Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Jaishree Steels Pvt. Ltd. And Anr vs West Bengal State Electricity ...
2021 Latest Caselaw 1437 Cal/2

Citation : 2021 Latest Caselaw 1437 Cal/2
Judgement Date : 17 November, 2021

Calcutta High Court
Jaishree Steels Pvt. Ltd. And Anr vs West Bengal State Electricity ... on 17 November, 2021
1


                      IN THE HIGH COURT AT CALCUTTA
                              CIVIL APPELLATE JURISDICTION
                                      ORIGINAL SIDE

     PRESENT:

     HON'BLE JUSTICE SUBRATA TALUKDAR
                   AND
     HON'BLE JUSTICE KESANG DOMA BHUTIA



                                 A.P.O.T. No. 117 of 2021
                                           With
                                  W.P.O. No. 260 of 2021

                       Jaishree Steels Pvt. Ltd. and Anr.
                                       -Vs.-
        West Bengal State Electricity Distribution Company Ltd. and Ors.

        For the Appellant               : Mr. Ratnanko Banerji
                                          Mr. Ratnesh Rai
                                          Mr. D.N. Sharma
                                          Mr. AnkurRai
                                          Ms. Vipra Garg


        For the Respondents             : Mr. SrijanNayak

Mr. Sujit Sankar Koley

Heard on : 24/09/2021

Judgment on : 17/11/2021

Subrata Talukdar, J:

The short point which arises for consideration in this appeal is

whether the appellants and, specifically the appellant No.1/ the Company,

were liable to suffer sudden disconnection of electricity supply by the

respondents/ the Distribution Company/ WBSEDCL/ the Licencee.

The appellants contend that previously they were under a licensing

agreement for supply of electricity for the contracted demand supplied by

the Durgapur Projects Limited (DPL). The contracted demand level being

upwardly revised upon mutual agreement of the parties, DPL started raising

incorrect bills qua the upward revision.

The escalation of the tariff demand became the subject of stiff

negotiation between the parties. While the appellants insisted on waiver of

the escalated bill amounts, DPL sought fulfilment of the demand on the

basis of instalments.

DPL thereafter merged with the Licensee/ WBSEDCL on and from 1 st

January 2019. The appellants further contend that consequent to the

merger, WBSEDCL failed to appreciate the basis of the transactions with

DPL leading up to the enhanced tariff demand. The appellants submit that

the notice of disconnection dated 8 th July 2021, if at all the same can be

treated to be one, is not in conformity with Section 56(1) of the Electricity

Act, 2003 (for short the 2003 Act). The appellants also contend that in the

alternate no disconnection could have been effected by the Licencee since

the purported enhanced tariff demand failed the limitation test of two years

as provided by Section 56 (2) of the 2003 Act.

The appellants submit that there are no current outstandings payable

to the Licencee and Late Payment Surcharge (LPSC) have been

surreptitiously introduced by the Licencee to pad up the current bills. In any

even stage LPSCs have lost their validity to be enforced having regard to the

restriction imposed by Section 56(2) of the 2003 Act (supra). From a

compilation of bills raised by the Licencee and claimed to be paid by the

appellants, it is sought to be demonstrated that out of the last outstanding

shown prior to disconnection, corresponding to the period of the amount of

Rs. 10.4 Crores approximately, the appellants have paid approximately

above Rs. 13 Crores, inclusive of current consumption charges. The

appellants dispute the add-on LPSCs and maintain that the disconnection is

thoroughly illegal. It is submitted that due to the sudden disconnection, the

factory has been left idle, the workers with their dependants have been left

without livelihood and, equally important, the appellants would have to

incur huge costs to re-fire the furnace.

Mr. Mukherjee, Learned Senior Counsel appearing for the appellants,

strongly relies on the reported decision in 2020) 4 SCC 650 to make the

point that in the event limitation in terms of Section 56(2) (supra) expires

qua any demand proposed to be raised by the Licencee, the result cannot be

disconnection of electricity supply. It may be arguably open to a Licencee to

raise the demand by way of an additional supplementary charge, which

however does not apply to the present facts.

