Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rdc Concrete ( India ) Pvt. Ltd. vs Mira Bhayandar Municipal Corporation ...
2025 Latest Caselaw 6703 Bom

Citation : 2025 Latest Caselaw 6703 Bom
Judgement Date : 10 October, 2025

Bombay High Court

Rdc Concrete ( India ) Pvt. Ltd. vs Mira Bhayandar Municipal Corporation ... on 10 October, 2025

Author: N. J. Jamadar
Bench: N. J. Jamadar
2025:BHC-AS:44106

                                                                                  -WP-12443-2025.DOC

                                                                                         Arun Sankpal



                                   IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                                CIVIL APPELLATE JURISDICTION
                                             WRIT PETITION NO. 12443 OF 2025


                       RDC Concrete (India) Pvt Ltd                                    ..Petitioner
                       A Private Limited Company,
 ARUN
 RAMCHANDRA            Duly registered under the provisions
 SANKPAL

 Digitally signed by   of the Companies Act, 1956, having
 ARUN
 RAMCHANDRA
 SANKPAL
 Date: 2025.10.10
 22:24:10 +0530
                       its registered office 701, Thane One,
                       Ghodbunder Road, Majiwada,
                       Thane (W) -400 610.


                              Versus

                       1. Mira Bhayandar Municipal Corporation
                       Through its Commissioner,
                       Having concerned Ward Office at,
                       Ward Office No. 6, Sahitya Ratna Lokshahir,
                       Anna Bhau Sathe Bhavan, Kashimira Police
                       Station, Kashimira, Thane: 401 107.


                       2. The State of Maharashtra,
                       Through the Office of Govt Pleader,
                       Department of Environment,
                       Government of Maharashtra,
                       New Administrative Building,
                       Madam Cama Road, Mantralaya,
                                                                                 ...Respondents
                       Mumbai 400 001.



                                                            1/20



                        ::: Uploaded on - 10/10/2025                 ::: Downloaded on - 11/10/2025 02:55:17 :::
                                                              -WP-12443-2025.DOC

Mr. Amogh Singh, with Atul Singh, for the Petitioner.
Mr. N. R. Bubna, for Respondent No.1.
Mrs. Suvita Prabhune, AGP, for Respondent No.2.

                                 CORAM: N. J. JAMADAR, J.
                            RESERVED ON: 6th OCTOBER, 2025
                         PRONOUNCED ON: 10th OCTOBER 2025


JUDGMENT:

1. Rule. Rule made returnable forthwith, and, with the consent of

the learned Counsel for the parties, heard finally.

2. The challenge in this Petition is to an order dated 30 th September

2025 passed by the Respondent No.1-Mira Bhayandar Municipal

Corporation, revoking the licence granted to the Petitioner to operate a

Ready Mix Concrete Plant.

3. Shorn of superfluities, the background facts leading to this

Petition can be stated as under:

3.1 The Petitioner is a limited company, registered under the

Companies Act, 1956. The Petitioner is engaged in the business of

manufacturing and supply of Ready Mix Concrete ("RMC"). The RMC

plant of the Petitioner is situated at Survey No. 30/1m Kasigaon, Mira

Road (E), Thane ("the subject premises") within the limits of the

Respondent No.1-Mira Bhayandar Municipal Corporation ("MBMC").

3.2 On 22nd June 2023, the Maharashtra Pollution Control Board

("MPCB") gave its consent to operate the RMC plant at the subject

-WP-12443-2025.DOC

premises. The consent to operate given by the MPCB is valid until 30 th

April 2026.

3.3 Pursuant to the aforesaid consent to operate, the Respondent

No.1, MBMC granted the licence to operate the RMC plant at the

subject premises. The said licence has been renewed for the period of 8 th

October 2024 to 7th October 2027. The Petitioner, in compliance with

the conditions subject to which the consent and licence have been

granted, is operating the said RMC plant at the subject premises.

