Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Executive Director G.M.I.D.C. Sinchan ... vs M/S Gurunanak Industries Now G.N.I. ...
2026 Latest Caselaw 388 Bom

Citation : 2026 Latest Caselaw 388 Bom
Judgement Date : 17 January, 2026

[Cites 6, Cited by 0]

Bombay High Court

Executive Director G.M.I.D.C. Sinchan ... vs M/S Gurunanak Industries Now G.N.I. ... on 17 January, 2026

2026:BHC-AUG:1677-DB


                       IN THE JUDICATURE OF HIGH COURT AT BOMBAY
                                  BENCH AT AURANGABAD

                             COMMERCIAL APPEAL NO.09 OF 2019

           1.    Executive Director,
                 G.M.I.D.C. Sinchan Bhavan, Aurangabad.

           2.    Chief Engineer and Chief Administrator,
                 C.A.D.A. at Aurangabad.

           3.    Superintendent Engineer,
                 J.P.C at Aurangabad.

           4.    Executive Engineer,
                 Jalna irrigation Division, Jalna.                     ...Appellant.
                                                                (Original Respondent No.2,3,4,5)

                 VERSUS

           1.    M/s Gurunanak Industries,
                 Now G.N.I. Infrastructure Pvt. Ltd.
                 Through Khushbirsing Basantsing Bindra
                 Age 63 years, R/o 5/29 Kranti Chowk Aurangabad.
                                                      (Orig.Plaintiff)

           2.    The State of Maharashtra,
                 Through The Collector, Jalna.                        ...Respondents

                 .....
                 Advocate for Appellate       : Mr. S. G. Bhalerao
                 Advocate for Respondent No.1 : Mr. A. P. Bhandari
                 AGP for Respondent No.2.     : Mr. A. R. Kale
                 .....


                                             CORAM             : ARUN R. PEDNEKER AND
                                                                 VAISHALI PATIL-JADHAV, JJ.

                               Date of Reserving the Judgment                : 08/01/2026

                               Date of Pronouncing the Judgment : 17/01/2026

           JUDGMENT :

( Per ARUN R. PEDNEKER, J. )

1. The present Commercial Appeal is filed by the original defendants, who

are aggrieved by and dissatisfied with the judgment and decree dated

09/08/2019, passed by the learned District Judge-1, Jalna, in Commercial Suit

Com Appeal 9-2019

No. 08 of 2019, whereby the suit for recovery of an amount of

Rs.5,76,25,112/-, along with interest at the rate of 15% per annum from

the date of filing of the suit till realisation is decreed.

2. Heard the learned Counsel Mr. S. G. Bhalerao for the appellants, the

learned Counsel Mr. A. P. Bhandari for respondent No.1 and the learned AGP

Mr. A. R. Kale for respondent No.2-State.

FACTS :

3. The case of the plaintiff, as pleaded in the plaint, in brief, is as

follows :

The original defendants invited tenders for the construction work of

"Nimna Dudhana Project - Earthen Dam, Chainages 580 to 2810 meters"

situated in Jalna District. The plaintiff emerged as the lowest bidder and

was awarded the contract by Defendant No.5 on 16/03/1995. The

stipulated period for completion of the work was 24 calendar months, i.e.

up to 15/03/1997.

4. The estimated cost of the work was Rs.2,09,92,740/-, whereas the

accepted contract value was Rs.2,80,25,309/-. The plaintiff furnished an

advance security deposit of Rs.2,80,253/- by way of bank guarantee as per

the contractual conditions.

Com Appeal 9-2019

5. Although the contractual period was initially 24 months, extensions

of time were granted from time to time, ultimately extending the period up

to 30/06/2003. During execution, additional work relating to excavation and

masonry dam from Chainage 2810 meters to 3040 meters was attached to

the original work, and the time for completion was correspondingly

extended.

6. It is the plaintiff's case that the site was not made available in its

entirety within a reasonable time, owing to which further extensions

became necessary. The plaintiff relies upon the Price Variation Clause

(Clause No.56 at Page 80 of the Tender), which permits escalation or

deduction in the contract price on account of variation in labour, material,

and fuel costs during the operative period of the contract, as calculated in

accordance with the prescribed formula.

7. The plaintiff asserts that the work was completed on 30/06/2013,

and the final measurements were recorded and the last Running Account

(R.A.) Bill was drawn on 12/04/2016. According to the plaintiff, excess

quantities had to be executed due to erroneous and inadequate

assumptions at the time of floating the tender.

8. Despite repeated requests since 2016, the defendants allegedly

failed to release the balance amount. The total outstanding amount

Com Appeal 9-2019

payable under the tender terms was claimed to be Rs.10,02,91,108/-,

whereas the defendants paid only Rs.4,26,65,996/- by cheque in the year

2016 . According to the plaintiff, the defendants failed to pay the correct

escalation amount as per Clause 56, leaving a balance of Rs.5,76,25,112/-,

which compelled the plaintiff to institute the suit. Thus Commercial Civil

Suit was filed by the respondents (original plaintiffs) seeking recovery of

compensation amounting to Rs.5,76,25,112/-, together with interest at the

rate of 24% per annum from the last date of payment, i.e. 12/04/2016.

9. The suit is contested by the defendants / present appellants by filing

a written statement. It is the case of the defendants that the department

granted extensions of time solely with the intention of enabling completion

of the tender work, as the progress of the work was not as expeditious as

agreed.

10. It is stated that after issuance of the work order and upon

completion of the work by the plaintiff, the defendants, after recording

measurements, made payments to the plaintiff from time to time. The

defendants tendered and paid all Running Account (R.A.) Bills. According to

the defendants, the plaintiff has intentionally misinterpreted Clause 56 of

the tender document.

11. It is further stated that there was a mutual agreement between the

Com Appeal 9-2019

parties and that, even as per Special Condition No. 4.41 of the tender

(Tender Page No. 38), read with Clause 10 of the B-1 Form, payments of

Running bills were to be made monthly, subject to availability of funds for

the work under the contract. The defendants contend that from time to

time they paid R.A. Bills after taking into consideration the price escalation

amounts. The plaintiff never raised any objection from the 1 st R.A. Bill till

the 56th R.A. Bill and accepted the amounts after verification of all R.A. Bills.

12. It is further pleaded that the period under consideration for price

variation under Clause 56 is from the date of commencement of the work,

i.e., from the date of the work order to the first R.A. Bill, and that the

calculation of price variation for this period is required to be on the basis of

the average of indices for the said period. For the second and subsequent

R.A. Bills, the period under consideration is from the date of payment of the

first R.A. Bill to the second R.A. Bill, and similarly for the remaining R.A. Bills

up to the final payment.

13. The defendants assert that from the 1st R.A. Bill to the 56th R.A. Bill

(covering the period from the year 1994 to 2013), the contractor accepted

all payments over a long period of nearly 20 years and has now, for the

first time, raised a claim towards price variation without any right or

justification.

Com Appeal 9-2019

14. It is further explained that "price variation" is intended to

compensate the contractor in accordance with inflation in labour, material,

and fuel prices prevailing in the market. The said clause operates both

ways. If the variation in the Wholesale Price Index (New Series) or the price

of High-Speed Diesel (H.S.D.) for Bombay is on the positive side, payment

on account of price variation is to be allowed to the contractor; however, if

it is on the negative side, the Government is entitled to recover the same

from the contractor, and such amount is deductible from the contractor's

bill for the respective period during which fluctuations occur.

15. According to the defendants, the scheme of Clause 56 clearly

indicates that escalation is taken into consideration while processing and

paying each R.A. Bill. The plaintiff accepted the payments up to the 56th

R.A. Bill, and the present dispute has been raised only at the stage of the

final bill i.e. 57th bill seeking recalculation of price variation for the last 20

years.

16. On the basis of the pleadings, the Commercial Court framed the

following issues and recorded findings as under :

                                       Issues                        Findings

               1    Whether the plaintiff proves that defendants
                    did not make full payment of work done and         Yes.
                    made only part payment ?

               2    Whether plaintiff proves his calculation of
                    suit amount is as per Clause No.56 of the          Yes.


                                                                     Com Appeal 9-2019



                  tender document?

            3     Whether plaintiff proves its interpretation is
                  correct and legal while referring to period          Yes.
                  under consideration for the calculation of
                  the price escalation ?

            4     Whether plaintiff is entitled to recover an
                  amount of Rs.5,76,25,112/- as per price              Yes.
                  escalation clause and as per work done ?

            5     Whether plaintiff is entitled for interest on Yes, @ 15% p.a.
                  suit amount or balance amount, if yes, at
                  what rate ?

            6     Whether plaintiff is entitled for 30 %
                  additional amount of contract for breach of           No.
                  contract by defendants ?

            7     Whether plaintiff proves that it is entitled to
                  10 % additional amount of outstanding                 No.
                  balance towards loss of overhead charges ?

            8     Whether the plaintiff is entitled for Rs.10
                  lacs towards cost of this litigation ?                No.


The Commercial Court held that the defendants failed to make full

payment in accordance with Clause 56 and decreed the suit accordingly.

Present Commercial Appeal is filed challenging the Judgment and decree of

the Commercial Court.

17. The learned Counsel for the appellants submits that when the matter

was argued before this Court, this Court, by order dated 24/02/2025,

observed that the work executed by the plaintiff was completed on

30/06/2013, whereas the suit was instituted on 21/12/2017. It was prima

facie observed that the suit would be governed by Article 18 of the First

Com Appeal 9-2019

Division of the Schedule to the Limitation Act, 1963, falling under the

category of "a suit for the price of work done by the plaintiff for the

defendant at his request, where no time has been fixed for payment."

18. It was further observed that the plaint did not disclose as to how the

suit was within the prescribed period of limitation, except stating that the

last Running Account Bill was measured and drawn on 12/04/2016. The

memorandum of appeal also contained a specific plea that the suit was

barred by limitation.

19. In view thereof, this Court directed the Commercial Court, Jalna, to

frame an issue on limitation and to decide the same in accordance with

law, after granting both parties an opportunity to lead additional evidence.

However, the parties were expressly restrained from amending their

pleadings.

20. Pursuant to the said directions, the Commercial Court framed the

issue on limitation and answered the same in favour of the plaintiff.

Thereafter, the appellants filed Civil Application No.11305 of 2025, seeking

permission to amend Commercial Appeal No.9 of 2019 so as to challenge

the order dated 14/05/2025 passed by the District Judge, Jalna, in

Commercial Suit No.8 of 2019, and to place the relevant supporting

documents on record. The said application came to be allowed by this

Com Appeal 9-2019

Court by order dated 07/01/2026.

21. The appellants/original defendants have challenged the judgment of

the Commercial Court primarily on two grounds. Firstly, it is contended that

the suit is barred by limitation. The learned Counsel for the appellants

submits that the contractual work was completed on 30/06/2013, and

therefore, the period of limitation commenced from the date of completion

of the work. Merely because the final payment under R.A. Bill No.57 was

paid in the year 2016, the same cannot extend the period of limitation. It is

urged that the suit instituted in 2017 is clearly barred, inasmuch as Article

18 of the Schedule to the Limitation Act, 1963, prescribes a period of three

years for filing a suit for the price of work done, reckoned from the date of

completion of the work.

22. On the issue of limitation, the learned Counsel for the appellants

places reliance on the judgment of this Court at the Principal Seat in

Arbitration Appeal No.6 of 2007 (State of Maharashtra v. Hindustan

Construction Company Ltd. & Anr.), decided on 01/02/2013.

23. The learned Counsel for respondents submits that Section 19 of the

Limitation Act squarely governs the issue in the present case. He contends

that although the work was completed earlier, the final payment under R.A.

Bill No.57 was made on 12/04/2016, and therefore, the period of limitation

Com Appeal 9-2019

commenced from the said date. On this premise, it is urged that the suit

instituted in the year 2017 is well within the prescribed period of limitation.

24. It is submitted that the present suit is not merely for "work done",

but for non-payment of the legally payable escalation amount, which could

be finally determined only upon preparation and payment of the final

Running Account Bill. Admittedly, the last R.A. Bill (No.57) was measured

and payment was released on 12/04/2016, and only thereafter did the

cause of action crystallise. The learned Counsel further submits that so

long as the final bill was not prepared and paid, the account between the

parties remained open and unsettled. The right to sue accrued only when

the appellants refused to pay the correct escalation amount despite

repeated demands made in the year 2016 and thereafter. The respondent

further submits that the appellants' reliance on Article 18 of the Limitation

Act, 1963 is misplaced. Even assuming Article 18 applies, the phrase "when

the work is done" must be read in conjunction with the contractual

obligation to finalise and pay the final bill, particularly where escalation is

an integral part of the consideration.

25. Secondly, the learned Counsel for the appellants submits that the

Commercial Court has erroneously interpreted Clause 56 of the tender

document relating to price escalation. According to the appellants,

escalation amounts were computed and included in each Running Account

Com Appeal 9-2019

Bill from R.A. Bill No.1 to R.A. Bill No.56 for the period between 1995 and

2013, and the final escalation amount was also adjusted in the final bill.

The plaintiff accepted all the R.A. Bills without demur. Having accepted the

payments over the entire contractual period, it is not open to the plaintiff

to recompute price escalation by taking an average from the date of

commencement of the contract till the final date of payment and thereby

claim an additional amount of Rs.5,76,25,112/-, which is contrary to the

contractual stipulations.

26. As regards the payment and computation of escalation, it is

submitted that there is no dispute concerning the correctness of the

individual Running Account Bills. According to the appellants/ defendants,

price escalation under Clause 56 is required to be computed with reference

to the cost of work done during the relevant period of each bill and, at the

minimum, contemporaneously at the time of payment of each Running

Account Bill. This, it is submitted, is the contractual scheme contemplated

under the tender, and the same has been followed throughout. The final

decretal amount, therefore, could not have been arrived at by recomputing

escalation for the entire contractual period at the end of the work.

POINTS FOR DETERMINATION :

27. Having considered the rival submissions, the following points arise

for determination :

Com Appeal 9-2019

(1) Whether the suit filed by the respondent / plaintiff is within the stipulated period of limitation ?

And : ......Yes.

(2) Whether the appellants / defendants have paid the amount towards "price escalation" in the the respective R. A. Bills No. 1 st to 57th accordance with Clause 56 of the Agreement ?

Ans : ......Yes.

DISCUSSION & REASONS :

POINT NO. 1 :

28. In paragraph No.13 of the plaint, the plaintiff has stated that the

work was executed and completed on 30/06/2013. It is further stated that

the last Running Account (R.A.) Bill was measured and drawn on

12/04/2016, and that the plaintiff requested the defendants to release the

balance payment in the year 2016. According to the plaintiff, the total

balance amount payable under the contract was Rs.10,02,91,108/-, out of

which Defendant No.5 paid only Rs.4,26,65,996/- by cheque, thereby failing

to pay the price escalation amount in accordance with the tender

conditions.

29. It is further pleaded that on 29/05/2017, the plaintiff addressed a

letter to Defendant No.5 calling upon it to release the final bill amount.

Com Appeal 9-2019

However, Defendant No.5 replied by denying liability and refused to act in

accordance with the tender terms. Consequently, the plaintiff issued a

statutory notice dated 05/08/2017 under Section 80 of the Code of Civil

Procedure, 1908, and thereafter instituted the suit on 21/12/2017.

30. In the written statement, the defendants have contended,

particularly in paragraph No.11, that there was no subsisting demand from

the plaintiff, as Running Account Bills were settled from time to time after

taking into account the applicable price escalation. It is their case that the

plaintiff never raised any objection from the 1 st R.A. Bill till the 56th R.A. Bill

and accepted all payments after due verification. The defendants denied

that the amount of Rs.4,26,65,996/- was a part payment and asserted that

the same constituted full and final settlement. It is further contended that

the plaintiff did not accept the payment under protest.

31. The defendants have also relied upon Clause 56 of the tender

document, contending that the "period under consideration" for calculating

price variation is bill-specific. According to them, for the first R.A. Bill, the

period under consideration is from the date of commencement of work till

the first R.A. Bill, and for the second and subsequent R.A. Bills, it is from

the payment of the preceding R.A. Bill to the next R.A. Bill, and so on, up to

the final payment. It is submitted that from R.A. Bill No.1 to R.A. Bill No.57

Com Appeal 9-2019

(covering the period from 1994 to 2013), the contractor accepted all

payments over a span of nearly 20 years, and has now, belatedly, raised a

claim for additional price escalation without any contractual or legal basis.

32. Thus, the core issue that arises for consideration on the question of

limitation is the starting point of limitation.

33. Clause 10 of the contract provides that bills are to be submitted

monthly or on or before the date fixed by the Engineer-in-Charge. If the

contractor fails to submit the bill within the stipulated time, the Engineer-

in-Charge is empowered to measure the work and prepare the bill. The bills

are required to be in printed form.

34. In the present case, R.A. Bills No.1st to 56 th were raised by the

plaintiff in accordance with the contract, and price escalation was granted

in each bill by applying the prescribed formula. These bills pertained to

specific periods during which the work was executed and price escalation

was computed and adjusted accordingly.

35. The defendants' witness, Surekha Bhimrao Korke, has stated that the

defendant issued a letter dated 30/01/2013 calling upon the contractor to

Com Appeal 9-2019

remain present on 06/02/2013 at 09.00 a.m. for taking final measurements

of the work done. However, neither the contractor nor his representative

remained present on the said date. It is pertinent to note that this assertion

does not find place in the pleadings.

36. It is further stated by the said witness that another letter dated

27/05/2013 was issued by the defendants calling upon the contractor to

remain present for accepting and acknowledging the final bill of the work

done. According to her, the contractor did not come forward to accept the

final bill. Consequently, on 01/07/2013, a letter was issued to Defendant

No.4 informing that the final measurement was carried out and that the

final bill, including the cost of price escalation, was prepared. It is stated

that although the contractor was informed, he did not respond for

acceptance of the final bill.

37. However, all the aforesaid facts were not pleaded in the written

statement, and evidence has been led on facts which are not part of the

pleadings. The said witness has, however, admitted that on 12/04/2016 the

final bill was paid and that the Letter of Credit (LOC) was received by their

office on 17/06/2016.

38. In the present case, the final bill was required to be settled after

completion of joint measurement of the work done. The same was

Com Appeal 9-2019

admittedly not settled on the alleged date of completion of work. There is

no specific pleading that the final bill stood settled on 30/06/2013. Bill

No.57 was paid on 12/04/2016, and there is no separate communication

indicating denial of any specific part of the said bill.

39. A running account bill, by its very nature, involves interim payments

made at specified intervals, depending upon the progress of the contract

works. A "running account" is account between parties having a series of

transactions, which remains open and is usually subject to settlement at

stated intervals. Such running account bills are only provisional in nature

and do not result in the final settlement of rights and liabilities between the

parties. There is no clause in the tender document to treat R. A. Bills as

final to the extent of work covered in the R.A. Bill. However, there is also

no clause to treat the payments made under R. A. Bills as advance till the

final bill. In absence of the above clauses we treat the R. A. Bills as interim

payment and the final settlement takes place only upon acceptance of the

final bill.

40. Article 18 of the Schedule to the Limitation Act, 1963 would apply

only where the amount payable is known and becomes payable on

completion of work. However, in the present case, although the physical

work may have been completed on 30/06/2013, the measurement of the

work and the escalated price was yet to be computed. The final bill was

Com Appeal 9-2019

required to be prepared after joint measurement and after working out the

escalation under the contractual clause. Therefore, limitation would

commence only upon denial or partial payment of the final bill which

occurred on 12/04/2016. The suit is filed on 21/12/2017 and is within

three years of payment of partial final bill and is thus within limitation and

would be covered under Article 55, of the Limitation Act.

POINT NO. 2 :

41. Coming to the next issue of price Escalation Claimed, namely,

whether the plaintiff is entitled to claim an amount of Rs.5,76,25,112/-

towards price escalation cost. For this purpose Clause 56 of tender

document provides for price variation clause.

42. Clause 56 of the tender document reads as under :

"Clause - 56 : PRICE VARIATION CLAUSE

I. If during the operative period of the contract as defined in condition (I) below, there shall be any variation in the consumer Price Index (new series) for IndusCommercial workers for Nanded Centre as per the Labour Gazette published by Commissioner of Labour, Government of Maharashtra and / or in the wholesale price index for all commodities prepared by the office of Economic Advisor, Ministry of Industry, Government of India, as compared to the respective figure therefore, on the date 30 days before the last date prescribed for receipt of tender and / or in the prices of petrol/ oil and lubricant, then subjects to the other conditions mentioned below, price adjustment on account of (I) Labour Component (ii) Material component and (iii) POL components, which respectively are 68%, 27% and 6%and of the total cost of work put to tender calculated as per the formula hereinafter appearing, shall be made. (Total of all these three components will be 100)

Com Appeal 9-2019

(A) Formula for labour component :

VI = 0.85    | P-Cost of Schedule 'A' I      |     |      K1       C1-CO|
             | materials used                | X   |      --- x    ------ |
             |                               |     |      100       CO    |


Where,

VI = Amount of price variation in Rupees to be allowed.

P = Cost of work done during the period under consideration K1= Percentage of Labour Component as indicated above. CO= Basic consumer price index for Nanded center ascertained as above on the date 30 days preceding the last date prescribed for receipt of tender.

C1= Average Consumer Price Index for Nanded Centre ascertained as above during the period under consideration.

(B) Formula for materials component :

V2 = 0.85    | P-Cost of Schedule            |     |      | K2   |1-10 |
             | 'A' materials used            | X   |      | -- x ----  |
             |                               |     |      | 100 | 0    |



Where,

V2 = Amount of Price variation in rupees to be allowed.

      P     =    Cost of work done during the period under
      consideration

K2 = Percentage of material component as indicated above. | 0 = Basic wholesale Price index ascertained as above on the date 30 days preceding the last date prescribed for receipt of tender. | 1 = Average wholesale price Index ascertained as above during the period under consideration.

(C) Formula for petrol, oil and lubricant component :

V3 = 0.85    |      P-Cost of Schedule       |     |      K3      PI-PO |
             |        'A' material used      | X   |      ---- X ------ |
             |                               |     |      100     PO    |


                                                               Com Appeal 9-2019




Where,

V3 = Amount of price variation in Rupees to be allowed. P = Cost of work done during the period under consideration. K3 = Percentage of petrol, oil and lubricant component, PI = Average price of H.S.D. for Bombay during the period under consideration.

II. Conditions referred to in Paragraph - I

i) The operative period of the contract shall mean the period commencing from the date of the work order issued to the contractor and ending on the date when the time allowed for the work specified in the Memorandum under Tender for work expires, taking into consideration the extension of time, if any, for completion of the work granted by Engineer in charge under the relevant clause of the conditions of contract in cases other than those where such extension is necessiated on account of default of the contractor the decision of the Engineer-in-charge as regards the Operative period of the contract shall be final and binding on the contractor. Where compensation for liquidated damages is levied on the contractor on account of delay in completion or inadequate progress under the relevant contract provisions. The escalation amount for the balance work from the date of levy of such compensation shall be worked out by paging the indices C1 I-1 and P-1 to levels corresponding to the date form which such compensation is levied.

ii) This price variation clause shall be applicable to all contracts in B1, B2 and C forms but shall not apply for piece works.

iii) Price variation shall be calculated, in accordance with the formula mentioned above, separately for labour, material and POL components.

Com Appeal 9-2019

iv) The price variation under this clause shall not be payable for the extra items required to be executed during completion of the work and also on the excess quantities payable under the provisions of clause 38 / 37 of the contract from B1 / B2 respectively. Since the rates payable for the extra items or the extra quantities under clause 38 / 37 are to be fixed as per the current RSR or as mutually agreed, to yearly revision till completion of such work. In other words, when the completion/ execution of extra item as well as extra quantities under clause 38 / 37 of the contract form B1/ B2 extends beyond the operative date of the then R.S.R., the rates payable for the same beyond that date shall be revised with reference to the next current R.S.R. prevalent at that time on year to year basis or revised in accordance with mutual agreement thereon, as provided for in the contract, whichever is less.

v) This clause is operative both ways, i.e. if the price variation in the said wholesale price index for all commodities, consumer price index (New series) or price of HSD for Bombay is on the plus side, payment on account of the price variation shall be allowed to the contractor and if it is on the negative side, the Government shall be entitled to recover the same from the contractor and the amount shall be deductible from the Contractor's bill for the respective period in which there are fluctuations."

43. We find that Clause 56 provides distinct formulas for computation of

price variation under the labour component, material component, and

petrol, oil and lubricant (POL) component. Clause 56(II)(i) defines the

operative period of the contract to mean the period commencing from the

date of issuance of the work order to the contractor and ending on the date

when the time allowed for completion of the work, as specified in the

Com Appeal 9-2019

memorandum under the tender, expires, after taking into consideration

any extension of time granted by the Engineer-in-Charge under the

relevant contractual provisions, save and except extensions necessitated

on account of default of the contractor. The decision of the Engineer-in-

Charge as regards the operative period of the contract is declared to be

final and binding on the contractor.

44. The operative period of the contract and the period under

consideration for calculation of price variation are two distinct concepts.

The operative period refers to the entire duration of the work, commencing

from the date of issuance of the work order and ending with the completion

of the work, while period under consideration relates to the period covered

in the respective running bills.

45. The plaintiff's case is that escalation has to be worked out by taking

an average for the entire contract period. However, we find it difficult to

accept this submission. The formulas prescribed under Clause 56 for

labour, material and POL components specifically refer to the "cost of work

done during the period under consideration". The period under

consideration would naturally mean the period for which the R. A. Bill is

submitted. R. A. Bill includes the price variation for the period covered in

the R. A. Bill. The contractor is paid the R. A. Bill taking into consideration

Com Appeal 9-2019

the escalation in prices at the relevant time for the work done.

46. If the interpretation suggested by the plaintiff is accepted, the entire

escalation for nearly 20 years would have to be recomputed afresh by

treating the entire contract period as a single unit, i.e. from the date of

issuance of the work order till completion of the work, and thereafter

applying the prescribed formula for price escalation. Such an

interpretation is contrary to the scheme and purport of the contract. At

every stage of work undertaken, Running Account Bill is prepared and

escalation price is included in each Running Bill. The purpose of price

escalation clause is to protect the parties to the contract from market price

variations of the Labour, material and Oil components and not to make

windfall profit.

47. This conclusion is further reinforced by Clause II(iv) of the price

variation clause, which specifically provides that price variation shall not be

payable for extra items or excess quantities executed under Clauses 38

and 37 of the contract. In such cases, rates are to be fixed as per the

current Schedule of Rates (RSR) or as mutually agreed, with yearly

revision. Once prices are revised under Clauses 38 or 37, escalation under

Clause 56 is not separately applicable, as the revision already accounts for

the increase in cost.

48. Thus, wherever revision of rates has already been made due to

Com Appeal 9-2019

permissible variation exceeding 25%, escalation is not again applied.

However, where there is no such revision, escalation is to be worked out

Running Bill-wise for the period covered by the respective Running bills.

49. The argument that the entire operative period of the contract should

be taken as one unit and that escalation should be averaged over the

entire period is not supported by the language of Clause 56. The formulas

clearly mandate computation of escalation with reference to the period for

which each bill is raised.

50. In the present case, price escalation was granted and paid in each

R.A. Bills No.1 to 56. Even in R.A. Bill No.57, escalation for the relevant

period was computed and paid by the defendants. There is no error

pointed out in each individual R.A. Bill towards escalation price. The prices

of labour, material and oil as on the last date of work i.e. 20 years after

commencement of work cannot be the basis for calculation of price

escalation for the whole tender work. Escalation is worked out at each R.

A. Bill period. The plaintiff has, therefore, erroneously interpreted Clause

56 of the agreement, while submitting his final Bill.

CONCLUSION :

51. In view of the above discussion, we find that no case is made out for

grant of Rs.5,76,25,112/- towards escalation cost. Consequently, the

Com Appeal 9-2019

judgment and decree dated 09/08/2019 passed by the learned District

Judge-1, Jalna, in Commercial Suit No. 08 of 2019, deserves to be set aside

and is accordingly set aside.

52. The present Commercial Appeal filed by the original defendants is

allowed with costs. Decree be drawn up accordingly.

( VAISHALI PATIL-JADHAV, J. ) ( ARUN R. PEDNEKER, J. )

vj gawade/-.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter