Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Atria Constructions vs The Municipal Commissioner And Ors
2025 Latest Caselaw 7807 Bom

Citation : 2025 Latest Caselaw 7807 Bom
Judgement Date : 21 November, 2025

Bombay High Court

M/S. Atria Constructions vs The Municipal Commissioner And Ors on 21 November, 2025

Author: G.S. Kulkarni
Bench: G. S. Kulkarni
2025:BHC-AS:50416-DB
                                                                                      WP 1022-25CORRECTED.DOC
       PRAJAKTA
       SAGAR
       VARTAK
       Digitally signed by
       PRAJAKTA SAGAR
       VARTAK
       Date: 2025.11.21
       16:12:49 +0530



      PSV/VSA/PVR
                                           IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                                   CIVIL APPELLATE JURISDICTION

                                                       WRIT PETITION NO. 1022 OF 2025

                             M/s. Atria Constructions, represented through
                             its partners Mr. Dhananjay Nivrutti Thite &
                             Mr. Anil Ramalinga Reddy                               ... Petitioner
                                           Vs.
                             (1) The Municipal Commis, Pune
                             (2) The City Engineer, PMC Building, Pune
                             (3) The Junior Engineer, Bldg. Development Dept., Pune
                             (4) The Deputy Engineer, Bldg, Development Dept., Pune
                             (5) Wellbuild Merchants Pvt. Ltd. through its Director
                             (6) The State of Maharashtra                           ... Respondents

                                                                WITH
                                                    WRIT PETITION NO. 10414 OF 2025

                             (1) Pooja B. Jain
                             (2) Rahul A. Jain
                             (3) Indermal V. Jain
                             (4) Dilip K. Bathiya
                             (5) Bhawarlal P. Jain
                             (6) Jagruti V. Doshi
                             (7) Sahit S. Oswal
                             (8) Piyush D. Lodha
                             (9) Champat Kumar Jain
                             (10) Sachin M. Palresha
                             (11) Akshay P. Jain
                             (12) Hitesh M. Jain
                             (13) Roshan J. Jain
                             (14) Pooja S. Swami
                             (15) Shaileshkumar K. Golesha
                             (16) Mahendra M. Jain
                             (17) Raj P. Kothari
                             (18) Anil B. Gundecha
                             (19) Surekha A. Semlani
                             (20) Kantilal B.Jain
                             (21) Kishor M. Oswal
                             (22) Sachin R. Jain
                             (23) Riteshkumar S. Jain
                             (24) Praful Mehta
                             (25) Vivek H. Gada
                             (26) Vaibhav P. Gandhi
                                                                  Page 1 of 62
                                                               21 November 2025



                                ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                          WP 1022-25CORRECTED.DOC



(27) Pravin M. Bora
(28) Vikram Kumar Jain
(29) Nilesh N. Shah
(30) Dilip N. Oswal
(31) Jayendra P. Shah
(32) Bharat M. Jain
(33) Ankita v. Kasat
(34) Shobha H. Bhattad
(35) Manish A. Masalia
(36) Shankarlal Kasaram Parihar
(37) Mukesh G. Oswal
(38) Sanjay K. Parmar
(39) Ritesh Singhvi
(40) Jugalkishor Toshniwal
(41) Jyoti D. Bothara
(42) Sudin S. Mehta
(43) Ritesha A. Rathor
(44) Vimla Jain
(45) Karishma Sarnot
(46) Nitesh Singhvi
(47) Nayana H. Valand
(48) Vishal J. Shah
(49) Rajgruhi Residency D Wing Co-op. Hsg. Society Ltd.     ... Petitioners
               Vs.
(1) Pune Municipal Commissioner
(2) The Executive Engineer, Bldg. Development Dept., Pune
(3) The City Engineer, PMC Building, Pune
(4) The Deputy Engineer, Bldg, Development Dept., Pune
(5) Wellbuild Merchants Pvt. Ltd. through its Director
(6) M/s. Atria Constructions
(7) The State of Maharashtra                              ...       Respondents
                         _______
Mr. Girish S. Godbole, Senior Advocate a/w. Mr. Vijay Upadhyay and Mr. Sitesh
Sharma for the petitioner in WP/1022/2025.
Mr. Pritesh Burad a/w. Ms. Samita Vaviya, Ms. Kiran Yadav i/b. Pritesh Burad
Associates for the petitioner in WP/10414/2025.
Mr. Vishwanath Patil for respondent nos. 1 to 4/PMC.
Mr. Ashish Kamat, Senior Advocate a/w. Mr. Shrey Fatterpekar, Ms. Nidhi, Mr.
Vishal Tiwari, Mr. Himanshu Singh i/b. White and Brief Advocates and Solicitors
for respondent nos. 5.
Mr. Mayur Khandeparkar a/w. Mr. Akshay Deshmukh, Mr. Sumit Chaudhary, Mr.
Sanket Kadam for the Intervenor/Applicant in IA/1309/2025.
Ms. Savita A. Prabhune, AGP for the State.
                                     _______


