the issue involved in the writ petition, simply
because a "termination" of contract implicitly includes a
communication of such termination to the other
contracting party.
Hence, a strong prima facie case has been made out
by the petitioner.
However, since the bank guarantee already stands
invoked, no injunction can be passed at this juncture as
per the prayer of the petitioner in respect of such bank
guarantee, since an order directing refund of the amount
will tantamount to granting the final relief to the
petitioner.
Inasmuch as the question of cancellation is
concerned, the respondent authorities ought to be given
an opportunity to explain and/or bring sufficient
materials before court to indicate whether there was,
actually, any termination of the contract between the
parties at all.
Hence, the respondents are directed to file their
affidavits-in-opposition within three weeks from date.
Reply, if any, shall be filed within one week thereafter.
The matter shall next be enlisted for hearing on
September 28, 2022 before the regular Bench taking up
these matters.
All action taken in the meantime shall abide by the
result of the writ petition.
It is, however, made clear that the question of
maintainability on the ground of availability of alternative
relief by way of damages is kept open to be argued by the
parties at the final hearing of the writ petition.
The prayer of learned counsel for the petitioner to
stay the hands of the respondent authorities in respect of
grant of a further tender to a third party cannot be
granted, since the nature of the work is of public utility
and it is well-settled by several judgments of the Supreme
Court as well as this court that such works ought not to
be readily stayed by courts of law.
However, the above direction of the intervening
action abiding by the result of the writ petition should
take care of the petitioner's apprehensions sufficiently.
(Sabyasachi Bhattacharyya, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!