Citation : 2026 Latest Caselaw 378 Bom
Judgement Date : 17 January, 2026
2026:BHC-AS:2050
55.ARA.33.2015.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
ARBITRATION APPEAL NO. 33 OF 2015
State of Maharashtra ....Appellant
Versus
M/s Patwardhan Infrasturcture Pvt. Ltd. ....Respondent
Mr. Kuldeep Patil, for Appellant.
Ms. Sonal a/w Ujwala Kamat, Anoop Sharma, Sumit Khanna,
Vaibhav Singh, for Respondent.
Mr. A. R. Patil, Addl. G. P. for State.
CORAM : SOMASEKHAR SUNDARESAN, J.
DATE: : JANUARY 17, 2026
JUDGEMENT :
Context and Factual Background:
1. This Appeal has been filed under Section 37 of the Arbitration
and Conciliation Act, 1996 ("the Act") impugning an Arbitral Award
dated November 7, 2012 ("Impugned Award") and a Judgment dated
September 24, 2014 ("Impugned Judgment"), which upheld the
Impugned Award, dismissing a challenge under Section 34 of the Act.
Digitally signed by AARTI AARTI GAJANAN GAJANAN PALKAR
2026.01.17 13:26:38 +0530 JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
2. The disputes and differences between the parties relate to the
award of a work on August 31, 1999 and a short four-page agreement
dated November 26, 1999, being signed ( "Agreement"). The Appellant,
the State of Maharashtra ("State"), awarded to the Respondent,
Patwardhan Infrastructure Pvt. Ltd. ("Patwardhan"), a contract for
construction of a two-lane bridge connecting Pen and Alibag across the
Dharamtar Creek, on a build, operate and transfer basis, pursuant to a
Tender inviting bids for the project ("Project").
3. The Project had been bid for by M/s Ameya Developers
"("Ameya"), which won the bid with a proposed concession period of 13
years, 7 months and 35 days. The State, Ameya and Patwardhan
executed a tripartite agreement for implementation of the Project. For
all purposes of this judgement, references to Patwardhan are references
to the concessionaire which is considered by all parties as being bound
by, and a beneficiary of, the obligations and rights respectively,
contracted for the Project.
4. The Agreement between the parties is a short four-page contract,
which essentially records that the Project stands awarded, pursuant to
the bid by Ameya in response to the Notice Inviting Bids dated
November 3, 1998 ("Notice Inviting Bids"), and the terms and
conditions contained in the draft agreement set out in the said notice.
The parties actually did not separately sign the draft agreement as an
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
executed agreement, but they have no quarrel that these terms, among
others, constitute the contract-forming documentation binding the
parties.
5. It is common ground between the parties that upon execution of
the Agreement, it included within its sweep, the provisions of the
Notice Inviting Bids and, thereby, the terms of the draft agreement
contained therein, and indeed the minutes of the meeting held in
relation to the Project before executing the Agreement. This judgement
proceeds on this consensus and interprets the terms and conditions
contained in the Notice Inviting Bids as also the minutes of the meeting
held between the parties. At the heart of the adjudication in the
underlying arbitration proceedings lies the interpretation of Clauses
3.4.19 and 3.7.2, as set out in the aforesaid terms and conditions, and
the minutes of the meeting held on August 18, 1999 ("MOM").
6. The Project, as is customary with toll-based concessions, entailed
the bidding private concessionaires quoting the period after which the
infrastructure facility constructed by them would revert to the State. In
the interregnum, the private concessionaire would get to charge toll for
usage of the bridge by vehicles. The toll data was indicated in the bid
documents, and the rate and frequency of escalation of the toll tariff
were also agreed stipulations in the Agreement.
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
7. It is common ground that there had been multiple disputes and
consequential arbitration proceedings between the parties under the
Agreement - including the proceedings underlying this Appeal, seven
in number. All these proceedings have been adjudicated by the same
Arbitral Tribunal. Owing to the outcome in one of them, the concession
period was extended by a further 573 days.
8. It is common ground that for adjudication of the core issue raised
in this Appeal within the contours of Section 37 of the Act, the other
arbitration proceedings between the parties and the resultant awards
do not bear much relevance, except for the adjustment of certain
amounts made by the Learned Arbitral Tribunal on the premise of
having awarded certain sums due to connected causes in some of the
other arbitral awards.
Core Issue:
9. The core issue that falls for consideration is whether the force
majeure clause contained in Clause 3.4.19 of the Agreement ceased to
be a force majeure clause by reason of the MOM, and whether the
parties had instead agreed to change the Project to one guaranteeing a
minimum assured return, whereby any loss of toll collection of more
than 20% would entail a rupee-for-rupee compensation by the State.
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
10. The upshot of the analysis and findings in the Impugned Award,
upheld in the Impugned Judgement, is that the Agreement envisaged
an obligation on the part of the State to compensate Patwardhan for
any drop in toll collection of more than 20% in any period, including a
part of a month.
