Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shiba Prosad Banerjee vs The State Of West Bengal And Others
2021 Latest Caselaw 457 Cal

Citation : 2021 Latest Caselaw 457 Cal
Judgement Date : 22 January, 2021

Calcutta High Court (Appellete Side)
Shiba Prosad Banerjee vs The State Of West Bengal And Others on 22 January, 2021
                        In the High Court at Calcutta
                       Constitutional Writ Jurisdiction
                                Appellate Side

The Hon'ble Justice Sabyasachi Bhattacharyya


                            WPA No.1724 of 2020
                            IA NO: CAN 1 of 2020

                           Shiba Prosad Banerjee
                                     Vs.
                     The State of West Bengal and others


For the petitioner                   :     Mr. Saptangshu Basu,
                                           Mr. Swarup Pal,
                                           Mr. Surya Maity,
                                           Ms. Amrita Maji,
                                           Ms. Mrinalini Majumder,
                                           Mr. Anirban Chakraborty

For the respondent-authorities       :     Mr. Jishnu Chowdhury,

Mr. Robiul Islam, Ms. Pramita Banerjee

For the respondent no.10 : Mr. Aurobinda Chatterjee, Mr. A. Sengupta

Hearing concluded on : 15.01.2021

Judgment on : 22.01.2021

Sabyasachi Bhattacharyya, J:-

1. The petitioner challenges the rejection of his bid and the acceptance of

respondent no.10 as the successful bidder in a tender floated by the

respondent-authorities on May 27, 2019 for supply of cooked diet for

indoor patients admitted to health facilities. The Revised Bid

Summary Report (Annexure P-1 at page 81 of the writ petition)

indicates that the petitioner's bid was rejected for non-submission of

Performance Certificate in prescribed format as per Clause 3 of the

Notice Inviting Tender (NIT). Learned counsel for the petitioner

submits that the petitioner duly submitted Performance Statement in

terms of the proforma given in Clause 3 of the NIT. By placing such

Performance Statement dated June 7, 2019 (annexed at page 86 of the

writ petition), learned counsel contends that all particulars, as

required by the NIT, were furnished by the petitioner. Despite having

done so, the tendering authorities rejected the petitioner's bid for non-

submission of Performance Statement in prescribed format.

2. Learned counsel for the petitioner further submits that the bid of the

private respondent was accepted unlawfully, although the same was

in contravention of the conditions stipulated in the NIT.

3. Clause 18.3 of the NIT provides that if any document required to be

submitted for e-tender by the bidder in his technical proposal is not

submitted or is found to be deficient in any manner at any stage after

opening of bid, the bid may be summarily rejected.

4. Clause 13.1 of the NIT provides that the bidder shall provide an

undertaking that the proprietor/promoter/director of the firm, its

employee, partner or representative are not convicted by a court of law

for offence involving moral turpitude in relation to business dealings

such as bribery, corruption, fraud, etc. The undertaking should also

contain the averment that the firm does not employ a government

servant, who has been dismissed or removed on account of corruption

and that the firm has not been debarred or blacklisted by any

Government Ministry/Department/Local Government/PSU, etc., in

the last 2 years from scheduled date of opening of the e-tender.

5. The undertaking submitted by the private respondent, annexed at

page 93 of the writ petition (Annexure P-4), was undated and, as such,

did not qualify for being considered within the contemplation of

Clause 13.1, it is submitted.

6. That apart, learned counsel for the petitioner argues, the Performance

Statement of the private respondent was not accompanied by a

notarised certification authenticating the correctness of the

information furnished. Such requirement appears at the end of Clause

3.1 of the NIT. Comparing the mere notarial stamp and seal appearing

on the Performance Statement of the private respondent (at page 92 of

the writ petition) with the full-fledged notarial certificate furnished by

the petitioner (annexed at page 85 of the writ petition), learned

counsel argues that the documents of the private respondent were

deficient on such score as well, thus disqualifying the bid of the

private respondent.

7. Learned counsel appearing for the respondent-authorities submits

that the undertaking furnished by the private respondent sufficiently

complied with the provisions of the NIT, since the last sentence of

such undertaking (although undated) mentioned that the firm had not

been debarred or blacklisted by any Government

Ministry/Department/Local Government/PSU, etc., in the last two

years from scheduled date of opening of the tender.

8. Learned counsel submits that the notarial stamp affixed to the

Performance Statement of the private respondent, although not a

'notarial certificate' in the strictest sense, fulfilled the criterion

stipulated in the NIT in that regard.

9. Learned counsel for the tendering authorities further contends that

the Performance Statement of the petitioner was insufficient. Pointing

out in particular to the details furnished under the first and third

columns thereof, learned counsel submits that the full address of the

purchaser in respect of the previous work done by the petitioner was

not furnished. Merely "C.M.O.H Burdwan" was mentioned under the

said column. In comparison, the Performance Statement of the private

respondent clearly mentioned the particular Hospital and the order

number and date of the previous work in details. As far as the

description and quantity of the past work was concerned, the

petitioner merely mentioned various years and the number of beds,

but did not mention any other detail thereof. In contrast, the private

respondent, in its Performance Statement, had clearly indicated the

number of beds and that the supply pertained to cooked diet in the

relevant column.

10. Referring to Item C under the document check list chart provided in

Clause 12.3 of the NIT, learned counsel for the respondent-authorities

submits that the same was a mandatory requirement. Since the

credential documents required under the said check list were to be

read into the eligibility criterion, as stipulated in Clause 3 of the NIT,

non-furnishing of the same by the petitioner exposed the petitioner's

bid to rejection. As per the last paragraph of Clause 3.1, documentary

evidence was to be furnished in support of the Performance

Statement. Clause 3.1, sub-clauses (a) and (b) specifically provide that

the intending tenderer should produce credentials as stipulated

therein to be eligible and to qualify for the bid. Such clause, implicitly,

mandates the production of documents in support of the bidders'

Performance Statement relating to past work done. However, the

petitioner was deficient on such score and his bid was, thus, rightly

rejected.

11. Learned counsel for the private respondent, apart from adopting the

arguments of the respondent-authorities, argues that the writ petition

was filed about six months after issuance of the work order in favour

of the private respondent. In the absence of appropriate explanation

for such inordinate delay, the writ petition ought to be dismissed on

such score alone.

12. It is further submitted by the private respondent that Clause 3.1, sub-

clauses (a) and (b) of the NIT contemplate 'completed work' during

three years prior to the date of issuance of the e-tender notice.

However, as borne out by the Performance Statement of the petitioner,

no completed work of such description was cited by the petitioner.

Thus, being in contravention of Clause 3.1 of the NIT, the petitioner's

bid was rightly rejected.

13. In reply to the arguments of the respondent-authorities, learned

counsel for the petitioner submits that sufficient details were

furnished in the Performance Statement of the petitioner. Counsel

submits that the term "C.M.O.H. Burdwan" sufficiently covered the

requirement of the proforma for Performance Statement provided in

Clause 3.1 of the NIT. C.M.O.H., Burdwan was the authority placing

the order and, as such, the individual Hospitals to which food was

supplied by the petitioner were immaterial. The mention of the

concerned C.M.O.H.s was sufficient to satisfy the NIT conditions.

Since the number of beds for which food was supplied in the

corresponding financial years was mentioned in the relevant column

of the petitioner's Performance Statement, there was no deficiency on

that score either.

14. In reply to the contentions of the private respondent, learned counsel

for the petitioner argues that there was delay in online uploading of

the necessary details pertaining to the tender. This, coupled with the

intervening pandemic situation, caused the delay in filing the writ

petition.

15. It is further argued that the requirement stipulated in Clause 3.1,

sub-clauses (a) and (b), of the NIT was not a part of the Performance

Statement mentioned in the NIT. Thus, the work experience indicated

in the Performance Statement of the petitioner, which covered several

periods and pertained to several C.M.O.Hs, was sufficient compliance

of the NIT.

16. Considering the submissions of both sides, a conjoint reading of the

clauses of the NIT does not rule out the view that the "documentary

evidence", as sought in the last paragraph of Clause 3.1, also

encompassed the eligibility criteria stipulated in the sub-clauses (a)

and (b) of Clause 3.1 of the NIT. In the absence of such specific

documents being produced by the petitioner, it was plausible for the

tendering authorities to reject the petitioner's bid. The credentials

stipulated in the said sub-clauses, being mandatory eligibility criteria,

can very well be read into the credentials to be disclosed in the

Performance Statement.

17. It is arguable whether the details furnished by the petitioner,

particularly under the first and third columns of his Performance

Statement, were sufficient. In contrast to the detailed Performance

Statement of the private respondent, the petitioner merely mentioned

the names of the respective authorities. Even if it is assumed for the

sake of argument that detailed address need not have been furnished,

the particulars of the hospitals in which the petitioner actually

provided food might have been a valid consideration for deciding the

petitioner's eligibility vis-à-vis the other bidders. That apart, the

petitioner did not mention whether the diet provided by the petitioner

in the past occasions was cooked or not.

18. In contrast, the Performance Statement of the private respondent was

much more specific, although it was comprised of lesser number of

works done. What is to be seen is whether the eligibility criteria

stipulated in the NIT were fulfilled and not the volume of past

experience of the bidder.

19. As regards the undertaking filed by the private respondent, the same

clearly stipulated that the firm had not been debarred or blacklisted

by any Government Ministry/Department/Local Government/PSU,

etc., in the last two years from the scheduled date of opening of the

tender. Such undertaking was precisely in consonance with the

requirement of the NIT (last paragraph of Clause 3.1 thereof) to the

letter. Thus, the bid of the private respondent could not be rejected on

the score of deficiency in that regard.

20. The last paragraph of Clause 3.1 required "notarised certification

authenticating the correctness of the information furnished". It did

not stipulate that a formal 'notarial certificate' had to be furnished in

the form maintained by the Notaries functioning under the

Government of West Bengal. Even assuming that the private

respondent deviated from the usual form used by Notaries in West

Bengal, the stamp and seal of the concerned Notary was imprinted on

the Performance Statement of the private respondent. There was no

bar in the tendering authorities considering such notarial certification

to be due compliance with the authentication of correctness of

information required under the NIT.

21. The writ court has to examine whether the tendering authority had

the discretion which was exercised by it in choosing a successful

bidder over others. It is well-settled that the court cannot impose its

own view on the tendering authority. The choice made by the

respondent-authorities in the present case was plausible and valid

and, as such, ought not to be interfered with.

22. That apart, the long delay of six months in preferring the writ petition

even after the issuance of work order, pursuant to which the

successful bidder has already commenced work, is itself an indicator

of the petitioner having approached court with unclean hands. There

is not a single sentence in the writ petition which pleads any

appropriate, let alone sufficient, cause for the delay. Hence, whatever

submission is made from the Bar in that regard cannot be accepted as

justification for the delay, in the absence of any specific pleading in

that regard. Thus, in any event, the writ petitioner ought not to be

granted the reliefs claimed in the writ petition at this belated juncture.

23. Accordingly, WPA No. 1724 of 2020 is dismissed on contest without

any order as to costs.

24. IA No: CAN 1 of 2020 is also disposed of accordingly.

25. Urgent certified website copies of the order shall be provided to the

parties upon due compliance of all the requisite formalities.

( Sabyasachi Bhattacharyya, J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter