Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Reliance Industries Ltd. And Anr. vs The Mumbai Metropolitan Region ...
2026 Latest Caselaw 3539 Bom

Citation : 2026 Latest Caselaw 3539 Bom
Judgement Date : 8 April, 2026

[Cites 25, Cited by 0]

Bombay High Court

Reliance Industries Ltd. And Anr. vs The Mumbai Metropolitan Region ... on 8 April, 2026

2026:BHC-OS:8906-DB
                                                                         Reliance-oswp-242-2018-J-R.doc




                                                                                                    Shephali



                               IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                   ORDINARY ORIGINAL CIVIL JURISDICTION
                                       WRIT PETITION NO. 242 OF 2018
                                                   WITH
                                   INTERIM APPLICATION NO. 2172 OF 2020
                                                    IN
                                       WRIT PETITION NO. 242 OF 2018


                     1.     Reliance Industries Limited,
                            A company incorporated under the
                            Companies Act, 1956 having its
                            Registered Office at Maker Chamber IV,
                            3rd Floor, Nariman Point,
                            Mumbai 400 021
                     2.     Mr. Rajumal Nahar,
SHEPHALI                    having his office at having his office at
SANJAY
MORMARE                     6th Floor, "B" Wing, Fortune 2000, "G"
 Digitally signed           Block, Bandra Kurla Complex,
 by SHEPHALI
 SANJAY
 MORMARE
                            Bandra (East), Mumbai 400 051.                             ...Petitioners
 Date: 2026.04.09
 15:15:50 +0530

                              ~ versus ~

                     1.     Mumbai Metropolitan Region
                            Development Authority (MMRDA),
                            an authority established under the
                            Mumbai Metropolitan Region
                            Development Authority Act, 1974 and
                            having its head Office at Plot C-14 &
                            C-15, 'E' Block, Bandra Kurla Complex,
                            Bandra (East), Mumbai 400 051.
                     2.     The Metropolitan Commissioner,
                            Mumbai Metropolitan Region
                            Development Authority, having office
                            at Plot C-14 & C-15, 'E' Block, Bandra
                            Kurla Complex, Bandra (East),
                            Mumbai 400 051.




                                                     Page 1 of 65


                    ::: Uploaded on - 09/04/2026                        ::: Downloaded on - 09/04/2026 21:35:21 :::
                                                   Reliance-oswp-242-2018-J-R.doc




 3.     The Deputy Metropolitan
        Commissioner,
        Mumbai Metropolitan Region
        Development Authority, having office
        at Plot C-14 & C-15, 'E' Block, Bandra
        Kurla Complex, Bandra (East),
        Mumbai 400 051.                                      ...Respondents

 A PPEARANCES
 For the Petitioners               Mr.    Vikram     Nankani,    Senior
                                   Advocate, with Mr. Vikramaditya
                                   Deshmukh, Mr. Ashwin Dave,
                                   Mr. Ameya Nabar & Ms. Swati Jain,
                                   i/b A. S. Dayal & Associates.
 For Respondents-MMRDA             Dr. Birendra Saraf, Senior Advocate,
                                   with Mr. Nishant Chotani, Mr. Nivit
                                   Srivastava,   Ms.      Sneha   Patil,
                                   Ms. Aditi Sinha, Mr. Hrishikesh
                                   Joshi & Ms. Isha Vyas, i/b Maniar
                                   Srivastava Associates.



                       CORAM   :    SHREE CHANDRASHEKHAR, CJ &
                                    SUMAN SHYAM, J.
           RESERVED ON         :    22nd JANUARY 2026.
        PRONOUNCED ON          :    8th APRIL 2026.

 JUDGMENT (Per Suman Shyam, J):

-

1. Rule. Rule is made returnable forthwith.

2. By consent of the parties, the matter is taken up for final

hearing.

Reliance-oswp-242-2018-J-R.doc

3. Assailing the demand-cum-show cause notice dated 12 th

September 2017 (Exhibit "R"), whereby, the Respondent No.1-

Mumbai Metropolitan Region Development Authority ("MMRDA")

had demanded additional premium/penalty as per statements 'A'

and 'B' annexed thereto, for the alleged delay of 7 years and 12

days in completion of construction of a Convention & Exhibition

Centre and Commercial Complex on Plot No. C-64, 'G' Block,

Bandra-Kurla Complex, Mumbai, the Petitioners have approached

this Court by filing this Writ Petition invoking the jurisdiction of

this Court under Article 226 of the Constitution of India. During

the pendency of the Writ Petition, by the communication dated

13th June 2019 (Exhibit "X") a further amount of

Rs.1116,83,10,102/- was demanded from the Petitioner No. 1 as

additional premium, along with interest, towards extension of

time for completing the construction of the building by using the

additional built up area of 72,500 sq mtrs. allotted under the

Supplementary Lease Deed dated 13 th July 2007. The said Notice

is also under challenge in this Writ Petition. The facts and

circumstances giving rise to the filing of the present Writ Petition,

shorn of unnecessary details, are as hereunder.

Reliance-oswp-242-2018-J-R.doc

4. The Petitioner No.1 is a company incorporated under the

provisions of the Companies Act, 1956. As per statements made in

the Writ Petition it is engaged inter alia in the business of

exploration of petroleum products and allied activities. Petitioner

No.2 is a shareholder of the Petitioner No.1 company. The

expression "Petitioner" shall here-in-after refer to the Petitioner

No.1 company. The Respondent No.1, MMRDA, is a statutory

authority constituted under Section 3 of the Mumbai Metropolitan

Region Development Authority Act, 1974. Respondent Nos.2 and 3

are its officers.

5. In the month of December 2005, Respondent No.1, being

the owner of the land, had invited bids for leasing out Plot No. C-

64 admeasuring approximately 75,000 sq. mtrs. situated in 'G'

Block of Bandra-Kurla Complex (BKC) for the purpose of

construction of "Convention and Exhibition Centre and

Commercial Complex". The Petitioner had submitted its bid for the

said plot and was declared successful bidder. As such, by the letter

dated 15th February 2006, the Respondent No.1 had approved the

proposal for leasing out the aforesaid plot of land to the Petitioner

for a maximum permissible built-up area of 65,000 sq. mtrs. for

Reliance-oswp-242-2018-J-R.doc

the Convention and Exhibition Centre and 50,000 sq. mtrs. for the

Commercial Complex, aggregating to 1,15,000 sq. mtrs., for a

total premium of Rs.1104 crores. Pursuant thereto, a registered

Lease Deed dated 1st September 2006 came to be executed by and

in between the Petitioner and Respondent No.1 for leasing out the

demised plot for a term of 80 years. Possession of the said plot of

land was handed over to the Petitioner on the same day i.e. on 1 st

September 2006.

6. Article 2(d) of the Lease Deed dated 1st September, 2006

stipulates that the lessee shall, within three months from receipt of

approval of plans, commence and within a period of four years

from the date of the lease, build and completely finish the

construction of the Convention and Exhibition Center and

Commercial Complex, fit for occupation. Article 2(e) lays down

that in case of failure to adhere to the said time limit, extension of

time may be granted upon payment of additional premium at the

prescribed rates.

7. On 14th October 2006 the Petitioner had applied for

permission to start excavation and removal of earth on site by

attaching a report of the Structural Consultants. By the said letter,

Reliance-oswp-242-2018-J-R.doc

the Petitioner had also informed the Respondents that it will not

carry out any construction activity on the site without prior

intimation to the MMRDA and also without obtaining the required

statutory permissions.

8. After the execution of the Leased Deed dated 1 st September

2006, the FSI for the plots in block 'G' of BKC was increased from

2.00 to 4.00. As such, in the month of February 2007, the

Petitioners had applied for allotment of additional built-up area of

72,500 sq. mtrs.. By the letter dated 7 th May 2007, the Respondent

No.1 had approved the allotment of additional built up area of

41,000 sq. mtrs. for the Convention Centre and 31,500 sq. mtrs.

for the Commercial Complex, aggregating to 72,500 sq mtrs.,

against payment of premium of a total amount of Rs.696 crores.

Upon allotment of the additional built up area, as aforesaid, a

Supplementary Lease Deed dated 13th July 2007 was executed by

and between the parties in respect of the additional built-up area.

9. It would be pertinent to note herein that after the allotment

of the additional built up area, Reliance Communication &

Infrastructure Ltd., along with another, had instituted Writ Petition

No.1165 of 2007 before this Court challenging the grant of the

Reliance-oswp-242-2018-J-R.doc

additional FSI of 71,500 sq mtrs to the Petitioner for the

Convention and Exhibition Centre (41,000 sq mtrs) and

Commercial Complex (31,500 sq mtrs). The Petitioner was

impleaded as Respondent No. 3 in that writ petition. By the

interim order dated 15th October 2007 passed in the said Writ

Petition, a Division Bench of this Court had restrained the

Petitioner from utilizing the additional FSI of 31,500 sq. mtrs.

allocated for the Commercial Complex.

10. On 17/04/2008, the Petitioner submitted revised plans

seeking necessary approvals. Based on the same, on 12 th

June,2008, Commencement Certificate (CC), upto the plinth level,

only in respect of the Convention & Exhibition Centre plot "A' of

plot C-64 in Block "G" of BKC Complex, with total permissible

built up area of 1,06,000sq mtrs. was issued in favour of the

Petitioner. However, no CC was issued in respect of the

commercial complex.

11. There is no controversy in this case about the fact that the

proposed development was composite in nature with common

basement and foundation. As such, by the letter dated 28 th

January 2009, the Petitioner had submitted progress report and

Reliance-oswp-242-2018-J-R.doc

informed the Respondent No.1 that commencement of

construction at site was affected due to the interim order passed

by the court since the basement and foundation of the Convention

& Exhibition Centre (CEC) as well as the Commercial Complex

(CC) was common. However, by letter dated 18 th February 2009,

the Respondent No.1 had replied that since there was no restraint

order in respect of the Convention & Exhibition Centre, hence,

the Petitioner to continue with the construction of the CEC as per

CC (1,06,000 sq mtrs) and also expedite the final hearing of the

proceeding pending in the court. The Petitioner was also asked to

furnish Bank Guarantee of Rs 20 crores towards liquidated

damage and Completion Guarantee for a sum of Rs 20 crores.

12. In response to the above, by the letter dated 16 th March

2009, the Petitioner had highlighted the design uncertainty in

proceeding with the construction and had sought the guidance of

the MMRDA in the matter. Due to the uncertain circumstances

arising in view of the pending Court proceedings, the Petitioner

had also sought extension of time to complete the project.

However, in the meantime, the Commencement Certificate issued

earlier on 12th June 2008 had lapsed in June 2009.

Reliance-oswp-242-2018-J-R.doc

13. While the matter was poised as above, in the 129 th Meeting

of the MMRDA held on 8th September 2011, the Respondent No.1

had resolved to extend the time for allotment of additional FSI in

'G' Block till December 2012. Accordingly, by the letter dated 8 th

November 2011, the Respondent No.1 had offered additional

built-up area to the Petitioner by recording that there would be no

time limit for construction of such additional built-up area.

14. However, in view of the pendency of Writ Petition No 1165

of 2007 and the interim order operating therein, on 14 th October

2010, the Petitioner had offered to surrender the additional built

up area of 72,500 sq.mtrs and sought refund of the amount of Rs

1064 crores being the premium, along with interest, paid for the

aforesaid built up area. The said request was followed by the

subsequent letters dated 3rd August 2020 and 10th January 2012

rehearing the request. In response to the above request of the

Petitioner, by the letter dated 1st February 2012, the Respondent

No.1 had informed the Petitioner that its request for refund of

lease premium by surrendering the additional built up area cannot

be considered as there is no provision in the Leased Deed as well

the Supplementary Lease Deed permitting the same. It was,

Reliance-oswp-242-2018-J-R.doc

however, clarified that in so far as the request for extension of

time for completion of construction on the plot under reference as

per Article 2(d) of the Lease Deed dated 1 st September 2006, is

concerned, the period during which the stay order of the court

was under operation, will not be considered for computing the

four years time period, meaning thereby, that the period, during

which the interim order passed in Writ Petition No.1165 of 2007

was operative, shall be excluded while computing the four-year

period stipulated under Article 2(d) of the Lease Deed dated 1 st

September, 2006. Be it stated here in that the Writ Petition No

1165 of 2007 was withdrawn on 12 th March 2012 as a result of

which, the stay order also got vacated on the same day.

15. In the wake of the aforesaid development, the Respondent

No.1, by letters dated 20th March 2012 and 3rd April 2012

approved allotment of further additional built-up area of 1,00,000

sq. mtrs. and 25,000 sq. mtrs. against payment of premiums of

Rs.1470 crores and Rs.367.50 crores respectively. With the

allotment of the additional built up area of 1,25,000 sq mtrs, the

total built-up area allotted by the Respondent No.1 to the

Petitioner for construction to be carried out on the same plot, was

Reliance-oswp-242-2018-J-R.doc

increased to 3,12,500 sq. mtrs. It is a matter of record that the

Petitioner had paid an aggregate premium of Rs.4,005 crores to

the Respondent No.1 for the allotment of the entire built up area

of 3,12,500 sq. meters.

16. In view of the allotment of additional built-up area, as

aforesaid, the Petitioner was required to revise the development

plans for a composite structure and also obtain various statutory

approvals afresh including the environmental clearance under the

EIA Notification dated 14th September 2006, height clearance from

Civil Aviation Authorities, approval from the High Rise Committee,

permission from the Municipal Corporation of Greater Mumbai

and other statutory authorities. Accordingly, various approvals

were obtained during the year 2013 and early part of the year

2014.

17. On 26th June 2013, Environment Clearance for the proposed

" Convention & Exhibition Centre and Commercial Complex" over

plot No. C-64 in Block-G of BKC was granted to the Petitioner for

the entire FSI of 3,12,500 Sq. Mtrs. In the said communication

also, the CEC & CC was shown as a composite construction.

Reliance-oswp-242-2018-J-R.doc

18. After compliance of the above requisites and submission of

the revised plans, the Respondent No.1 had issued

Commencement Certificate dated 16th April 2014 for construction

upto the 7th floor level of the composite building comprising

Convention & Exhibition Centre and Commercial Complex.

Thereafter, further Commencement Certificates were issued on

23rd December 2016, 17th April 2017 and 19th May 2017.

19. In the meantime, in its 131st Meeting held on 22nd October

2012, the Respondent No.1 had considered granting extension of

time for completion of construction by taking note of the delay

caused in obtaining multiple statutory permissions/ clearance

form different agencies. After considering the matter, the

Respondent No.1, vide Resolution No.1283 adopted in the said

meeting, had recommended extension of time from four years to

six years for completing the construction. The said resolution was,

however, kept in abeyance for some. Finally, in its 138 th Meeting

held on 26th August 2015, the Respondent No.1 had resolved to

amend Article 2(d) to provide six years time period for completion

of construction in respect of plots leased after the date of the

resolution and further resolved to constitute a One Man

Reliance-oswp-242-2018-J-R.doc

Committee to examine the issue of recovery of additional

premium in the cases where delay was attributable to time

required for obtaining statutory permissions.

20. Notwithstanding the above developments,the Respondent

no.1 had insisted on an undertaking from the Petitioner to pay

the additional premium for grant of extension of time for

completing the construction of the building. As such, on 18 th

November 2016, the Petitioner had submitted an undertaking to

the above effect thus, agreeing to pay the additional premium for

extension of time for completing the construction of the building

over Plot No- C-64 in Block "G" of the BKC before receipt of

Occupation Certificate or decision of the Authority, which ever was

earlier, with a further undertaking not to create any third party

liability on the project till receipt of the Occupation Certificate.

21. Based on such undertaking, the Respondent No 1 had issue

further Commencement Certificate dated 19th May 2017 for the

Fire Check floor and the 15th (part) floor.

22. While the above process was under way, the Respondent No.

1 had issued the impugned Notice dated 12 th September 2017,

Reliance-oswp-242-2018-J-R.doc

alleging that as per Article 2(d) of the Lease Deed dated 01 st

September 2006, the Petitioner had the obligation to erect and

completely finish the construction, fit for occupation, within four

years from the date of execution of the Lease Deed. However,

although, there was delay of 7 years and 12 days the Petitioner

had failed to pay the penalty for the entire period of delay till

completion of the construction, fit for occupation. It was further

mentioned that the amount on account of delay in construction,

along with interest, has been shown in Annexures "A" and "B". It

was alleged that the Petitioner had committed breach of the terms

and conditions of the Deed of Lease. As such, the MMRDA had the

power to recover the said amount as arrears of land revenue and

also resume the land as per Articles 5 & 6 of the Lease Deed. The

Petitioner was, therefore, called upon to remedy the situation

within 30 days, failing which, the Authority will have the right to

determine the lease and enter upon the leased premise and also

proceed to recover the amount due as arrears of land revenue.

23. It would be pertinent to mention here-in that the Notice

dated 12th September, 2017 does not mention the amount claimed

by the Respondent No. 1. The figures projected in the Statements

Reliance-oswp-242-2018-J-R.doc

"A" & "B" annexed to the Writ Petition are also not legible.

However, it appears that upon receipt of the Notice dated 12 th

September 2017, the Petitioner had sent reply dated 11 th October

2017 denying its liability to pay the amount claimed with a further

request to withdraw the show cause notice dated 12 th September,

2017. However, no action was taken by the Respondents on such

request made by the Petitioner.

24. Aggrieved by the dated 12th September 2017 the Petitioner

had instituted Writ Petition on 30 th November, 2017 which was

originally registered as Writ Petition (L) No 3395 of 2017. On 8 th

December 2017, this Court, while issuing notice, had recorded the

statement made on behalf of Respondent No.1 that till next date

of hearing no coercive steps would be taken pursuant to the

impugned notice. Records reveal that the said ad-interim order

was extended by the court from time to time. Subsequently, the

said writ petition was registered as Writ Petition No.242 of 2018

i.e. the present Writ Petition.

25. On 06th February 2019, the Architect engaged by the

Petitioner had applied for part Occupation Certificate for the built

up area of 44,621 sq.mtrs. That apart, by the letter dated 18 th

Reliance-oswp-242-2018-J-R.doc

February 2019, the Petitioner had deposited a sum of

Rs.646,77,68,594 (Rupees Six Hundred and Forty Six Crores

Seventy Seven Lakhs Sixty Eight Thousand Five Hundred and

Ninety Four) after deducting TDS amount of Rs.21,32,20,676/-

and furnished a Bank Guarantee of an amount of

Rs.13,12,54,85,287/- (Rupees Thirteen Hundred Twelve Crores

Fifty Four Lakhs Eighty Five Thousand Two Hundred and Eighty

Seven) based on an alternate computation treating the delay to be

for the period from 01st September 2010 to 17th February 2019. It

was also mentioned in that letter that the amount was being

deposited under protest and without prejudice to the rights and

contention of the Petitioner in the pending Writ Petition.

