Citation : 2026 Latest Caselaw 873 Bom
Judgement Date : 27 January, 2026
2026:BHC-OS:2217
Megha 2_carbpl_33334_2024_fc.docx
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
COMMERCIAL ARBITRATION PETITION (L) NO.33334 OF 2024
WITH
INTERIM APPLICATION (L) NO.39240 OF 2024
IN
COMMERCIAL ARBITRATION PETITION (L) NO.33334 OF 2024
Kanti Builders Pvt. Ltd. ...Petitioner
V/s.
Witty Enterprises Pvt. Ltd. ...Respondent
______________
Mr. Vishal Kanade with Ms. Apurva Gupte, Mr. Amogh Singh & Mr.
Krishnakant P. Deshmukh i/b. Mr. Dhirendra Pratap Singh for the
Petitioner.
Mr. Vikhil Dhoka with Mr. Abhijit Mukherjee i/b. M/s. GM Legal for
the Respondent.
______________
CORAM: SANDEEP V. MARNE, J.
RESERVED ON: 14 JANUARY 2026.
PRONOUNCED ON: 27 JANUARY 2026.
JUDGMENT:
1) By this Petition under Section 34 of the Arbitration and Conciliation Act, 1996 (the Arbitration Act), the Petitioner challenges impugned Award dated 5 August 2024 and modified Award dated 25 September 2024 passed by the learned sole Arbitrator. By the impugned Awards, the Arbitral Tribunal has awarded a sum of Rs.99,91,472/- to the Petitioner. Despite its claim being partially allowed, the Petitioner has still challenged the impugned Awards on
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
the ground that the Tribunal has not allowed the whole claim of Rs. 4,36,42,078/-.
2) Petitioner is an incorporated entity engaged inter alia in the business of real estate development. The Respondent is also an incorporated entity engaged in the business of running a school imparting primary and secondary education across the country. The Petitioner was the original owner of land bearing Survey No.41(part) corresponding to CTS No.374/B/10 admeasuring 2419.10 sq.mtrs at Borivali (West), Mumbai, (subject property), which was reserved for public purpose of secondary school in the development plan for Greater Mumbai. By registered Deed of Conveyance dated 22 December 2017, the Petitioner conveyed the said property to the Respondent. It appears that the Respondent executed lease of the land in favour of Pratiksha Foundation Charitable Trust for availing additional benefit of FSI upto 4.00 for educational activities by a public charitable trust. On 9 February 2018, the Petitioner and the Respondent entered into construction contract by which the Respondent was granted the work of construction of the school building on the subject property. Under the construction contract, the Respondent agreed to pay to the Petitioner an amount of Rs.23,40,00,000/- plus applicable GST in a phased manner linked to stage of construction. The plans for construction of the building were approved by MCGM on 10 May 2014 and commencement certificate upto 8th floor was issued on 28 May 2019. According to the Petitioner it completed construction of the school building in 2019. The Respondent thereafter started the work of installation of lift, fire fighting equipment, toilets, etc.
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
3) Petitioner alleges that the Respondent took forcible physical possession of the school building in December 2020 and started commercial use thereof by operating banquet hall in the basement and stilt areas of ground floor without occupation certificate being issued. On 12 December 2020, the Petitioner issued notice to the Respondent calling it upon to discontinue the activities. The Petitioner filed Petition under Section 9 of the Arbitration Act seeking interim measures against the Respondent, in which order dated 11 March 2021 was passed restraining the Respondent from occupying any portion of the building and from creating any third party right therein.
4) The Petitioner invoked arbitration clause by issuing notice under Section 21 of the Arbitration Act on 31 May 2021 and nominated an arbitrator. According to the Petitioner, the Respondent admitted its liability for payment of amount of Rs.7.75 crores vide letter dated 12 August 2021. An amount of Rs.1 crore was paid by RTGS and two cheques for Rs.2 crores and Rs.4,36,42,078/- were issued by the Respondent towards outstanding liability. The Respondent also deducted an amount of Rs.38,57,922/- towards TDS on the whole of the outstanding amount. The amount of Rs. 2 crores was honoured by the Respondent by making the payment through RTGS. However, the cheque in respect of second amount of Rs.4,36,42,078/- got dishonoured. The Petitioner called upon the Respondent to pay the balance amount. The occupation certificate for the school building was received on 20 January 2022. For dishonour of the cheque the Petitioner has filed Complaint under Section 138 of the Negotiable Instruments Act, 1881 ( the NI Act) in the Magistrate's
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
Court. The Petitioner has also filed a civil suit for recovery of amount of Rs.88,00,000/- remaining unpaid under the Deed of Conveyance. The Petitioner also filed Statement of Claim before the nominated Arbitrator on 19 April 2022 claiming amount of Rs.7,96,00,000/- from the Respondent alongwith interest. The Respondent, in addition to defending the claim of the Petitioner, filed counterclaim claiming amount of Rs.7,31,70,147/- alongwith interest and further amount of Rs.2,85,64,231/- alongwith interest. The Respondent also claimed sum of Rs.10 crores towards damages.
5) Based on the pleadings, the Tribunal framed issues. Parties led evidence in support of their respective claims. The Arbitral Tribunal has made Award dated 5 August 2024 partly allowing the claim of the Petitioner in the sum of Rs.1,75,38,857/-. However, after holding that the Respondent was entitled to receive from Claimant Rs.79,91,472/- the Arbitrator has directed deduction of the said amount and has allowed net claim of the Petitioner in the sum of Rs.95,47,385/-. The Tribunal has awarded interest @ 15% per annum. After delivery of the main Award dated 5 August 2024, the Respondent filed Application under Section 33 of the Arbitration Act for corrections in the Award. The Tribunal has accordingly allowed the said Application of the Respondent and has effected various corrections in the Award substituting figure of Rs. 79,91,472/- awarded in favour of the Respondent by sum of Rs.99,91,472/-. After deduction of amount of Rs.99,91,472/- awarded to the Respondent from the claim of the Petitioner of Rs.1,75,38,857/-, the Tribunal has awarded net amount to the Petitioner in the sum of Rs.75,47,385/-.
27 January 2026
Megha 2_carbpl_33334_2024_fc.docx
6) The Petitioner is aggrieved by the Award dated 5 August
2024, as modified by order dated 25 September 2024. Since the claim amount of the Petitioner is restricted to Rs.1,75,38,857/- and since the Tribunal has not awarded entire claim of Rs.4,36,42,078/- Petitioner has filed the present Petition under Section 34 of the Arbitration Act.
7) Mr. Kanade, the learned counsel appearing for the Petitioner submits that the impugned Award suffers from patent errors as the learned Arbitrator has ignored the settled position of law that admissions are the best form of evidence constituting waiver of proof. That in the present case there is explicit admission of liability in the form of letter dated 12 August 2021 issued by the Respondent, in addition to another undated letter. That the Arbitral Tribunal has failed to take into consideration the effect of letter dated 12 August 2021 and has concentrated only on the undated letter for the purpose of raising a misplaced inference that the amount of Rs.7.75 crores agreed by the Respondent was payable under both the Agreements. That letter dated 12 August 2021 records that the payments under the Conveyance Deed was fully paid up and net balance of Rs.7.75 crores was only in respect of the Construction Contract. That ignorance of vital piece of evidence in the form of letter dated 12 August 2021 constitutes perversity and patent illegality in the Award. That the expectation of the Tribunal of Petitioner independently proving execution of work to the extent of Rs.7.75 crores falls into insignificance in the light of explicit admission of liability by the Respondent.
8) Mr. Kanade would further submit that the Arbitral Tribunal has erred in rejecting the Petitioner's prayer for admitted
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
amount on the ground of lack of alternate prayer. He would submit that the Petitioner had specifically raised pleadings qua amount of Rs.4,36,42,078/-. That the Tribunal could have considered and granted the claim for lesser amount in absence of a specific prayer. That rejection of an admitted claim on the ground of absence of alternative prayer would constitute a patent error apparent on face of record. Mr. Kanade would further submit that the Tribunal erred in allowing counterclaim of the Respondent of Rs.1,09,47,700/- contrary to clause 7.3 of the Construction Contract. That under the contract, the liability to pay the development cess and development charges for fungible FSI was squarely the responsibility of the Respondent. That development cess and development charges are both components of fungible FSI. He would therefore submit that the Arbitral Tribunal has grossly erred in allowing counterclaim of the Respondent of Rs. 1,09,47,700/-. On above broad submissions, Mr. Kanade would pray for setting aside the impugned Awards.
9) Mr. Dhoka, the learned counsel appearing for the Respondent opposes the Petition submitting that the purported claim of the Petitioner for Rs.4,36,42,078/- was an afterthought and was never really raised before the Arbitral Tribunal. That the Petitioner had claimed an altogether different sum of Rs.7,96,00,000/- of which the breakup was provided in the Particulars with Statement of Claim. That the said amount of Rs.7,96,00,000/- was indicated as outstanding amount payable under the Construction Contract dated 9 February 2018. He would submit that the purported letter dated 12 August 2021 was never enforced by the Petitioner. That the Petitioner did not claim amount of Rs.4,36,42,078/- as an alternate claim in the event of failure
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
in the main claim of Rs.7,96,00,000/-. That the Arbitral Tribunal has rightly considered the position that the undated letter specifically referred to two agreements and that therefore the amount specified therein was not relatable to only Construction Contract. He would therefore submit that no interference is warranted in the impugned Award not upholding the claim of Rs.4,36,42,978/- He would submit that the Awarded sum has already been paid by the Respondent to the Petitioner.
10) So far as second objection of reimbursement of Rs.2,09,47,700/- towards development charges and development cess paid to Municipal Corporation of Greater Mumbai (MCGM) is concerned, Mr. Dhoka would submit that Clauses 7.3 and 8.7 of the Construction Contract read with point Nos.11 and 13 of Annexure A thereof specifically provide that the Respondent shall bear and pay the premium payable to the MCGM strictly for fungible FSI and Additional FSI only and all other payments payable to MCGM such as IOD, deposit, scrutiny fees, validation charges, staircase premium, open space deficiency premium, lift and lobby area premium, etc. were to be borne by the contractor. That the said clauses unequivocally provide that all charges including development charges and development cess payable to MCGM while obtaining approval were to be borne by the Petitioner alone. He would submit that the Respondent had already obtained approval by MCGM to the construction plans as per FSI 1.00. That therefore parties were fully aware about charges payable to MCGM for constructing school building beyond FSI 1.00 at the time of execution of contract itself. That therefore the charges agreed for all payments other than additional FSI and fungible FSI
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
were payable by the Petitioner alone. He would submit that the amounts towards development charges and development cess was charged by the MCGM distinctly. Mr. Dhoka submits that no case is made out for interference in the Award in exercise of powers under Section 34 of the Arbitration Act. That the Petitioner cannot seek re- appreciation of the evidence on record. That the view taken by the Arbitral Tribunal is a plausible view. He accordingly prays for dismissal of the Petition.
11) Rival contentions of the parties now fall for my consideration.
12) The disputes between the parties have arisen out of performance of Construction Contract dated 9 February 2018. The transaction between the parties is of unique nature where the owner of the land (Petitioner) first sold the subject property to the Respondent, who is in the business of setting up of schools. This was done possibly on account of the fact that the land was reserved in the development plan for setting up the secondary school. After acquiring ownership in the land by virtue of registered Deed of Conveyance dated 22 December 2017, the Respondent apparently executed Lease Deed in favour of a charitable trust on 6 February 2018. The Petitioner contends that the lease was executed for the purpose of availing additional FSI upto 4.00, which was admissible only to public charitable trusts for educational purpose. Otherwise, the MCGM had already sanctioned plans for construction of school building on the plot by sanctioning of FSI 1.00. It is not necessary to go into the nitty- gritties of complex transactions between the parties relating to
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
ownership of the subject property. It is possible that ownership of the land was changed for the purpose of availing extra FSI than the one which would have been availed in normal circumstances. Be that as it may. The Petitioner, who was original owner of the subject property, was awarded the contract for construction of school building and accordingly Construction Contract dated 9 February 2018 was executed between Petitioner and Respondent. Under the Contract, the Petitioner was to construct a school building on the land for contract value of Rs.23,40,00,000/-, which was payable in a phased manner depending on the progress of construction. The revised plans by granting FSI 4.00 were approved by the MCGM on 28 May 2019. The MCGM also sanctioned proportionate fungible FSI to the extent of 35%. This is how 8 storey building was proposed to be constructed on the plot. Petitioner alleges that the Respondent took forcible possession of the building even before issuance of occupation certificate, which necessitated filing of Application under Section 9 of the Arbitration Act by the Petitioner.
13) According to the Petitioner, substantial amount was due and payable to it from the Respondent under the Construction Contract and that an additional amount of Rs.88,00,000/- still remained unpaid under the Conveyance Deed. The Petitioner claims that though much higher amounts were due and payable by the Respondent to it, the Respondent admitted liability only in respect of Rs.7.75 crores by letter dated 12 August 2021 and agreed to pay the same within one month of receipt of occupation certificate. The Petitioner also relies on undated letter issued after letter dated 12 August 2021 under which the Respondent once again admitted liability for the sum of Rs.7.75 crores.
27 January 2026
Megha 2_carbpl_33334_2024_fc.docx
It was stated in the said undated letter that an amount of Rs.1 crore was paid through RTGS and balance amount payable was Rs.6.75 crores. According to the Petitioner, two cheques in the sum of Rs.2 crores and Rs.4,36,42,078/- were issued after deducting amount of Rs.38,57,922/- towards TDS. According to the Petitioner, while the amount of Rs.2 crores was paid by RTGS, the cheque in the sum of Rs.4,36,42,078/- got dishonoured.
14) It is on the strength of letter dated 12 August 2021 coupled with the undated letter that the Petitioner claims that at least sum of Rs.4,36,42,078/- ought to have been awarded by the Arbitral Tribunal. However, what is done by the Tribunal is that it took into consideration the value of the work performed under the contract and deducted various amounts received by the Petitioner from the Respondent for the purpose of determining Petitioner's entitlement to balance amount. This is how Petitioner's entitlement is restricted to Rs. 1,75,38,857/-. However, after deducting the amount sanctioned to the Respondent in the counterclaim of Rs. 99,91,472/-, the Tribunal has awarded net amount of Rs.75,47,385/- in Petitioner's favour.
15) The Petitioner filed claim before the Arbitral Tribunal claiming an amount of Rs.7,96,00,000/-. It would be apposite to consider the breakup of the said amount of Rs.7,96,00,000/- as reflected in the particulars of claim, which reads thus:-
PARTICULARS OF CLAIM AND BREAK-UP OF OUTSTANDING AMOUNT:
SR PARTICULARS AMOUNT (in Rs.)
NO.
27 January 2026
Megha 2_carbpl_33334_2024_fc.docx
CONVEYANCE DEED
1. Total Amount payable by the Respondent to
the Claimant under the Conveyance Deed 15 Crores 50 Lakhs
dated 22.12.2017
2. Total Amount paid by the Respondent to the
Claimant under the Conveyance Deed dated 14 Crores 62 lakhs
22.12.2017
3. TOTAL AMOUNT OUTSTANDING 88 Lakhs
CONSTRUCTION CONTRACT
4. Total Amount payable by the Respondent to 23 Crores 40 Lakhs
the Claimant under the Construction
Contract dated 9th February 2018
5. Total Amount payable by the Respondent to 23 Crores 40 Lakhs + 4
the Claimant under the Construction Crores 21 Lakhs=
Contract dated 9th February 2018 alongwtih
GST amount of 18% (i.e. Rs.4 cores 21
Lakhs) 27 Crores 61 Lakhs
6. Total Amount paid by the Respondent under 18 Crores 86 Lakhs
the Construction Contract dated 9th February
7. Under clause 7 of the Construction Contract 78 Lakhs 78 Thousand dated 9th February 2018, the same deductions will be given to the Respondent, as the said amount was to be paid by the Claimant:
Particulars Amount
Scrutiny fees Rs.1.50 Lakhs
IOD Deposit 0.50 Lakhs
Debris Deposit 1 Lakh
Staircase Premium 30.21 lakhs
Open space premium 20 Lakhs
Labour welfare 25.57 lakhs
Total 78.78 lakhs
8. Total Outstanding amount payable by the 7 Crore 96 Lakhs
Respondent To the Claimant under the
Construction Contract Dated 9th February
2018 will be:
Total Amount payable Rs. 27 Crores 61 lakhs
(sr.No.5):
Minus Rs.18 Crores 86 Lakhs
Total amount paid by
Respondent (sr.no.6):
Minus 78 Lakhs 78 Thousand
Deductions available
27 January 2026
Megha 2_carbpl_33334_2024_fc.docx
to the Respondent
(sr.no.7)
Total Rs.7 crore 96 Lakhs
OUTSTANDING:
Sr. No.5-(sr.no.6
and7)=
9. Total Amount payable under both Rs.43 crores 11 lakhs
Agreements cumulatively:
Sr.No.1+Sr.No.5
10.Total amount received from Respondent 33 Crores 48 Lakhs
under both Agreement
16) Thus, as per the particulars of claim, Petitioner claimed
that an amount of Rs.88,00,000/- was outstanding under Conveyance Deed dated 22 December 2017. In respect of Construction Contract, the total amount due and payable by the Respondent was indicated as Rs.23.40 crores and adding after 18% GST, the said amount was worked out to Rs.27,61,00,000/-. According to the Petitioner the amount paid by the Respondent was Rs.18.86 crores. The Petitioner also gave credit in the sum of Rs.78,78,000/- to the Respondent and this is how it claimed total amount of Rs.7,96,00,000/-. The prayers in the Statement of Claim raised by the Petitioner read thus:-
a) that the Arbitral Tribunal be pleased to pass an order of permanent injunction against the Respondents, its members, servants and agents restraining them in any manner from occupying the said school building and/or conducting any activity of whatsoever nature in the said school building till the time balance consideration under the Agreement dated 9 th February, 2018 is paid to the Claimant by the Respondent.
b) That the Arbitral Tribunal be pleased to order and decree against the Respondent that a sum of Rs.7,96,00,000/- (Rupees SevenCrores Ninety Six Lakhs) be payable to Claimants along with 18% interest till realization of the same.
17) However, it appears that the Petitioner mainly pressed its claim before the Arbitral Tribunal in the sum of Rs.4,36,42,078/- based
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
on letter dated 12 August 2021. Before considering the effect of the letter dated 12 August 2021, it would be necessary to note the fact that the Respondent had attempted to raise the defence of forgery in the said letter. However, the defence of forgery in the letter dated 12 August 2021 has been rejected by the Arbitral Tribunal. The Tribunal also rejected the defence of the Respondent that it was pressurised by the Claimant/Petitioner to issue letter dated 12 August 2021.
18) Coming back to the effect of the letter dated 12 August 2021, the same is extracted below for the facility of reference:-
PRATIKSHA FOUNDATION CHARITABLE TRUST (A Jain Minority Trust)
12th August 2021
To, Kanti Builders (P) Limited, Utopia Vity, P.B. Marg, Worli, Mumbai- 400013.
Sub: Confirmation of Full & Final Outstandings.
Sir,
We refer to the Conveyance Deed and Construction Agreement signed with you for construction of our school project located at property bearing CTS No.374 B/10 of village Eksar, Borivali West. Post our personal meeting for account settlement, we herewith confirm the following:
1. The entire payment towards the Conveyance Deed has been fully paid up.
2. A net balance of Rs.7.75 crores (Seven Crores Seventy Five Lacs only) is payable by us towards full and final payment towards construction agreement full and final outstanding dues. (this includes GST, extra work payment, extra steel payment and interest on delayed payments, if any)
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
As agreed, we shall clear the above outstanding payment within one month of receipt of Occupation Certificate.
We also look forward to your assistance, as assured by you, in claiming the excess premium amount paid to MCGM under your instructions worth Rs.12350800/- (Rupees One crore twenty three lacs fifty thousand eight hundred only).
We acknowledge your support and cooperation in completing our school project and look forward to associate with you in the near future for our other forthcoming projects.
Thanking you,
For Witty Enterprises(P) Limited For Pratiksha Foundation
Charitable Trust
sd/- sd/-
Dr. Vinay Jain Dr. Vinay Jain
Director Director
19) Thus, letter dated 12 August 2021 refers to both,
Conveyance Deed as well as Construction Agreement and recorded that the entire payment towards Conveyance Deed was fully paid and net balance of Rs.7.75 crores was due and payable towards Construction Agreement. The letter recorded that the net balance payment of Rs.7.75 crores represented not only full and final payment under the Construction Agreement, but also included payment towards GST, extra work payment, extra steel payment and interest on delayed payments.
20) The Petitioner also relied upon another undated letter issued by the Respondent, which reads thus:
To M/s. Kanti Builders Pvt. Ltd.
Trade View, Utopia City, Pandurang Budhkar Marg, Worli, Mumbai- 400 013.
27 January 2026
Megha 2_carbpl_33334_2024_fc.docx
Sub: Registered Conveyance Deed dated 22nd December, 2017 ('the
said Agreement') in respect of properties bearing CTS Nos.
374B/10 and CTS Nos. 374B/9 of Village Eksar, Borivali (West) reserved for Secondary School and Play-Ground respectively and Construction Contract dated 9 th February, 2018 for construction of School Building thereon.
Ref: Order dated 11 March, 2021 in Arbitration Petition (L) No.186 of 2021 passed by the Hon'ble High Court at Mumbai.
Dear Sir,
1. You are aware that the considerations as agreed under the aforesaid Agreements entered between ourselves and yourselves were to be paid in installments as recorded therein. Accordingly we have been making payments in installments as per the aforesaid Agreements.
2. Thus, by way of this letter we acknowledge that the balance amount payable was Rs.7.75 Crores under the aforesaid Agreements out of which we have paid an amount of Rs.1 Crore through ICICI Bank RTGS No.ICICR22021110800008968 dated 08.11.2021 leaving balance of Rs.6.75 Crores.
3. We have through our Architect have applied for Occupation Certificate for the completed school building which shall be obtained by us at our risks and costs.
4. Thus, we are enclosing herewith the postdated cheques towards full and final payment of entire balance as under:
Sr. Cheque No. Drawn on Dated Amount (Rs)
No.
1000843 ICICI BANK 15.12.2021 2,00,00,000
2000844 ICICI BANK 30.12.2021 4,36,42,078
TDS Amount 38,57,922
Total Amount 67,500,000
5. You are kindly requested to co-operate.
Thanking you, yours faithfully
Witty Enterprises P. Ltd.
Authorised Signatory
21) The liability of Rs.7.75 crores is shown to have been
discharged in the undated letter by paying Rs.1 Crore through RTGS
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
and by issuing two cheques for Rs.2 Crores and Rs.4,36,42,078/- after deducting TDS amount of Rs.38,57,922/-. According to the Petitioner the amount of Rs.2 crores is satisfied by RTGS payment by the Respondent and cheque for amount of Rs.4,36,42,078/- got dishonoured. According to the Petitioner therefore, an amount of Rs.4,36,42,078/- remained due and payable by the Respondent to the Petitioner. If the Petitioner was confident that what was due and payable under the Construction Contract was only Rs.4,36,42,078/- it ought to have based its claim on the two letters and ought to have claimed only the amount of Rs.4,36,42,078/-. However, far from providing particulars of break-up of amount of Rs.7.75 crores as reflected in the undated letter, the Petitioner decided to press its claim for having executed total work worth Rs.27,61,00,000/- and after deducting the amount of Rs.18,86,00,000/- paid by the Respondent claimed balance Rs.7,96,00,000/- (which figure did not match with the total figure of 7.75 crores reflected in the letter dated 12 August 2021 or the alleged balance figure of Rs.4,36,42,078 reflected in the undated letter). Thus, there is absolutely no match between the particulars filed alongwith the Statement of Claim and the particulars indicated in the undated letter.
22) In the light of the above peculiar position, no fault can be found in the following findings of the Arbitral Tribunal in paragraph 272 of the Award:
272. While considering this alternate claim made by the Claimant, it is noticed that there is no specific alternate prayer to the extent of the claim of Rs.4,36,42,078/-, in the Statement of Claim. It is also to be noted that Claimant has filed Commercial Suit No. 37961 of 2022 against the Respondent to recover dues of Rs. 88 lakh plus
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
interest which arises under the said conveyance. Lack of such prayer, is not an embargo for considering a claim for lesser amount than made at prayer clause (b) to the SOC.
23) In my view, the Petitioner was required to make a conscious choice in respect of its claim. It could have either claimed (i) the alleged admitted sum in the letter dated 12 August 2021 together with undated letter or (ii) could have given particulars of due amount as per work executed and after deducting the paid amount, could have claimed the balance sum. The Petitioner made a conscious choice of not claiming former sum but claimed only the latter sum. Having done so, the Tribunal cannot be found fault with for having adjudicated the claim in the manner in which the same was presented before it. Perusal of the Awards would indicate that the Tribunal has taken into consideration the amount of contract value and has deducted the amount already paid to the Respondent and this is how the sum payable to the Respondent is arrived at Rs.1,75,38,857/-. I do not find any patent error in this exercise undertaken by the Arbitral Tribunal.
24) Mr. Kanade has strenuously contended that the Arbitral Tribunal has erroneously considered only the undated letter for holding that the amount of Rs. 7.75 crores reflected therein was in respect of both the contracts. In my view, it is not necessary to go into this aspect particularly because the Petitioner never based its claim merely on the basis of alleged admission in the two letters. Though some reference is to be found to the letters in paragraph 5(xvii) of the Statement of Claim, it is more than apparent that the Claimant ultimately pressed claim for Rs. 7,96,00,000/-, which was not based on alleged admitted figure, but based on quantum of work allegedly performed. In this
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
regard, it would be apposite to reproduce paragraph 5(xvii) of the Statement of Claim:
xvii) The Claimant submits that the amount payable under the construction Contract was much more but the Respondent admitted its liability towards payment of Rs.7,75,00,000/- (Rupees Seven Crores Seventy Five Lakhs Only). On 12th August, 2021 the Respondent vide a letter admitted its liability of Rs.7,75,00,000/-
as full and final payment towards Construction Agreement. The letter further recorded that the same will be cleared within 1 month from the date of receiving the Occupation Certificate. Thereafter, the Respondent addressed another letter to Claimant and again acknowledged its liability for payment of Rs.7.75 Crores. Along with the said letter the Respondent made a stamen that 1 crore is paid by RTGS and balance 6.75 crores will be paid in two installments. Two cheques were also attached to the said letter. The first cheque was of Rs.2 Cores bearing Cheque 000843 drawn on ICICI bank which was dated 15th December 2021. The second cheque was of Rs.4,36,42,078/- (Rupees Four Crores Thirty Six Lakhs Forty Two Thousand Seventy Eight Only) bearing cheque No.000844 dated 30th December, 2021 drawn on ICICI Bank. As per the said letter an amount of Rs.38,57,922/- (Rupees Thirty Eight Lakhs Fifty Seven Nine Hundred Twenty Two Only) was deducted by Claimant towards TDS. The Respondent cleared the first amount of Rs.2 Crores by way of RTGS on or around the same date as mentioned in the cheque so the first cheque was not deposited. The cheque dated 30th December, 2021 of Rs.4,36,42,078/- (Rupees Four Crores Thirty Six Lakhs Forty Two Thousand Seventy Eight Only) was dishonored. In complete disregard to the Order passed by Hon'ble Bombay Court. The Claimant states that the balance consideration payable as of today is Rs. 7,96,00,000/- (Rupees Seven Crores Ninety Six Lakhs). The claimant has attached the list of the entire schedule of amount receivable under the construction contract with the compilation of documents.
25) Having himself not pressed the claim before the learned Arbitrator only on the basis of alleged admissions in the two letters, Petitioner cannot now criticise the Tribunal for not granting any relief in terms of alleged admissions. Also of relevance is the fact that the Petitioner led no evidence to prove execution of any extra work under the Construction Contract. After appreciation of evidence, the Tribunal
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
has arrived at a conclusion that total work performed under the contract by the Petitioner was only Rs.21,15,00,000/-. Nothing is brought to my notice, nor any submission is raised to demonstrate any perversity in the said finding. Therefore, Petitioner's claim of having executed any extra work cannot be accepted in absence of evidence on record. The Petitioner has also not pointed out any error in the figure of Rs.19,26,25,872/- treated as having paid by the Respondent to the Petitioner under Construction Contract. As per the particulars of claim presented by the Petitioner, credit was required to be given to the Respondent in respect of certain amounts. After undertaking the above exercise, the Tribunal has rightly held that total sum payable by the Respondent to the Petitioner was only Rs.1,75,38,857/-. Thus, the Tribunal has conducted a factual enquiry about the actual work performed by the Petitioner and exact amount it received from the Respondent. In the light of above exercise undertaken by the Tribunal, it cannot be contended that there is any element of perversity on the part of the Tribunal only on account of figures reflected in letter dated 12 August 2021 and the undated letter.
26) I am therefore of the view that no interference is warranted in the impugned Award in not awarding the claim of the Petitioner in the sum of Rs.4,36,42,078/-.
27) So far as sanction of counterclaim of the Respondent in the sum of Rs.2,09,47,700/- is concerned, the same is sought to be challenged on the ground that payment of development cess and development charges was the responsibility of the Respondent. The Tribunal has considered the position that originally the FSI in respect
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
of the land was 1.00. The Tribunal also considered the position that for availing FSI 4.00 certain amounts were required to be paid as premiums to the MCGM. Under the Construction Contract, it was agreed that all other payments except for fungible FSI and additional FSI were to be paid by the Petitioner. After considering the effect of clauses 7.3 and 8.7 and clause 13 of Annexure-A of the Construction Contract, the Arbitral Tribunal has arrived at a conclusion that it was the responsibility of the Petitioner to pay development charges and development cess. The above interpretation of the Arbitral Tribunal of contractual clauses does not suffer from any patent illegality. It is well settled position that interpretation of contractual stipulations is in the exclusive domain of the Arbitral Tribunal and even if any error is committed in the interpretation, such error is within the jurisdiction of the Tribunal. The interpretation of the contractual clauses by the Arbitral Tribunal is not something which no fair-minded would undertake. It is a plausible interpretation. In my view, therefore, no case is made out for interference in the award of counterclaim in favour of the Respondent.
28) Considering the overall conspectus of the case, I am of the view that the Petitioner has failed to make out any of the enumerated grounds under Section 34 of the Arbitration Act for laying a valid ground of challenge to the impugned Award. The Arbitral Tribunal has considered the evidence on record and has thereafter arrived at a conclusion that the Petitioner must receive only the amount due and payable under the contract. The Tribunal is rightly not got swayed by alleged admissions contained in the letter dated 12 August 2021 and undated letter. Instead, it has committed an indepth exercise to
27 January 2026 Megha 2_carbpl_33334_2024_fc.docx
examine the exact liability of the Respondent to pay amounts under the Construction Contract. The Tribunal has objectively decided the issue before it by adjudicating the claims of the Petitioner in the manner in which they were pleaded and pressed before it. Merely because another method of adjudication may also be possible by considering the only effect of alleged admissions in the two letters, it cannot be contended that the view taken by the Arbitral Tribunal is such that no fair-minded person would ever adopt the same.
29) In my view therefore, the impugned Award is unexceptional warranting dismissal of the Petition. The Commercial Arbitration Petition is accordingly dismissed.
30) Considering the peculiar facts and circumstances of the case, I deem it appropriate not to award any further costs in favour of the Respondent.
31) In view of dismissal of the Commercial Arbitration Petition, nothing survives to be adjudicated in the Interim Application and the same is accordingly disposed of.
[SANDEEP V. MARNE, J.].
Signed by: Megha S. Parab
Designation: PA To Honourable Judge 27 January 2026 Date: 27/01/2026 16:57:22
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!