Learned Senior Counsel submits that the Hon'ble Single Bench fell

into deep error by comprehending the dispute between the parties to be in

the nature of a complex arithmetical analysis which should be best left for a

decision by the Central Grievance Redressal Officer (for short the CGRO) as

provided by the 2003 Act.

Per contra, the Licencee, on the basis of a subsequent affidavit

directed to be filed by the order of the Hon'ble Single Bench dated 23 rd July

2021 has argued that with the migration of the billing process to WBSEDCL,

the outstanding dues of the appellants stood at around Rs. 8.81 Crores as

in the first quarter of 2019. Throughout 2019 the appellants were granted

payment by instalments which, however, was not maintained by them.

The failure to honour the instalments continued throughout 2020.

Such failure, in addition to raising the consumption charges, also led to

imposition of LPSCs. The current payments being made by the appellants

were therefore required to be adjusted against previous outstanding dues.

At Paragraphs 11,12 and 13 of the said subsequent affidavit (below)

the following is pleaded on behalf of the Licencee. The pleadings are sought

to be supported by a Chart disclosing the outstanding dues of the appellant

No.1/ the Company for the billing months December 2020 to June 2021.

The aforesaid paragraphs read as follows:

"11) In this way for Bill month June 2021: Total OSD was Rs. 9231931426, out of which Amount for the said month was Rs. 12130967.89 for consumption period of 01.06.21 to 01.07.21. The accrued LPSC was Rs. 994130.45 and the payable after due date amount is Rs. 10,44,50,283/-. The petitioner paid Rs. 1,932,866/- on 8 th June, 2021 and Rs. 14,131,551.00/- on 14th June, 2021 whereas the actual date of the entire payment was scheduled on 14 th December, 2020 and 13th January 2021 respectively. The outstanding amount in the said bill was meant for the month of December 2020, January 2021, February 2021, March 2021, April 2021 and May 2021.

12) In the meanwhile disconnection notice was sent to consumer every month on expiry of due date. Last notice was served vide our memo no. C/BC/BUR/DPL/22/290 dated 19.04.21 for the outstanding due up to March 2021. Disconnection was not effected on sympathetic ground due to pandemic. Finally disconnection was effected on 08.07.21.

13) Present OSD as on date amounting Rs. 10,44,50,282.16 includes OSD of bill month December 2020 (partially) to June 2021. A Table showing details of current consumption charges along with outstanding dues for the period mentioned in the bills and payment made therein and accrued Late Payment Surcharge, amount

adjusted against outstanding dues are as follows:-

A       B           C                D                E              F            G                H
Bill    Normal      OSD Amt.         LPSC     Amt.    LPSC    Amt.   Actual due   Payment Amt.     Payment
Mont    Due Date                     during    this   cropped due    date    of   during   the     Date
h                                    bill             to     delay   payment      month
                                                      payment        was
Dec-    13.01.202   4,842,682.86
20      1
Jan-    15.02.202   17,947,166.7                      1,170,900.8    13.07.202    15,000,000.0     04.01.202

                                     8                307,919.84                  4,218,080.00     05.01.202

                                                      792,534.56                  10,000,000.0     28.01.202

                                                      243,584.81                  4,512,015.00     30.01.202

Feb-    15.03.202   14,617,457.3                      523,244.07     13.10.202    10,000,000.0     03.02.202

                                     5                291,000.00     13.10.202    6,000,000.00     17.02.202

                                                      279,759.69     13.10.202    5,432,227.00     23.02.202

                                                      470,935.59     12.11.202    10,000,000.0     26.02.202



Mar-    13.04.202   15,669,954.8     594,517.94       594,517.94     12.11.202    12,806,012.0     15.03.202



Apr-    17.05.202   23,305,001.0                      289,866.00     12.11.202    5,000,000.00     07.04.202

                                                      633,468.71     12.11.202    10,384,738.0     13.04.202


May-    14.06.202   15,937,051.4     1,533,761.7      1,533,761.7    14.12.202    22,381,667.0     27.05.202

Jun-    15.07.202   12,130,967.8     994,130.45       132,769.17     14.12.202    22,381,667.0     27.05.202


                                                      861,361.28     13.01.202    14,131,551.0     14.06.202

Total               104,450,282.16   8,125,624.2      8,125,624.2                 131,799,151.00





For more explanation, it may be stated that for example the billing month of February 2021, Total OSD was Rs. 103795229/-, out of which Amount ofr

the said month was Rs. 1,46,17,457.32 for consumption period of 01.02.2021 to 01.03.2021. The accrued LPSC was Rs. 15,64,939.35 due to delayed payment of (Rs. 1,00,00,000/- on 03.02.2021 Rs. 60,00,000/- on 17.02.2021 Rs. 54,32,227.00 on 23.02.2021 and Rs. 1,00,00,000/- on 26.02.2021). For these payments the LPSC accrued during this month (Rs. 523244.07 + 291000+279759.69+470935159 = Rs. 1564939.35) which has been claimed through energy bill of February 2021. The Outstanding Amount of Rs. 24,278.62 in the said bill was meant for the month of October 2020, November 2020, December 2020 and January 2021.

15) This affidavit is being done only to the extent of explanation of the dues of Rs. 104,450,282.16/- which include LPSC accrued therein "

By way of reply, the appellants point out that there was no imposition

of LPSCs by DPL between 2016 to 2019. For the first time pertaining to the

monthly cycle of February 2019 the alleged outstanding of Rs. 8.81 Crores

was shown by WBSEDCL against the regular account of the appellants. The

appellants rely on bank statements for confirmation of the fact that for the

entire period between February 2019 till date, all current bills have been

paid. The appellants argue that LPSCs have been imposed to the extent of

Rs. 9.12 Crores from September 2019 till June 2021. Such LPSCs have no

relation whatsoever to payment of the regular monthly consumption bills by

the appellants but have been exclusively imposed for the so-called delay in

paying the supplementary bills. As a measure of the net bill imposed

towards consumption charges by the appellants between August 2019 to

June 2021, the appellants also produce a chart showing break-up of the net

bill amount into two parts, viz. actual outstanding bills and LPSC charge.

MONTH NET BILL AMOUNT OUTSTANDING LPSC CHARGED (Excluding BILL INCLUDED (in Rs.) outstanding (in Rs.) Amount) (in Rs.) Aug'19 8,10,81,955.00 86,50,066.00 2,64,757.00 Sept'19 2,53,79,676.00 7,39,01,406.00 1,36,08,974.00 Oct'19 2,42,05,325.00 0 1,04,87,695.00 Jan'20 2,66,81,621.00 8,48,80,156.00 1,23,87,775.00 Feb'20 2,78,83,374.00 9,75,43,143.00 1,39,26,971.00 Jun'20 2,21,14,509.00 10,60,23,055.00 82,23,511.00 Jul'20 2,26,71,179.00 10,96,57,648.00 85,37,011.00 Aug'20 1,71,43,929.00 2,26,71,178.00 21,48,219.00 Oct'20 3,40,09,278.00 11,82,24,153.00 64,14,185.00

Nov'20 21,87,55,895.00 13,39,37,188.00 26,57,815.00

Dec'20 1,95,29,571.00 11,71,08,663.00 20,17,556.00

Jan'20 1,79,47,167.00 10,29,09,339.00 25,14,940.00

Feb'20 1,43,70,951.00 8,94,24,278.00 15,64,939.00

Apr'20 2,33,05,001.00 9,15,23,346.00 9,23,334.00

May'20 9,24,46,680.00 1,56,65,313.00 15,33,761.00

Jun'21 1,21,30,969.00 9,23,19,314.00 9,94,130.00

TOTAL 9,12,05,573.00

The appellants allege that it is not on account of outstanding

consumption charges but purely on account of the LPSC amount, that the

disconnection was effected on 8th July 2021. Such disconnection being also

contrary to the statute, is utterly capricious.

Having heard the parties and closely examined the materials placed,

this Court is unable to come to a conclusion pari materia with that of the

Hon'ble Single Bench that the problem posed in this appeal can only be

remedied by experts. In this connection it would be useful to refer to certain

portions of the discussion made by the Hon'ble Single Bench in three of its

orders passed while hearing and ultimately deciding the writ petition. The

observations in the first order dated 23rd July 2021 read as follows:

"The writ petitioner is aggrieved by a disconnection of electricity supply for omission of payment of what the petitioner calls 'late payment surcharge' for the year 2015-16. At the relevant time electricity was being supplied to the petitioners by one Durgapur Projects Ltd. (DPL). The supply operations of the said DPL have since been taken over by and merged into, the West Bengal State Electricity DistributionCompany Limited (WBSEDCL).

It is submitted by Mr. S.N. Mookherji, learned Senior counsel for the petitioner that the principal amount of dues for the said period as claimed, have been paid. At no point of time was late payment surcharge claimed by either DPL or WBSEDCL. It is submitted that in the year 2019, for the first time, WBSEDCL has claimed about a sum of about ₹10.45 crores towards the purported Late Payment Surcharge.

Mr. S. S. Koley, learned counsel appearing for the WBSEDCL submits that his client is surprised to note the reasons attributed by the petitioner behind the demand of the said sum of ₹10.45 crores. It is submitted that the demand arose out of arrears of electricity dues for the period from December, 2020 till June, 2021. Given the divergence of facts, this Court directs the WBSEDCL to file an affidavit justifying its contention that the dues of ₹ 10.45 crores arose for the aforesaid period i.e., 2020- 3 21. It shall also be indicated as to whether the said sum of ₹ 10.45 crores includes any amount towards any late payment surcharge and to what extent. The licencee may also produce any document or evidence to show that the demand for late payment surcharge of ₹9 lacs towards late payment charges, has been continuous since 2015- 16 till the year 2020.

Let such affidavit be filed within a period of ten days from date; reply thereto, if any, be filed within a day thereafter. List this matter in the same position as 'motion' eleven days hence."

The observations in the second order dated 3 rdAugust2021 read as

follows:

"Affidavit-in-opposition and the affidavit-inreply, filed in Court today, are taken on record. Having heard learned counsel for the parties, let this matter stand adjourned until tomorrow to consider passing of interim orders."

The observations in the third order dated 4 th August 2021 read as

follows:

"WBSEDCL has filed affidavit explaining the current dues to the extent of Rs.10,44,50,282.16. These dues, according to WBSEDCL, have arisen out of current consumption from December, 2020 to June, 2021. It is explained that the payment amount during the month against Column-G at page 7 of Rs.13,17,99,151/- is the payment made against bills on dates later than the due date.

Therefore, the accumulated past dues including LPSC during this current period have been mentioned at the bottom of the bills annexed to the rejoinder.

Mr. S.K. Kapur, learned Senior Counsel appearing for the petitioner, would counter the argument of the WBSEDCL by submitting that there are no current dues that could be outstanding. It is also submitted that if any amount of dues was there during the period from January to June, 2021, disconnection would have been effected much earlier. It is also argued that the sum of Rs.10,44,50,282.16, now explained as current dues for the period from December 2020 to June 2021, is an afterthought and actually represent late payment charges for amounts that accrued sometime in the year 2015.

There is prima facie evidence before this Court that all sums against bills raised have not been paid within the due dates. In fact, payments against some bills have been made in instalments from time to time, after the due date.

Having considered the entire facts, this Court is of the view that a large number of disputed questions of fact emerge which cannot be gone into by a writ court. The Electricity Act, 2003 provides for a Central Grievance Redressal Officer (CGRO) under Section 42 of the Act. The dispute between the parties is referred to the Central Grievance Redressal Officer (CGRO)."

The observations in the fourth order dated 9 thAugust 2021 read as

follows:

"The matter is taken up for further hearingpursuant to this Court's order dated 4th August, 2021. On thatday, detailed arguments of the parties were recorded and this Court expressed views that the Central Grievance Redressal Officer(CGRO) shall receive pleadings from the petitioner as well asWBSEDCL and dispose of the issue raised in the writ applicationwithin a period of one month.At the request of Mr. S.K. Kapoor, learned SeniorCounsel, this Court had adjourned the matter today to enable thepetitioner to cite judgments on the question of alternative remedy and disputed question of fact. Opening his submission today, Mr. Kapoor relied upon the chart set out by WBSEDCL at page 7 of their affidavit. Mr. Kapoor tried to demonstrate before this Court that even a plain reading of column D and column H would indicate that his client had, at all times, made payment of monthly bills albeit with some delay.He, therefore, submits that there are no disputedquestions of fact and this Court can entertain the writ application and test propriety of the entire claims of therespondent against the petitioner.Reference is also made to Section 56 of the Electricity Act, 2003 and it is submitted that no notice of disconnection, as

stipulated thereunder, has been issued by the

WBSEDCL.

...........

Having carefully considered the submissions of Mr.Kapoor, this Court notes that the table, set out in paragraph may be simple for a chartered accountant or a person regularlydealing with the bills, payments and late payment thereof. A writ Court does not even have the expertise to see though any improper demand of WBSEDCL or any lawful claim of the petitioner. The parties are at each other's throats on the figures, numbers and facts. There are therefore absolutely no admitted

facts herein."

To the best of the mind of this Court in the event the two charts

respectively relied upon by the appellants and the Licencee are placed next

to each other, it would require not too much effort to decipher that at the

bottom of the rival contentions lies the LPSC figures. There is no dispute

raised by the Licencee connected to payment of current consumption

charges. The LPSCs have been a source of friction between both the parties

stemming from the migratory phase of billing from the first quarter of 2019

following the merger of DPL with the Licencee. Whether such LPSCs should

be at all allowed to remain in their present form in the bills in issue or, only

their quantum requires to be reassessed by an expert in the nature of a

CGRO, is one issue.

The other issue which a Writ Court is competent to decide is whether

the presence of the LPSCs should automatically result in disconnection of

electricity supply de hors the statute. This Court is unable to accept the

single line contention of the Licencee in its affidavit filed pursuant to the

order dated 23rd July 2021 of the Hon'ble Single Bench that the appellants

are habitual defaulters.

From the affidavit of the Licencee it has been, inter alia, pleaded that

the monthly billing period commencing from December 2020 to June 2021

grew in size due to the add-on factor of the LPSCs.

Nowhere from the Charts relied upon by both the parties it could be

shown to this Court that the current outstandings were not paid by the

appellants. Therefore to permit a disconnection to stand when on the face of

the record the appellants are far from being characterised as habitual

defaulters would be ill-fitted to sound reason and equity. To permit a factory

to remain closed only for the CGRO to compute whether the LPSCs were

there to stay and, if at all, to what extent in the face of a statutory limitation

and zero current consumption outstandings, will defeat the balance of

convenience which lies in favour of the appellants.

In the backdrop of the above discussion, it would be appropriate for

this Court to turn around the conclusion arrived at by the Hon'ble Single

Bench.

The CGRO would therefore decide the dispute connected to imposition

of the LPSCs qua their validity and proportionality. The CGRO shall take a

decision within a period of three months from the date of communication of

this order upon affording the parties an opportunity of hearing and

presenting materials in support of their stand. The Licencee/ the

WBSEDCL shall reconnect the electricity supply to the Appellant No.1/ the

Company within 48 Hours of receiving notice of this order and upon

compliance of the necessary formalities.

The notice of the disconnection dated 8 th July, 2021 stands thus set

aside.

Needless to add, the appellants shall continue to pay the regular

consumption charges upon reconnection being effected.

A.P.O.T. 117 of 2021 with W.P.O. No. 260 of 2021 stand

accordingly disposed of.

There will be no order as to costs.

Parties shall be entitled to act on the basis of a server copy of the

order placed on the official website of the Court.

Urgent Xerox certified photocopies of this judgment, if applied for, be

given to the parties upon compliance of the requisite formalities.

I agree.

(Kesang Doma Bhutia, J.) (Subrata Talukdar, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter