Citation : 2022 Latest Caselaw 2131 Cal
Judgement Date : 20 April, 2022
20.04.2022
rc/ct.no.10
Item No.341
WPA No. 12886 of 2017
Gobinda Das & Ors.
Vs.
The State of West Bengal & Ors.
Mr. Udayan Ray ...for the petitioners
Mr. Chandi Charan De
Mr. Anirban Sarkar ...for the State
On the prayer of the petitioners liberty is granted to
them to implead the Collector, Land Acquisition, Howrah
as respondent no. 7 in the writ petition. The cause title of
the writ petition be amended accordingly.
The petitioners are directed to serve copy of the writ
petition along with annexures thereto upon the respondent
no. 7 in course of this day.
It is submitted on behalf of the parties that exchange
of affidavits is not required in the matter.
The petitioners have prayed for parity with the co-
owners of the property in question who have been granted
enhanced compensation by the respondents in terms of
the order passed in C.O.No. 15853(W) of 1995.
The petitioners are recorded co-owners of the plot in
question which was requisitioned by the Government for
construction of godown for storage of foodgrains under
Food and Supplies Department. Possession of the plot was
taken on April 12, 1945 and notification was published in
the Calcutta Gazette on March 13, 1980. The land was
acquired vide LA Case No. 1(ActVIII) of 1979-80. Being aggrieved by the amount of compensation assessed by the
Collector Land Acquisition, Howrah, the petitioners filed a
petition for enhancement of compensation which was sent
to the Tribunal which by an order dated 15.09.1989,
allowed the prayer of the petitioners and granted
compensation @20% per cottah along with 30% solatium
thereon and 12% per annum on the enhanced
compensation. Further interest @15% from the date of
compensation till payment of the amount was also
awarded by the Tribunal. Pursuant to the said order
several representations were made by the petitioners which
fell on deaf ears. Some of the claimants being the co-
owners of the plots in question moved an application
under Article 226 of the Constitution India before this
Court for realisation of their dues and by an order dated
August 03, 1992 in C.O.No. 10559(W) of 1992, a
coordinate Bench of this Court directed the authority to
dispose of the claim of the co-owners within 12 weeks from
the date of communication of the order. Pursuant to such
order, part payment was made to the said claimants/co-
owners by the Collector, Land Acquisition, Howrah who
abstained from making payment of the interest @12% per
annum on the enhanced compensation. Some of the co-
owners subsequently filed another writ petition before this
Court and by an order dated November 16, 1995 in
C.O.No.15853(W) of 1995, a co-ordinate Bench of this
Court directed disposal of the matter and payment, if admissible, within a month from the date of
communication of the order. Due to non-compliance of the
said order a contempt application was filed against the
respondents during pendency of which the State of West
Bengal preferred an appeal against the judgment and order
passed in the LA Case along with an application under
Section 5 of the Limitation Act praying for condonation of
delay in preferring the appeal. The application for
condonation of delay was rejected by the Hon'ble Division
Bench of this Court by an order dated August 25, 2006 in
CAN No. 3095 of 2006. Thereafter the said co-owners were
granted the enhanced compensation in terms of the
direction of this Court in CO No. 15853(W) of 1995.
Learned counsel for the petitioners submits that as
the interest of the petitioners are covered by the said
judgment in view of the fact that the LA case being LA
Case No. 1(ActVIII) of 1979-80 is with regard to the plot of
the petitioners as well, the petitioners are also entitled to
payment of enhanced compensation in compliance with
the order of this Court passed in CO No. 15853(W) of
1995. The petitioners submitted a representation in this
regard before the concerned authority on February 19,
2016 which is yet to be disposed of. The petitioners pray
for a direction upon the authority to consider and dispose
of the said representation at the earliest and disburse the
enhanced compensation in their favour within a stipulated
time frame.
Having considered the submissions made by the
learned counsels appearing on behalf of the parties, this
Court is of the view that as the petitioners stand on the
same footing as the other co-owners of the property in
question who were granted enhanced compensation in
terms of the order passed in CO No. 15853(W) of 1995, the
petitioners are also entitled to the same benefit.
Accordingly the writ petition is disposed of directing
the respondent no. 7 to consider and dispose of the
application submitted by the petitioners dated February
19, 2016 within two months from the date of
communication of this order after affording reasonable
opportunity of hearing to all the interested parties
including the petitioners, in accordance with law.
The decision taken by the authority shall be
communicated to the petitioners within a week thereof.
With the above observations and directions this writ
petition being WPA No. 12886 of 2017 is disposed of.
There shall be, however, no order as to costs.
Since no affidavit is invited, the allegations
contained in the petition are deemed not to be admitted.
Urgent certified website copy of this order, if applied
for, be furnished to the parties upon compliance of
necessary formalities.
(Suvra Ghosh,J)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!