11. After Ameya submitted its bid on March 15, 1999, and before the
award of the Project, two letters, both dated July 2, 1999, were written
by Ameya to the State. One letter drew reference to newspaper reports
about the proposed construction of another bridge connecting Rewas
and Karanja in the same Raigad district on a build, operate and transfer
basis. Ameya apprehended that the new bridge would establish a
shorter link for traffic between Mumbai and Alibag and that such a
bridge would have an adverse impact on the traffic envisaged by Ameya
when submitting its bid. When making its bid, the new bridge was not
in contemplation at all, and such adverse impact had not been factored
in. Ameya wanted an assurance that should such new bridge be
completed and be made open to traffic before the end of the concession
period for the Project, and if there were an adverse change in traffic,
Ameya should be suitably compensated.
12. Another letter of the same date sought to make some minor
corrections of certain clerical errors that were said to have crept into
the bid documents without any change in the proposal offered, since
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
"the project costs, rate of interest and concession period remain
unaltered". A "slight difference" in the traffic assumed by Ameya based
on its own estimate was sought to be corrected. Ameya stated that such
data was likely to be referred to only in case there was any change in
the concession period, but it would be preferable that a correct
statement be brought on record.
13. The two letters dated July 2, 1999, led to a meeting held by the
Chief Engineer, Public Works of the State on August 18, 1999, to
discuss the issues relating to the Project, which in turn led to the MOM.
For felicity, the following extract from the MOM are vital to note:
At the outset, the Entrepreneur pointed out the very possibility of major variation in traffic intensity on the present facility as the Govt. has floated a tender for the construction of a major bridge connecting Rewas & Karanja. The Entrepreneur claimed that since Rewas Karanja project is a development that has taken place after the submission of his offer for the subjected work, he has not considered its effect while submitting his bid.
The following observations emerged from discussion at length.
I) The viability of Rewas Karanja project on B.O.T. Basis is not yet established.
II) The possible increase/decrease in traffic due to Rewas Karanja Project is a time based theme and unpredictable under present circumstances.
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
III) Although clause 3.7.2 of the contract is applicable for subjected work, in true spirit of the clause such a major change, totally strange to the Entrepreneur.
IV) Clause 3.4.19 of the contract provides that if there is variation more than 20% in traffic due to reasons beyond the control of the Entrepreneur, Govt. will compensate the Entrepreneur suitably.
It was, therefore, agreed by all, that a decision in this regard can be taken when Rewas Karanja Bridge is completed and opened to traffic, on merits of the case & on the basis of variation in actual traffic at that time.
[Emphasis Supplied]
14. The two clauses referred to in the aforesaid extract of the MOM,
namely, Clause 3. 7.2 and Clause 3.4.19 would also be appropriate to
extract :-
3.7.2. If traffic intensity data observed during the last few years is available with the Department, will be made available to the Entrepreneur if asked for in writing. The Government shall not accept any responsibility on account of loss suffered by the Entrepreneur either due to the use of the above data or any change in traffic plying as a result of construction of new roads/links or improvements to the exiting road network in the vicinity or any other similar change.
3.4.19 If any time during the execution / completion of the project the Entrepreneur not able to proceed with
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
constructing/completion of the project beyond a period of one month due to any reason beyond his control such as fire earth quake, floods, storm or any other such calamity, riots, civil commotion the Government shall compensate the Entrepreneur for such loss in a manner and form as may be decided by the Government. If also, the Entrepreneur is not able for a period even less than a month to collect any toll or if the toll collection is drastically reduced below 20% of normal toll collection due to any reasons whatever beyond his control such as transporter's strike, riots, civil commotion, closure of bridges for more than 24 hours for traffic on account of structural repairs (not due to Entrepreneur's fault) the Government shall compensate him for such deficit/shortfall in toll collection along with simple interest equivalent to prime lending rate of State Bank of India prevalent at the time. Amount of such deficit/shortfall, along with the interest thereon shall be paid by the Government to the Entrepreneur in one lump sum within 6 months after the demand for such force major claim is submitted to the Government. The Government however, shall have the option of extending the concession period in lieu of such payment. If there is any shortfall in toll collection due to wrong estimation of traffic by the Entrepreneur or if he fails to collect toll for any other reason, the Government shall not compensate the deficit loss or shortfall.
[Emphasis Supplied]
15. Whether the contents of the MOM extracted above had the effect
of materially altering the aforesaid clauses, and if so, whether facts and
events transpired that would attract these provisions as altered, fell for
consideration by the Learned Arbitral Tribunal.
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
Contentions of Parties:
16. Against this backdrop, I have heard at length Mr. Kuldeep Patil,
Learned Advocate on behalf of the State, and Ms. Sonal, Learned
Advocate on behalf of Patwardhan. With their excellent assistance, I
have navigated the record, neatly compiled into a convenience
compilation.
17. Mr. Patil would submit that such a reading is totally perverse and
no reasonable judicial mind would arrive at such a conclusion - of
treating a force majeure clause as ceasing to be a force majeure clause,
to accommodate a claim for compensation for a shortfall in toll in the
admitted absence of a force majeure event. He would submit the
findings are contrary to the contract, and perverse. The Learned
Arbitral Tribunal has held that Clause 3.7.2 and Clause 3.4.19
underwent material alterations, and that forms the basis its award of a
full compensation for any shortfall in toll collection of more than 20%.
Mr. Patil would submit that the MOM did not effect any amendment at
all to these clauses, since the parties only agreed to defer the decision to
the situation of a real event of the Rewas-Karanja bridge coming up and
getting operational. Since that project, or indeed any other like project,
never came up, he would submit, the MOM has no implication at all for
the contract between the parties.
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
18. In contrast, Ms. Sonal would contend that the Agreement must
be examined in the context of the era in which it was contracted. In the
1990s, private participation in public infrastructure was at nascent
stage and the State was seeking to provide strong support to private
players to take up infrastructure investment. Clause 3.4.19 originally
provided a benchmark of traffic falling to below 20% (i.e. a traffic fall of
more than 80%), while the MOM referred to that very clause as
entailing compensation if toll collections fell by more than 20%. This,
Ms. Sonal would submit is a material change and indicative of how the
bargain had changed between the parties. Ms. Sonal would also
differentiate between "failure to collect" and "fall in toll collection" to
contend that a failure envisaged in the exception in Clause 3.4.19 has to
be a positive failure in the character of a breach while the MOM had
made the exception in Clause 3.4.19 irrelevant since the very metric was
changed from a fall in traffic to below 20% to a fall in toll collection by
20%.
19. Likewise, Clause 3.7.2 had provided that there would be no
implication for the State at all from other links and projects in the
vicinity, Ms. Sonal would submit, but the State had agreed in the MOM
that it would visit the impact of Rewas-Karanja bridge as and when it
became operational. Therefore, with the MOM having been agreed to
even before the work was awarded and before the Agreement was
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
signed, and being an integral part of the contract, the bargain between
the parties had changed. On this premise, Ms. Sonal would assert that
the findings of the Learned Arbitral Tribunal fall within the ambit of
being plausible findings, and that scope of interference by the Section
34 Court should not be forgotten - it is not open to substitute one
plausible interpretation of the contract with another that finds more
favour with the Court.
Analysis and Findings :-
Scope and Standard of Review:
20. Before delving into the analysis, a few points would need to be
underscored. First, the jurisdiction of the Section 37 Court being an
appeal from a decision of the Section 34 Court is necessarily concurrent
with and circumscribed by the contours of jurisdiction under Section
34 of the Act. In other words, this Court in exercise of jurisdiction
under Section 37 of the Act has to act in conformity with the scope of
jurisdiction under Section 34 of the Act. Second, the challenge under
Section 34 in the instant case was launched before October 23, 2015,
when the amendments of 2015 to the Act took effect. In fact, both the
instruments - the Impugned Award and the Impugned Judgement -
relate to the period prior to 2015. Therefore, the grounds of
interference did not include Section 34(2-A), which inserted the ground
of "patent illegality" and indeed the Explanation 1 to Section 34(2)(b)
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
(ii), which sought to regulate the application of the " public policy"
ground for interference with arbitral awards, did not then exist in law.
21. Therefore, when one tests if the Section 34 Court was right in its
exercise of jurisdiction over the Impugned Award, one must apply
Section 34 as it then stood and assess how the challenge ought to have
been considered under Section 34 of the Act. It is with this perspective
in mind that the analysis that follows must be read.
Contract Formation:
22. I have already made a brief note on the contract formation
between the parties at the start of this judgement. Therefore, suffice it
to say that the parties have consensus that what applies to them are the
provisions contained in the terms and conditions enclosed in the Notice
Inviting Bids, read with the MOM, and there is no quarrel that the
amalgam of the two and their combined effect would bind them. This
reiteration is felt necessary since, when asked for the signed contract,
both advocates pointed to the four-page contract signed on November
26, 1999, which in turn alludes in a circular manner to "contract
documents" constituting the term "Contract Documents" without
explicitly listing which documents comprise them. Clause 2 of the
signed agreement dated November 26, 1999, alludes to other
documents such as additional details of the proposal, the bank
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
guarantee towards security deposit, and other correspondence between
the parties, which would be treated as "Reference Documents".
23. However, there is no difference of view between both the parties
that the terms set out in the Notice Inviting Bids and the MOM jointly
constitute the Agreement - the parties only differ on the implications
of their joint impact on their respective rights and obligations.
24. The short question that falls for consideration in these
proceedings is whether the MoM, and in particular, the portions
extracted above have the effect of materially modifying Clause 3.4.19
and Clause 3.7.2, and if so modified, what such modified position is;
and more importantly, whether the Impugned Award returns a
reasonable, defensible and plausible view that ought not to be
interfered with.
25. The Impugned Award holds that the Chief Engineer who
conducted the meeting which led to the MOM had the full authority to
amend the terms on which the Project was to be implemented and that
the MOM constitutes a significant and material change to Clause 3.4.19
in the draft contract annexed to the Notice Inviting Bids. This view has
been concurrently upheld in the Impugned Judgement which also
emphatically holds that the Clause 3.4.19 and Clause 3.7.2 stood
materially deviated from, due to the MOM, and the result would be that
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
any shortfall in traffic by 20% would automatically have to be
compensated by the State.
Analysis of the Relevant Clauses and the MOM:
26. Therefore, at the threshold, it would be appropriate to examine
the contents of the clauses and the MOM extracted above, just to see
what they entail, and not with an intent to reinterpret the provisions. It
is made clear that such an exercise is necessary to see whether the
outcome that has transpired is a finding that no reasonable and
prudent person would return, and whether the findings are a product of
a non-judicial approach.
27. Clause 3.7.2 stipulates that if traffic data observed in the previous
few years were available with the State, it would be made available for
the asking. However, the State would not accept any responsibility on
account of loss suffered due to the use of such data. The upshot is that
the concessionaires ought to conduct their own traffic analysis and
formulate their bids accordingly. Likewise, Clause 3.7.2 provides that if
there is any change in traffic as a result of the construction of any new
roads or links, or improvements to the existing road network in the
vicinity, or any other change, there would be no compensation. The
(then) proposed Rewas-Karanja bridge would fall squarely within the
ambit of this exclusion of compensation for loss. The MOM has to be
read in this context, as is done later in this judgement.
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
28. As regards Clause 3.4.19, it is evidently a force majeure clause,
which reduces to writing the approach of the parties in the event of
force majeure conditions arising. A plain reading of Clause 3.4.19
would show that if the concessionaire is not able, for a period of even
less than one month, to collect any toll, or if the toll collection is
drastically reduced to below 20% of normal toll collection due to any
force majeure conditions whatsoever, which are also illustrated with
examples, the State would compensate the concessionaire either in
funds or by extension of the concession period, as the State opts.
29. The illustrative examples of "any reasons whatever" beyond the
concessionaire's control are set out in the words " such as transporter's
strike, riots, civil commotion, closure of bridges for more than 24 hours
for traffic on account of structural repairs (not due to Entrepreneur's
fault)" in Clause 3.4.19. Therefore, while the words "any reasons
whatever" may appear to be a wide phrase, unmistakably, these words
are housed in a force majeure clause. The sentences preceding the
sentence in which this phrase is used, and the words that follow this
wide phrase, all indicate without doubt, that the provision is a force
majeure clause.
30. It is also apparent from the very same clause that any wrong
estimation of traffic by the concessionaire or failure to collect toll " for
any other reason" would not lead to the State having to compensate for
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
the deficit arising out of the shortfall. The reference to wrong
estimation of traffic ties in with the requirement for the concessionaire
to estimate traffic under Clause 3.7.2. The reference to "any other
reason" would contextually indicate the "reasons" for the failure to
collect toll, being reasons other than force majeure conditions. Failure
to collect toll for such reasons would not be compensated.
31. Be that as it may, these were the clauses in the Notice Inviting
Bids that Ameya had before it made its bid. When Ameya raised
concerns about the newly proposed Rewas-Karanja bridge, the meeting
that led to the MOM was held. The MOM essentially lists out the
concerns and the observations made by the parties, and concludes with
what the parties "agreed" at the meeting. The MOM records that the
new project was only being conceptualised and there was no insight
into whether it would actually be implemented. However, the parties
agreed in the MOM that as and when, and if and when, the Rewas-
Karanja bridge was to be completed and traffic actually started plying
within the concession period of the Project, depending on the actual
impact on traffic, a decision would be taken.
32. Therefore, what transpired in the meeting that led to the MOM is
that the parties agreed to agree on a decision, if and when, and as and
when, the Rewas-Karanja bridge was to get operational within the
concession period of the Project.
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
33. Now, it is common ground that the Rewas-Karanja bridge was
never implemented. It is also common ground that no other
comparable project in the vicinity was implemented.
34. However, Patwardhan made a claim for a rupee-for-rupee
compensation for the shortfall in toll collection for the months in which
the toll collection fell by more than 20%. This was claimed on the
premise that the MOM had changed the bargain between the parties.
Any shortfall of more than 20% was claimed as triggering the State's
liability to compensate Patwardhan. This has been unanimously
allowed in the Impugned Award and upheld in the Impugned
Judgement.
35. What the Learned Arbitral Tribunal and the Section 34 Court
have done is to examine the provisions of Clause 3.4.19 and the MOM
to return a finding that the MOM rewrote Clause 3.4.19 in such a
material manner that the latter ceased to be a force majeure provision.
To begin with the MOM does not contain any agreement. The MOM is
an outcome of Patwardhan's expression of concerns about the
implications of the Rewas-Karanja bridge that was being reported in
the newspapers. The parties merely agreed to defer a decision on such
implications to a date when the Rewas-Karanja bridge actually comes
about, and after appreciating the actual impact, if any, of such bridge
on the Project.
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
36. It is the set of "observations" of the parties "that emerged" and
were recorded in the MOM that precede the portion which records the
above agreement (to defer the decision to a later date) reached by the
parties, that have been treated by the Learned Arbitral Tribunal and the
Section 34 Court as an amendment to Clause 3.4.19 and indeed Clause
3.7.2. Even if one were to accept for the sake of argument that these
"observations that emerged" constituted an "agreement to amend"
Clause 3.4.19 and Clause 3.7.2, by no stretch of imagination could one
contend that these observations resulted in a detailed force majeure
clause ceasing to have anything to do with force majeure.
37. The two forums are not wrong in indicating that the observations
(if one were to treat them as an agreement) are at material variance
with the two clauses, but in my opinion, no judicial reading could treat
such variation as being a means of effacing and wiping out the very
words "force majeure" from Clause 3.4.19.
38. The two concurrent findings take a view that every shortfall in
toll collection by 20% would need to be made good by the State by
compensating Patwardhan for such shortfall. This is clearly
implausible. Clause 3.4.19 provides for a benchmark as to when the
obligation to compensate would kick in, specifically, when a force
majeure event occurs. If an impact that meets that threshold were to
occur, i.e., a shortfall in traffic by 80% (truly in accord with a force
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
majeure condition) for any reason whatsoever, the State would
compensate. Even the compensation is not meant to only write out a
cheque in Patwardhan's name - the State could simply allow for a
longer concession period to enable Patwardhan to collect toll and
recoup this impact. Even if the observations in the MOM in its
description of Clause 3.4.19 were to be treated as an agreement to
amend, all that would be amended is the benchmark - it would change
from an over-80% fall in traffic to an over-20% fall in toll collection.
Such a benchmark may change, but it is still intended to trigger
compensation should such a fall were to occur due to a force majeure
event. The types of force majeure events are also listed in Clause
3.4.19. While these are evidently illustrations of events that fall outside
the control of the concessionaire, they are equally events that the State
would not intend to occur or would do its best to ensure they do not
occur. It is the occurrence of such events that would need to constitute
a valid reason for a shortfall (in collections, as per the Learned Arbitral
Tribunal's reading of the MOM; or in traffic, as per the clause on its
own), and when such shortfall meets the benchmark threshold, the
obligation to compensate would be triggered.
39. What the Learned Arbitral Tribunal and the Section 34 Court
have done is turn this on its head. They have simply taken the
observations in the MOM to treat them as an amendment not just to
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
the benchmark for compensating for a force majeure event but even for
circumstances that do not even constitute a force majeure event. In
disputes over infrastructure contracts, whether an event that has
occurred is a force majeure event is itself often a mixed question of fact
and contract, for which evidence has to be led. It is after the occurrence
of a force majeure event is establishd, that the next step would be to
examine if the benchmark threshold for compensation has been
reached. If that threshold has been reached, the next step would then
be compensation, with the form of compensation being left to the
option of the State - whether to pay money or extend the concession
period to enable the collection of tolls from the public for a longer
period.
40. All of this has been thrown to the winds in the concurrent
findings. They have simply made a leap, or rather multiple leaps of
faith - first, to treat observations in the MOM as an agreement; second,
to ignore what the MOM records the parties have actually agreed upon;
and third, to treat such observations as having been an amendment of
such a nature that the parties intended to change the foundational risk-
reward profile of the Project by making a conditional compensation
clause into a minimum guaranteed return contract.
41. It cannot be forgotten that the MOM pre-dates the award of the
work and the execution of the Agreement. If the parties were to alter
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
the very basic structure of their bargain from what was set out in the
Notice Inviting Bids, there would be a reasonable prospect that such a
vital, fundamental change would be an explicit part of the
documentation they would execute. I have already made by
observations about the manner of contract formation in this case.
Without doubt, such contract formation has led to ambiguity being
asserted in the arbitral proceedings.
Dispute Resolution Fails Business Efficacy Test:
42. In defence of the Impugned Award and the Impugned
Judgement, Ms. Sonal invokes the business efficacy test to resolve the
ambiguity in the contract. Indeed, the business efficacy test ought to
have been applied to resolve the ambiguity perceived in the manner of
contract formation, on which I have already commented above.
43. Therefore, it would be appropriate to examine what this test is,
and how it would play out in the facts of the case.
44. In Nabha Power1 the Supreme Court noticed various earlier
judgements on how to give commercial sense to terms in a contract that
may not lend themselves to a clear unequivocal meaning, in the
following terms:
49. We now proceed to apply the aforesaid principles which have evolved for interpreting the terms of a commercial contract in
1 Nabha Power Ltd. v. Punjab SPCL - (2018) 11 SCC 508
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
question. Parties indulging in commerce act in a commercial sense. It is this ground rule which is the basis of The Moorcock [The Moorcock, (1889) LR 14 PD 64 (CA)] test of giving "business efficacy" to the transaction, as must have been intended at all events by both business parties. The development of law saw the "five condition test" for an implied condition to be read into the contract including the "business efficacy" test. It also sought to incorporate "the Officious Bystander Test" [Shirlaw v. Southern Foundries (1926) Ltd. [Shirlaw v. Southern Foundries (1926) Ltd., (1939) 2 KB 206 : (1939) 2 All ER 113 (CA)] ].
This test has been set out in B.P. Refinery (Westernport) Proprietary Ltd. v. Shire of Hastings [B.P. Refinery (Westernport) Proprietary Ltd. v. Shire of Hastings, 1977 UKPC 13 : (1977) 180 CLR 266 (Aus)] requiring the requisite conditions to be satisfied: (1) reasonable and equitable; (2) necessary to give business efficacy to the contract; (3) it goes without saying i.e. the Officious Bystander Test; (4) capable of clear expression; and (5) must not contradict any express term of the contract. The same penta-principles find reference also in Investors Compensation Scheme Ltd.v. West Bromwich Building Society [Investors Compensation Scheme Ltd. v. West Bromwich Building Society, (1998) 1 WLR 896 : (1998) 1 All ER 98 (HL)] and Attorney General of Belize v. Belize Telecom Ltd. [Attorney General of Belize v. Belize Telecom Ltd., (2009) 1 WLR 1988 (PC)] Needless to say that the application of these principles would not be to substitute this Court's own view of the presumed understanding of commercial terms by the parties if the terms are explicit in their expression. The explicit terms of a contract are always the final word with regard to the intention of the parties. The multi-clause contract inter se the parties has, thus, to be understood and interpreted in a manner that any view, on a particular clause of the contract, should not do violence to another part of the contract.
[Emphasis Supplied]
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
45. In coming to the foregoing view, the Supreme Court endorsed
and reiterated what had been stated in a long line of judgements that
had endorsed these principles including in the cases of Dhanrajamal
Gobindram2 (paragraph 19); D.N. Revri3 (paragraph 7); and Satya Jain4
(paragraphs 33 to 35).
46. The invocation of the business efficacy test to resolve ambiguous
positions emerging from a contract would therefore need to meet five
factors. The resolution of the ambiguity must be (i) reasonable and
equitable; (ii) necessary to give business efficacy to the contract; (iii) it
should 'go without saying'; (iv) capable of clear expression; and (v)
must not contradict any express term of the contract. Each of these
tests fails in the matter in hand.
47. First, the purported efficacy sought to be given by the impugned
findings is not reasonable or equitable. The extrapolations made by the
Learned Arbitral Tribunal and the Section 34 Court from the MOM,
have converted the Project for which the Notice Inviting Bids had
envisaged the private sector bearing the risk of the project with some
specific protections into a risk-free State-underwritten project with
guaranteed income of least 80% of the toll collections projected by the
private bidder. Since it has been held that the contract moved from a
2 Dhanrajamal Gobindram v. Shamji Kalidas and Co. - (1961) 3 SCR 1020 : AIR 1961 SC 1285 3 Union of India v. D.N. Revri & Co. - (1976) 4 SCC 147 4 Satya Jain v. Anis Ahmed Rushdie - (2013) 8 SCC 131
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
shortfall in traffic to a shortfall in toll collections, the two forums ought
to have dealt with the baseline from which such shortfall is to be
computed. The baseline appears to be whatever Patwardhan projected
as its anticipated toll collection, with a fall of more than 20% from that
being held as a trigger for compensation. In my opinion, far from
giving business efficacy, this is an absurd turn and a foundational
change of the very foundation of the Project's contractual design.
48. Indeed, other bidders would be entitled to say that if the Project
had been a guaranteed 80% toll collection proposition they would have
quoted a different concession period and ought to have been selected.
While this may be in the realm of speculation, the point being made is
that one has to examine if the emphatic reading given in the Impugned
Award and the Impugned Judgement to the MOM is in consonance
with public policy imperatives of how a contract that is a product of
open bidding ought to play out to be in compliance with law. On this
count, the resolution provided by the Learned Arbitral Tribunal is
contrary to the fundamental policy of Indian law.
49. Second, the findings do not give any efficacy to the contract. The
baseline contract terms entailed the conditions under which
compensation for force majeure would be dealt with. To translate that
into a purported amendment that obviates the very need for a force
majeure event is inexplicable. The MOM was a product of a meeting to
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
discuss the implications of the Rewas-Karanja bridge. That project did
not even get started. No other like project in the vicinity transpired.
Indeed, the claim raised by Patwardhan is simply a claim made at the
end of the contract, simply pointing out that the shortfall it suffered
must be compensated. The Learned Arbitral Tribunal comprising
retired senior Public Works Department officials, has simply granted
this compensation by holding that Clause 3.4.19 stood materially
amended. To hold that a force majeure clause was so materially
deviated from that it ceased to even be a force majeure clause is
irrational, to say the least - and that too with nothing more to show
than the mere contents of the MOM, which are extracted above.
50. Within the "observations that emerged" as recorded in the MOM
that have been treated as amendments to the two clauses, sub-para
(III), which deals with Clause 3.7.2, speaks of a shortfall in traffic. Sub-
para (IV), which deals with Clause 3.4.19, alludes to a shortfall in toll
collection. Therefore, it is not as if the observations in the very same
meeting to discuss the potentially cannibalising project consistently
changed the metric from traffic shortfall to toll collection shortfall.
Therefore, these were nothing more than observations recorded. After
these observations, the parties decided not to decide at that stage, but
to defer to a later stage. To treat these observations as material and
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
inexorable amendments is totally arbitrary and perverse and fails to
give efficacy to the contract.
51. Third, the outcome rendered in the two concurrent findings are
not writ so large that it "goes without saying". On the contrary, it has
taken abject violence to the language of Clause 3.4.19 and indeed the
MOM itself, to conjure the outcome rendered. Therefore, the outcome
fails the third test too.
52. Fourth, the outcome is not capable of clear expression. To make
the outcome clear in its expression, one must find that the parties
decided that force majeure conditions were irrelevant for operation of
the force majeure clause, and that a project that entailed the
concessionaire running the project risk in consideration for which he
could charge tolls from all members of the public for its use was
suddenly accorded protection for any shortfall in toll collection of more
than 20%. The very discussion occurred in the context of a competing
project that never even got implemented. The outcome in the MOM
was that the parties agreed to defer the issue to a stage when such a
competing project actually transpired. Nothing of that sort transpired.
53. To deal with this, the Learned Arbitral Tribunal has conjured
another inexplicable proposition. The Learned Arbitral Tribunal and
the Section 34 Court have held that the MOM may have recorded a
discussion in the context of the Rewas-Karanja bridge, but that does
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
not mean it is restricted to that project. If this was their line of
reasoning, they ought to have pointed out what alternative factor, akin
to the Rewas-Karanja bridge, took place that led to the shortfall in toll
collection for the perceived gap to be compensated. Simply stating that
the material variation in how Clause 3.4.19 is described in the
"observations" contained in the MOM constitutes an amendment to
how the parties understood Clause 3.4.19, even if accepted, cannot
shrug off the need for a competing bridge-like or other similar
causation for the shortfall.
54. Finally, the resolution returned in the concurrent findings is
directly contrary to other provisions in the contract. The last sentence
of Clause 3.4.19 provides that a failure to collect toll arising out of any
other reason would not be compensated. The word "other" has to
necessarily relate to some base reason for which the clause was drafted
- that reason is the occurrence of a force majeure event. If, for any
reason other than a force majeure event, there were to occur a failure to
collect toll, the State is expressly protected from any obligation to
compensate. The resolution of the dispute provided in the concurrent
findings flies in the teeth of this provision.
55. That apart, even Clause 3.7.2 explicitly provides that the State
would not compensate for any change in traffic pattern due to other
linkages and other projects that may be undertaken. As a matter of
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
fact, no other project was undertaken in the vicinity. Even the MOM
which discussed the potential means of dealing with one such other
potential project contains the "observations" that Clause 3.7.2 would
indeed apply. Yet, "in true spirit" the parties' observation that "such a
major change" was observed as being strange. The use of the word
"such" necessarily benchmarks the need for the change to be of the
order of magnitude as a competing bridge that would provide a better
link between Mumbai and Alibag, seriously affecting the Project.
Therefore, it was agreed that should there arise an impact if and when,
and as and when, the Rewas-Karanja bridge was to get implemented,
the parties would have a discussion. Indeed, no such project ever came
up.
56. Since the Learned Arbitral Tribunal and the Section 34 Court
have treated these "observations" as agreements, they ought to have
noticed that the parties had observed that Clause 3.7.2 indeed applies.
If the parties had agreed to delete that clause, even the "observations"
would have said so, rather than stating that it indeed applies. Since no
cannibalising project ever came up in the vicinity, there was no basis to
infer that Clause 3.7.2 was altered or given a complete go-by.
57. Patwardhan's defence of reading the "failure to collect" as a
positive violation and breach of collection is disingenuous, to say the
least. If a private concessionaire failed to collect tolls despite being
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
given the power to charge and collect toll, it could never be because of a
breach by such concessionaire, willful or otherwise. It could only be
because despite his best efforts at collecting tolls, he failed to collect -
say, due to the use of force by local users against which he could not do
much and the State could not enforce the rule of law. Therefore, to
distinguish the "failure to collect" from a "shortfall in collection" does
not lend itself to acceptance. These are merely two ways of expressing
the same situation in a toll-based road contract. The core element is
that if such a failure were due to a force majeure condition, and the
impact were of the order agreed by the parties, there would be
compensation. If the failure to collect were due to any reason other
than force majeure, there would be no question of compensation. This
is an express provision with which the resolution provided by the
Learned Arbitral Tribunal and the Section 34 Court is in irreconcilable
conflict.
Conclusion:
58. This facet, along with the analysis set out above, to my mind,
emphasises the absence of a judicial approach in the course of dispute
resolution, rendering the Impugned Award contrary to public policy of
India. As reiterated above, the scope and standard of review adopted
by me is a narrow one, bearing in mind that the scope is limited to
applying the contours of the Section 34 jurisdiction in my capacity as
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
the Section 37 Court. That said, I must state that even if this had been
an arbitral award challenged after October 23, 2015, to my mind, even
the narrowed scope of challenge due to Explanation 1 would not be a
hurdle in returning a finding that the Impugned Award is contrary to
the fundamental public policy of India.
59. My disagreement with the Impugned Award is not based on
finding errors in its reading of the Agreement. Interpretation of a
contract is in the domain of the Learned Arbitral Tribunal, and it is
entitled to make errors provided they are not so egregious or so
manifestly perverse as to cut to the root of the matter. The very
foundational and fundamental change to the very project design (a
guaranteed revenue of 80% toll collection, as against a design of
compensating for force majeure events that have material impact)
being perceived by the Learned Arbitral Tribunal, the perversity indeed
cuts to the root of the matter.
60. In my opinion, for the reasons set out above, the reasoning and
the outcome in the Impugned Award are not in the realm of mere
errors but in the realm of manifest perversity, in changing the very
nature of the contract represented by the Agreement with an
impossible view on the impact of the MOM on the Agreement. This is
why, much against the grain of the standard approach to arbitral
awards, in my opinion, despite the concurrent findings, this case
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
represents a fit case for interference under Section 34 read with Section
37 of the Act.
61. Without burdening this judgement further with extracts from
well-known and oft-reiterated principles governing interference with
arbitral awards, it would suffice to quote only from Associate Builders5,
which in turn cites Western Geco6 as follows:
28. In a recent judgment, ONGC Ltd. v. Western Geco International Ltd. , this Court added three other distinct and fundamental juristic principles which must be understood as a part and parcel of the fundamental policy of Indian law. The Court held : (SCC pp. 278-80, paras 35 & 38-40) "35. What then would constitute the 'fundamental policy of Indian law' is the question. The decision in ONGC does not elaborate that aspect. Even so, the expression must, in our opinion, include all such fundamental principles as providing a basis for administration of justice and enforcement of law in this country. Without meaning to exhaustively enumerate the purport of the expression 'fundamental policy of Indian law', we may refer to three distinct and fundamental juristic principles that must necessarily be understood as a part and parcel of the fundamental policy of Indian law. The first and foremost is the principle that in every determination whether by a court or other authority that affects the rights of a citizen or leads to any civil consequences, the court or authority concerned is bound to adopt what is in legal parlance called a 'judicial approach' in the matter. The duty to adopt a judicial approach arises from the very nature of the power exercised by the court or the authority does not have to be separately or additionally enjoined upon the fora concerned. What must be remembered is that the importance of a judicial approach in judicial and quasi-judicial determination lies in the
5 Associate Builders v. DDA - (2015) 3 SCC 49 6 ONGC vs. Western Geco International Ltd. - (2014) 9 SCC 263
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
fact that so long as the court, tribunal or the authority exercising powers that affect the rights or obligations of the parties before them shows fidelity to judicial approach, they cannot act in an arbitrary, capricious or whimsical manner. Judicial approach ensures that the authority acts bona fide and deals with the subject in a fair, reasonable and objective manner and that its decision is not actuated by any extraneous consideration. Judicial approach in that sense acts as a check against flaws and faults that can render the decision of a court, tribunal or authority vulnerable to challenge.
***
38. Equally important and indeed fundamental to the policy of Indian law is the principle that a court and so also a quasi-judicial authority must, while determining the rights and obligations of parties before it, do so in accordance with the principles of natural justice.
Besides the celebrated audi alteram partem rule one of the facets of the principles of natural justice is that the court/authority deciding the matter must apply its mind to the attendant facts and circumstances while taking a view one way or the other. Non-application of mind is a defect that is fatal to any adjudication. Application of mind is best demonstrated by disclosure of the mind and disclosure of mind is best done by recording reasons in support of the decision which the court or authority is taking. The requirement that an adjudicatory authority must apply its mind is, in that view, so deeply embedded in our jurisprudence that it can be described as a fundamental policy of Indian law.
39. No less important is the principle now recognised as a salutary juristic fundamental in administrative law that a decision which is perverse or so irrational that no reasonable person would have arrived at the same will not be sustained in a court of law. Perversity or irrationality of decisions is tested on the touchstone of Wednesbury principle of reasonableness. Decisions that fall short of the standards of reasonableness are open to challenge in a court of law often in writ
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
jurisdiction of the superior courts but no less in statutory processes wherever the same are available.
40. It is neither necessary nor proper for us to attempt an exhaustive enumeration of what would constitute the fundamental policy of Indian law nor is it possible to place the expression in the straitjacket of a definition. What is important in the context of the case at hand is that if on facts proved before them the arbitrators fail to draw an inference which ought to have been drawn or if they have drawn an inference which is on the face of it, untenable resulting in miscarriage of justice, the adjudication even when made by an Arbitral Tribunal that enjoys considerable latitude and play at the joints in making awards will be open to challenge and may be cast away or modified depending upon whether the offending part is or is not severable from the rest."
29. It is clear that the juristic principle of a "judicial approach" demands that a decision be fair, reasonable and objective. On the obverse side, anything arbitrary and whimsical would obviously not be a determination which would either be fair, reasonable or objective.
[Emphasis Supplied
62. I have consciously not gone into judgements that relate to awards
challenged after October 23, 2015. Applying the principles extracted
above, in my opinion, the Learned Arbitral Tribunal has not adopted a
judicial approach. The multiple leaps of faith, as articulated above -
first, treating observations that emerged and were recorded in the
MOM as an agreement; second, to ignore what the MOM records as the
parties having actually agreed upon; and third, treating such
observations as having been amendments of such a magnitude and
nature that the parties intended to change the foundational risk-reward
JANUARY 17, 2026 Aarti Palkar
55.ARA.33.2015.doc
profile of the Project by transforming a conditional compensation
clause into a minimum guaranteed revenue contract, whereby a force
majeure provision ceased to have anything to do with force majeure -
all together point to the absence of a judicial approach and to perversity
leading to the fundamental policy of Indian law being violated.
63. Therefore, while it is not usual for two concurrent findings to be
reversed by the Section 37 Court, in the facts of this case, for the
reasons set out above, in my opinion, it is necessary to allow this
Petition, and set aside the Impugned Award and the Impugned
Judgement.
64. All actions required to be taken pursuant to this order shall be
taken upon receipt of a downloaded copy as available on this Court's
website.
[SOMASEKHAR SUNDARESAN, J.]
JANUARY 17, 2026 Aarti Palkar
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!