                                     Page 2 of 62
                                  21 November 2025



   ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



                 CORAM                    :    G. S. KULKARNI &
                                               ARIF S. DOCTOR, JJ.
                 RESERVED ON  :                4 AUGUST, 2025
                 PRONOUNCED ON :               21 NOVEMBER, 2025

Judgment (Per G.S. Kulkarni. J.) :-

1.       Rule returnable forthwith. By consent of the parties heard finally.


2.       These are two proceedings filed under Article 226 of the Constitution of

India.


3.       Writ Petition No. 1022 of 2025 is filed by M/s. Atria Constructions

assailing a Stop Work Notice dated 10 December 2024 issued to such petitioner

by respondent nos.3 and 4, namely the Junior Engineer and the Deputy Engineer

of Building Development Department of the Pune Municipal Corporation-

respondent no.1 (for short, "the Municipal Corporation").


4.       Writ Petition No.10414 of 2025 is filed by 49 petitioners who have

purchased flats in the building in question constructed by M/s. Atria

Constructions, who contend that they are being deprived of the flats purchased by

them in view of the municipal corporation halting grant of Occupation Certificate

by issuance of the impugned stop work notice.


5.       For convenience, we refer to the facts on record of the first writ petition

filed by M/s. Atria Constructions, who is referred as "the petitioner", and the

petitioners in the companion petition would be referred as "the flat purchasers".




                                       Page 3 of 62
                                    21 November 2025



     ::: Uploaded on - 21/11/2025                       ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                            WP 1022-25CORRECTED.DOC



        Facts:-


6.      This is a peculiar case as the facts would unfold. The dispute pertains to a

building project described as 'Rajgruhi Residency' comprising construction of

four wings which include four podiums plus amenities plus 20 floors, being the

construction of each of the wings.


7.      At the outset, we may observe that as the facts unfold, the entire

controversy underlies a dispute between respondent no.5-Wellbuild Merchants

Pvt. Ltd./the owner of the land (for short, "Wellbuild") who was also the

developer of the 'A' and 'B' wings, which work was in fact contracted to the

petitioner. Further the petitioner under an agreement dated 18 August 2021

entered into with Wellbuild, is undertaking construction of wings 'C' and 'D'. It

is also not in dispute that the construction of Wings 'A' and 'B' was completed

long back. Also, an Occupancy Certificate was granted, consequent to which the

flat purchasers are in occupation of their respective tenements, who have also

formed a cooperative society.


8.      Insofar as Wings 'C' and 'D' are concerned, the construction of which is

undertaken by the petitioner, the construction of Wing 'D' stands fully completed

and is awaiting an Occupancy Certificate, which has already been applied by the

petitioner.     Also large number of flats in Wing-D are already sold by the

petitioner, and such flat purchasers are awaiting occupancy of their respective flats.

The construction of Wing-C has reached upto 4 floors.



                                       Page 4 of 62
                                    21 November 2025



     ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



9.       It is at this stage, a very peculiar dispute has arisen, which appears to be

wholly between Wellbuild and the petitioner. The flat purchasers of Wing-D are

sandwiched between these disputing parties. It also appears that the municipal

machinery is being used to settle these private disputes.


10.      The following discussion on the facts would shed light on such factual

conspectus:-


11.      On 25 October 2019, a Memorandum of Understanding was executed

between the petitioner and Wellbuild, whereby the petitioner invested a sum of

Rs. 40 Crores to ensure completion of the project.


12.      On 18 August 2021 and 26 August 2021, Articles of Agreement/

Development Agreement along with a Power of Attorney were executed and

registered between the petitioner and Wellbuild, whereunder the petitioner was

appointed as the "developer" by Wellbuild to complete the project which is

primarily the Wings 'C' and 'D' of the said project.


13.      About 19 months back i.e. in December 2023, the petitioner fully

completed the construction of Wing/Tower-D. The plans in this regard are dated

13 October 2021 and were duly sanctioned by the Municipal Corporation. For

the D-Wing, the total FSI for construction was approved at 15,870.02 sq. meters

with 80 approved flats/tenements.


14.      The land on which the project of these buildings (Wings A, B, C & D) is

being undertaken, has also a DP work of a storm water drain, which was to be

                                        Page 5 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



realigned. On 02 February 2024, in regard to the realignment of Nala/storm

water line, a work order was issued by the Drainage Department of the Municipal

Corporation. The petitioner has contended that 70% of the realignment of the

storm water drain (nala) already stands completed, hence the purported

grievances of the residents of Towers A and B would not survive.


15.      It is on such backdrop, as on date, the petitioner's position is that the

petitioner has completed the work of Tower/Wing 'D'. It is the petitioner's case

that at this crucial juncture, Wellbuild terminated the Articles of Agreement dated

18 August 2021. Thus, the disputes and differences had arisen between Wellbuild

and the petitioner on such count.


16.      It needs to be stated that Wellbuild, even prior to the receipt of the

petitioner's reply to the termination notice dated 16 April 2022, filed an

application under Section 9 of the Arbitration and Conciliation Act, 1996 (for

short, "ACA") being Civil Miscellaneous Application No. 544 of 2024 before the

Court of learned District & Sessions Judge (Commercial Division) at Pune. On

29 April 2024, the petitioner also filed a cross application under Section 9 of the

ACA being Civil Miscellaneous Application No. 582 of 2024.


17.      The disputes were also taken by WellBuild before different authorities, the

same need not be detailed, suffice it to observe that Wellbuild approached the

Maharashtra Pollution Control Board (for short, "MPCB") applying to the said

authority not to process the petitioner's application for "revalidation of consent to

establish and consent to operate", which was pending consideration before the
                                        Page 6 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                     WP 1022-25CORRECTED.DOC



MPCB.        On 29 August 2024, Wellbuild in fact instructed its Director to

withdraw the pending application for grant of revised Environmental Clearance.


18.      The applications filed by Wellbuild, as also by the petitioner under Section

9 of the ACA were adjudicated by the Competent Court by an order dated 20

September 2024, whereby the Section 9 ACA application filed by Wellbuild was

rejected, and the Section 9 application filed by the petitioner was partly allowed.

An appeal was preferred against the said order by both the parties under Section

37 of the ACA. A Division Bench of this Court, by a common judgment and

order dated 22 November 2024 disposed of both the appeals, wherein the orders

passed on Section 9 proceedings filed by the petitioner were sustained. Thereafter

inter se between the parties it was agreed that the disputes and differences be

referred for adjudication by appointing an arbitral tribunal. Accordingly, a former

Judge of this Court was appointed as the sole arbitrator to adjudicate the disputes

between the parties. The request for continuation of interim relief also came to be

rejected by the Appellate Court. The relevant part of the said order reads thus:


         "61. M/s. AC has furnished an undertaking to this Court, which reads as
         follows :-

             "AFFIDAVIT/UNDERTAKING ON                   BEHALF       OF      THE
             RESPONDENTS ABOVENAMED:

