Citation : 2026 Latest Caselaw 2177 Bom
Judgement Date : 26 February, 2026
2026:BHC-AS:9826
F-J-905-WP-12061-2024.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 12061 OF 2024
Patel Builders and Developers Through ...Petitioners
Its Partners Bilal Rauf Patel & Ors
Versus
The State of Maharashtra Through ...Respondents
Its Secretary & Ors
Mr. Nitin Gaware Patil, a/w Mr. Prajwal Thorat, i/b Sachin
Thorat for the Petitioners.
Mr. R. S. Pawar, AGP for Respondents.
CORAM: SOMASEKHAR SUNDARESAN, J.
RESERVED ON: February 23, 2026
PRONOUNCED ON: February 26, 2026
Judgement :
1. Rule. Rule made returnable forthwith. By consent of the
parties, heard finally.
Context and Background :-
2. This is a Petition challenging the validity, legality and
propriety of an order dated August 1, 2024 (" Impugned Order"), passed Digitally signed by
ASHWINI ASHWINI JANARDAN JANARDAN VALLAKATI by Respondent No. 2, the Chief Controller of Revenue Authority VALLAKATI Date:
2026.02.26 10:51:42 +0530 ("CCRA"), who has re-assessed the value of stamp duty payable by the
February 26, 2026
F-J-905-WP-12061-2024.doc
Petitioners in connection with a Development Agreement that governed
a development already completed on a plot of land in close proximity to
a railway line.
3. The property in question is land bearing Survey No.47, Hissa
No.1A and Survey No.47, Hissan No.1H situated in village Uttekhol, Tal.
Mangaon, Dist. Raigad ("Subject Land"). On April 18, 2022, the
Petitioners submitted the Development Agreement for adjudication of
stamp duty to Respondent No.3, Collector of Stamps (" Stamp
Collector"), Raigad-Alibaug under Section 31 of the Maharashtra
Stamps Act, 1958 ("Stamp Act"). On April 19, 2022, the Stamp Collector
valued the property at Rs.5,14,73,000/- and asked the Petitioners to pay
Rs.25,73,700/- at the rate of 5% of the market value of the property
under Article 5(g-a)(i) of Schedule-I of the Stamps Act. The entire
amount was paid and a certification was issued with a final order under
Section 31 for the aforesaid sum.
4. On December 29, 2022, the Petitioners received a notice
from the Stamp Collector stating that a review of the adjudication is
being taken up on the premise that the adjudication had been made with
a deficit of Rs.82,84,155/-. The Petitioners filed a reply on January 11,
2023, pointing out that the amount originally adjudicated by the Stamp
February 26, 2026 Ashwini Vallakati
F-J-905-WP-12061-2024.doc
Collector was accurate. To demonstrate the same, it was submitted that
the original computation had accurately taken into account the actual
constructed area based on the development potential and the
constraints and restrictions on the development that had actually been
applicable to the Subject Land.
5. The permission granted by the Town Planning Officer,
Alibaug, by letter dated March 4, 2022, was relied upon to indicate that
the Floor Space Index ("FSI") of 1.1 had been granted and the total
actual constructed area aggregated to 4,386.59 square metres. Out of
this, 45% was to be given to the landowner and 55% was attributable to
the developer, and therefore, the original adjudication by the Stamp
Collector was asserted as being accurate.
6. On April 26, 2023, the CCRA issued a notice contending that
the deficit stamp duty was Rs. ~82.84 lakhs, as stated above, and taking
up revision under Section 53A of the Stamp Act. A detailed reply was
filed and a personal hearing followed on May 26, 2023, and a final
hearing took place on December 5, 2023. The CCRA adjudicated the
market value for purposes of stamping the Development Agreement at
Rs.25,31,04,500/- and called for stamp duty payment in the sum of
Rs.1,26,55,255/-.
February 26, 2026 Ashwini Vallakati
F-J-905-WP-12061-2024.doc
Contentions of the Parties:
7. Mr. Nitin Gaware Patil, Learned Advocate for the Petitioners
would submit that the original computation was accurate and was in
conformity with the guidelines for computation of market value as
applicable to Development Agreements. He would submit that the FSI
of 1.1 that had been taken into account was accurate and was also in
conformity with the actual approval for the development and the actual
potential that had been permitted. The development had even been
completed, with Occupation Certificate and Completion Certificates
have also been issued. The CCRA's computation, he would submit, is
totally incorrect since, in the teeth of the applicable FSI of 1.1, the CCRA
has adopted FSI of 4.0 on the total land admeasuring 5,010 square
metres.
8. Mr. Gaware Patil would contend that the Konkan Railway
line passes through the plot of land, which is why two parts of the survey
number, with an appropriate distance from the railway line have been
developed. The development was subject to approval by the Konkan
Railway Corporation Limited ("Konkan Railway"), which too had
granted its No Objection Certificate with specific terms and conditions
that would ensure that the building height is limited such that, in the
February 26, 2026 Ashwini Vallakati
F-J-905-WP-12061-2024.doc
event of its collapse, no debris would fall on the railway line. He would
submit that a 15-metre area adjoining the railway track is required to be
kept vacant, and therefore, the assumption of the entire land being
available for development is also wrong. The Konkan Railway imposed
height restrictions led to one building being limited to ground plus four
storeys and another being limited to ground plus seven storeys. The
overall height of these buildings has been specifically stipulated, and
therefore, any assessment of market value that ignores these factors
would be totally inappropriate.
9. Mr. R. S. Pawar, Learned AGP on behalf of the Respondents,
would submit that the Development Agreement nowhere refers to an
FSI of 1.1, and therefore, the assessment cannot be faulted with. He
would point to the reply affidavit filed by the Respondents to contend
that the adoption of an FSI of 4.0 is consistent with the applicable
Development Control Regulations and that the remaining FSI could be
used in the future, if and when there is a change in the regulatory
framework, particularly since the Development Agreement is silent.
Therefore, he would defend the Impugned Order and the computation
of the deficit stamp duty in revision on the premise that the original
adjudication had missed this element and had simply adopted the
contentions of the Petitioners.
February 26, 2026 Ashwini Vallakati
F-J-905-WP-12061-2024.doc
Analysis and Findings:
10. Having heard the Learned Advocates for the parties and
having examined the material on record, it is seen that the Petitioners
are right and the re-computation of stamp duty in revision is
unsustainable. The Annual Statement of Rates (" ASR") applicable for
areas falling in all Municipal Corporations, Municipal Councils, Nagar
Panchayats, etc., other than the Municipal Corporation of Greater
Mumbai, is noteworthy. Guideline No. 46 in the ASR specifically
requires consideration of the fact that where properties entail
restrictions on development, such as a site abutting a railway line,
resulting in the permissible FSI being incapable of exploitation due to
height limits and other restrictions, the constructed area certified by the
Competent Authority should be considered for valuation.
11. The said guideline is extracted as under:
46 fodklkoj izfrca/k vlysys {ks= ¼mnk- Funnel of vision, Vicinity of aerodrome / airport, existing fuel station, site abutting Railway tack boundry etc½ feGdrhps ewY;kadu½ :-
eatwj fodkl fu;a=.k fu;ekoyhe/;s bekjr map e;kZnk o brj fucZ/a kkeqGs vuqKs; pVbZ {ks= funsZ'kkadkuqlkj cka/kdke {ks= okijys tkÅ 'kdr ukgh v'kk Hkw[kaMkoj @ feGdrhoj LFkkfud izkf/kdj.kkps l{ke izkf/kdkjh ;kauh izekf.kr dsY;kuqlkjps cka/kdke {ks= eqY;kaduklkBh fopkjkr ?;kos-
February 26, 2026 Ashwini Vallakati
F-J-905-WP-12061-2024.doc
12. It is obvious that the factor to be considered is the limitation
and restriction on development owing to regulatory stipulations due to
the land abutting a railway line. The actual limitations imposed by
Konkan Railway are part of the record and were highlighted to the
CCRA. The conditions imposed by the Maharashtra State Road
Development Corporation ("MSRDC"), which have also stipulated the
distance to be maintained from the highway of MSRDC, form part of the
record. Based on the stipulations by Konkan Railway and MSRDC, the
building plans sanctioned by the Mangaon Nagar Panchayat on March
29, 2022, are explicitly clear - the built-up area explicitly permitted was
4,386.59 square metres.
13. The No Objection Certificate issued by Konkan Railway on
October 5, 2020, and by the MSRDC on March 24, 2022, form the basis
of the sanction granted by the Mangaon Nagar Panchayat on March 29,
2022, which renders a specific computation of built-up area.
14. The total area of the Subject Land was indeed 5,010 square
metres, but on such land, factoring in the restrictions, the two buildings
of specific height alone could be developed, and evidently, the built-up
area aggregated to 4,386.59 square metres.
February 26, 2026 Ashwini Vallakati
F-J-905-WP-12061-2024.doc
15. Evidently, the initial computation made by the Stamp
Collector factored in these precise heads of data and arrived at an
adjudication of the originally assessed stamp duty. This is seen in the
adjudication order dated April 20, 2022, in which, the market value has
been arrived at, taking into account the aforesaid factual data that is
evident from the material on record. Needless to say, the assessment
effected on April 19, 2022, factors in the restrictions applicable to the
development and arrived at the computation of market value and the
resultant stamp duty.
16. Therefore, it is evident that the CCRA indeed had before him
the entire material that formed part of the record, and therefore, the
CCRA ought to have made his adjudication in conformity with the
applicable guidelines. The CCRA ought to have taken into account the
limitations on the development to arrive at the actual built-up area in
order to compute the market value for purposes of adjudication of
stamp duty. Such objective material is writ large in the record made
available to the CCRA. Indeed, the height restrictions set out in the
sanction by the Mangaon Nagar Panchayat are directly in conformity
with the limits imposed by Konkan Railway, and therefore, it is clear
that the built-up area was 4,386.59 square metres.
February 26, 2026 Ashwini Vallakati
F-J-905-WP-12061-2024.doc
17. It is clear that the CCRA, in ignoring relevant material, has
effected two errors. First, he has adopted the entire area of 5,010 square
metres as the area being developed. Second, he has applied an FSI of
3.68, which is inappropriately inflated and has unduly returned a
finding that is in direct conflict with the applicable guidelines that
govern the assessment of market value, and indeed in conflict with the
regulatory restrictions actually applicable to the Subject Land and set
out in the approvals applicable to the development.
18. It is also clear that a detailed reply to the purported valuation
report dated August 11, 2023, was submitted by the Petitioners, squarely
pointing out all these facets to the CCRA. The specific restrictions
imposed by Konkan Railway were also highlighted. Therefore, while an
FSI of 4 could have been theoretically adopted from the Development
Control Regulations applicable locally, the specific restrictions to which,
the development was subject, and were in fact subjected to, have been
totally ignored. The guidelines to be applied for purposes of the
computation also form part of the record, and it is evident that applying
an FSI in excess of 1.1 is totally untenable. Therefore, the CCRA was
entirely arbitrary in ignoring relevant material before him in the form of
the limits applicable under the approvals granted by Konkan Railway
and by MSRDC, and taking into account irrelevant material such as the
February 26, 2026 Ashwini Vallakati
F-J-905-WP-12061-2024.doc
blanket and blind application of the full hypothetical potential under the
Development Control Regulations. This approach has rendered the
Impugned Order to be arbitrary in nature, necessitating that it be
quashed and set aside.
19. In these circumstances, I am satisfied that a case has been
made out for quashing and setting aside the Impugned Order. The
Respondents were required to specifically apply their minds to the
computations that have been made in the original order of the Stamp
Controller, and the restrictions imposed by Konkan Railway and
MSRDC, and indeed the approved sanction plans approved by the
Mangaon Nagar Panchayat.
20. Learned Advocate for the Petitioners submits that his
statement may be recorded, that in the unlikely event of the restrictions
currently imposed being revisited by the authorities, should there be any
change at all to the development potential in future, it would never be
covered by the Development Agreement that is being stamped. He
submits that exploiting such potential would necessitate a new
development project, for which a new instrument would need to come
into being. Such statement is accepted and taken on record. The
February 26, 2026 Ashwini Vallakati
F-J-905-WP-12061-2024.doc
Petitioners shall also issue a written confirmation to this effect to the
Respondents.
21. With the aforesaid directions, the Petition is allowed, and
Impugned Order is quashed and set aside. No order as to costs.
22. All actions required to be taken pursuant to this order shall
be taken upon receipt of a downloaded copy as available on this Court's
website.
[ SOMASEKHAR SUNDARESAN, J.]
February 26, 2026 Ashwini Vallakati
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!