3.4 The Petitioner asserts, in the wake of an unfortunate road

accident in the locality where the RMC plant of the Petitioner is

situated, involving a vehicle, not belonging to the Petitioner, and the

death of a boy therein, a complaint was lodged with the Respondent

No.1. Pursuant thereto , without verifying the facts, the Respondent

No.1 issued a show-cause notice to the Petitioner on 11 th September

2025, which was served on the Petitioner on 12 th September 2025 at

11.30 am, contending that the RMC plant was being operated in breach

of the guidelines contained in the Notification dated 7 th November 2016

issued by the MPCB. It was inter alia alleged that a school, namely,

Swami Dayanand High School, was situated within the radius of 200

mtrs of the RMC plant and, thus, there was breach of the sitting criteria,

i.e., commercial RMC plant should not be located within the 200 mtrs

from School, Colleges, Hospitals and Courts.

-WP-12443-2025.DOC

3.5 The Petitioner alleges, though the Petitioner was called upon to

submit an explanation forthwith, without providing any effective

opportunity of hearing, on 12th September 2025, under five hours of the

service of the notice on the Petitioner, the Respondent No.1 MBMC,

passed an order to revoke the licence to operate the RMC plant with

immediate effect and sealed the plant.

3.6 On 15th September 2025, the Petitioner filed a Reply to the notice

contending that the action of revocation of licence was wholly arbitrary,

it was taken for extraneous considerations and on the basis of false

allegations. In fact, Swami Dayanand High School was being run

unauthorisedly. Even otherwise, RMC Plant was not situated within the

radius of 200 mtrs of the said school. The applicability of the

Notification dated 7th November 2016 to the subject RMC plant was also

questioned.

3.7 As the Respondent No.1 did not revoke the order dated 12 th

September 2025 and restore the licence to operate the RMC plant, the

Petitioner has invoked the writ jurisdiction.

4. On 26th September, 2025, as the Respondent No.1 expressed

willingness to provide an opportunity of hearing to the Petitioner and

pass an order, the Petitioner was given opportunity to file additional

reply and/or documents before the Competent Authority and,

-WP-12443-2025.DOC

thereupon, the Competent Authority was directed to pass an

appropriate order.

5. By an order order dated 30th September 2025, the Respondent

No.1 again passed the order to revoke the licence to operate the RMC

plant and directed the Petitioner to immediately cease and desist the

operations at the RMC plant.

6. The Petitioner has thus amended the Petition and assailed the

legality and validity of the subsequent order dated 30 th September

2025, as well.

7. I have heard Mr. Amogh Singh, the learned Counsel for the

Petitioner, Mr. N. R. Bubna, the learned Counsel for Respondent No.1

and Mrs. Savita Prabhune, the learned AGP, for the Respondent No.2-

State. With the assistance of the learned Counsel for the parties, I have

also perused the material on record.

8. Mr. Amogh Singh, the learned Counsel for the Petitioner, took a

slew of exceptions to the impugned order. First and foremost, Mr.Singh

would urge the first order of revocation of licence dated 12 th September

2025 was passed in gross violation of the fundamental principles of

natural justice. The show-cause notice, dated 11th September 2025, was

served on the Petitioner on 12th September 2025 at about 11.30 am and,

under five hours thereof, the order to close the operations at subject

premises was passed without providing any opportunity of hearing of

-WP-12443-2025.DOC

whatsoever nature. The haste with which the Respondent No.1 passed

the said order on the very day on which the notice was served indicates

the extraneous driving force behind the said high-handed action. On

this count alone, according to Mr. Singh, the entire action stood

vitiated.

9. Secondly, Mr. Singh would urge, the very premise of the action

that the RMC plant was being operated in breach of the guidelines

under the Notification dated 7th November 2016 is completely flawed.

Mr. Singh would urge that, by the Notification issued on 27 th November

2024, the MPCB has framed separate guidelines for the RMC plants for

sitting criteria in Mumbai Metropolitan Region of Maharashtra.

Therefore the said Notification dated 7th November 2016, does not at all

apply to the subject RMC plant. Resultantly, the very foundation of the

action is manifestly wrong.

10. Thirdly, the order dated 30th September 2025, also suffers from

the same vice of revoking the licence by resorting to inapplicable

provisions. In addition, the Respondent No.1 has taken into account the

other alleged breaches of the conditions of licence, of which no notice

was ever given to the Petitioner. The impugned order dated 30 th

September 2025 thus suffers from a patent illegality as it came to be

passed on the basis of the grounds which did not form part of the show-

cause notice.

-WP-12443-2025.DOC

11. An effort was made by Mr Singh to urge that on facts also the

allegation that the RMC plan is located within the radius of 200 mtrs

from the Swami Dayanand High School is not correct.

12. In opposition to this, Mr. Bubna, the learned Counsel for the

Respondent No.1, forcefully refuted the submissions on behalf of the

Petitioner. Mr. Bubna made a valiant effort to support the impugned

orders. Mr. Bubna would urge, the Petition is required to be determined

keeping in view the disastrous consequences the RMC plant has on the

environment, if it is operated in a densely populated area. Viewed

through this prism, according to Mr. Bubna, no fault can be found with

the impugned orders.

13. Mr. Bubna would urge, if the submission on behalf of the

Petitioner is accepted, a RMC plant within the limits of the Mumbai

Metropolitan Region would not be subject to any restriction in the

matter of sitting criteria. Neither the Notification dated 7th November

2016 would apply, nor the sitting criteria under the Notification dated

27th November 2024 wold govern such RMC plant. Such a construction,

which would lead to an absurd situation, cannot be adopted, was the

thrust of the submission of Mr. Bubna.

14. Laying emphasis on the Notification dated 27 th November 2024 as

regards the sitting criteria, Mr. Bubna would urge under the said

guidelines, the commercial plant should not be located within 500 mtrs

-WP-12443-2025.DOC

from school, colleges, hospitals and Courts. The Respondent No.1-

MBMC, has, according to Mr. Bubna, correctly applied the guidelines

contained in the Notification dated 7th November 2016.

15. Mr. Bubna would submit that the ground that the principles of

natural justice were not followed is unworthy of countenance. Pursuant

to the order passed by this Court, the Petitioner was provided an

efficacious opportunity of hearing. The contention that the other

grounds, which were taken into account by the Competent Authority,

while passing the order dated 30th September 2025, were not informed

to the Petitioner is of no consequence as the Petitioner was aware of all

those breaches and was provided a fair opportunity of hearing.

Therefore, viewed from any perspective, the challenge to the impugned

orders does not warrant acceptance, submitted Mr. Bubna.

16. To begin with, it is necessary to note few uncontroverted facts.

The grant of consent to establish the RMC plant by MPCB vide

communication dated 12th January 2023 is not in dispute. Nor the fact

that by a further communication dated 26 th June 2023, the first consent

to operate was granted subject to certain conditions, for the period upto

30th April 2026. There is material to indicate that in consonance with

the consent given by MPCB, the Respondent No.1 initially granted a

licence to operate the RMC plant on 31 st March 2023 and the said

licence seems to have been further renewed on 11 th October 2024 for

-WP-12443-2025.DOC

the period of 8th October 2024 to 7th October 2027, albeit subject to

certain terms and conditions.

17. Incontravertibly, the show-cause notice was issued on 11 th

September 2025. The Petitioner was called upon to submit his

explanation along with the documents in regard to a grievance that the

Petitioner was operating the RMC plant within a radius of 200 mtrs of

Swami Dayanand High School. Even if the aspect of the date and time

of service of the said notice on the Petitioner is kept aside, the fact

remains that on 12th September 2025, the licence to operate the RMC

plant was revoked.

18. The first question that thus wrenches to the fore is, whether an

efficacious opportunity was given to the Petitioner. The answer to the

aforesaid question hinges upon the nature and contents of the notice to

be given by an authority who is invested with the power to take

administrative decisions which have civil and, at times, penal

consequences.

19. Issuance of notice where there is a statutory mandate to provide

an opportunity of hearing, presents not much difficulty. Where the

statute mandates that the Authority shall provide an opportunity to

make a representation, and also consider the representation so made,

the obligation to give notice before taking action can only be construed

-WP-12443-2025.DOC

as peremptory. A notice to the person likely to be affected must also be

such as to enable the noticee to make an effective representation.

20. Even where there is no statutory obligation to give notice, the

Authority which takes the administrative decision is enjoined to give a

notice to the affected person as the administrative decision would entail

civil consequences. Such a notice must equip the noticee to not only

clearly appreciate the grounds of noncompliance/default/breach

complained of but also the action which would be taken in the event of

failure to show the cause.

21. A profitable reference in this context can be made to the decision

of the Supreme Court in the case of Gorkha Security Services Vs

Government (NCT of Delhi) and Ors,1 wherein the Supreme Court

examined the adequacy of the contents of show-cause notice. In the said

case, the question arose in the context of the form and content of the

show-cause notice that was required to be served, before deciding as to

whether the noticee was to be blacklisted or not. The observations of

the Supreme Court in paragraphs 21 and 22 of the said judgment are

instructive and, hence, extracted below

"21 The Central issue, however, pertains to the requirement of stating the action which is proposed to be taken. The fundamental purpose behind the serving of Show Cause Notice is to make the noticee understand the precise case set up against him which he has to meet. This would require the statement of imputations detailing out

1 (2014) 9 SCC 105.

-WP-12443-2025.DOC

the alleged breaches and defaults he has committed, so that he gets an opportunity to rebut the same. Another requirement, according to us, is the nature of action which is proposed to be taken for such a breach. That should also be stated so that the noticee is able to point out that proposed action is not warranted in the given case, even if the defaults/ breaches complained of are not satisfactorily explained. When it comes to black listing, this requirement becomes all the more imperative, having regard to the fact that it is harshest possible action.

22. The High Court has simply stated that the purpose of show cause notice is primarily to enable the noticee to meet the grounds on which the action is proposed against him. No doubt, the High Court is justified to this extent. However, it is equally important to mention as to what would be the consequence if the noticee does not satisfactorily meet the grounds on which an action is proposed. To put it otherwise, we are of the opinion that in order to fulfil the requirements of principles of natural justice, a show cause notice should meet the following two requirements viz:

i) The material/ grounds to be stated on which according to the Department necessitates an action;

ii) Particular penalty/action which is proposed to be taken. It is this second requirement which the High Court has failed to omit.

we may hasten to add that even if it is not specifically mentioned in the show cause notice but it can be clearly and safely be discerned from the reading thereof, that would be sufficient to meet this requirement."

(emphasis supplied)

22. The Supreme Court has, thus, enunciated that in order to fulfill

the requirements of principles of natural justice, a show-cause notice

was to satisfy two requirements; first, the alleged infirmities, breaches,

or defaults, which constitute the material or ground necessitating the

action. Second, the nature of the action which is proposed to be taken

-WP-12443-2025.DOC

so that the noticee is in a position to show that the proposed action is

not warranted, even if it is assumed that there is no satisfactorily

explanation regarding the alleged infirmities, breaches or defaults.

23. In the case of UMC Technologies Private Limited Vs Food

Corporation of India & Anr,2 the Supreme Court emphasised the

necessity of reasonable opportunity of hearing before any action is

taken. The observations in paragraph 13 read as under:

"13. At the outset, it must be noted that it is the first principle of civilised jurisprudence that a person against whom any action is sought to be taken or whose right or interests are being affected should be given a reasonable opportunity to defend himself. The basic principle of natural justice is that before adjudication starts, the authority concerned should give to the affected party a notice of the case against him so that he can defend himself. Such notice should be adequate and the grounds necessitating action and the penalty/action proposed should be mentioned specifically and unambiguously. An order travelling beyond the bounds of notice is impermissible and without jurisdiction to that extent. This Court in Nasir Ahmad v. Assistant Custodian General, Evacuee Property (1980) 3 SCC 1, has held that it is essential for the notice to specify the particular grounds on the basis of which an action is proposed to be taken so as to enable the noticee to answer the case against him. If these conditions are not satisfied, the person cannot be said to have been granted any reasonable opportunity of being heard."

(emphasis supplied)

24. In the said case, after adverting to the previous precedents,

including Gorkha Security Service (Supra), the Supreme Court

2 (2021) 2 SCC 551.

-WP-12443-2025.DOC

postulated, it is clear that a prior show-cause notice granting a

reasonable opportunity of being heard is an essential element of all

administrative decision-making and particularly so in the decisions

pertaining to blacklisting which entail grave consequences for the entity

being blacklisted.

25. If the show-cause notice dated 11th September 2025 is appraised

on the aforesaid touchstone, it can be legitimately inferred that the said

notice falls foul of reasonable opportunity test. The Petitioner was

called upon to give an explanation along with the documents forthwith.

No outer limit for showing cause or furnishing the explanation was

provided. A show-cause of even less than 24 hours, even if the

contention of the Petitioner that the show-cause notice was served on

him on 12th September 2025 at 11.30 am is discounted, cannot be said

to be reasonable by any standard.

26. Thus, the resultant action of revoking the licence and a direction

to immediately close the operations on 12th September 2025 rendered it

clearly high handed, arbitrary and in flagrant violation of fundamental

principles of natural justice.

27. The justifiability of the action on the count that the RMC plant

was being operated in breach of the conditions in the guidelines as to

sitting criteria next warrants consideration. It is pertinent to note, the

sole ground mentioned in the show cause notice was, the breach of the

-WP-12443-2025.DOC

condition not to have the RMC plant within the radius of 200 meters of

a school. A reference was made to the guidelines issued by the

Maharashtra Pollution Control Board vide notification dated 7 th

November, 2016. The sitting criteria in terms of the said notification

read as under:

"B. SITTING CRITERIA The following sitting criteria shall be considered for establishment of RMC Plant.

......

3. Commercial RMC plant should not be located within 200 m from schools, colleges, hospitals and courts."

28. The edifice of the challenge to the action was sought to be built

on the premise that the aforesaid notification dated 7 th November, 2016

no longer governed the RMC plants within the limits of Mumbai

Metropolitan Region in view of the Circular dated 27 th November, 2024

issued by MPCB and the separate guidelines for the RMC plants in

respect of sitting criteria in Mumbai Metropolitan Region of

Maharashtra dated 27th November, 2024.

29. The circular dated 27th November, 2024 explicitly records that the

guidelines for RMC plants issued vide notification dated 7 th November,

2016 for sitting criteria were applicable for the entire State of

Maharashtra. The MPCB vide notification dated 27th November, 2024

has issued the guidelines for RMC plant for sitting criteria which would

be applicable only for the Mumbai Metropolitan Region area in the

-WP-12443-2025.DOC

State of Maharashtra. And the notification dated 7th November, 2016

would be applicable for the rest of the Maharashtra.

30. The circular dated 27th November, 2024 is explicitly clear and

unambiguous. The decision of MPCB to have two different sitting

criteria; one for the RMC plants for Mumbai Metropolitan Region area

and the other for the rest of the Maharashtra is unequivocal. The

notification dated 27th November, 2016 would continue to govern the

RMC plants situated in the State of Maharashtra, other than the

Mumbai Metropolitan Region. Whereas the guidelines prescribed vide

the notification dated 27th November, 2024 would apply to the RMC

plants in Mumbai Metropolitan Region.

31. In the Notification dated 27th November, 2024, under Clause-C of

the guidelines captioned 'Sitting Criteria' for commercial plants, the

following provisions are made:

       "C.     SITTING CRITERIA
       1)      New commercial plants within the jurisdiction of Municipal

Corporation/Municipal Councils areas of MMR shall be allowed only after getting approval of committee at HQ, MPCB.

2) New commercial plants (outside the corporation areas of MMR) shall maintain a buffer zone of approximately 500 mtr. Distance from human habitation having 1000 souls or more as per census population and 500 mtrs. from major road (National/State Highway, Major District Roads).

3) Commercial plants (outside the Municipal Corporation/ Municipal Councils area) should not be located within 500 mtr. From schools, colleges, hospitals and Courts.

4) Land required for the new Commercial RMC plant (outside the Municipal Corporation/Municipal Councils area) shall be minimum 4000 sq. mtrs.

-WP-12443-2025.DOC

5) All existing/new plants shall be fully covered from all sides like a box structure by using tin/similar type of material within a period of 03 months from the date of issuance of this Notification and shall submit Bank Guarantee of Rs.25.0/- Lakh towards compliance of the same."

32. A faint attempt was made by Mr. Bubna to submit that the

commercial plants within the Mumbai Metropolitan Region now should

not be located within 500 meters from School, Colleges, Hospitals and

Courts. I am afraid, the submission is plainly against the express text of

sub-clause (3) of the guidelines. The restriction of the RMC plant not

being located within 500 meters from the Schools, Colleges, Hospitals

and Courts does not apply to the commercial plants within the

Municipal Corporation/Municipal Council areas, as the same appears to

have been exempted by employing the expression, (outside the

Municipal Corporation/Municipal Council area). This device of

exclusion is further underscored by the fact that in clause (2) also the

rule making authority has exempted the RMC plants within the

corporation limits of MMR from maintaining the minimum buffer zone

of approximately 500 meters distance from human habitation having

1000 souls or more as per census population and 500 meters from

major road. Likewise, in clause (4) the requirement of minimum 4000

square meters land for new commercial RMC plant is not made

applicable by exempting the commercial plants within the Municipal

Corporation/Municipal Council area.

-WP-12443-2025.DOC

33. The rule making authority, it seems, took cognizance of the

scarcity of land in the Municipal Corporation area, within the limits of

MMR, and the possible impracticability of the implementation of those

restrictions and thus exempted the RMC plants from the requirements

of maintaining the buffer zone, distance and the minimum area of the

land which houses the RMC plants. The guidelines made applicable for

RMC plants for sitting criteria in MMR region by Notification dated 27 th

November, 2024, therefore cannot be read to mean that the commercial

plants within MMR region now should not be located within 500 meters

from Schools, Colleges, Hospitals and Courts. To achieve the balance,

the rule making authority has taken care to provide additional

conditions and restrictions than those found in the sitting criteria in the

Notification dated 7th November, 2016.

34. It is imperative to note that the order dated 30 th September, 2025

records that to ascertain which of the guidelines apply to the subject

RMC plant, guidance was sought from MPCB. However, there was no

response from MPCB. The Competent Authority thus recorded the view

that the guidelines dated 7th November, 2016 apply to the subject RMC

plant.

35. The said view of the respondent No.1 is clearly unsustainable.

Suffice to note that the MPCB took care to again reiterate in the

Notification dated 27th November, 2024 that the guidelines issued

-WP-12443-2025.DOC

thereunder are only for MMR area of Maharashtra and existing

guidelines published vide notification dated 7 th November, 2016 remain

in force in the rest of the Maharashtra.

36. The aforesaid being the governing norm, the impugned action

based on the sitting criteria prescribed under the notification dated 7 th

November, 2016 is wholly unsustainable.

37. Mr. Bubna made an endeavour to persuade the Court to sustain

the impugned action for the reasons given in the order dated 30 th

September, 2025. In addition to the ground of the subject RMC plant

being located within the radius of 200 meters of School, in the

impugned order dated 30th September, 2025, the Competent Authority

seems to have considered the purported breaches of the other

conditions subject to which the licence to operate was granted, namely,

deficiencies in tree plantation alongwith the periphery of the plot and

water treatment and disposal facility for generated effluent in the RMC

plant.

38. Indisputably, none of the above deficiencies and breaches were

brought to the notice of the petitioner in the show cause notice dated

11th September, 2025. The petitioner was not given an opportunity to

demonstrate that there were no deficiencies, as alleged, and that the

petitioner has not committed breach of any of the conditions subject to

which the consent has been granted by MPBC and the license issued by

-WP-12443-2025.DOC

the respondent No.1. As enunciated in the case of UMC Technoligies

(supra) an order travelling beyond the bounds of the notice is

impermissible and without jurisdiction.

39. The conspectus of aforesaid consideration is that the endeavour

of Mr. Bubna to sustain the impugned action on the basis of the grounds

adverted to by the respondent No.1 in the order dated 30 th May, 2025,

in respect of which the petitioner was not given any opportunity to

show cause, cannot be countenanced.

40. Resultantly, the impugned orders deserve to be quashed and set

aside. However, it is required to be clarified that this determination

would not preclude the respondent No.1 and MPCB from taking

appropriate action in respect of the subject RMC plant if it is found that

the RMC plant is being operated in breach of the conditions subject to

which the consent to operate has been given by MPCB and licence has

been issued by respondent No.1, after providing an effective

opportunity of hearing and in accordance with law.

41. Hence the following order:

: O R D E R:

       (i)     Petition stands allowed.

       (ii)    The orders dated 12th September 2025 and 30th

       September 2025 stand quashed and set aside







                                                            -WP-12443-2025.DOC

(iii) The licence to operate RMC plant stands restored

subject to the terms and conditions incorporated in the

licence dated 11th October 2024 and the consent of the

MPCB.

(iv) It is clarified that if MPCB or the Respondent No.1

find that there is breach of any of the conditions subject o

which consent and licence to operate RMC plant have

been granted, the MPCB and the Respondent No.1 are at

liberty to take appropriate action in accordance with law

after providing an opportunity of hearing to the Petitioner.

No costs.

[N. J. JAMADAR, J.]

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter