Citation : 2026 Latest Caselaw 388 Bom
Judgement Date : 17 January, 2026
2026:BHC-AUG:1677-DB
IN THE JUDICATURE OF HIGH COURT AT BOMBAY
BENCH AT AURANGABAD
COMMERCIAL APPEAL NO.09 OF 2019
1. Executive Director,
G.M.I.D.C. Sinchan Bhavan, Aurangabad.
2. Chief Engineer and Chief Administrator,
C.A.D.A. at Aurangabad.
3. Superintendent Engineer,
J.P.C at Aurangabad.
4. Executive Engineer,
Jalna irrigation Division, Jalna. ...Appellant.
(Original Respondent No.2,3,4,5)
VERSUS
1. M/s Gurunanak Industries,
Now G.N.I. Infrastructure Pvt. Ltd.
Through Khushbirsing Basantsing Bindra
Age 63 years, R/o 5/29 Kranti Chowk Aurangabad.
(Orig.Plaintiff)
2. The State of Maharashtra,
Through The Collector, Jalna. ...Respondents
.....
Advocate for Appellate : Mr. S. G. Bhalerao
Advocate for Respondent No.1 : Mr. A. P. Bhandari
AGP for Respondent No.2. : Mr. A. R. Kale
.....
CORAM : ARUN R. PEDNEKER AND
VAISHALI PATIL-JADHAV, JJ.
Date of Reserving the Judgment : 08/01/2026
Date of Pronouncing the Judgment : 17/01/2026
JUDGMENT :
( Per ARUN R. PEDNEKER, J. )
1. The present Commercial Appeal is filed by the original defendants, who
are aggrieved by and dissatisfied with the judgment and decree dated
09/08/2019, passed by the learned District Judge-1, Jalna, in Commercial Suit
Com Appeal 9-2019
No. 08 of 2019, whereby the suit for recovery of an amount of
Rs.5,76,25,112/-, along with interest at the rate of 15% per annum from
the date of filing of the suit till realisation is decreed.
2. Heard the learned Counsel Mr. S. G. Bhalerao for the appellants, the
learned Counsel Mr. A. P. Bhandari for respondent No.1 and the learned AGP
Mr. A. R. Kale for respondent No.2-State.
FACTS :
3. The case of the plaintiff, as pleaded in the plaint, in brief, is as
follows :
The original defendants invited tenders for the construction work of
"Nimna Dudhana Project - Earthen Dam, Chainages 580 to 2810 meters"
situated in Jalna District. The plaintiff emerged as the lowest bidder and
was awarded the contract by Defendant No.5 on 16/03/1995. The
stipulated period for completion of the work was 24 calendar months, i.e.
up to 15/03/1997.
4. The estimated cost of the work was Rs.2,09,92,740/-, whereas the
accepted contract value was Rs.2,80,25,309/-. The plaintiff furnished an
advance security deposit of Rs.2,80,253/- by way of bank guarantee as per
the contractual conditions.
Com Appeal 9-2019
5. Although the contractual period was initially 24 months, extensions
of time were granted from time to time, ultimately extending the period up
to 30/06/2003. During execution, additional work relating to excavation and
masonry dam from Chainage 2810 meters to 3040 meters was attached to
the original work, and the time for completion was correspondingly
extended.
6. It is the plaintiff's case that the site was not made available in its
entirety within a reasonable time, owing to which further extensions
became necessary. The plaintiff relies upon the Price Variation Clause
(Clause No.56 at Page 80 of the Tender), which permits escalation or
deduction in the contract price on account of variation in labour, material,
and fuel costs during the operative period of the contract, as calculated in
accordance with the prescribed formula.
7. The plaintiff asserts that the work was completed on 30/06/2013,
and the final measurements were recorded and the last Running Account
(R.A.) Bill was drawn on 12/04/2016. According to the plaintiff, excess
quantities had to be executed due to erroneous and inadequate
assumptions at the time of floating the tender.
8. Despite repeated requests since 2016, the defendants allegedly
failed to release the balance amount. The total outstanding amount
Com Appeal 9-2019
payable under the tender terms was claimed to be Rs.10,02,91,108/-,
whereas the defendants paid only Rs.4,26,65,996/- by cheque in the year
2016 . According to the plaintiff, the defendants failed to pay the correct
escalation amount as per Clause 56, leaving a balance of Rs.5,76,25,112/-,
which compelled the plaintiff to institute the suit. Thus Commercial Civil
Suit was filed by the respondents (original plaintiffs) seeking recovery of
compensation amounting to Rs.5,76,25,112/-, together with interest at the
rate of 24% per annum from the last date of payment, i.e. 12/04/2016.
9. The suit is contested by the defendants / present appellants by filing
a written statement. It is the case of the defendants that the department
granted extensions of time solely with the intention of enabling completion
of the tender work, as the progress of the work was not as expeditious as
agreed.
10. It is stated that after issuance of the work order and upon
completion of the work by the plaintiff, the defendants, after recording
measurements, made payments to the plaintiff from time to time. The
defendants tendered and paid all Running Account (R.A.) Bills. According to
the defendants, the plaintiff has intentionally misinterpreted Clause 56 of
the tender document.
11. It is further stated that there was a mutual agreement between the
Com Appeal 9-2019
parties and that, even as per Special Condition No. 4.41 of the tender
(Tender Page No. 38), read with Clause 10 of the B-1 Form, payments of
Running bills were to be made monthly, subject to availability of funds for
the work under the contract. The defendants contend that from time to
time they paid R.A. Bills after taking into consideration the price escalation
amounts. The plaintiff never raised any objection from the 1 st R.A. Bill till
the 56th R.A. Bill and accepted the amounts after verification of all R.A. Bills.
12. It is further pleaded that the period under consideration for price
variation under Clause 56 is from the date of commencement of the work,
i.e., from the date of the work order to the first R.A. Bill, and that the
calculation of price variation for this period is required to be on the basis of
the average of indices for the said period. For the second and subsequent
R.A. Bills, the period under consideration is from the date of payment of the
first R.A. Bill to the second R.A. Bill, and similarly for the remaining R.A. Bills
up to the final payment.
13. The defendants assert that from the 1st R.A. Bill to the 56th R.A. Bill
(covering the period from the year 1994 to 2013), the contractor accepted
all payments over a long period of nearly 20 years and has now, for the
first time, raised a claim towards price variation without any right or
justification.
Com Appeal 9-2019
14. It is further explained that "price variation" is intended to
compensate the contractor in accordance with inflation in labour, material,
and fuel prices prevailing in the market. The said clause operates both
ways. If the variation in the Wholesale Price Index (New Series) or the price
of High-Speed Diesel (H.S.D.) for Bombay is on the positive side, payment
on account of price variation is to be allowed to the contractor; however, if
it is on the negative side, the Government is entitled to recover the same
from the contractor, and such amount is deductible from the contractor's
bill for the respective period during which fluctuations occur.
15. According to the defendants, the scheme of Clause 56 clearly
indicates that escalation is taken into consideration while processing and
paying each R.A. Bill. The plaintiff accepted the payments up to the 56th
R.A. Bill, and the present dispute has been raised only at the stage of the
final bill i.e. 57th bill seeking recalculation of price variation for the last 20
years.
16. On the basis of the pleadings, the Commercial Court framed the
following issues and recorded findings as under :
Issues Findings
1 Whether the plaintiff proves that defendants
did not make full payment of work done and Yes.
made only part payment ?
2 Whether plaintiff proves his calculation of
suit amount is as per Clause No.56 of the Yes.
Com Appeal 9-2019
tender document?
3 Whether plaintiff proves its interpretation is
correct and legal while referring to period Yes.
under consideration for the calculation of
the price escalation ?
4 Whether plaintiff is entitled to recover an
amount of Rs.5,76,25,112/- as per price Yes.
escalation clause and as per work done ?
5 Whether plaintiff is entitled for interest on Yes, @ 15% p.a.
suit amount or balance amount, if yes, at
what rate ?
6 Whether plaintiff is entitled for 30 %
additional amount of contract for breach of No.
contract by defendants ?
7 Whether plaintiff proves that it is entitled to
10 % additional amount of outstanding No.
balance towards loss of overhead charges ?
8 Whether the plaintiff is entitled for Rs.10
lacs towards cost of this litigation ? No.
The Commercial Court held that the defendants failed to make full
payment in accordance with Clause 56 and decreed the suit accordingly.
Present Commercial Appeal is filed challenging the Judgment and decree of
the Commercial Court.
17. The learned Counsel for the appellants submits that when the matter
was argued before this Court, this Court, by order dated 24/02/2025,
observed that the work executed by the plaintiff was completed on
30/06/2013, whereas the suit was instituted on 21/12/2017. It was prima
facie observed that the suit would be governed by Article 18 of the First
Com Appeal 9-2019
Division of the Schedule to the Limitation Act, 1963, falling under the
category of "a suit for the price of work done by the plaintiff for the
defendant at his request, where no time has been fixed for payment."
18. It was further observed that the plaint did not disclose as to how the
suit was within the prescribed period of limitation, except stating that the
last Running Account Bill was measured and drawn on 12/04/2016. The
memorandum of appeal also contained a specific plea that the suit was
barred by limitation.
19. In view thereof, this Court directed the Commercial Court, Jalna, to
frame an issue on limitation and to decide the same in accordance with
law, after granting both parties an opportunity to lead additional evidence.
However, the parties were expressly restrained from amending their
pleadings.
20. Pursuant to the said directions, the Commercial Court framed the
issue on limitation and answered the same in favour of the plaintiff.
Thereafter, the appellants filed Civil Application No.11305 of 2025, seeking
permission to amend Commercial Appeal No.9 of 2019 so as to challenge
the order dated 14/05/2025 passed by the District Judge, Jalna, in
Commercial Suit No.8 of 2019, and to place the relevant supporting
documents on record. The said application came to be allowed by this
Com Appeal 9-2019
Court by order dated 07/01/2026.
21. The appellants/original defendants have challenged the judgment of
the Commercial Court primarily on two grounds. Firstly, it is contended that
the suit is barred by limitation. The learned Counsel for the appellants
submits that the contractual work was completed on 30/06/2013, and
therefore, the period of limitation commenced from the date of completion
of the work. Merely because the final payment under R.A. Bill No.57 was
paid in the year 2016, the same cannot extend the period of limitation. It is
urged that the suit instituted in 2017 is clearly barred, inasmuch as Article
18 of the Schedule to the Limitation Act, 1963, prescribes a period of three
years for filing a suit for the price of work done, reckoned from the date of
completion of the work.
22. On the issue of limitation, the learned Counsel for the appellants
places reliance on the judgment of this Court at the Principal Seat in
Arbitration Appeal No.6 of 2007 (State of Maharashtra v. Hindustan
Construction Company Ltd. & Anr.), decided on 01/02/2013.
23. The learned Counsel for respondents submits that Section 19 of the
Limitation Act squarely governs the issue in the present case. He contends
that although the work was completed earlier, the final payment under R.A.
Bill No.57 was made on 12/04/2016, and therefore, the period of limitation
Com Appeal 9-2019
commenced from the said date. On this premise, it is urged that the suit
instituted in the year 2017 is well within the prescribed period of limitation.
24. It is submitted that the present suit is not merely for "work done",
but for non-payment of the legally payable escalation amount, which could
be finally determined only upon preparation and payment of the final
Running Account Bill. Admittedly, the last R.A. Bill (No.57) was measured
and payment was released on 12/04/2016, and only thereafter did the
cause of action crystallise. The learned Counsel further submits that so
long as the final bill was not prepared and paid, the account between the
parties remained open and unsettled. The right to sue accrued only when
the appellants refused to pay the correct escalation amount despite
repeated demands made in the year 2016 and thereafter. The respondent
further submits that the appellants' reliance on Article 18 of the Limitation
Act, 1963 is misplaced. Even assuming Article 18 applies, the phrase "when
the work is done" must be read in conjunction with the contractual
obligation to finalise and pay the final bill, particularly where escalation is
an integral part of the consideration.
25. Secondly, the learned Counsel for the appellants submits that the
Commercial Court has erroneously interpreted Clause 56 of the tender
document relating to price escalation. According to the appellants,
escalation amounts were computed and included in each Running Account
Com Appeal 9-2019
Bill from R.A. Bill No.1 to R.A. Bill No.56 for the period between 1995 and
2013, and the final escalation amount was also adjusted in the final bill.
The plaintiff accepted all the R.A. Bills without demur. Having accepted the
payments over the entire contractual period, it is not open to the plaintiff
to recompute price escalation by taking an average from the date of
commencement of the contract till the final date of payment and thereby
claim an additional amount of Rs.5,76,25,112/-, which is contrary to the
contractual stipulations.
26. As regards the payment and computation of escalation, it is
submitted that there is no dispute concerning the correctness of the
individual Running Account Bills. According to the appellants/ defendants,
price escalation under Clause 56 is required to be computed with reference
to the cost of work done during the relevant period of each bill and, at the
minimum, contemporaneously at the time of payment of each Running
Account Bill. This, it is submitted, is the contractual scheme contemplated
under the tender, and the same has been followed throughout. The final
decretal amount, therefore, could not have been arrived at by recomputing
escalation for the entire contractual period at the end of the work.
POINTS FOR DETERMINATION :
27. Having considered the rival submissions, the following points arise
for determination :
Com Appeal 9-2019
(1) Whether the suit filed by the respondent / plaintiff is within the stipulated period of limitation ?
And : ......Yes.
(2) Whether the appellants / defendants have paid the amount towards "price escalation" in the the respective R. A. Bills No. 1 st to 57th accordance with Clause 56 of the Agreement ?
Ans : ......Yes.
DISCUSSION & REASONS :
POINT NO. 1 :
28. In paragraph No.13 of the plaint, the plaintiff has stated that the
work was executed and completed on 30/06/2013. It is further stated that
the last Running Account (R.A.) Bill was measured and drawn on
12/04/2016, and that the plaintiff requested the defendants to release the
balance payment in the year 2016. According to the plaintiff, the total
balance amount payable under the contract was Rs.10,02,91,108/-, out of
which Defendant No.5 paid only Rs.4,26,65,996/- by cheque, thereby failing
to pay the price escalation amount in accordance with the tender
conditions.
29. It is further pleaded that on 29/05/2017, the plaintiff addressed a
letter to Defendant No.5 calling upon it to release the final bill amount.
Com Appeal 9-2019
However, Defendant No.5 replied by denying liability and refused to act in
accordance with the tender terms. Consequently, the plaintiff issued a
statutory notice dated 05/08/2017 under Section 80 of the Code of Civil
Procedure, 1908, and thereafter instituted the suit on 21/12/2017.
30. In the written statement, the defendants have contended,
particularly in paragraph No.11, that there was no subsisting demand from
the plaintiff, as Running Account Bills were settled from time to time after
taking into account the applicable price escalation. It is their case that the
plaintiff never raised any objection from the 1 st R.A. Bill till the 56th R.A. Bill
and accepted all payments after due verification. The defendants denied
that the amount of Rs.4,26,65,996/- was a part payment and asserted that
the same constituted full and final settlement. It is further contended that
the plaintiff did not accept the payment under protest.
31. The defendants have also relied upon Clause 56 of the tender
document, contending that the "period under consideration" for calculating
price variation is bill-specific. According to them, for the first R.A. Bill, the
period under consideration is from the date of commencement of work till
the first R.A. Bill, and for the second and subsequent R.A. Bills, it is from
the payment of the preceding R.A. Bill to the next R.A. Bill, and so on, up to
the final payment. It is submitted that from R.A. Bill No.1 to R.A. Bill No.57
Com Appeal 9-2019
(covering the period from 1994 to 2013), the contractor accepted all
payments over a span of nearly 20 years, and has now, belatedly, raised a
claim for additional price escalation without any contractual or legal basis.
32. Thus, the core issue that arises for consideration on the question of
limitation is the starting point of limitation.
33. Clause 10 of the contract provides that bills are to be submitted
monthly or on or before the date fixed by the Engineer-in-Charge. If the
contractor fails to submit the bill within the stipulated time, the Engineer-
in-Charge is empowered to measure the work and prepare the bill. The bills
are required to be in printed form.
34. In the present case, R.A. Bills No.1st to 56 th were raised by the
plaintiff in accordance with the contract, and price escalation was granted
in each bill by applying the prescribed formula. These bills pertained to
specific periods during which the work was executed and price escalation
was computed and adjusted accordingly.
35. The defendants' witness, Surekha Bhimrao Korke, has stated that the
defendant issued a letter dated 30/01/2013 calling upon the contractor to
Com Appeal 9-2019
remain present on 06/02/2013 at 09.00 a.m. for taking final measurements
of the work done. However, neither the contractor nor his representative
remained present on the said date. It is pertinent to note that this assertion
does not find place in the pleadings.
36. It is further stated by the said witness that another letter dated
27/05/2013 was issued by the defendants calling upon the contractor to
remain present for accepting and acknowledging the final bill of the work
done. According to her, the contractor did not come forward to accept the
final bill. Consequently, on 01/07/2013, a letter was issued to Defendant
No.4 informing that the final measurement was carried out and that the
final bill, including the cost of price escalation, was prepared. It is stated
that although the contractor was informed, he did not respond for
acceptance of the final bill.
37. However, all the aforesaid facts were not pleaded in the written
statement, and evidence has been led on facts which are not part of the
pleadings. The said witness has, however, admitted that on 12/04/2016 the
final bill was paid and that the Letter of Credit (LOC) was received by their
office on 17/06/2016.
38. In the present case, the final bill was required to be settled after
completion of joint measurement of the work done. The same was
Com Appeal 9-2019
admittedly not settled on the alleged date of completion of work. There is
no specific pleading that the final bill stood settled on 30/06/2013. Bill
No.57 was paid on 12/04/2016, and there is no separate communication
indicating denial of any specific part of the said bill.
39. A running account bill, by its very nature, involves interim payments
made at specified intervals, depending upon the progress of the contract
works. A "running account" is account between parties having a series of
transactions, which remains open and is usually subject to settlement at
stated intervals. Such running account bills are only provisional in nature
and do not result in the final settlement of rights and liabilities between the
parties. There is no clause in the tender document to treat R. A. Bills as
final to the extent of work covered in the R.A. Bill. However, there is also
no clause to treat the payments made under R. A. Bills as advance till the
final bill. In absence of the above clauses we treat the R. A. Bills as interim
payment and the final settlement takes place only upon acceptance of the
final bill.
40. Article 18 of the Schedule to the Limitation Act, 1963 would apply
only where the amount payable is known and becomes payable on
completion of work. However, in the present case, although the physical
work may have been completed on 30/06/2013, the measurement of the
work and the escalated price was yet to be computed. The final bill was
Com Appeal 9-2019
required to be prepared after joint measurement and after working out the
escalation under the contractual clause. Therefore, limitation would
commence only upon denial or partial payment of the final bill which
occurred on 12/04/2016. The suit is filed on 21/12/2017 and is within
three years of payment of partial final bill and is thus within limitation and
would be covered under Article 55, of the Limitation Act.
POINT NO. 2 :
41. Coming to the next issue of price Escalation Claimed, namely,
whether the plaintiff is entitled to claim an amount of Rs.5,76,25,112/-
towards price escalation cost. For this purpose Clause 56 of tender
document provides for price variation clause.
42. Clause 56 of the tender document reads as under :
"Clause - 56 : PRICE VARIATION CLAUSE
I. If during the operative period of the contract as defined in condition (I) below, there shall be any variation in the consumer Price Index (new series) for IndusCommercial workers for Nanded Centre as per the Labour Gazette published by Commissioner of Labour, Government of Maharashtra and / or in the wholesale price index for all commodities prepared by the office of Economic Advisor, Ministry of Industry, Government of India, as compared to the respective figure therefore, on the date 30 days before the last date prescribed for receipt of tender and / or in the prices of petrol/ oil and lubricant, then subjects to the other conditions mentioned below, price adjustment on account of (I) Labour Component (ii) Material component and (iii) POL components, which respectively are 68%, 27% and 6%and of the total cost of work put to tender calculated as per the formula hereinafter appearing, shall be made. (Total of all these three components will be 100)
Com Appeal 9-2019
(A) Formula for labour component :
VI = 0.85 | P-Cost of Schedule 'A' I | | K1 C1-CO|
| materials used | X | --- x ------ |
| | | 100 CO |
Where,
VI = Amount of price variation in Rupees to be allowed.
P = Cost of work done during the period under consideration K1= Percentage of Labour Component as indicated above. CO= Basic consumer price index for Nanded center ascertained as above on the date 30 days preceding the last date prescribed for receipt of tender.
C1= Average Consumer Price Index for Nanded Centre ascertained as above during the period under consideration.
(B) Formula for materials component :
V2 = 0.85 | P-Cost of Schedule | | | K2 |1-10 |
| 'A' materials used | X | | -- x ---- |
| | | | 100 | 0 |
Where,
V2 = Amount of Price variation in rupees to be allowed.
P = Cost of work done during the period under
consideration
K2 = Percentage of material component as indicated above. | 0 = Basic wholesale Price index ascertained as above on the date 30 days preceding the last date prescribed for receipt of tender. | 1 = Average wholesale price Index ascertained as above during the period under consideration.
(C) Formula for petrol, oil and lubricant component :
V3 = 0.85 | P-Cost of Schedule | | K3 PI-PO |
| 'A' material used | X | ---- X ------ |
| | | 100 PO |
Com Appeal 9-2019
Where,
V3 = Amount of price variation in Rupees to be allowed. P = Cost of work done during the period under consideration. K3 = Percentage of petrol, oil and lubricant component, PI = Average price of H.S.D. for Bombay during the period under consideration.
II. Conditions referred to in Paragraph - I
i) The operative period of the contract shall mean the period commencing from the date of the work order issued to the contractor and ending on the date when the time allowed for the work specified in the Memorandum under Tender for work expires, taking into consideration the extension of time, if any, for completion of the work granted by Engineer in charge under the relevant clause of the conditions of contract in cases other than those where such extension is necessiated on account of default of the contractor the decision of the Engineer-in-charge as regards the Operative period of the contract shall be final and binding on the contractor. Where compensation for liquidated damages is levied on the contractor on account of delay in completion or inadequate progress under the relevant contract provisions. The escalation amount for the balance work from the date of levy of such compensation shall be worked out by paging the indices C1 I-1 and P-1 to levels corresponding to the date form which such compensation is levied.
ii) This price variation clause shall be applicable to all contracts in B1, B2 and C forms but shall not apply for piece works.
iii) Price variation shall be calculated, in accordance with the formula mentioned above, separately for labour, material and POL components.
Com Appeal 9-2019
iv) The price variation under this clause shall not be payable for the extra items required to be executed during completion of the work and also on the excess quantities payable under the provisions of clause 38 / 37 of the contract from B1 / B2 respectively. Since the rates payable for the extra items or the extra quantities under clause 38 / 37 are to be fixed as per the current RSR or as mutually agreed, to yearly revision till completion of such work. In other words, when the completion/ execution of extra item as well as extra quantities under clause 38 / 37 of the contract form B1/ B2 extends beyond the operative date of the then R.S.R., the rates payable for the same beyond that date shall be revised with reference to the next current R.S.R. prevalent at that time on year to year basis or revised in accordance with mutual agreement thereon, as provided for in the contract, whichever is less.
v) This clause is operative both ways, i.e. if the price variation in the said wholesale price index for all commodities, consumer price index (New series) or price of HSD for Bombay is on the plus side, payment on account of the price variation shall be allowed to the contractor and if it is on the negative side, the Government shall be entitled to recover the same from the contractor and the amount shall be deductible from the Contractor's bill for the respective period in which there are fluctuations."
43. We find that Clause 56 provides distinct formulas for computation of
price variation under the labour component, material component, and
petrol, oil and lubricant (POL) component. Clause 56(II)(i) defines the
operative period of the contract to mean the period commencing from the
date of issuance of the work order to the contractor and ending on the date
when the time allowed for completion of the work, as specified in the
Com Appeal 9-2019
memorandum under the tender, expires, after taking into consideration
any extension of time granted by the Engineer-in-Charge under the
relevant contractual provisions, save and except extensions necessitated
on account of default of the contractor. The decision of the Engineer-in-
Charge as regards the operative period of the contract is declared to be
final and binding on the contractor.
44. The operative period of the contract and the period under
consideration for calculation of price variation are two distinct concepts.
The operative period refers to the entire duration of the work, commencing
from the date of issuance of the work order and ending with the completion
of the work, while period under consideration relates to the period covered
in the respective running bills.
45. The plaintiff's case is that escalation has to be worked out by taking
an average for the entire contract period. However, we find it difficult to
accept this submission. The formulas prescribed under Clause 56 for
labour, material and POL components specifically refer to the "cost of work
done during the period under consideration". The period under
consideration would naturally mean the period for which the R. A. Bill is
submitted. R. A. Bill includes the price variation for the period covered in
the R. A. Bill. The contractor is paid the R. A. Bill taking into consideration
Com Appeal 9-2019
the escalation in prices at the relevant time for the work done.
46. If the interpretation suggested by the plaintiff is accepted, the entire
escalation for nearly 20 years would have to be recomputed afresh by
treating the entire contract period as a single unit, i.e. from the date of
issuance of the work order till completion of the work, and thereafter
applying the prescribed formula for price escalation. Such an
interpretation is contrary to the scheme and purport of the contract. At
every stage of work undertaken, Running Account Bill is prepared and
escalation price is included in each Running Bill. The purpose of price
escalation clause is to protect the parties to the contract from market price
variations of the Labour, material and Oil components and not to make
windfall profit.
47. This conclusion is further reinforced by Clause II(iv) of the price
variation clause, which specifically provides that price variation shall not be
payable for extra items or excess quantities executed under Clauses 38
and 37 of the contract. In such cases, rates are to be fixed as per the
current Schedule of Rates (RSR) or as mutually agreed, with yearly
revision. Once prices are revised under Clauses 38 or 37, escalation under
Clause 56 is not separately applicable, as the revision already accounts for
the increase in cost.
48. Thus, wherever revision of rates has already been made due to
Com Appeal 9-2019
permissible variation exceeding 25%, escalation is not again applied.
However, where there is no such revision, escalation is to be worked out
Running Bill-wise for the period covered by the respective Running bills.
49. The argument that the entire operative period of the contract should
be taken as one unit and that escalation should be averaged over the
entire period is not supported by the language of Clause 56. The formulas
clearly mandate computation of escalation with reference to the period for
which each bill is raised.
50. In the present case, price escalation was granted and paid in each
R.A. Bills No.1 to 56. Even in R.A. Bill No.57, escalation for the relevant
period was computed and paid by the defendants. There is no error
pointed out in each individual R.A. Bill towards escalation price. The prices
of labour, material and oil as on the last date of work i.e. 20 years after
commencement of work cannot be the basis for calculation of price
escalation for the whole tender work. Escalation is worked out at each R.
A. Bill period. The plaintiff has, therefore, erroneously interpreted Clause
56 of the agreement, while submitting his final Bill.
CONCLUSION :
51. In view of the above discussion, we find that no case is made out for
grant of Rs.5,76,25,112/- towards escalation cost. Consequently, the
Com Appeal 9-2019
judgment and decree dated 09/08/2019 passed by the learned District
Judge-1, Jalna, in Commercial Suit No. 08 of 2019, deserves to be set aside
and is accordingly set aside.
52. The present Commercial Appeal filed by the original defendants is
allowed with costs. Decree be drawn up accordingly.
( VAISHALI PATIL-JADHAV, J. ) ( ARUN R. PEDNEKER, J. )
vj gawade/-.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!