Citation : 2022 Latest Caselaw 4971 Cal
Judgement Date : 2 August, 2022
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRITJURISDICTION
APPELLATE SIDE
****
PRESENT: THE HON'BLE JUSTICE SABYASACHI BHATTACHARYYA
WPA NO. 18989 OF 2021
SRI DIPANKAR SAHA ... Petitioner
Vs.
CESC Limited and another ... Respondents
For the petitioner : Mr. Abhrotosh Majumdar,
Mr. Srijib Chakraborty,
Mr. Subhom Kumar Das
For the respondent : Mr. Subir Sanyal,
Mr. Debanjan Mukherjee
Heard on : July 08, 2022
Judgment on : August 02, 2022
SABYASACHI BHATTACHARYYA, J.
1. The writ petitioner sought an individual metered electricity connection
for his advocate's chamber at Room No. 105, 4th Floor, 10 Old Post
Office Street, Kolkata-700 001.
2. The CESC Limited declined to give the same and indicated that it was
willing to give such connection if an application is made for a block
meter which would cater to the needs of several persons.
3. It is contended by learned counsel for the petitioner that Section 43 of
the Electricity Act, 2003 (for short, "the 2003 Act") casts a duty on the
distribution licensee to give electricity supply on an application being
made by an owner or occupier of a premises within one month after
receipt of the application for such purpose. The first proviso to Section
43, it is argued, makes it abundantly clear that the distribution
licensee would have to supply the electricity even if it requires
extension of distribution mains or commissioning of new sub-stations.
4. Learned counsel cited the judgment of Brihanmumbai Electric Supply
and Transport Undertaking vs. Maharashtra Electricity Regulatory
Commission (MERC) and othersreported at (2015) 2 SCC 438 in support
of the proposition that, in case an application is made by an owner or
occupier of a premises for supply of electricity, Section 43 requires the
licensee to provide electricity from its own network. For this purpose, if
it is not having its network, it will have to lay down its network, if
required, in order to supply electricity to a consumer.
5. By addressing an inspection report produced by the CESC Ltd., it is
contended that the CESC Ltd. is required either to install additional
service line or refurbish, repair or reinstall the existing service lines for
the purpose of providing electricity to the petitioner.
6. Clause 18 of Regulation No. 53 of 2013, framed by the West Bengal
Electricity Regulatory Commission (WBERC), it is contended, provides
for installation of block meters in bustees, markets, etc. where it may
not be possible to segregate one consumer from an adjacent consumer
because of existence of alarge number of consumers in a relatively
small premises and where because of multiplicity of a wiring, there
may arise fire and safety hazards. Thus, it is submitted, only when the
twin conditions of inability to segregate and multiplicity of wirings are
satisfied, Clause 18 can be pressed into service for insisting upon
block meters. Since it is not the case of CESC that the premises-in-
question contain wires which cannot be segregated between the
consumers, the said provision is not applicableto the present case.
7. It submitted by learned counsel for the petitioner that installation of
block meters and sub-meters will not decrease but increase the
multiplicity of wirings. Regulation 14 of the WBERC Regulation, which
prohibits splitting of load, has to be read with Clause 18. Since
splitting of load is not permissible, conversely, owners or occupiers of a
premises cannot be compelled to apply for a block meter.
8. Even if the petitioner applies for block meter along with others, the
wiring would never decrease, since each of those persons would have
to install sub-meters to quantify individual consumption.
9. By placing reliance on a Coordinate Bench judgment dated February
18, 2021 rendered in WPO 39 of 2021 (Partha Ghosh vs. CESC Ltd. and
others), it is argued that the petitioner cannot be made to wait for
getting electricity connection in his name for his chamber, which will
affect his livelihood, till the CESC Ltd. takes safety measures for
supplying electricity or for installing block meters.
10. Such order was passed in respect of 9, Old Post Office Street, which is
the premises adjacent to the one where the petitioner seeks electricity
connection.
11. It the CESC Ltd has accepted the direction for installation of individual
metered connection in respect of 9, Old Post Office Street, it is not
open to the CESC Ltd. to take a discordant stand in respect of the
petitioner, who is similarly circumstanced at 10, Old Post Office Street.
12. It is well settled, learned counsel contends, that the court generally
adopt a "hands-off" policy when the question of public safety arises for
consideration. However, on a conjoint reading of Section 43 of the
2003 Act and Clause 13 of the WBERC Regulation, the CESC Ltd. is
duty-bound to give individual metered connection to the petitioner.
13. Learned counsel further points out that in case the petitioner is
required to obtain the electricity supply through a block metered
connection, if any of the other joint consumers defaults in making
payment, either the petitioner would have to pay on behalf of such
defaulting joint consumer to enjoy continued supply of electricity or
face disconnection of supply for no fault on his part. The petitioner, it
is argued, cannot be subjected to such fortuitous circumstances in
view of the statutory mandate contained in Section 43 of the 2003 Act.
14. Learned Counsel appearing for the CESC Ltd. argues that the report of
the District Inspector produced by the CESC Ltd clearly indicates that
there is lack of sufficient and technically feasible available space at the
premises-in-question for installing any further meter with the
connected Main Switch.
15. Since the portico, where multiples wirings have already passed, is also
being used as a parking lot for all two-wheelers, the meter installation
space is not easily accessible to the technical persons of the CESC Ltd.
and easily susceptible to fire hazards, which constitutes violation of
Clause 9(2) of the 2006 Regulations.
16. In the event an additional metered connection is given individually to
the petitioner, there is every chance of fire hazards.
17. Learned counsel further submits that at least ten others applications
for separate metered supply are pending in respect of the self-same
premises-in-question. Such situationnecessitatesinstallation of block
meter(s) to enable the CESC Ltd to cater to supply of electricity to the
intending new consumers. In the event the petitioner is to be given
such connection, the pending application has to be dealt with first.
18. It is further argued by the CESC Ltd that the installation of block
meter(s) would reduce the number of cables, crisscross of internal
wiring and other related problems since only two cables from the block
meter installed at the Meter Room would go to the Junction Box of the
concerned floor of the premises, from which wire/cable would go to the
respective rooms/sub-meters of each of the rooms of the concerned
floor.
19. Hence, installation of block meter will decrease the multiplicity of
wires, thereby reducing the fire and electrical hazards. In case of
installation of individual separate meters, independent respective four
cables/wires (2 incoming and 2 outgoing) of each of such meter would
go all the way from the meter board space at the ground floor to the
respective rooms of the consumers at different floors, which is not
possible.
20. The question of the installation of block meter(s) increasing the load
factor to the existing service mains is misconceived, it is argued. Load
factor means how much energy was used in a time period vis-à-vis
how much energy would have been used during peak period. At
present there areseven service mains installed in respect of the
premises-in-question, which would permit installation of one block
meter which may cater to 25 to 35 sub-meters/consumers depending
on the strength of the cable of the service mains. The CESC Ltd. has
never taken a stand that the service mains are fully loaded or
saturated.
21. Learned counsel for the CESC Ltd.further submits that safety
standards have not been compromised by the CESC Ltd at all. As per
Clause 13 of the 2010 Regulations, the licensee is to ensure safe
condition of all its wires, fittings, apparatus and supply lines placed on
the consumer's premises.
22. Clause 7.2 of the WBERC (Electricity Supply Code) Regulations, 2013
stipulates that the service lines between the main switch and the
meter will be owned by the consumer and shall have to be maintained
by the consumer as well. Therefore, it is argued, after the main switch
position, the licensee has no responsibility to maintain the cable and
apparatus fitting of the consumers, which are to be maintained by the
consumers themselves.
23. Procurement of electricity supply from an existing consumer by others
person is beyond the point of supply of the licensee, that is, the main
switch.
24. To get supply of electricity under Section 43 of the 2003 Act is not an
absolute right, it is submitted, but is subject to compliance of all other
requirements and formalities. It is clarified that the CESC Ltd has not
refused supply of electricity but in view of the congestion in the
premises-in-question leading to multiplicity of wirings of a large
number of consumers in a relatively small premises, it has agreed to
provide block meter so as to cater to supply of electricity to the
petitioner in terms of the Clause 18 of the 2013 Regulations.Thus, the
twin conditions of the said clause are fully satisfied in the instant case,
it is argued.
25. Learned counsel for the CESC Ltd. distinguishes the judgment cited by
the petitioner, rendered by the Supreme Court and reported in (2015)
2 SCC 438, and contends that the said citation is misconceived in the
present context as the CESC Ltd is ready to provide electricity to the
petitioner from its own network but through a block meter.
26. The unreported judgment in Partha Ghosh vs. CESC (supra) is also not
applicable to the present case as the premises are different and the
condition of the premises are different and distinguishable.
27. Clause 18 has no connection with clause 14 of the WBERC
Regulations as the concept of splitting of loads to prevent avoidance of
the tariff slab and the concept of block meter in order to avoid fire
hazard in the given situation are two different concepts.
28. It is the settled position that the technical feasibility of supply of
electricity must be left to the decision of the technical persons of the
licensee/ supplying authority and the court should not embark upon
an enquiry to decide such technical feasibility. In support of such
contention, learned counsel placed reliance on the judgment reported
at AIR 1989SC 788, (200) 2 CHN, 637 and (2002) 1 CHN 24.
29. Upon considering the submission of the parties, it transpires that the
inspection report authored by the District Inspector, Calcutta Central
District of the CESC Limited is succinct and relevant. It is elucidated
from the said report that seven service mains are feeding 225 meters
installed at the meter board of 10, Old Post Office Street, Kolkata
700001.
30. It is evident that the meter boards are in good condition but the
consumer wirings are in a poor condition. That report specifically
mentions that the existing service cables are almost at saturation level
and may break down with continuous increase of load.
31. It is further mentioned in the report that there is no place for taking
further service mains to the premises and/or for installation of even
one additional meter.
32. The meter board is congested and already full, leavingonly space for
heat dissipation. Additional meters, if installed, will take away such
space for heat dissipation, causing multiplicity of wiring and increased
criss-cross of electricity wires which may cause severe fire hazards and
would be unsafe for the premises and its occupiers.
33. Large number of consumer, the report states, are enjoying electricity
connection jointly to the said meters.
34. The said report suggests installation of block meter as a solution to
cater to several connections at the said premises for the sake of
security and safety.
35. There is nothing on record to rebut the presumption of correctness
attached to the official report submitted by the CESC Ltd., which is
authored by an expert in the field.
36. The three judgments cited by the CESC Limited, as recorded above,
clearly reiterate the proposition that the Court should not readily
interfere in technical matters to override expert opinion.
37. In the present case, Section 53 of the 2003 Act is also attracted. The
said provision stipulates measures relating to safety and electricity
supply.
38. Clause 13 of the Safety Regulations of 2010 provide that the licensee is
to ensure safe condition of all its wires, fittings, apparatus and supply
lines placed on the consumer's premises and to take precaution to
avoid dangers. However, as rightly contended by the CESC Limited,
the licensee cannot be responsible for the wirings and apparatus
belonging to the consumers, beyond the main switch area.
39. Also, clause 7.2 of the WBERC (Electricity Supply Code) Regulations,
2013 stipulates that service line between the main switch and the
meter will be owned and maintained by the consumer.
40. Learned counsel for the CESC limited is justified in contending that
the right given under Section 43 of the 2003 Act is not an unfettered
right but is qualified by the others provision of the Statute and the
Regulations, which have statutory force.
41. The safety and security of consumers and others with regard to the
electricity installation and cables is within the domain in the
distribution licensee. The Court ought not to override the specific
opinion of the CESC expert to the effect that installation of a block
meter is absolutely essential due to the huge number of connections at
10, Old Post Office Street having already reached the last straw. The
CESC limited is justified in arguing that the installation of even one
more additional meter would tip the balance beyond the safety zone.
The already existent multiple wirings,that is evident from the
photograph annexed to the pleadings and the averments in the
opposition of the CESC Limited, clearly indicates that the existent
wirings are already in a criss-cross mess. If additional meters are
started to be given not only to the petitioner, but also the others
pending applicants, the balance would be tilted against safety.
42. Clause 14 of the WBERC Regulations in respect of splitting of load
pertains to avoidance of tariff and is not directly relatable to the
concept of a block meter.
43. In such view of the matter, since the CESC Limited has taken a
specific stand that a block meter is the necessity of the hour at the
premises-in-question, the Court ought not to interfere with such
decision, since it is not supposed to have any expertise whatsoever on
the subject.
44. Hence, there is no scope of interference in the present writ petition.
Accordingly, WPA No. 18989 of 2021is disposed of without any order
as to costs, granting liberty to the petitioner to approach the CESC
Limited for installation of a block meter, along with other consumers
at 10, Old Post Office Street, Kolkata 700001. If such an approach is
made, nothing in this order shall prevent the CESC Limited from
giving such connection to the petitioner and the other pending
applicants by installing block meter(s) for them as well as the existing
consumers at the premises, without being prejudiced in any manner
by the findings arrived at by this Court.
45. Urgent photostat certified copy of this order be supplied to the
respective parties upon compliance of usual formalities.
(SABYASACHI BHATTACHARYYA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!