26. Upon receipt of the above amount, on 20 th February 2019,

the Respondent No.1 had issued part Occupation Certificate for

44,621 sq. mtrs. However, soon thereafter i.e. on 13 th June 2019,

the Petitioner was served with another communication demanding

payment of a further amount of Rs.1116,83,10,102/- as additional

premium for the delay in completing the construction of the

additional built up area as allotted under the Supplementary

Lease Deed dated 13th July 2007.

Reliance-oswp-242-2018-J-R.doc

27. Despite the notice dated 13th June 2019, the Petitioner,

through its Architect, had applied for further part Occupation

Certificate for the built up area of 1,24,000 sq. mtrs. However, the

Respondent No. 1 refused to process the same until the amount of

Rs.1116,83,10,102/- was paid. Under such circumstances, the

Petitioner had filed Interim Application No.2171 of 2020 arising

out of this Writ Petition, seeking a direction upon the Respondent

No.1 for issuance of Occupation Certificate without insisting upon

payment of the additional premium. By the judgment and order

dated 12th July 2021 passed in the Interim Application No. 2171 of

2020, this Court had allowed the prayer made in the Interim

Application and directed the Respondent No.1 to process the

applications seeking Occupation Certificates including the

application dated 3rd February 2020, without insisting on payment

of the amount mentioned in the subsequent demand notice dated

13th June 2019. In the said order it was also observed that when

the court was in seisin of the matter and considering the earlier

interim order dated 8th December 2017, the Respondents ought

not to have issued the notice dated 13th June 2019. By carrying

out amendments in the writ petition, the Petitioner has

challenged the letter dated 13th June 2019.

Reliance-oswp-242-2018-J-R.doc

28. The Respondent Nos. 1 and 2 have opposed the Writ

Petition by filing joint Reply. The plea taken by the Respondents in

their Reply, reduced to their essence, is to effect that that the Writ

Petition involves disputed questions of fact, which cannot be

adjudicated in a Writ Petition; that the Writ Petitioners have an

alternate, efficacious remedy by way of Civil Suit; that the dispute

is purely contractual in nature involving interpretation of the

terms and conditions of the contract, which cannot be entertained

in a Writ Petition; that this is not a case of infringement of any

constitutional, statutory or fundamental right of the Petitioner;

that the Demand Notice has issued on account of breach of

conditions of the Lease Deed and, therefore, the same does not

involved violation of any constitutional right; that Articles 2(a)

and 2(d) of the Lease Deed, which require completion of the

construction within a period of four years from the date of Lease

Deed are binding and mandatory clauses in the Lease Deed.

Therefore, those are enforceable under the law; even if the delay

in construction has occurred due to interim order of Court or on

account of force majeure, even than, in view of Article 2(d), any

extension of time could only been granted upon payment of

additional premium. Since the MMRDA would not have any power

Reliance-oswp-242-2018-J-R.doc

to waive such amount, therefore, payment of additional

premium/penalty was inevitable in case of delay; that the restraint

order of the Court was limited only to the additional area of

31,500 sq.mtrs. of commercial FSI. Therefore, the same did not

prevent commencement and completion of construction of the

Convention Centre; that allotment of additional built-up area was

optional. Since the Petitioners have opted for the additional built-

up area, therefore, the allotment of additional built up area

cannot be a justifiable ground for the delay in completion of

construction; that the Petitioners have issued an unconditional

undertaking on 14th December 2016 agreeing to pay the additional

premium/penalty for grant of extension of time. Therefore, they

would be bound by such undertaking; that the Writ Petitioner has

approached this Court by suppressing material facts and

particulars pertaining to the undertaking dated 14 th December

2016, therefore, the Writ Petition is liable to be dismissed on such

count alone; that the decision of the MMRDA to extend the time

period from four years to six years was applicable prospectively,

i.e., with effect from August, 2015 and therefore, the same would

not cover the case of lessees such as the Petitioner in respect of

whom, the Lease Deed was executed prior to August, 2015.

Reliance-oswp-242-2018-J-R.doc

29. By filing Rejoinder, the Writ Petitioner, while denying the

assertions made by the Respondents, has reiterated that it is a case

of violation of fundamental right of the Petitioner guaranteed

under Article 14 of the Constitution of India. It has further been

asserted that even in contractual matters, unfair treatment

extended by the State or its instrumentality would be amenable to

writ jurisdiction of this Court; that due to the allotment of the

additional built-up area and the integrated design of the project, it

would be impossible to complete the original portion of the

building within four years since it included common structures

such as common basement and services, etc. The Petitioners have

also denied the contention that the restraint order of the Court did

not affect the integrated planning and common infrastructure of

the project so as to permit bifurcation of the construction; it has

also been alleged that the Petitioner being similarly situated

Lessee, extension of time from four years to six years would be

equally applicable to them as denial of such benefit would amount

to unfair discrimination; the Petitioners have further contended

that similarly situated entities such as Bharat Diamond Bourse &

Indian Oil Corporation have been granted extension of time

without levy of additional premium; it has also been contended

Reliance-oswp-242-2018-J-R.doc

that the undertaking dated 14th December 2016 was obtained

under coercion viz. On the threat of withholding Occupation

Certificate and, therefore, the same cannot preclude the Petitioner

from agitating its grievance as per law; the Petitioner has also

denied suppression of material facts.

30. In their additional Reply, the Respondents have controverted

the statements made in the Rejoinder Affidavit while maintaining

their original stand justifying the demand for the additional

premium.

31. This Writ Petition was analogously heard along with three

other Writ Petitions being Writ Petition No.864 of 2018, Writ

Petition No.2377 of 2018 and Writ Petition No.3209 of 2017,

involving similar issues wherein, identical reliefs were sought by

the Writ Petitioner(s).

32. We have heard the learned Senior Counsel appearing for the

parties and have also perused the pleadings and documents placed

on record.

33. Mr. Vikram Nankani, learned Senior Counsel appearing for

the Petitioners, has argued that the impugned demand notice

Reliance-oswp-242-2018-J-R.doc

dated 12th September 2017 and the subsequent communication

dated 13th June 2019 issued by Respondent No.1 seeking recovery

of additional premium on account of alleged delay in completion

of construction are arbitrary, illegal and unsustainable in law.

According to the learned Senior Counsel, the demand proceeds on

an erroneous interpretation of Clauses 2(a), 2(c) and 2(d) of the

Lease Deed dated 1st September 2006, in as much as under Clause

2(c), no construction work could commence until the plans and

specifications were approved by the planning authority. It is

therefore submitted that the timeline for completion of

construction cannot be computed independent of such approvals.

34. The learned Senior Counsel further submits that the project

contemplated construction of a Convention and Exhibition Centre

and Commercial Complex as a composite development.

Subsequent to the execution of the Lease Deed, Respondent No.1

had allotted additional built-up area of 72,500 sq. mtrs. under the

Supplementary Lease Deed dated 13 th July, 2007, and thereafter,

further additional built-up area of 1,25,000 sq. mtrs. in the year

2012. The allotment of such additional built-up area required

revision of the development plans and fresh statutory approvals

Reliance-oswp-242-2018-J-R.doc

and therefore, the timelines originally contemplated under the

Lease Deed dated 1st September 2006 cannot be strictly applied to

such construction.

35. The learned Senior Counsel further has submitted that the

allotment of additional built-up area was unconditional and

Respondent No.1 had itself clarified that there would be no time

limit for construction of such additional built-up area. Therefore,

by granting such additional development rights during the

subsistence of the Lease Deed, Respondent No.1 must be deemed

to have waived the condition relating to completion of

construction within four years.

36. It is also submitted that the development of the project was

affected by the order of injunction passed by this Court in Writ

Petition No.1165 of 2007, which restrained utilization of a portion

of the additional built-up area until 12th March 2012. The

Petitioners had requested Respondent No.1 to exclude the said

period while computing the four-year period stipulated under the

Lease Deed which was confirmed by the Respondent No. 1 vide

communication dated 1st February 2012. As such, such time line

cannot be enforced.

Reliance-oswp-242-2018-J-R.doc

37. The Senior Counsel has further submitted that the project

required several statutory approvals from various authorities

including environmental clearance, aviation height clearance,

approval of the High-Rise Committee and permissions from the

Municipal Corporation of Greater Mumbai. According to the

Petitioner, these approvals were obtained over a period of time

and the commencement certificate for the integrated project was

eventually issued only in the year 2014. The learned Senior

Counsel therefore submits that the period of four years

contemplated under Clause 2(d) of the Lease Deed must be

construed in a commercially reasonable manner and the same

must be computed only after approval of the development plans

and issuance of the necessary commencement certificates.

38. The learned Senior Counsel has further argued that the

Respondent No.1 had itself recognized the practical difficulties

faced by developers in completing construction within four years

and at its 138th Meeting held on 26th August 2015, resolved to

amend the standard form of lease by extending the period for

completion of construction from four years to six years. According

to the Petitioner's Counsel, restricting the benefit of the said

Reliance-oswp-242-2018-J-R.doc

decision only to leases executed after 26 th August 2015 would be

arbitrary and discriminatory, since all developers in Bandra-Kurla

Complex are required to obtain similar statutory approvals. It is,

therefore, contended that the impugned action of the Respondent

No.1 violates Article 14 of the Constitution of India.

