Citation : 2021 Latest Caselaw 454 Cal/2
Judgement Date : 12 July, 2021
IN THE HIGH COURT AT CALCUTTA
Ordinary Original Civil Jurisdiction
ORIGINAL SIDE
Present:
THE HON'BLE JUSTICE MOUSHUMI BHATTACHARYA
I.A No: G.A. 2 of 2021
in
A.P. 827 of 2018
Indian Oil Corporation Ltd.
Vs.
Tapas Kumar Das
For the Petitioner : Mr. Jishnu Saha, Sr. Adv.
Mr. M.S. Yadav, Adv.
For the Respondent : Mr. Debajyoti Datta, Adv.
Mr. Subhasish Bandopadhyay, Adv.
Last Heard on : 09.07.2021.
Delivered on : 12.07.2021.
MOUSHUMI BHATTACHARYA, J.
1. This is an application for amending the grounds of challenge in an
application under Section 34 of The Arbitration and Conciliation Act, 1996
(the Act). The impugned Award dated 30th July, 2018 was passed by a
learned Sole Arbitrator allowing some of the claims filed by the claimant
(respondent before this court) in relation to termination of a dealership
executed between the respondent herein and the petitioner Indian Oil
Corporation Limited.
2. According to the petitioner, the application for amendment should be
allowed since the proposed grounds contained in the Schedule to the
application, were urged by the petitioner before the Arbitrator.
3. Mr. Jishnu Saha, learned senior counsel appearing for the petitioner-
Indian Oil Corporation Limited, submits that the new grounds pertain to the
Marketing Discipline Guidelines for certain types of dealerships of Indian Oil
Corporation Limited, which provides for the remedies available to a dealer in
the event of termination of the dealership. Counsel submits that the
grounds pertaining to the Guidelines were missed out through inadvertence
in the application challenging the impugned Award. Counsel submits that
the issues framed by the Arbitrator in the impugned Award would show that
the petitioner had urged the new grounds in the arbitration proceedings.
Counsel relies on Fiza Developers & Inter-Trade Pvt. Ltd. vs AMCI (INDIA) Pvt.
Ltd. & Anr; (2009) 17 SCC 796 on the proposition that an award may be set
aside by a court on its own initiative if the subject-matter of the dispute is
not arbitrable or the Award is in conflict with the public policy of India.
Counsel relies on State of Maharashtra vs. Hindustan Construction Company
Limited; (2010) 4 SCC 518 on the point that court can grant leave to amend
an application under Section 34 if the circumstances of the case so warrant.
Venture Global Engineering vs Satyam Computer Services Limited and
Another; (2010) 8 SCC 660 has been shown to urge that facts disclosed after
passing of the Award may be brought on record as grounds if such facts
have a positive link with the facts constituting the Award. Emkay Global
Financial Services Limited vs Girdhar Sondhi ; (2018) 9 SCC 49 has been
relied upon on the point that if there are matters which are relevant for
determination of issues arising under Section 34 and which were not before
the Arbitrator, such matters can be brought to the notice of the court.
4. Mr. Debajyoti Datta, learned counsel appearing for the respondent
opposes the application for adding new grounds for setting aside the Award
primarily on the factual score. Counsel submits that in seeking to introduce
new grounds, namely on the lack of jurisdiction, the nature and character of
the setting aside application is being changed which is not permissible in
law. It is also submitted that the amendments are being carried out beyond
the period of 120 days within which an application has to be made for
setting aside an Award. Counsel submits that grounds which are sought to
be added now do not have a foundational basis in the original application.
Counsel submits that if Section 34 (2) (b) is read with the amended Section
34 (2A) of the Act, there will be no need to add the proposed grounds.
Counsel relies on Pushpa P. Mulchandani and others vs Admiral
Radhakrishin Tahilani (Retd.) and others; (2000) 4 Mh.L.J. 819 and Esteem
Mercantile Pvt. Ltd. vs M/s K.H. Parekh and another; (2002) 2 Mh.L.J. 216 in
support of the proposition that amendments cannot be allowed to be carried
out beyond the period specified in Section 34(3) of the Act.
5. I have heard learned counsel for the parties and seen the documents
relevant for deciding the question whether the petitioner should be allowed
to amend the arbitration petition by addition of the grounds set forth in the
Schedule to the present application.
6. The grounds contained in the Schedule relate to the Marketing
Discipline Guidelines for specific kinds of Dealership and that the contracts
entered into between the Public Sector Oil Marketing Companies and such
dealers are subject to the terms and conditions of the Marketing Discipline
Guidelines. The grounds relate to the agreement between the petitioner and
the respondent being subject to the terms and conditions contained in the
said Guidelines of 2005 which automatically became a part of the agreement
entered into between the parties. The Guidelines were framed by the
Ministry of Petroleum for the conduct of certain dealerships of public sector
Oil Marketing Companies. From the grounds, the grievance of the petitioner
appears to be that the Arbitrator ignored a fundamental term of the
agreement between the parties by holding that the Guidelines had
been governing the dispute between the parties. As stated above, the
petitioner's stand is that the Guidelines also provide the remedies which are
available to a dealer on the termination of the dealership.
7. The issue which falls for consideration is whether permitting the
petitioner to incorporate the additional grounds of challenge to the existing
Arbitration Petition would enlarge the scope of the arbitration petitions
beyond permissible limits or allow new grounds to be brought in for the first
time to the challenge to the Award. The test is whether the additional
grounds can be traced to the arbitration proceedings that is in pleading or
document which was before the Arbitrator. If the contents or point urged in
the additional grounds can be found in the contentions urged by the parties
before the Arbitrator, it cannot then be said that the additional grounds are
sought to be introduced by the petitioner for the first time in a Section 34
proceeding. The only point urged in the additional grounds is the relevance
of the Marketing Discipline Guidelines which form part of the agreement
between the parties and which the Arbitrator failed to give sufficient
importance to. On a perusal of the Award, it is found that the issues were
settled over the five and six sittings of Arbitration and Guidelines were
incorporated in issue no. 3 which is set out below :-
"3. Whether the Claimant is entitled to challenge the termination of his
dealership by the Respondent when the Claimant did not prefer any appeal
therefrom in accordance with the Marketing Discipline Guidelines?"
8. Issue No. 20 also mentions the Guidelines which appears as :-
"20. Whether the claimant not having challenged the termination order
in accordance with the Marketing Discipline Guidelines is entitled to challenge
the show cause notice?"
9. Besides the issues, the submission of Indian Oil Corporation Limited
(respondent before the Arbitrator) has also clearly been noted in the
impugned Award namely that the claimant, Tapas Kumar Das (respondent
before this Court) has not exhausted the remedy provided in the Marketing
Discipline Guidelines by preferring an appeal against the order of
suspension and termination. The Award proceeds to discuss the various
provisions of the Marketing Discipline Guidelines including the Chapters 5,
6 and Clause VI relating to irregularities for penal action and other actions
taken against a dealer. Clause IV provides that in the event of termination,
the dealer will have the right of appeal before the appropriate authority
empowered to decide the matter within 30 days of the termination order.
The claimant's contentions, recorded in the Award, also mentions the
Guidelines.
10. The letter of termination dated 15th January, 2013, which was a part
of records before the Arbitrator also mentions the Marketing Discipline
Guidelines - 2005. It is evident from the above that the Marketing Discipline
Guidelines was a crucial part of the proceedings before the Arbitrator and
including the issue of whether the arbitration proceedings were
maintainable at all or not. The present application does not call for a
decision on whether the Arbitrator's view on the Guidelines was correct or
not. The limited question is whether the petitioner should be prevented from
incorporating the Guidelines as part of its grounds for challenge to the
Award under Section 34 of the Act.
11. The ratio of the decisions shown by the parties can be summarized on
the premise that a new ground is generally not permitted to be introduced
by way of an amendment whereas a ground which has a foundational link to
the unamended ground would pass muster. The logic to the aforesaid rule
can be found in the limitation envisaged in Section 34(3) of the Act which
provides a specific time frame of three months from the date of receiving the
Award for making an application for setting aside the Award. An additional
period of 30 days has been given to a party for making such application
upon satisfaction of the Court that the applicant was prevented by sufficient
cause from making the application within the three months. Allowing an
applicant to introduce a new ground to an existing application under
Section 34 would defeat the statutory objective of 34(3) which permits an
aggrieved party to approach a court within the statutory time limit and not
beyond. A ground which does not have any link to an existing petition would
become a new ground and hence the subject matter of a separate Section 34
application.
12. In Venture Global, the Supreme Court allowed facts to be brought in
on the basis that the said facts which were disclosed after passing of the
Award have a causative link with the facts inducing the Award. The
Supreme Court held that facts which would have a bearing on the
proceedings for setting aside and for determining whether the Award was
induced by fraud may be made part of the Section 34 proceedings. In Emkay
Global, the Supreme Court was of the view that an application for setting
aside an Arbitral Award will not ordinarily require anything beyond what
was before the Arbitrator. The Supreme Court in fact held in favour of
bringing matters to the notice of the Court by way of affidavits even where
they were not part of the records in the arbitration proceedings, but were
relevant for determination of the issues before the court. In Fiza Developers,
the Supreme Court was of the view that the scope of amendment in a
section 34 application is restricted to the question whether any ground
exists for setting aside of the Award and also held the necessity for framing
of issues where material facts are in dispute. The decisions sought to be
relied upon by learned counsel appearing for the respondent, who opposes
the application for amendment proceed on the basis that if the existing
petition does not contain the ground proposed to be added, the additional
grounds must be rejected since it would have a bearing on Section 34(3) of
the Act (Ref: Esteem Mercantile) and on the general proposition that
amendments beyond the prescribed period of limitation cannot be allowed
since that would amount to entertaining a fresh petition (Ref: Pushpa P.
Mulchandani). In Prakash Industries Ltd. vs Bengal Energy Ltd. and Another;
AIR 2020 Cal 279 the proposed amendments were disallowed on the ground
that the amendments were more than amplification of the existing grounds.
The facts in that case make it clear that the petitioner sought to bring in
grounds in relation to the Sale of Goods Act which did not have a foundation
in the Section 34 application which had already been filed. The application
of the petitioner was hence rejected on that basis. Ground No. XVII of the
existing grounds in the present case broadly covers the right of the
respondent (claimant in the arbitration) to make claims and in the reference
for an award. Although the Guidelines have specifically been referred to in
the existing grounds, there are other grounds which go to the root of the
Arbitrator's power to decide the disputes between the parties. Read with the
other pleadings which were before the Arbitrator and which expressly
mentions the Marketing Discipline Guidelines, it cannot be said that the
additional grounds are new grounds despite a pleading to such effect in
paragraph 6 of the instant application. The relevant test is whether the
petitioner would be constrained to file a new application under Section 34
for challenging the Award under the additional grounds. The petitioner
would pass the test since the Marketing Discipline Guidelines constitutes a
prominent and significant part of the records before the Arbitrator and
disallowing the petitioner from bringing the said Guidelines into the existing
application would deprive the petitioner from an important challenge to the
impugned Award. This would militate against the liberal stand taken by the
courts in respect of amendments where the objective is to primarily allow a
party to amend its pleading as may be necessary for the purpose of
determining the real questions in controversy between the parties. There is
no doubt that the Marketing Discipline Guidelines go to the very root of the
matter and are crucial for determining the challenge to the impugned
Award.
13. The admitted factual position is also that the existing Section 34 was
made within the 120 days statutory time limit, although the present
application for amendment has been filed after three years.
14. G.A No. 2 of 2021 is allowed by reason of the above discussion. The
petitioner is given leave to amend A.P. No. 827 of 2018 in the manner as
indicated in the Schedule annexed to the application. The petitioner is given
leave to re-verify the petition upon the same being amended within four
weeks from the date of this order. The Department is accordingly directed to
take requisite steps within the aforesaid time frame. A copy of the amended
and re-verified petition should be served on the respondent within a week
from the amendments being carried out. A.P No. 827 of 2018 shall be listed
upon mentioning. The petitioner will however be liable for payment of costs
assessed at Rs. 25,000/- to be paid to the State Legal Services Authority, for
the delay in filing the present application.
Urgent Photostat certified copy of this Judgment, if applied for, be
supplied to the parties upon compliance of all requisite formalities.
(Moushumi Bhattacharya, J)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!