Citation : 2021 Latest Caselaw 357 Cal/2
Judgement Date : 7 April, 2021
IN THE HIGH COURT AT CALCUTTA
Original Civil Jurisdiction
(Original Side)
AP 279 of 2020
Universal Consortium of Engineers Pvt. Ltd.
Vs.
Sri Kanak Mitra & Anr.
Before: The Hon'ble Justice Arijit Banerjee
For the Petitioner : Mr. Uday Chandra Jha, Adv.
Mrs. Maheswari Sharma, Adv.
Ms. Tulika Roy, Adv.
For the Respondents : Mr. Manab Ranjan Sarbadhikari, Adv.
Mr. Soupal Chatterjee, Adv.
Heard On : 04.02.2021, 10.02.2021 & 12.02.2021 CAV On : 12.02.2021 Judgment On : 07.04.2021 Arijit Banerjee, J.:
1. This is an application under Section 11 of the Arbitration and
Conciliation Act, 1996 (in short 'the Act of 1996'), for appointment of an
arbitrator for adjudication of disputes and differences that have arisen
between the parties in relation to a Development Agreement dated December
15, 2006 (in short, 'the said Agreement') entered into by and between the
parties. It is not in dispute that the said Agreement contains an arbitration
clause for resolution of disputes and differences between the parties
touching the said Agreement.
2. Schedule 'F' to the Development Agreement dated 15.12.2006 which
contains the Arbitration Clause reads as follows:
" SCHEDULE 'F'
ARBITRATION
1. All disputes and differences between the parties
hereto arising out of this agreement regarding this
constructing or interpretation of any of the terms and
conditions herein contained or determination of any
liability or touching these presents shall be referred to
the arbitration and the same shall be deemed to be a
reference within the meaning of the Arbitration and
Conciliation Act, 1996 or any statutory enactment or
modification thereunder and the Award so delivered
shall be conclusive and binding on the parties hereto.
2. The Arbitrator shall have summary power.
3. The parties hereto agree and covenant with each other
that they have full trust and faith in the Arbitrator and
agree not to challenge and / or dispute the same in
any manner whatsoever or howsoever."
3. The respondents opposed the application primarily on two grounds.
Firstly, it was argued that no notice under Section 21 of the Act of 1996 was
given by the petitioner to the respondents. In the absence of such a notice,
the present application is premature and not maintainable. Secondly, the
respondents have filed a complaint against the petitioner before the National
Consumer Forum, New Delhi, in relation to disputes arising out of the said
Agreement. It was submitted that initiation of an arbitration proceeding by
appointment of an arbitrator would mean that there will be parallel
proceedings which ought not to be permitted. Although a third ground has
been indicated in the written notes of argument filed by the respondents,
i.e., the said Agreement is not registered as required under Section 17 of the
Registration Act, this point was not argued when the matter was heard. In
any event, this point can be rejected at the threshold since the said
Agreement being of the year 2006, there was at that time no requirement for
registering the said Agreement.
4. In support of his contention that for initiation of an arbitration
proceeding, issuance of notice under Section 21 of the Act of 1996 is
mandatory, learned Counsel appearing for the respondents has relied on
several decisions. Prior to noting such decisions, it may be helpful to set out
Section 21 of the Act of 1996:
"21. Commencement of arbitral proceedings.-Unless
otherwise agreed by the parties, the arbitral proceedings
in respect of a particular dispute commence on the date on
which a request for that dispute to be referred to
arbitration is received by the respondent. "
5. Learned Counsel relied on the decision of the Delhi High Court in the
case of Alupro Building Systems Pvt. Ltd. v. Ozone Overseas Pvt. Ltd.:
2017 SCC Online Del 7228. Learned Counsel particularly relied on
Paragraphs 25 and 30 of the said judgment which are set out hereunder:
"25. A plain reading of the above provision indicates that
except where the parties have agreed to the contrary, the
date of commencement of arbitration proceedings would
be the date on which the recipient of the notice (the
Petitioner herein) receives from the claimant a request for
referring the dispute to arbitration. The object behind the
provision is not difficult to discern. The party to the
arbitration agreement against whom a claim is made,
should know what the claims are. It is possible that in
response to the notice, the recipient of the notice may
accept some of the claims either wholly or in part, and the
disputes between the parties may thus get narrowed
down. That is one aspect of the matter. The other is that
such a notice provides an opportunity to the recipient of
the notice to point out if some of the claims are time
barred, or barred by any law or untenable in fact and/or
that there are counter-claims and so on.
30. Considering that the running theme of the Act is the
consent or agreement between the parties at every stage,
Section 21 performs an important function of forging such
consensus on several aspects viz. the scope of the
disputes, the determination of which disputes remain
unresolved; of which disputes are time-barred; of
identification of the claims and counter-claims and most
importantly, on the choice of arbitrator. Thus, the
inescapable conclusion on a proper interpretation of
Section 21 of the Act is that in the absence of an
agreement to the contrary, the notice under Section 21 of
the Act by the claimant invoking the arbitration clause,
preceding the reference of disputes to arbitration, is
mandatory. In other words, without such notice, the
arbitration proceedings that are commenced would be
unsustainable in law. "
6. Learned Counsel relied on a decision of the Bombay High Court in the
case of Bombay Gas Company Ltd. v. Parmeshwar Mittal & Ors.: AIR
1998 Bombay 118. Reliance was placed particularly on Paragraph 10 of the
said judgment. With great respect I have not been able to appreciate as to
why the said judgment was relied upon. In the context of Sections 34 and 21
the Arbitration Act, 1940, the learned Judge held that an application under
Section 34 surely implies readiness and willingness of the party to go for
arbitration, but it cannot be equated with a notice under Section 21 which
constitutes commencement of an arbitral proceedings. In my opinion the
said decision is not relevant for the purpose of the present case.
7. Learned Counsel also referred to a decision of this Court in the case of
Magma Leasing Ltd. v. NEPC Micon Ltd. & Anr: AIR 1998 Calcutta
1994. Again in my opinion, this case has no relevance to the case in hand.
The learned Judge was considering the meaning of the phrase 'not later than
when submitting his first statement on the substance of the dispute', which
appears in Section 8(1) of the Act of 1996.
8. Mr. Sarbadhikari then referred to the Hon'ble Supreme Court decision
in the case of M/s. Sundaram Finance Ltd. v. M/s. NEPC India Ltd.: AIR
1999 SC 565. Again, with great respect, that case is in no way germane to
the facts of the present case. In that case the Hon'ble Supreme Court
explained that the Court can pass interim orders under Section 9 of the
1996 Act before or during the arbitral proceedings, i.e., even before notice
under Section 21 of the 1996 Act is received by the respondents.
9. Finally learned Counsel referred to the judgment of the Hon'ble
Supreme Court in the case of Union of India v. Parmar Construction
Company: 2019 (3) CHN (SC) 343. This case also, in my opinion, is in no
way relevant for the purpose of deciding the issue in hand.
10. The facts of the case as placed before the Court by Learned Counsel
for the petitioner and not disputed by Learned Counsel for the respondents,
are that a Development Agreement dated 15.12.2006 was entered into by
and between the petitioner (the Developer) and the respondents (owners of
the land in question). Construction of the proposed building was completed
and the owners' share was handed over to them on 20.01.2018, 24.02.2018
and 11.04.2018.
11. By a letter dated 08.01.2019 the respondent no.1 raised certain
disputes pertaining to the area of the owner's allocation, the amount to be
received by him in terms of the Development Agreement, quality of the
building materials, etc. In the said letter it was stated that unless the
grievances were redressed, the respondent no.1 would take appropriate
steps. The said letter was replied to by the petitioner by its letter dated
28.01.2019 followed by a letter dated 01.02.2019. In the letter dated
01.02.2019, it was specifically stated that the respondent no.1 had been
handed over more area than what he was entitled to under the Agreement
and he was required to pay for the same. It was further stated that the
petitioner had invested a huge amount of money for removing the tenants
(which was the responsibility of the owners as per the Agreement) and
further that the unnecessary allegations against the petitioner were causing
loss of reputation and goodwill to the company. It was further stated as
follows:
"Even after receipt of this letter if you are not satisfied
about the explanation you have option to refer the dispute
to the Arbitrator. In case you feel the matter should be
referred to the Arbitrator, we are ready to do the same in
terms of the Agreement entered into by and between the
parties."
12. Learned Counsel for the petitioner submitted that after receipt of the
said letter, the respondent no.1 wrote a letter dated 19.03.2019 repeating
the same allegations. As such, it is clear that there are disputes between the
parties which are continuing.
13. Learned Counsel submitted that the letter dated 01.02.2019 was
sufficient compliance with Section 21 of the Act of 1996. In this connection
he relied on the following two decisions: (i) Nea Agrex S.A. v. Baltic
Shipping Company Ltd.: 1976 2 ALL ER 842, (ii) Unreported judgment of
Delhi High Court in the case of Badri Singh Vinimay Pvt. Ltd. v. MMTC
Ltd., delivered on 06.01.2020 in O.M.P 225 / 2015. Learned Counsel also
relied on the Supreme Court decision in State of Goa v. Praveen
Enterprises: (2012) 12 SCC 581 in support of his submission that an
application under Section 11 of the Act of 1996 is itself a request for
arbitration and is sufficient compliance with Section 21 of the Act.
14. As regards the other contention of the respondents, Learned Advocate
for the petitioner submitted that the Consumer Forum does not have
jurisdiction to entertain the petitioner's counter claim. Hence, if the
petitioner's request for arbitration is declined on the ground that
proceedings between the parties are pending before the National
Commission under the Consumer Protection Act, the petitioner's claim will
suffer casualty without being adjudicated.
15. I have given my anxious consideration to the rival contentions of the
parties.
16. With reference to the second contention of the respondents regarding
pending of proceedings between the parties hereto before the National
Commission, the same is wholly meritless. The petitioner is a Developer and
contends that it has mistakenly handed over more constructed area to the
respondents than they were entitled to under the Development Agreement.
On that account, the petitioner has a money claim against the respondents.
This cannot be adjudicated by the National Commission under the
Consumer Protection Act. The petitioner, by no stretch of imagination can be
considered to be a 'Consumer' within the meaning of the Consumer
Protection Act. Hence, pendency of the proceedings before the National
Commission cannot be a ground for disallowing the present application.
17. As regards the main contention of the respondents that this
application cannot be allowed since the petitioner has not served any notice
under Section 21 of the Act of 1996 on the respondents, the same also is
unacceptable. Section 21 merely lays down as to when the arbitral
proceedings in respect of a particular dispute will be deemed to have
commenced, which is when a request for the dispute to be referred to
arbitration is received by the respondent. I am unable to read into Section
21 any mandate to the effect that a Section 11 application will not be
maintainable unless a notice under Section 21 has been served by the
petitioner on the respondent. To that extent, with respect, I am unable to
agree with the decision of the Delhi High Court in the case of Alupro
Building Systems Pvt. Ltd. (Supra). Further, as I have understood the
decision of the Hon'ble Apex Court in State of Goa (Supra) it is, inter alia,
to the effect, that an application under Section 11 of the Act of 1996 is itself
a request by the petitioner for arbitration.
18. However, the above discussion becomes academic since, in my
opinion, the letter dated 01.02.2019 written by the petitioner, when read in
a commercial perspective, clearly constitutes a notice under Section 21 of
the Act of 1996. Too much technicality should not be resorted to in
interpreting such a notice. If the intention of the party issuing the notice is
clear that he desires arbitration, that should suffice. An overly legalistic
approach is not to be adopted. In a commercial dispute, a notice asking for
arbitration ought not to be construed too strictly. In the case of Nea Agrex
S. A. (Supra) which involved a charterparty, the charterers' agents
presented to the owners' agents a detailed claim for damages demanding
immediate payment and then they said "please advise your proposals in
order to settle this matter, or name your arbitrators." The English Court of
Appeal consisting of Lord Denning, M.R., Goff L.J. and Shaw L.J., while
considering whether such a communication could be considered as a notice
requiring arbitration, held as follows:
"30. Mr. Rokison says that the request is equivocal. It
gives the ship-owners an alternative. It does not amount to
an unequivocal request for arbitration. So it cannot be
deemed to be the commencement of the arbitration. That
seems to me too legalistic an approach. In a commercial
dispute, a letter requesting arbitration should not be
construed too strictly. The writer should not be impaled on
a time-bar because he writes in polite and courteous
terms, or because he leaves open the possibility of
settlement by agreement. Suppose the characters had
written to the owners: "Unless you are prepared to settle
the matter amicably, we must ask you to agree to the
appointment of an arbitrator". That would, to my mind, be
quite sufficient. When such a letter follows upon a genuine
claim promptly made, it should be interpreted as a request
for arbitration - a request made then and there - coupled
with a willingness to come to an amicable settlement. The
arbitration is deemed to commence with the sending of the
letter, and time no longer runs against him.
31. Likewise with the letter in this case, it can and should
be construed as a request for the difference to be
submitted to arbitration - with a saving that the request
will be withdrawn if a settlement can be reached. That is
sufficient to commence the arbitration."
19. The decision in Alupro Building Systems Pvt. Ltd. (Supra) has been
distinguished by a Learned Judge of the Delhi High Court in the case of
Badri Singh Vinimay Pvt. Ltd. (Supra). In that case, Prateek Jalan, J.
held that the communication issued by the party wanting arbitration was
clear enough and amounted to a notice under Section 21 of the Act of 1996.
The Learned Judge distinguished the decision in Alupro Building Systems
Pvt. Ltd. (Supra) on facts and noted that in that case there was no notice to
the respondents at all. However, in the present case, as I have recorded my
opinion above, the petitioner's letter dated 01.02.2019 clearly contemplated
disputes between the parties and resolution of such disputes through the
process of arbitration, in the event the disputes were not resolved amicably.
20. In view of the aforesaid, all the objections raised by the respondents to
resist this application fail. This application is allowed.
21. Mr. Samrat Sen (9830173356), Senior Advocate, Bar Library Club,
Calcutta High Court, is appointed as sole Arbitrator to adjudicate the
disputes between the parties in relation to the Development Agreement
dated 15.12.2006. The Arbitrator will be free to fix his own remuneration.
He will also be at liberty to engage secretarial staff to assist him in
conducting the arbitral proceedings and to fix their remunerations. The
remuneration of the Arbitrator and the secretarial staff will be borne equally
by the parties. Since, no venue of arbitration is mentioned in the arbitration
clause, the arbitration will be held in Calcutta at a place to be decided by
the Arbitrator.
22. AP 279 of 2020 is accordingly disposed of.
Urgent certified photocopy of this judgment and order, if applied for, be
given to the parties upon compliance of necessary formalities.
(Arijit Banerjee, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!