39. To sum up his arguments, the learned Senior Counsel has

submitted that the present case is squarely covered by the decision

of this Court rendered in the case of Raghuleela Builders Pvt. Ltd.

& Anr vs. MMRDA & Ors. , whereby in identical fact situation and

similar circumstances, this Court, by interpreting similar clauses in

the lease deed, has held that the demand of additional premium

on account of delay in completing the construction was arbitrary

and illegal and, accordingly struck down such demand.

40. Dr. Birendra Saraf, learned Senior Counsel appearing for the

Respondent Nos.1 and 2,on the other hand, has opposed the

prayer made in the Writ Petition and has also questioned the

maintainability of the Writ Petition by contending that the dispute

between the parties arise out of contractual obligations contained

in the Lease Deed and the Supplementary Lease Deed and the

same involves several disputed questions of fact which cannot be

Reliance-oswp-242-2018-J-R.doc

adjudicated in a writ petition in exercise of jurisdiction under

Article 226 of the Constitution of India. He has further argued that

the Writ Petition is hit by delay and laches and the relief prayed

for is also barred by limitation. According to Dr. Saraf, , since the

Petitioner had earlier sought extension of time for completion of

construction and had not challenged the communications issued

by Respondent No.1 at the relevant time, hence, the challenge

made to such demand notices is not maintainable at this point of

time.

41. The learned Senior Counsel for the Respondents has further

argued that the recovery sought by Respondent No.1 is strictly in

accordance with the provisions of the MMRDA Act, the MMRDA

(Disposal of Land) Regulations, 1977 as well as the terms and

conditions of the Lease Deed executed by and between the parties.

According to learned counsel, the clauses contained in the Lease

Deed are statutory in nature. Therefore, under Article 2(e),

extension of time for completion of construction can be granted

only upon payment of additional premium at the prescribed rates

which cannot be waived even by the MMRDA.

Reliance-oswp-242-2018-J-R.doc

42. Dr. Saraf has further argued that the Petitioner had

furnished undertakings promising to pay the amount of additional

premium for the delay in completing the construction. Therefore,

the Petitioner cannot now resile from such promise.

43. The learned Senior Counsel for the Respondents has also

argued that the reliance placed by the Petitioner on the judgment

in Raghuleela Builders Pvt. Ltd. & Anr. (Supra) is misplaced in as

mush as the said decision was rendered in the peculiar facts of

that case.

44. To sum up his arguments, Dr. Saraf has submitted that the

Petitioners have approached this Court without disclosing material

facts and producing the relevant documents. Since they have

approached this court with unclean hands, hence, the Petitioners

are not entitled to any relief from the court of equity. As such, the

Writ Petition be dismissed.

45. In support of his above arguments, Dr. Saraf, has relied

upon the following decisions:-

(a) State of Punjab and Ors. vs. Dhanjit Singh Sandhu1

1 (2014) 15 SCC 144.

Reliance-oswp-242-2018-J-R.doc

(b) Atur Park-4 Co operative Housing Society Ltd. vs State of Maharashtra2

(c) State of Goa vs. Dr. Alvaro Alberto Mousinho3

Plea regarding Maintainability of the Writ Petition :-

46. Insofar as the plea regarding maintainability of the Writ

Petition is concerned, at the very outset, it deserves to be

mentioned herein that although the maintainability of the Writ

Petition has been questioned inter-alia on the ground that several

disputed questions of facts are involved there-in, yet, after

examining the record, we find that the material assertions made in

the Writ Petition are all based on documents annexed thereto,

which are admitted documents. Moreover, in view of the plea

raised by the Petitioner that the action of the Respondent No. 1 in

levying additional premium/penalty for the delay in completion of

construction is not only contrary to the terms and conditions of

the Lease Deed, but also, arbitrary and illegal and hence, in

violation of the fundamental rights guaranteed to the Petitioner

under Article 14 of the Constitution, we are of the view that the

2 2023 SCC Online Bom 874.

3 (2019) 10 SCC 465.

Reliance-oswp-242-2018-J-R.doc

issues raised in the Writ Petition have an element of public law

character.

47. In the case of Joshi Technologies International IBC vs. U.O.I.

& Ors. , the Hon'ble Supreme Court has observed that there is no

absolute bar to the maintainability of a Writ Petition, even in

contractual matters or where there are disputed questions of fact

or even when monitory claim is raised, provided, the Court is

called upon to examine the issue which has a public law character

attached to it. Having regard to the core controversy involved in

this proceeding and considering the fact that the issues involved in

this Writ Petition would call for determination by this Court based

on interpretation of the relevant Articles of the Lease Agreement

as well as the documents exchanged by and between the parties so

as to ascertain fairness in the action of the Respondent No 1, we

are unable to agree with the stand of the Respondents that the

Writ Petition ought to be dismissed on the ground that it raises

disputed questions of facts.

48. Likewise, from a reading of Section 44 of the MMRDA, Act

1974, we find that the provision for Appeal provided thereunder,

is available for disputes regarding recovery of money due to the

Reliance-oswp-242-2018-J-R.doc

authority as arrears of land revenue. Since the challenge made to

the impugned demand notice is on the ground that the same is

contrary to the terms of the Supplementary Lease Deed and hence,

illegal and arbitrary as such, we are of the opinion that the said

controversy cannot be effectively adjudicated in an Appeal filed

under Section 44. Therefore, we reject the contention of the

Respondents that the Petitioner has an effective and efficacious

alternative remedy.

49. We also find that all material facts necessary for

appreciating the controversy have been disclosed in the Writ

Petition. Therefore, we are of the view that the Writ Petition

cannot also be dismissed on account of suppression of material

facts as well.

50. In so far as the grounds of delay and laches as well as the

plea of the claim being barred by the Law of Limitations is

concerned, save and except making a bald assertion on such count

the Respondents have failed to mention as to on which date the

cause of action for the petitioner to institute the proceeding had

ceased and on what count. There is also no oral argument

advanced to that effect.

Reliance-oswp-242-2018-J-R.doc

51. In Banda Development Authority, Banda vs. Motilal Agarwal

& Ors.4 the Hon'ble Supreme Court has observed that no limitation

has been prescribed for filing a Writ Petition under Article 226 of

the Constitution of India. However, the High Court will treat the

delay in filing the Writ Petition as unreasonable, if the same is

filed beyond the period of limitation prescribed for filing a Civil

Suit for a similar cause. From the above, it would be apparent that

although un-explained delay in instituting a Writ Petition could be

a valid ground to decline relief to the Petitioner, yet, the law of

Limitation would not have strict application in a Writ Petition.

52. There is no dispute in this case about the fact that the

Respondent No. 1 is an instrumentality of the State and, therefore,

would be an "other authority" within the meaning of Article 12 of

the Constitution of India.

53. Law is well settled that arbitrariness in the decision making

process of the State or its instrumentality is a facet of Article 14 of

the Constitution of India. In E.P..Royappa v State of Tamil Nadu,5 it

was pointed out that Article 14 would strike at arbitrariness in

State action and ensure fairness and equality of treatment. 4 (2011) 5 SCC 394.

5 (1974) 4 SCC 3.

Reliance-oswp-242-2018-J-R.doc

54. The present is not a proceeding simpliciter for enforcing a

money claim but raises significant questions pertaining to the

validity and fairness in the impugned action of the Respondent No

1, which are required to be adjudicated on the touch stone of

Article 14. As such, we are of the considered opinion that such

plea cannot be brushed aside merely on the ground of delay and

laches, more so, since such delay has evidently not given rise to

any parallel right of a third party.

55. In view of the foregoing discussions, we are of the view that

the Writ Petition is maintainable in law as well as in the facts and

circumstances of the case.

56. It would be further pertinent to note herein that in an

earlier decision rendered by a co-ordinate Bench of this Court

dated 20th November 2019 in Raghuleela Builders Pvt. Limited

and Anr. vs. The Mumbai Metropolitan Regional Development

Authority & Ors. (Supra) wherein, identical issues were involved,

this Court had entertained the Writ Petition. In that case also the

Petitioners had challenged a similar Demand Notice dated 12 th

September 2017 issued by the Respondent No.1, by invoking

similar provisions of the Lease Deed as well as the Supplementary

Reliance-oswp-242-2018-J-R.doc

Lease Deed, demanding payment of a sum of Rs. 432 Crores as

penalty for the delay in completion of construction of the building.

That was also a case wherein, although the initial built up area

was 30550 sq. meters, which was to be consumed by constructing

9 (nine) floors in the building, yet, subsequently, due to the

increase in the FSI, the Respondent No.1 had allotted additional

built up area of 67000 sq. meters to the Petitioner resulting in

construction of 11 additional floors in the same building. Due to

the addition in the built up area, the construction of the building

could not be completed within four years, as stipulated in Article

2(d) of the original Lease Deed, as a result of which, Demand

Notice dated 12th September 2017 was served for recovery of

penalty/additional premium along with interest calculated

thereon.

57. By the Judgment and Order dated 20 th November 2019, in

Raghuleela Builders Pvt. Ltd. & Anr. (Supra), the Division Bench

had set aside the impugned Demand Notice dated 12 th September

2017 by holding that such a demand was not maintainable in the

eyes of law. That apart, it was also observed that in view of the

change in policy of the MMRDA increasing the time limit for

Reliance-oswp-242-2018-J-R.doc

completion of the building "Fit for occupation", from four years to

six years, the demand for penalty/additional premium for delay in

completion of construction within four years was ex-facie

unreasonable, unjustified and discriminatory.

58. The Special Leave Petition (C) No. 6411 of 2020 preferred

by the Respondent No.1 assailing the Judgment and Order dated

20th November 2019 was dismissed by the Hon'ble Supreme Court

by the order dated 27 th July 2020 after taking note of the findings

recorded in paragraphs No. 38 and 40 of the Judgment and Order

dated 20th November 2019. However, it was clarified that since the

judgment of the Division Bench of the Bombay High Court was

rendered in the facts of that case, hence, it cannot influence any

other matter in this behalf. With the above observation the Special

Leave Petition was dismissed.

59. In the order dated 27th July 2020 the Hon'ble Supreme

Court, while dismissing the Special Leave to Appeal (C) No(s)

6411/2020, had observed as follows:-

"We are not inclined to exercise our jurisdiction under Article 136 of the Constitution of India in the given facts of the case and more so as reflected from paragraphs 38 and 40 of the impugned judgment.

Reliance-oswp-242-2018-J-R.doc

Mr. K. K. Venugopal, learned Attorney General for India expresses some apprehension on account of there being other matters pending.

We clarify that the present matter is in the given facts of the case as stated aforesaid and thus, cannot be said to influence any other matter in this behalf.

The special leave petition is dismissed in terms aforesaid. Pending applications shall also stand disposed of."

60. It appears that the Respondent No. 1 had filed a Review

Petition seeking review of the order dated 27 th July 2020, which

was also dismissed by the Hon'ble Supreme Court vide order

dated 29th September 2020 passed in Review Petition (Civil) No.

1764 of 2020 arising out of SLP (C) No. 6411 of 2020.

61. From a plain reading of the decision rendered in Raghuleela

Builders Pvt. Ltd. & Anr. (Supra) we are of the opinion that, even

if the said decision is treated to have been rendered in the fact

situation of that case, even then, we can take note of the legal

principles emanating therefrom. In that view of the matter we are

unable to agree with the submission of the learned Counsel for the

Respondents that the decision in the case of Raghuleela Builders

Pvt. Ltd. & Anr. (Supra) cannot be looked into by this Court even

for the purpose of deciding the question of maintainability of the

Writ Petition.

Reliance-oswp-242-2018-J-R.doc

62. It is to be noted herein that the question of

maintainability of a Writ Petition is a mixed question of law

and facts. Therefore, such question would obviously have to

be considered having due regard to the peculiar facts and

circumstances of each case. Having regard to the facts and

circumstances of this case and considering the fact that a

similar Writ Petition, raising similar issues in Raghuleela

Builders Pvt. Ltd. & Anr. (Supra) had earlier been entertained

by this Court, for the sake of maintaining uniformity in

judicial decisions, we are not inclined to non-suit the Writ

Petitioner merely on the plea of maintainability as raised by

the Respondents.

On Merits:-

63. During the Course of arguments, the learned Counsel for

the Respondents has made it clear that the demand for additional

penalty on account of delay in completing the construction had

been raised by the Respondent No.1 in deference to Article 2(d) &

(e) of the Lease Deed dated 1 st September 2006 which is as per

Form 'D' of Regulation No 10 of the Mumbai Metropolitan Region

Reliance-oswp-242-2018-J-R.doc

Development Authority (Disposal of Land) Regulations, 1977.

Therefore, the question as to whether such a claim /demand of

the Respondent No. 1 for payment of additional premium/ penalty

on account of delay in completing the construction was

maintainable in the eyes of law as well as in the facts and

circumstances of the case would undoubtedly have to be answered

by this court in the light of materials brought on record and by

constructing the relevant clauses of the Lease Agreement. For the

above purpose Articles 2 (d) and (e) of the Lease Deed dated 1 st

September 2006 would be relevant and therefore, the same are

being reproduced herein-below for ready reference:-

"(d) Time limits for commencement and completion of construction work: That the Lessee shall within three months from the receipt of approval of its plans and specifications of building or buildings intended to be erected on the said plot of land, commence and within a period of four years from the date of this lease at his own expense and in a substantial and workman like manner and with the sound materials and in compliance with the said Development Control Regulations and Building Regulations and all Municipal Rules, bye-laws and Regulations applicable hereto and in strict accordance with the approved plans, elevations, sections, specifications and details as specified in the Section 5, 6 & 8 of the said RFP and the said allotment letter, to the satisfaction of the Metropolitan Commissioner and conforming to the Bandra-

Kurla Complex Notified Area, Development Control Regulations, 1979 & all other relevant Rules, Regulations & Acts and further as provided in Section 5 of the said RFP and the said allotment letter, build and completely finish fit for occupation a (i) "Convention & Exhibition Centre" and (ii) "Commercial Complex"to be used as (i) "Convention & Exhibition Centre" and (ii) "Commercial Complex" with all requisite drains and other proper conveniences thereto.

Reliance-oswp-242-2018-J-R.doc

PROVIDED THAT the construction of Convention and Exhibition Centre will be commenced before the commencement of construction of Commercial Complex and Occupation Certificate of Convention and Exhibition Centre (65000 sq. mtr. shall be obtained prior to the request for Occupation Certificate of Commercial Complex (50000 sq. mtr) as set out in the said RFP and the said allotment letter the Lessee shall scrupulously observe the approved Work Execution Plan (copy Whereof is set out in the SIXTH SCHEDULE hereunder written).

PROVIDED FURTHER THAT as set out in the said allotment letter, the Lessee shall submit the periodic progress report of the Convention and Exhibition Center say in the first week of every third month to the Metropolitan Commissioner, Mumbai Metropolitan Region Development Authority. The Evaluation Committee appointed by the Metropolitan Commissioner as referred in the Proviso to clause (a) hereinabove, will review the progress of the development of Convention Center report by the Lessee and submit its report to the Metropolitan Commissioner. The Evaluation Committee as indicated above will satisfy itself regarding the development of the Convention and Exhibition Center which has to be of international standards and if necessary the Evaluation Committee will make suggestions in that respect to the Metropolitan Commissioner and the Lessee shall incorporate changes so directed by the Metropolitan Commissioner.'

(e) Extension of time stipulated for construction of building or development of land:

(i) If the Lessee shall not perform and observe the limitations of the time mentioned in clause 2 (d) above for construction of the intended (i) "Convention & Exhibition Centre" on plot of land admeasuring 55000 sq. mtr. and (ii) "Commercial Complex" on plot of land admeasuring 20000 sq. mtr. or otherwise development of said plot of land leased to him for reasons beyond his control, the Metropolitan Commissioner may permit extension of such time on payment of additional premium at the following rates:

                   Up to 1 year _____               25    percent    of  the
                                                    respective premium paid
                                                    for     "Convention    &
                                                    Exhibition Centre" and
                                                    "Commercial Complex"








                                                         Reliance-oswp-242-2018-J-R.doc




                   Between 1 and 2 years___      35    percent    of  the
                                                 respective premium paid
                                                 for     "Convention    &
                                                 Exhibition Centre" and
                                                 "Commercial Complex"

                   Between 2 and 3 years ___     40    percent    of    the
                                                 respective premium paid
                                                 for "Convention Exhibition
                                                 Centre" and "Commercial
                                                 Complex"

          (ii)     If the Metropolitan Commissioner shall refuse to

permit such extension of time or shall find the Lessee of having committed breach of any condition or covenant during limitation of time mentioned in clause 2(d) hereto before Metropolitan Commissioner may forfeit and determine the Lease: provided that in the event of such determination of lease 25 percent of the premium paid by the Lessee to the Lessor shall stand forfeited and the the remaining 75 percent of such premium shall be refunded to him; provided further that the power to so determine the Lease shall not be exercised unless and until the Metropolitan Commissioner shall be given to the Lessee or left on some part of the demised premises a nonce in writing of his intention to do so and of specific breach of the covenant or condition in respect of which forfeiture is intended and default shall have been made by the Lessee in remedying such breach within three months from the service of notice on him or the notice being left on the demised premises."

64. Article 2 of the Supplementary Lease Deed dated 13 th July

2007 mentions that the incremental premises agreed to be

constructed shall be deemed to be integral part of the demised

premise defined in Lease Deed dated 1 st September 2006. Article 2

reads as follows :-

"2. It is here by agreed and declared by and between the parties hereto that all the conditions and covenants including the term of the lease as

Reliance-oswp-242-2018-J-R.doc

contained in the said Deed of Lease shall be deemed to be incorporated herein and shall regulate the lease hereby granted. It is further agreed and declared by the parties hereto that the incremental premises hereby agreed to be constructed and to be leased by the lessor to the lessee shall be deemed to be the integral part of demised premises as defined in the said Deed of Lease dated 1 st September 2006 and annexed hereto as ANNEXURE."

65. At the very out set it must be noted here-in that as per

Article 2(d) the lessee is required to complete the construction

within four years from the date of execution of the lease deed.

However, Article 2 (c) of the Lease Deed makes it clear that no

work shall commence or be carried out contrary to the

Development Control Regulations and the Building Regulations

applicable to the plot of land and until the plans, elevations,

sections, specifications and details shall have been approved.

Therefore, in view of Article 2(c), the construction no construction

can commence until all statutory approvals including the approval

of building plan etc. are received. Article 2(a) of the Lease Deed

mentions that the lessee shall, within three months, submit plans

etc. for approval. However, there is no condition in the Lease Deed

laying down any time line for granting of such approval by the

Respondent No. 1.

Reliance-oswp-242-2018-J-R.doc

66. In a construction of this nature, permission of multiple

statutory authorities including the Municipal Corporation, Fire

department, Environment clearance, height clearance etc. will be

necessary, without which even the Commencement Certificate

cannot be issued. Unless the Commencement Certificate is issued,

the construction work cannot commence. These statutory

authorities are not bound by the terms and conditions of the Lease

Agreement. Notwithstanding the same, the Lease Agreement is

completely silent as to who will be responsible in case of delay in

granting approval by these Statutory Authorities, coming in the

way of early commencement and completion of the construction.

67. Not only that, the Lease Deed is also silent as to what would

be the effect on the time line of four years for completion of the

construction, as laid down in Article 2(d) in case, there is delay in

granting of statutory approvals. As such, if there is delay in

granting permissions/ approval by the statutory authorities for any

reason whatsoever, leading to delay in commencement of

construction, then in that event, the Lessee will be left with no

scope to complete the construction within the stipulated time, that

too, for no fault on its part. Notwithstanding the same, as per

Reliance-oswp-242-2018-J-R.doc

Article 2(d), as interpreted by the Respondent No 1, the lessee

would still be liable to pay penalty for the delay in completing the

construction beyond the period of four years from the date of

execution of the Lease Deed. Viewed from that perspective, Article

2(d) of the Lease Deed appears to be ex-facie unfair, unreasonable

and hence, unconscionable. However, since the Articles of the

Lease Deed are not under challenge, hence, the said aspect of the

matter need not detain this Court.

68. As has been noted hereinabove, the initial built-up area,

which is the subject matter of Lease Deed dated 1 st September

2006, was only 65,000 sq. mtrs. for the Convention & Exhibition

Centre and 50,000 sq.mtrs for the Commercial Complex, totaling

to 1,15,000 sq.mtrs. Article 2(d) of the Lease Deed providing four

years' time limit for completing the construction would, therefore,

apply to the 1,15,000 sq. mtrs of built up area.

69. Subsequent to the execution of the Lease Deed dated 1st

September 2006, there was increase in the FSI leading to

allotment of additional built-up area of 72,500 sq. mtrs to the

Petitioner. This 72,500 sq. mtrs was not within the ambit of the

original Lease Deed dated 1st September 2006. As such, the

Reliance-oswp-242-2018-J-R.doc

Supplementary Lease Deed 13th July 2007 had to be executed.

However, as had been noted above, soon thereafter, i.e. on 15 th

October 2007, an interim order was passed by this High Court in

Writ Petition No. 1165 of 2007 which had affected the

construction work, at least in sofar as 31,500 sq. mtrs pertaining

to the Commercial Complex is concerned. The aforesaid stay order

remained in force until 12th March 2012. Therefore, although a

plinth Commencement Certificate (CC) was issued on 12 th June

2008 permitting construction upto the plinth level, yet, in view of

the composite design of the Convention & Exhibition Centre as

well as the Commercial Complex, having common foundation and

basement, the Petitioner could not commence construction due to

the operation of the stay order. The said fact was also informed to

the Respondent No. 1 vide communication dated 28th January

2009.

70. From the statements made in the Writ Petition and from the

examination of various documents on record, including EIA

Certificate dated 26th June 2013 as well as Article 2 of the

Supplementary Lease Deed dated 13 th July 2007, it is evident that

although the area of 72,500 sq. mtrs was allotted subsequently,

Reliance-oswp-242-2018-J-R.doc

yet, it was treated as an integral part of the construction to be

carried out with the original built up area.

71. The Writ Petition No. 1165 of 2007 was withdrawn on 12 th

March 2012. As such, on 20th Mach 2012, i.e., after the

withdrawal of the Writ Petition No. 1165 of 2007, the Respondent

No. 1 had approved the allotment of additional 1,00,000 sq. mtrs

to the Petitioner and, thereafter, on 3 rd April 2012, another 25,000

sq. mtrs was allotted thus, increasing the total allotment of built-

up area upto 3,12,500 sq. mtrs. The Commencement Certificate

upto the seventh floor level pertaining to the 3,12,500 sq. mtrs

was issued only on 16th April 2014.

72. In a composite construction of this nature involving complex

layouts, warranting multiple Commencement Certificates to be

issued by the Respondent No. 1, it is inconceivable that the Lessee

would adhered to two different timelines for construction of the

original allotment and the additional built-up area, the

construction whereof is to be carried out over the same plot and in

respect of the same construction. Since the construction in this

case was evidently and admittedly not severeable in nature,

Reliance-oswp-242-2018-J-R.doc

therefore, we cannot but hold that there could only be one date of

completion of the entire building "fit for occupation".

73. In view of the above discussion, we are also of the opinion

that although a plinth Commencement Certificate was issued on

12th June 2008 granting permission to complete the construction

only upto the plinth level, yet, in view of the pending Court

proceeding, and operation of the interim order dated 15 th October

2007 such certificate was not capable of being acted upon and,

accordingly, was also not acted upon by the Petitioner. Thereafter,

the Commencement Certificate for the entire building came to be

issued on 16th April 2014. Therefore, commencement of

construction only took place pursuant to the issuance of the

Commencement Certificate dated 16th April 2014.

74. We also find from the materials on record that in view of

the long continuation of the interim order dated 15 th October

2007, the Petitioner wanted to surrender the additional built-up

area of 72,500 sq. mtrs under the Supplementary Lease Deed

dated 13th July 2007 but the said proposal was declined by the

Respondent No. 1. On the contrary, on 8 th November 2011, the

Respondent No. 1 had issued a communication categorically

Reliance-oswp-242-2018-J-R.doc

representing that there would be "no time-limit" for construction

of the additional built-up area.

75. Further, by the communication dated 1 st February 2012, the

Respondent No. 1 had also confirmed that the period, during

which, the stay order passed by the Court was in force, shall not

be counted for computing the time-limit of four years.

76. The reflections made in the communication dated 8 th

November 2011 as well as 1st February 2012, in our opinion,

clearly holds out a promise to the Petitioner by the Respondent No

1, based on which, the Petitioner had altered its position. Under

such circumstance, the Respondent No. 1 cannot subsequently

resile from such promise. Therefore, any action on the part of the

Respondents to act contrary to the reflection made in the letters

dated 8th November 2011 and 1st February 2012 prejudicially

affecting the interest of the Petitioner would be hit by the doctrine

of promissory estoppel and hence, would be liable to be interfered

with by this court. (See Motilal Padampat Sugar Mills Co. Ltd. vs.

State of Uttar Pradesh & Ors).6

6 (1979) 2 SCC 409.

Reliance-oswp-242-2018-J-R.doc

77. It would be significant to note here-in that it is not a case

where the construction was delayed due to negligence on the part

of the Lessee. On the contrary, it appears from the materials on

record that the construction was delayed due to delay in issuance

of statutory approvals including environment clearance. Since

even as per the terms and conditions of the Lease Deed, the

construction cannot commence without the approval of the plan

and issuance of the Commencement Certificate, hence, by a

reasonable and harmonious construction of the Articles of the

Lease Deed, we hold that, in such a case, the time line of four

years for completing the construction under Article 2(d) ought to

be computed from the date of issuance of the Commencement

Certificate and not from any prior date.

78. Having regard to the facts and circumstances of this case,

we find that even the condition precedent for invoking the Article

2(d) of the Lease Deed dated 1 st September 2006 was not met in

this case in as much as the construction of the original built-up

area was evidently completed by the Petitioner within the period

of four years from the date of issuance of the Commencement

Certificate i.e. 14th April 2014 by the Respondent No. 1 after

Reliance-oswp-242-2018-J-R.doc

excluding the period during which the interim order passed by the

High Court was in force. As such, viewed from that angle also, in

our opinion, there was no legal justification for the Respondent

No.1 to insist on additional premium/penalty from the Petitioner

under Article 2(d) on account of alleged delay in completing of

the construction beyond the period of four years.

79. In the above context, it would be relevant to note here-in

that, even if the provision of Article 2(d) of the Lease Deed dated

1st September 2006 is given full weightage, even then, the four

years period for completing the construction reckoned from the

date of executions of the Lease Deed would expire on 30 th August

2010. The interim order passed by the Court on 15 th October 2007

was vacated on 12th March 2012. Therefore, the said order had

remained in force for a period of 4 (four) years 4(four) months

and 26 (twenty six) days, i.e. 1610 days' in total. If the said period

is added to the completion period, then in that event, even under

Article 2(d), the Petitioner would be entitled for 8 years, 4

months, 226 days', with effect from 1st September 2006, to

complete the construction without seeking extension of time. In

view of the determination made here-in above, such period of 8

Reliance-oswp-242-2018-J-R.doc

years 4 months 26 days will have to be counted from 14 th

April,2014 i.e the date on which the first effective Commencement

Certificate facilitating the commencement of construction of the

building was issued. If that be so, by such interpretation of the

Clauses of the Contract, we are of the view that the time available

to the Petitioner to complete the construction of the initial built up

area, without seeking extension of time, would be till August

2022. In so far as the additional built up area is concerned, in

view of the communication dated 8th November 2011, there would

be no time restriction applicable for completing the construction

of the additional built up area. As such, the question of seeking

time extension for completing the construction of the additional

built up area would not at all arise in the eyes of law.

80. After a careful examination of the documents brought on

record, we find that there is no clarity as to on which date the

construction of the entire built-up area of 3,12,500 sq. mtrs was

actually completed by the Petitioner. The impugned Notice dated

12th September 2017 which had imposed additional premium/

penalty upon the Petitioner for delay of 7 years 12 days in

completing the construction also does not furnish any relevant

Reliance-oswp-242-2018-J-R.doc

particulars in support of the above allegation. The said notice also

appears to be totally vague as regards basis for arriving at the

conclusion that there was 7 years 12 days delay. It is also not

clear, if the penalty was applied for the alleged delay in

completing the construction of the total built-up area including

the Additional Built-up Area or any part thereof.

81. Be that as it may, if the projection made by the Respondent

No. 1 in the impugned notice dated 12 th September 2017 is taken

into account on their face value, even then, if such delay has been

computed with effect from 30th August 2010 i.e. on expiry of 4

years from the date of execution of the Lease Deed dated 1 st

September 2006, the question of delay of seven years twelve days

by excluding the period during which the interim order of the

court was operating, would not arise in this case. We say so

because there was substantial delay in granting statutory

approvals and Commencement Certificate which period, in our

view, would also have to be added to the time available to the

Petitioner to complete the construction.

82. It is pertinent to note herein that the Respondent No. 1 had

made recovery of substantial amount from the Petitioner as

Reliance-oswp-242-2018-J-R.doc

additional premium/penalty for delay in completion of

construction. However, a transparent procedure valid in the eyes

of law has not been followed in the matter. This we say so because

the Respondent No. 1 had never served any default notice to the

Petitioner intimating that it would be liable to pay penalty due to

delay and completion of construction. There was also no notice

ever served upon the Petitioner indicating as to on which date, the

four years period mentioned in Article 2(d) of the Lease Deed

dated 1st September 2006, would come to an end. Such prior

notice, in our opinion, was sine- qua- non in view of the

intervening developments in the matter , particularly the

operation of the interim order passed by this Court. Before

demanding and/or recovering the amount of penalty, no Show

Cause Notice was also required to be served upon the Petitioner

giving it an opportunity to show cause as to why such penalty

should not be recovered by the Respondents. However, no such

notice was served. Therefore, the entire process of recovery, in our

view, was not only conducted in a completely arbitrary, whimsical

and capricious manner but the same was also in violation of the

principles of natural justice.

Reliance-oswp-242-2018-J-R.doc

83. It must be borne in mind then that in a matter of this nature

where penalty is sought to be levied alleging default committed by

a party, unless allegation is admitted, the recovery of penalty

cannot be based on mere ipse dixit of the authority more so, if the

controversy arises out of implementation of terms and conditions

of a contract wherein the authority itself is a party. In such

matters, the recovery would be permissible only after that

controversy is resolved in accordance with the law.

84. In the above context, it would be pertinent to mention

herein that even as per Rule 11(A) of the MMRDA (Disposal of

Lands) Regulations 1977, no action to determine the lease could

be initiated by the Metropolitan Commissioner without serving

prior notice as regards specific breach of the covenants and

conditions in respect of which, default has been alleged.

85. In so far as the undertaking given by the Petitioner to pay

the additional premium/penalty and the consequent deposit of the

amount of Rs 646,77,68,594 /- is concerned, it must be noted

herein that the Writ Petitioner had not only objected to the

demand for payment of additional premium/penalty for the

alleged delay in completing the construction but had also

Reliance-oswp-242-2018-J-R.doc

deposited the amount under protest, thereby, categorically

conveying that the deposit was not made voluntarily or in

discharge of its contractual obligation. Such protest was not only

raised contemporaneously but the same was also in writing and

unambiguous in nature, thus, putting the Respondent No. 1 on

clear notice that the Petitioner has not accepted the decision in

principle.

86. It also appears from the materials on record that apparently

due to the pressure mounted by the Respondent No. 1 demanding

payment of additional premium/penalty, the Petitioner was

compelled to deposit the penalty as otherwise the Petitioner would

not only be prevented from obtaining the Occupation Certificate

thus, causing serious economical prejudice to its interest but the

same would also expose the Petitioner to the risk of termination of

the Lease. Since the Petitioner had evidently made the deposit of

penalty under duress and under compelling circumstances, hence,

the principles of waiver, estoppel and acquiescence would not

operate against the Petitioner in this case. From the protest raised

by the Petitioner, it was apparent that the Petitioner had reserved

its right to agitate the matter at an appropriate time, thus, keeping

Reliance-oswp-242-2018-J-R.doc

the cause alive. Therefore, we hold that the claim for refund of the

amount made by the Petitioner would not be barred under the law

merely on account of the undertaking given by it.

87. Section 72 of the Indian Contract Act provides that a person

who receives payment made by the payee under coercion must

repay or return the same.

88. In Fatima Khatoon Chowdrain vs. Mahmoed Jan Chowdhury

(1868) 12 Moo Ind App 65, the Privy Council has held that

payment made not voluntarily but under species of compulsion

would be liable to be returned.

89. In Valpy vs Manley (1845) 1 CP 594, the Court of England

& Wales has held that money paid under the constraint of threats

to interfere with the legal right is sufficient to make it recoverable.

90. In Ram Kishen Singh vs. Dooli Chand (1881) 8 IA 93 before

the Privy Council, it was held that if a person pays money to save

his property which has been wrongly attached in execution, he is

entitled to recover it.

Reliance-oswp-242-2018-J-R.doc

91. Relying upon the case of Ram Kishen Singh (Supra), the

Privy Council in the case of Kanhaya Lal vs The National Bank of

India Limited7 has held that if a payment is made under protest

and involuntarily, under coercion, the party making such payment

would be entitled to claim refund of the same.

92. Materials on record unequivocally go to show that the

deposit of penalty was dehors any proper demand raised in

writing but was forced under the circumstances created by the

Respondent No. 1, as noted above. Hence, by any stretch of

reasonable reckoning, the deposit of the penalty as well as the

undertaking, cannot be treated as voluntarily so as to prevent the

Petitioner to seek refund of the amount in accordance with law.

93. In view of the foregoing discussion, we are of the un-

hesitant opinion that the demand for payment of the

penalty/additional premium for alleged delay in completing the

construction was not maintainable under Article 2(d) & (e) of the

Lease Deed. Moreover, such amount was realized by the

Respondent No. 1 in a most arbitrary, high handed, unfair, and

unreasonable manner by subjecting the Petitioner to undue

7 1913 SCC Online PC 4.

Reliance-oswp-242-2018-J-R.doc

pressure and threat of termination of the Lease, thus putting its

business interest in peril. The Petitioner was made to deposit the

amount of penalty under coercion. The imposition of the penalty

was also not preceded by proper Show Cause notice thus, acting in

clear contravention of the principle of natural justice. Therefore,

consequences under the law on such counts must follow.

94. In the case of State of Punjab and Ors. vs. Dhanjit Singh

Sandhu (Supra) relied upon by Dr. Saraf, the allottees of the land

had accepted the terms and conditions of the allotment letter and

also took possession but they did not raise any construction within

the specified time, as a result of which, due to violation of specific

condition, the authority wanted to go for resumption of the plot.

In that case, the allottees, after availing the benefit of extension,

had later on demanded refund. It was in such context that the

Apex Court has held that as per the doctrine of "approbate and

reprobate" a party cannot be permitted to "blow hot and cold" at

the same time. In Atur Park-4 Co operative Housing Society Ltd. vs

State of Maharashtra (Supra), the core question, as projected in

paragraph 30, was as to whether, the Petitioner there-in could be

the permitted to seek compensation and seek acquisition under

Reliance-oswp-242-2018-J-R.doc

Fair Compensation Act for the land belonging to it which was

affected by an adjoining road.In Dr Alvaro Alberto Mousinho De

Noronha Ferreira (Supra), the controversy was as regards

conversion of land from agricultural to non-agricultural land and

the applicability of rates there-in. Therefore, the above decisions

relied upon by Dr. Saraf in our view, are distinguishable on facts

and as such, the same would not be of any assistance to the

Respondents in the facts and circumstances of this case.

95. Having held as above, we deem it appropriate to record

here-in that although the learned Counsel for the Petitioner has

argued that this case is squarely covered by the decision rendered

in Raghuleela Builders Pvt. Ltd. & Anr . (Supra),yet, the said

assertion has been strongly contested by the Respondent's Counsel

by submitting that in view of the observations made by the

Hon'ble Supreme Court in the order dated 27 th July 2020, no

reliance can be placed on the said judgment on any count for the

purpose of deciding the present Writ Petition. On a careful

examination of the decision in Raghuleela Builders Pvt. Ltd. &

Anr. (Supra) we also find that the said decision was rendered in

the facts of that case. However, it is important to note here-in that

Reliance-oswp-242-2018-J-R.doc

one of the question raised in the said proceedings was pertaining

to the question as to whether, the decision of the MMRDA to apply

the extension of time from 4 years to 6 years for completing the

construction only to the post August 2015 was valid in the eyes of

law, is also a question raised in the present proceeding. While

answering the said question, it was held in Raghuleela Builders

Pvt. Ltd. & Anr. (Supra), as follows:-

"38. The MMRDA constituted a single member committee of retired Judge of the Supreme Court to decide whether the MMRDA should give concession in recovery of premium considering the time required for plot owner to obtain permissions from various authorities for construction of building thereon. It is contended that one member committee has concluded that the charging of premium for extension of time for completing construction in Bandra-Kurla Complex area, specifically in case where additional built up area has been allotted by the MMRDA, was illegal. In its 138th meeting held on 26th August 2015, the MMRDA had acknowledged the difficulties faced by the lessees and that the condition of completion of construction within 4 years of the execution of the lease was adversely affecting the tendering process. The MMRDA had appointed an expert one man committee of retired Supreme Court Judge in that regard. The single member committee has advised that the period of 6 to 7 years be granted for completion of construction.

39. The lease deed entered into by the MMRDA with the lessees are as per form D, prescribed under the MMRDA (Disposal of Lands) Regulations 1977. Clause 2(a) of the lease deed provides that for building plans to be submitted to country and town planing division for approval within 3 months from the date of lease. Clause 2(c) of the lease deed provides that no work is to be carried out until all plans, elevations, specifications are approved by the concerned authorities. Clause 2(d) provides that within 3 months of the approval of plans, the lessee is to commence construction which is to be completed within four years of the lease. Clause 2(e) provided for extension of time. Clause 2(e) contemplates a situation when the time for completion of construction can be extended, parties to the

Reliance-oswp-242-2018-J-R.doc

contract contemplated that certain uncertainties or situations may arise which may require more time for completion of the construction. In view of this, time is not essence of the contract between the parties and rightly so since construction of any building in Bandra Kurla Complex, several permissions are required from the various authorities and not only from the MMRDA who is planning authority for the Bandra Kurla area, namely, (1) The environmental clearance under the Environmental Impact Notification from the Ministry of Environment and Forest.

(2) Building height clearance from the Ministry of Civil Aviation because of the close proximity to Airport.

                (3)        Clearance from the high rise committee.
                (4)        Permission from the the MCGM.
                (5)        Permission from the traffic police.

Each of these authorities is required to be approached separately since there is no single window clearance / nodal agency which would co-ordinate with the aforesaid authorities for granting of all necessary permissions. In view of the delay in obtaining permissions which are beyond the control of lessee, no work could be carried out as per clause 2(d) of the lease deed.

40. The MMRDA had issued a letter of allotment dated 20th March 2012 allotting additional 67,000 sq. meters at consideration of 984 crore. Part payment of Rs.196 crore was received on 20th March 2012. The supplementary lease deed was executed for additional built up area of 67,000 sq. meters.

The letter of allotment dated 20th March 2012, the acceptance of part payment of consideration for additional built up area allotted, diluted the time period of four years and there was no question of application of condition of occupation certificate for built up area within 4 years when additional built up area was allotted for raising additional 11 floors on the same building.

41. The resolution passed by MMRDA for extending the time period for completing construction from 4 years to 6 years only for leases executed after 26th August 2015 also appears to be arbitrary, discriminatory, without basis and justification. The said set of circumstances are prevailing for the construction being carried out under the leases executed prior to 26th August 2015. Therefore, not extending this benefit of this extension of time from 4 years to 6 years to the prior leases in respect of other plots in the BKC, is completely arbitrary, discriminatory, capricious and violative of Article 14 of the Constitution of

Reliance-oswp-242-2018-J-R.doc

India. There is no reasonable basis or justification for this decision. The classification sought to be made between the leases prior and subsequent to 26th August 2015 is not founded on intelligible differentia and neither does this differentia has any logic, rational, nexus to the object sought to be achieved. The MMRDA has sought to treat equals as unequal. The lessees of plots are being discriminated on the basis of their date of execution of their leases. The lessees who are placed in similar circumstances prevailing for construction in Bandra Kurla area are entitled to equal treatment guaranteed under Article 14 of the Constitution of India.".

96. It is not in dispute that the Lease Deed involved in

Raghuleela Builders Pvt. Ltd. & Anr. (Supra) was also in Form 'D'

of the Regulations of 1977 wherein the same Articles 2 (d) and (e)

were involved. The Writ Petitioner there-in was also a similarly

situated lessee, from whom, penalty for delay in completing the

construction beyond the period of 4 years was raised by the

Respondent No 1. The Petitioner in that case had also raised

identical plea as regards the applicability of the time extension

Clause. The Lease Deed in that case was also executed prior to 26 th

August 2015. If that be so there can be no doubt about the fact

that the legal principles discussed and the findings & observations

recorded in paragraphs 38 and 41 of Raghuleela Builders, in so

far as uniform applicability of the 6 years time extension clause is

concerned, would be applicable to the facts of the present case as

well. Therefore, we hold that by applying the principles parity, the

Respondent No. 1 would be duty-bound to extend the same

Reliance-oswp-242-2018-J-R.doc

benefit of extension of time for completion of construction to six

years to the present Petitioner as well.

97. In the facts and circumstances of this case, we are also of

the opinion that there is no legal justification for the Respondent

No. 1 to confine the benefit of the time extension clause only to

those Lease Agreements which were executed after 26 th August

2015 as such an approach would be highly arbitrary and

discriminatory in nature. Therefore, having regard to the peculiar

facts and circumstances of this case, we do not find any justifiable

ground to take a different view on the aforesaid issue.

98. Law is well settled that for maintaining judicial discipline

and propriety, a decision rendered by a Coordinate Bench on the

same issue must be respected and followed by a Coordinate

Bench. In the case of Mary Pushpam vs. Televi Curusumary & Ors.8

the Hon'ble Supreme Court has observed that when a decision of a

Coordinate Bench of the same High Court is brought to the notice

of the Bench, it is to be respected and would be binding, subject to

the right of the Bench of such co-equal forum to take a different

view and refer the question to a larger Bench. In other words, any

8 (2024) 1 SCR 11.

Reliance-oswp-242-2018-J-R.doc

decision of a Coordinate Bench would be binding on a Bench of

equal strength subject to the condition that if a different view is

sought to be taken in the matter, then the issue would have to be

referred to a larger Bench.

99. The above legal principle has taken a firm footing in the

Indian Jurisprudence by a long line of judicial pronouncements.

We do not deem it necessary to burden this judgment by referring

to all those decisions. However, suffice it to mention here-in that

unless there are justifiable grounds to take a different view in the

matter warranting reference to a larger Bench, the previous

decision of a coordinate Bench would be binding on a Bench of

equal strength.

100. Consequently, it is held that notwithstanding Article 2(d) of

the Lease Deed dated 1 st September 2006, in view of the decision

taken by the Respondent No 1 to extend the period of construction

from four years to six years, the Petitioner, being a similarly

situated Lessee, would also be entitled to six years' time for

completion of the construction. Since, the Commencement

Certificate for the entire built up area of 3,12,500 sq. mtrs. was

issued by the Respondent No.1 only on 16 th April 2014, as such,

Reliance-oswp-242-2018-J-R.doc

we are of the opinion that the Petitioner would be entitled to six

years' time period, with effect from 16th April 2014, for completing

the construction for the simple reason that in view of the built-up

area subsequently allotted to the Petitioner, there was no scope to

commence construction of the composite construction prior to 14 th

April 2014. Therefore, adding the period of 4 years 4 month and

26 days, during which period, the interim order dated 15 th

October 2007 was in force, the Petitioner, in our opinion, would

be entitled to total time period of 10 years 4 months 26 days with

effect from 14th April 2014. Alternately, even if the period of 10

years 4 months 26 days is counted from 1 st September 2006, i.e.,

the date of the Lease Deed, even then, the Petitioner would be

entitled to such period of time for completing the construction of

the initial built-up area without seeking extension of time. In so

far as the additional built up area is concerned, in view of the

communication dated 08/11/2011, as noted above, no time limit

would at all be applicable for the construction of such built up

area.

101. Therefore, we are constrained to hold that the condition

precedent so as to invoke Articles 2(d) & (e) of the Lease Deed

Reliance-oswp-242-2018-J-R.doc

Dated 1st September, 2006 was not met in this case. As such, we

are also of the view that no additional premium/ penalty was

either payable or recoverable from the Petitioner on account of

delay in completing the construction.

102. For the reasons stated above, this Writ Petition succeeds

and the same is hereby allowed in terms of payer clauses(a),(a)

(i),(a)(ii)(a)&(b). The impugned Demand Notices dated

12/09/2017 and 13th June 2019 are accordingly, set aside.

103. Consequently, we hold that the Petitioner would be entitled

for refund of the amount of Rs.646,77,68,594 (Rupees Six

Hundred and Forty Six Crores Seventy Seven Lakhs Sixty Eight

Thousand Five Hundred and Ninety Four) deposited as additional

premium/ penalty for the alleged delay in completion of the

construction. The Respondent No 1 is, therefore, directed to

refund the aforesaid amount to the Petitioner within a period of

90 (ninety) days from the date of receipt of the Certified Copy of

this order, failing which, the amount would carry interest at the

same rate at which, interest was payable by the Petitioner under

the Lease Agreement due to delay in paying premium, to be

calculated from the date of this order till the date of the refund.

Reliance-oswp-242-2018-J-R.doc

104. In so far as the Bank Guarantee(s) furnished by the

Petitioner including that for an amount of Rs.13,12,54,85,287/-

(Rupees Thirteen Hundred Twelve Crores Fifty Four Lakhs Eighty

Five Thousand Two Hundred and Eighty Seven ) the same shall be

kept valid for a period of 90 (Ninety) days from the date of this

order.

105. With the above observations, the Rule is made absolute.

106. The Writ Petition stands disposed of.

107. Parties to bear their own cost.

108. In view of disposal of the Writ Petition, nothing survives in

the Interim Application and the same is disposed of accordingly.

(SUMAN SHYAM, J)                                         (CHIEF JUSTICE)








 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter