Citation : 2021 Latest Caselaw 1413 Cal
Judgement Date : 12 February, 2021
6
12.02.2021
Ct. No.23
sb.
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRIT JURISDICTION
APPELLATE SIDE
(Via Video Conference)
WPA 4163 of 2021
Purulia Metal Casting Pvt. Ltd. & Anr.
Vs.
Damodar Valley Corporation & Ors.
Mr. Debabrata Saha Roy,
Mr. Indranath Mitra,
Mr. Pingal Bhattacharya,
Mr. Subhankar Das,
Mr. Neil Basu
... For the petitioners
Mr. Jaydip Kar, Sr. Advocate
Mr. Prasun Mukherjee
Mr. Deepak Agarwal
... For DVC
The petitioner no.1 is a consumer under Damodar
Valley Corporation (in short "DVC") for its factory situated
at Bongabari, Purulia. The petitioners in this writ petition
have challenged the summary statement raised by DVC,
the licensee, dated 1st January, 2021 along with the
amended bills claiming a sum of Rs.1,98,56,638/- and the
disconnection notice dated 30th January, 2021 issued by
DVC in terms thereof threatening to disconnect the supply
of petitioner no.1 within 15 days from the date of issuance
of the said notice. The 15 days time period from 30th
January, 2021 takes us to 15th February, 2021. The
petitioners say that nothing is payable according to the
demand made and therefor has not paid the amount
claimed or any part thereof. The petitioners apprehend
2
disconnection by tomorrow. The disconnection, if effected,
will stop the operation of the factory and will cause
immense loss to the work-in-progress. The employees of
the petitioner no.1 including the petitioner no.2 will be
deprived of their livelihood if the disconnection takes place.
The petitioners say that after several rounds of
litigation ultimately, by an order dated 19th March, 2020,
the West Bengal Electricity Regulatory Commission, (in
short, WBERC) fixed the retail tariff for the year 2009-10,
2010-11 and 2012-13. By another order dated 19th June,
2020, WBERC fixed the retail tariff for the year 2006-07
and 2008-09.
As per records it is an admitted position that a net
principal amount of Rs.4,69,48,597/- was an excess
payment made by the petitioners for the period 2006-09.
DVC has given 6% interest to the petitioners in terms of
the order dated 10th May, 2010 passed by the Appellate
Tribunal for electricity. The interest at the rate of 6% on
the principal sum of Rs.4,69,48,597/- come to
Rs.2,29,38,727/-.
It is the case of the petitioners that from the
principal sum of Rs.4,69,48,597/-, the electricity bills
dated 6th January, 2010, 5th February, 2010, 5th March,
2010, 6th April, 2010 and 10th May, 2010 have deducted
which brings the figure of Rs.4,69,48,597/- to
Rs.2,59,55,634/- being the net principal amount
refundable.
3
Against an aggregate interest of Rs.2,29,38,727/-,
DVC has adjusted the Delayed Payment Surcharge (in
short "DPS") and arrived at sum of Rs.4,58,12,272/- said
to be payable by the petitioner No.1 to DVC for the period
2010-2013. This alleged DPS, according to DVC, is in
terms of the agreement between the petitioners and DVC.
After the adjustment of Rs.2,59,55,634/- from
Rs.4,58,12,272/- a sum of Rs.1,98,56,638/- has allegedly
become realisable by DVC from the petitioner no.1.
On behalf of the petitioners, it is submitted that
DVC has wrongfully charged DPS though such DPS is
neither realisable by DVC nor payable by the petitioners.
There has been no delay on the part of the petitioner no.1
in making payment as the bill raised by DVC without the
tariff order being fixed cannot be said to be bills payable by
the petitioners. DVC has in an unauthorised manner
reduced the interest accrued on the principal sum by
deducting DPS therefrom. There is, as such, according to
the petitioners, no amount payable if a proper account is
taken in the matter.
On behalf of DVC it is submitted that the bill has
been raised in terms of the various orders passed in the
proceedings inter se between the parties as also in terms of
the order of the Central and the State Electricity Regulatory
Commission. There is, as such, no error in the bill and the
petitioners are liable to pay the said sum of
Rs.1,98,56,638/-. It is also submitted on behalf of DVC that
the petitioners have disputed the bill raised by DVC. A
4
billing dispute is required to be adjudicated by the Regional
Grievance Redressal Officer, (in short, RGRO) set up in
terms of Section 42(5) of the said Act and then by the
electricity Ombudsman under Section 42(6) of the said Act.
The petitioners should be asked to approach the concerned
RGRO for redressal of his disputes. Some of the consumers
in similar circumstances have approached the RGRO. DVC
also says that in terms of the agreement between the
petitioners and respondents there is an arbitration
agreement and the disputes raised by the petitioners are
squarely covered by the arbitration clause and as such they
could have approached the arbitrator. The writ petition is
not maintainable in view of the subsistence of the
arbitration agreement and availability of a statutory forum.
DVC has relied upon a judgment reported in (2007)
8 SCC 381 (Maharashtra Electricity Regulatory
Commission vs. Reliance Energy Ltd. & Ors.). Relying
upon paragraphs 22, 31 and 33 it is submitted that RGRO
is the only forum which can be approached by the
petitioners.
After considering the respective submissions and
the materials on record, the right of DVC to realise DPS and
the accounting procedure as raised by the petitioners
cannot be gone into without calling for affidavits.
So far as the interim protection as to the threat of
disconnection is concerned, the Court is required to balance
the scales. It is an admitted position that a sum of
Rs.4,69,48,597/- is the net principal amount payable by
DVC to the petitioners. It is also an admitted position that a
sum of Rs.2,29,38,727/- has accrued as interest on the
principal sum. The aggregate sum of such interest and
principal is Rs.6,98,87,324/-. The DPS realised is an issue
required to be adjudicated after filing of affidavits.
With regard to the realization of DPS, I also find
substance in the contention of the petitioners at this stage.
As to whether DVC can realize DPS is dependant on various
factors like the interpretation of the clause for the same in
the agreement, the limitation as to the bills, the
interpretation of various orders. These issues cannot be
gone into without complete disclosure in the affidavits to be
filed. At this stage, the adjustment of the interest payable
to the petitioner against DPS, and then against the
principal sum cannot be said to be realisable from the
petitioners without there being detailed enquiry in this
regard after filing of affidavits. DVC also did not take any
steps to disconnect the electricity between 2009 - 2013
when according to them bills remained unpaid. The balance
of convenience and inconvenience is therefor tilted in favour
of the petitioners. The petitioners have also made out a
prima facie case and are, therefor, entitled to an order of
injunction restraining DVC from disconnecting the supply
of the petitioners for non-payment of the amount claimed in
the bill dated 1st January, 2021, till the final disposal of the
writ petition. The petitioner no.1, however, shall continue to
pay the regular consumption bills that may be raised by
DVC from time to time during the pendency of the writ
petition.
With regard to the contention raised by DVC that
the matter should be sent to the RGRO, I am of the view
that the dispute in hand is not a classical billing dispute
wherein either the meter is defective or erroneous meter
reading involving any outstanding energy charge for the
consumption made by the petitioners in regular course as
considered by the Commission in case of Reliance Energy
(supra). The bill is on account of alleged arrears after
adjustment of an admitted sum. The adjustment includes
the legality to realise DPS and bills for the period 2009 to
2013 after about seven years. These issues also cannot be
effectively decided by the RGRO or the arbitrator. This
Court is empowered to go into the legality of realisation of
DPS and adjustment on account thereof as also for bills
unrealised for over seven years.
Since I have admitted the writ petition for being
finally heard after the affidavits, I have not dealt with the
judgments cited in details.
Let affidavit-in-opposition be filed within a period of
three weeks from date. Reply thereto, if any, be filed within
two weeks thereafter.
Liberty to mention for inclusion in the list under the
heading "Hearing" after six weeks.
(Arindam Mukherjee, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!