             I Shri. Anil Reddy age: 56 years, Occ: Business, having office at
             440/441, Nanapeth, PGI Building, Pune 411002, the partner of the
             the Respondent No.1 abovenamed, hereby undertake as follows:

             a. M/s. Atria Constructions undertakes not to sell balance 5 flats in
             Tower D and balance 63 flats in Tower C in the scheme "Rajgruhi
             Residency" further at less than Rs.9,500/- (Rupees Nine Thousand
             Five Hundred Only) per Sq.ft on saleable area on rera carpet basis viz
             rera carpet area + 35% as defined in Articles of Agreement dated
             19/08/2021.

                                        Page 7 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                              ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                WP 1022-25CORRECTED.DOC



       b. The Respondent No.1 undertakes to continue to sale the units
       not be below the rate of Rs. 9500/- (Rupees Nine Thousand Five
       Hundred Only) per Sq.ft on saleable area on rera carpet basis viz rera
       carpet area + 35% as defined in Articles of Agreement dated
       19/08/2021 and inform the Appellant about the rate of selling of
       units and give him 30 days' notice to make any further offer and is
       obligated to conclude the transaction at such higher rate and in
       favour of the purchaser nominated by the Respondent or bring any
       fresh Purchaser for more than the rate provided by the Respondent
       No.1. The parties hereby agree that such offer and/or counteroffer
       shall not be below the rate of Rs. 9500/- per sq. ft. (Rupees Nine
       Thousand Five Hundred Only) on saleable area on rera carpet basis
       viz rera carpet Page 21 of 25 area + 35% as defined in Articles of
       Agreement dated 19/08/2021.

       c. Both the Appellant and the Respondent No. I agree and
       undertake that they shall not in any manner communicate with
       and/or approach the prospective purchaser nominated by the other
       side. All communication in relation to the proposed transaction(s)
       shall be only between the Appellant and Respondent No. 1."

   62. Despite the undertaking, even if we accept Mr Kamat's contention
   that M/s. AC will accept cash amounts; it is always open to WMPL to
   lead cogent evidence and recover damages or proper market value.
   However, at this stage, it will not be appropriate to stop the construction
   or restrain the sale of apartments for a rate not below Rs.9500/- per sq.
   ft. even though the agreement between the parties refers to average
   minimum rate of Rs.8000/- per sq. ft. WMPL, had pleaded that the rate
   in the area would be Rs.9500/- per sq. ft. Mr. Kamat clarified that this
   would be the minimum rate.

   63. M/s. AC, consistent with the undertaking quoted above, shall not
   agree to sell any apartments at a rate of less than Rs.9500/- per sq. ft.
   The undertaking given on behalf of M/s AC is now accepted as an
   undertaking to this Court.

   64. However, no case is made to restrain the execution of agreements
   regarding 17 apartments. These were transactions entered into much
   earlier, but no formal agreements were executed. Such execution had to
   be deferred on account of status quo orders and statements. Therefore, at
   this stage, there is no point in imposing any restrictions regarding these
   17 allotments or agreements. The position of the remaining purchasers is
   not much different from that of these 17 allottees.

   65. M/s AC will, however, not claim any equities regarding sale of
   apartments. This position must be made clear to the 17 allottees by
   informing them about the pendency of disputes and legal/arbitration
   proceedings.

   66. Regarding the challenges to the order by which the learned District
   Judge has granted interim relief to M/s. AC, at least prima facie, the
   reliefs are broad-based to some extent. While WMPL cannot be allowed
   to take the law into its hands and physically obstruct the construction of
   the project, no blanket injunction can be granted restraining WMPL

                                  Page 8 of 62
                               21 November 2025



::: Uploaded on - 21/11/2025                              ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                       WP 1022-25CORRECTED.DOC



         from filing complaints to statutory and Environmental protection
         authorities about the alleged deficiencies. This cannot be called some
         unlawful obstruction. With such modification and clarification, the
         order granted favouring M/s AC is sustained.

         67. The learned counsel for the parties proposed that the interim
         arrangement could operate until the arbitrator enters on reference and
         decides the issue of interim relief. Mr. Kamat submitted that the
         arrangement that this Court's orders could be treated as ad-interim relief
         and the applications under Section 9 could then be treated as
         applications under Section 17 before the Arbitral Tribunal. The Arbitral
         Tribunal could then dispose of these applications and decide on the
         interim relief that could operate pending the disposal of the arbitration
         proceedings.

         68. Mr. Godbole submitted that there could be no objection to this
         Court's order operating as an ad-interim arrangement. He, however,
         submitted that there are subsequent developments and therefore, the
         parties could be given liberty to file applications under Section 17 before
         the Arbitral Tribunal. The Arbitral Tribunal could then decide such
         applications without being influenced by the ad-interim arrangement
         that could be made by this Court.

         69. Any direction to treat the applications under Section 9 as Section 17
         applications would involve complications, though it might save paper.
         Subsequent developments might be difficult to record. Therefore, it
         would be appropriate to grant the parties leave to file applications under
         Section 17, which could then be decided without being influenced by
         this interim arrangement.

         70. The above arrangement will operate as an ad-interim arrangement.
         The parties may file their applications under Section 17 within four
         weeks from today. The above ad-interim arrangement shall operate until
         the Arbitral Tribunal disposes of Section 17 applications, if filed or until
         the Arbitral Tribunal may direct. The Arbitral Tribunal must decide the
         applications under Section 17 without being influenced by any
         observations in the impugned judgments and orders dated 20 September
         2024 or this judgment and order."



19.      It is thus clearly seen from the aforesaid orders passed by the Division

Bench that the disputes inter se between Wellbuild and the petitioner were to be

the subject matter of the arbitral proceedings.


20.      Thereafter on 02 December 2024, the petitioner preferred a Civil Suit

being Special Civil Suit No. 2012 of 2024 before the Court of learned Civil Judge


                                        Page 9 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                               ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



Senior Division, Pune against the Co-operative Society formed by the flat

purchasers of 'A' and 'B' Wings of the said project. In the said civil suit, the

learned trial Judge passed an ad-interim order restraining the society and its

residents from creating obstruction in the work of realignment of the Nala and

also restrained illegal use of ramp of Tower 'C', which was yet to receive the

completion certificate.

21.      The petitioner contends that, thus there were two sets of orders, namely,

orders passed by the Court(s) under the ACA, as also orders passed by the Civil

Court against the society, hence there was no impediment for the petitioner to

carry forward the project by obtaining the O.C. in regard to 'D' Wing, which was

complete.

22.       The petitioner contends that on 06 December 2024 at about 04.57 p.m.

(being a Friday), the petitioner received a WhatsApp notice from the Deputy

Engineer, Building Development Department of the Municipal Corporation

(respondent no.4) informing the petitioner of a hearing scheduled before

respondent no.2-City Engineer of the Municipal Corporation on 9 December

2024, however, no details as to the reason/ context of such hearing were informed

to the petitioner.

23.      The petitioner has contended that most surprisingly, the hearing, which

was held in pursuance of the said WhatsApp notice dated 06 December 2024,

was attended by several persons, namely, an RTI Activist, representatives of

Wellbuild and their advocates, all this was without any intimation of this nature of

hearing to the petitioner.
                                        Page 10 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



24.      The petitioner tendered its written response, post conclusion of the

hearing held by respondent no.2-City Engineer, inter alia highlighting the

recommendation in regard to Revalidation of the Consent to Establish and

Renewal of the Consent to Operate being duly recommended as per the minutes

of the consent committee meeting dated 14 November 2024 held between the

petitioner and Wellbuild.

25.      It is the petitioner's case that immediately on the next day i.e. on 10

December 2024, the "impugned stop work notice" came to be issued by

respondent no.3-Deputy Engineer of the Municipal Corporation, which is stated

to be issued on an approval being granted by respondent no.2-City Engineer. The

impugned stop work is issued inter alia on the grounds of :- (i) Refusal of Consent

to Establish under Section 27 of the Water (Prevention & Control of Pollution)

Act, 1974 and Section 21(4) of the Air (Prevention & Control of Pollution) Act,

1981, (ii) Non-receipt of Consent to Operate in respect of each project,

(iii) Failure to furnish revised Clearance as per sanctioned IOD dated

22/02/2023, (iv) Alleged deviations in actual construction from Environmental

Clearance Certificate and (v) Failure to complete shifting work of Nala as per

order dated 22 May, 2023 passed by Respondent No.1.

26.      The petitioner has contended that on 19 December 2024, in pursuance of

the minutes of the Consent Committee Meeting dated 14 November 2024, the

petitioner is stated to have received Revalidation of Consent to Establish, for a

further period of 5 years. Also renewal of Consent to Operate [Part II] valid till

12 January 2026 was granted.
                                        Page 11 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



27.       It is the case of the petitioner that one Mr. Dilip Kale, Architect of

Wellbuild, at the behest of Wellbuild and without there being any requirement

from the Municipal Corporation, issued a certificate dated 21 August 2024. This

certificate was contrary to the sanctioned plans, which had formed the basis of

issuance of a Commencement Certificate dated 13 October 2021 as issued to the

petitioner. According to the petitioner, in such certificate, Mr. Dilip Kale falsely

stated that FSI of Tower 'D' is about 14599.71 sq. meters and the construction of

Tower 'D' as undertaken was of 15870 sq. meters. Being aggrieved by such

incorrect/false recording of the area in the certificate issued by Mr. Dilip Kale, the

petitioner issued an email dated 31 January 2025 to him to furnish certified

copies of official plans, building wise, which were submitted before the

environment Committee in 2017 and details of disclosure of information in that

regard.


28.       On 26 February 2025, the petitioner also obtained renewal of 'Consent to

Operate' part III valid till 30 June 2026.


29.       Thereafter on 24 April 2025, the petitioner applied for an architect's

certificate along with the papers which were made available by Architect Mr. Dilip

Kale. Architect Mr. Vilas Tarvade issued a certificate stating that the architect's

certificate issued by Mr. Dilip Kale (Wellbuild's Architect) disclosed incorrect and

inaccurate figures and that even the reference contained therein to the IOD

submitted for environment clearance (for short, "EC") on 19 August 2023 was

grossly inaccurate and erroneous. He also recorded that on a detailed scrutiny of

                                        Page 12 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                    WP 1022-25CORRECTED.DOC



the record, the IOD which was submitted for E.C. on 19 August 2023 came to be

duly withdrawn and a fresh IOD dated 26 November 2023 was submitted for EC

(Environment Clearance) along with a proposal no. SIA/MH/INFRA2/

450922/2023.


30.      It is on such backdrop, the petitioner has contended that the impugned

stop work notice dated 10 December 2024 is illegal on each of the grounds on

which the same has been issued. The petitioner's case on each of the points as

contained in the stop work notice submitted to the municipal corporation in a

tabular form is required to be noted which read thus:-

        "
        No. Alleged Deficiency highlighted               Petitioner's response
            in Show Cause Notice
          1.   Refusal of Consent to Establish (i) The Consent to Establish for the
               under Section 27 of the Water Project "Rajgruhi Residency" vide UAN
               (Prevention & Control of CE1505000801 had expired on
               Pollution) Act, 1974 and 12/01/2021.
               Section 21(4) of the Air (ii) The revised sanction plan
               (Prevention & Control of CC/2042/2021 was sanctioned from
               Pollution) Act, 1981            Pune Municipal Corporation by
                                               Wellbuild Merchants Pvt Ltd on
                                               13/10/2021. A valid Consent to
                                               Establish is a precursor for sanction of
                                               Building Plan alongwith a valid
                                               Environment Clearance Certificate
                                               (iii) The Revalidation of Consent to
                                               Establish was applied by Wellbuild
                                               Merchants Pvt Ltd on 28/4/2023 vide
                                               UAN 000161756 which was rejected on
                                               14/01/2024 due to negligence in
                                               responding to the show cause notice

                                               (iv) The Revalidation of Consent to
                                               Establish was applied by Atria
                                               Constructions on 02/02/2024 vide
                                               UAN 0000197009 which was finally
                                               recommended     in    the    Consent
                                               Committee meeting on 14/11/2024.


                                        Page 13 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                            ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                            WP 1022-25CORRECTED.DOC



                                        (v) We have now received the
                                        Revalidation for Consent to Establish on
                                        19/12/2024 valid till 12/01/2026
                                        (Annexure - । D)

                                        (vi) The Consent to Operate obtained
                                        by Wellbuild Merchants Pvt Ltd. vide
                                        UAN 000094164 dated 03/07/2021
                                        had expired on 03/06/2021

                                        (vii) The Part Completion Certificate for
                                        A & B Building completed by Wellbuild
                                        Merchants Pvt Lid were issued before
                                        Consent to Operate dated 03/07/21 was
                                        obtained

                                        (viii) The Renewal of Consent to
                                        Operate   obtained   by   Wellbuild
                                        Merchants Pvt Ltd. vide UAN
                                        0000116949 dated 30/07/2021 expired
                                        on 03/06/2023

                                        (ix) The Consent to Renewal! was
                                        applied by Atria Construction on
                                        16/04/2024

                                        (x) The Renewal of Consent to Operate
                                        was recommended in the Consent
                                        Committee meeting on 14/11/2024.
                                        This was highlighted in the meeting, in
                                        the CE Office on 9/12/2024 and was
                                        also attached in our submission on
                                        10/12/2024.

                                        (xi) We have now received the Renewal
                                        for Consent to Operate on 19/12/2024
                                        valid till 30/06/2025 (Annexure -E)
    2   Non-receipt of Consent to Explained above
        Operate in receipt of each
        project

    3   Failure to furnish revised Sanctioned Environment Clearance
        Environment Clearance as per Details
        sanctioned   IOD       dated (i) The Environment Clearance order
        22/02/2023                   IEC/Samitee/-5, dated October 13,
                                     2017, sanctioned a total built-up of
                                     72,032.18 sq. mtrs. for a plot area of
                                     18,000 sq. mtrs.

                                        Revised     Environment Clearance
                                        Application
                                        (ii) An Approved Intimation of

                                  Page 14 of 62
                               21 November 2025



::: Uploaded on - 21/11/2025                           ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



                                        Disapproval (IOD) dated December 20,
                                        2023, vide IOD Zone/2/7472, was
                                        submitted for a Revised Environment
                                        Clearance for an increased built-up area
                                        of 84,131.86 sq. mtrs. Before the-State
                                        Environment Assessment Committee
                                        (SEAC)      vide    Application     No.
                                        S[A/MH/INFRA2/450922/2023. The
                                        SEAC cleared the proposal in its 187th
                                        meeting dated December 27, 2023, and
                                        forwarded it to the State Environment
                                        Impact Assessment Authority (SEIAA).

                                        Construction Status as on 20.12.2024
                                        (i) As of date, we have constructed
                                        68,132.86 sq. Mtrs, as mentioned in
                                        your Work Stop Notice order.

                                        Voluntary Construction Halt

                                        (i) Construction for Building C has been
                                        halted voluntarily, as we have reached
                                        the threshold built area permitted under
                                        the sanctioned limit in the Environment
                                        Clearance dated October 13, 2017.

                                        Undertaking

                                        (i) We undertake not to carry out any
                                        additional construction until the SEIAA
                                        clears the project as per the IOD dated
                                        December 20, 2023, vide 10D
                                        Zone/2/747, and revised sanction is
                                        obtained from the Pune Municipal
                                        Corporation

    4   Alleged deviations in actual Environment Clearance Compliance
        construction from Environment (i) As mentioned above, there are no
        Clearance Certificate         deviations   from     the Certificate
                                      Environment Clearance Certificate
                                      dated October 13, 2017.

                                        Inspection Report

                                        (i) The Inspection Report bearing No. F.
                                        No. EC- 2334/RON/2023-NGP, dated
                                        December 19, 2023. This Certified
                                        Compliance Report highlights that no
                                        deficiencies or deviations in construction
                                        were found.

                                        Environment Clearance History

                                        (i)   The Certified Compliance Report

                                  Page 15 of 62
                               21 November 2025



::: Uploaded on - 21/11/2025                           ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



                                        references the grant of Environment
                                        Clearance vide:
                                        SEAC-III-2014/C.R.194/TC-3,     dated
                                        December 10, 2015, for a plot area of
                                        18,000 sq. mtrs. with a total built-up
                                        area of 56,950.70 sq. mtrs.

                                        (ii) IEC/Samitee/-5, dated October 13,
                                        2017, for a plot area of 18,000 sq. mtrs.
                                        with a total built-up area of 72,032.18
                                        sq. mtrs.

                                        Architect's Certification

                                        (i) The licensed Architect has certified
                                        on 21/08/2024 that the total built-up
                                        area constructed till date is 68,132.86 sq.
                                        mtrs., which is within the EC sanctioned
                                        limit of 72,032.18 sq.mtrs (Annexure -
                                        F)

                                        (ii) There are no deviations in
                                        construction beyond the granted
                                        Environment Clearance. The State
                                        Environment Assessment Committee
                                        (SEAC) has recommended the grant of a
                                        further Revised Environment Clearance
                                        Certificate and forwarded the proposal
                                        to the State Environment Impact
                                        Assessment Authority (SEIAA).

    5   Shifting / Re-alignment work of Background of Work Order
        Nala as per Order bearing (i) A Work Order, Ja Kra 3457 dated
        Outward No. MC/UDCPR- 2/2/2024 was issued to Atria
        20/SEC/3. 1.1(ii)/443, dated Constructions by the Executive,
        22/05/2023                      Drainage Department referencing an
                                        Order dated May 22, 2023. This Order
                                        granted      permission     to    Atria
                                        Constructions to shift/realign the
                                        Nala/Storm Water Line as outlined in
                                        the proposed plan. The Order specified
                                        that Atria Constructions would bear all
                                        expenses for the realignment. Please
                                        refer to Clause 11 and Clause 19 of the
                                        order Ja Kra 3457 dated 2/2/2024

                                        1. That the entire work needs to be
                                        completed before 1/2/2025, and

                                        2. That a final Completion Certificate
                                        would not be granted until obtaining a
                                        completion    certificate  from    the

                                  Page 16 of 62
                               21 November 2025



::: Uploaded on - 21/11/2025                            ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                            WP 1022-25CORRECTED.DOC



                                        Department of Drainage Maintenance
                                        and   Repair     of the Municipal
                                        Corporation of Pune.

                                        Obstructions by CHS Building A &
                                        Building
                                        (i)      Despite the Work Order,
                                        Respondent       Societies   (Rajgruhi
                                        Residency Building A CHS Ltd. and
                                        Rajgruhi Residency Building B CHS
                                        Ltd.) colluded to obstruct the
                                        development work. Atria Constructions
                                        had requested the Societies to
                                        temporarily shift vehicles to facilitate
                                        excavation and pipe-laying work.
                                        Despite Court Orders, the instructions
                                        have been willfully defied.
                                        Letter to Chief Engineer, PMC
                                        (i)     On April 22, 2024, Atria
                                        Constructions wrote to the Executive
                                        Engineer, Drainage and Repairs
                                        Department,        Pune       Municipal
                                        Corporation,       highlighting     the
                                        obstructions and non-cooperation from
                                        the Societies.

                                        PMC's Warning to Societies

                                        (i) On May 05, 2024 (Annexure-G)and
                                        on October 17, 2024 (Annexure-H), the
                                        Superintendent Engineer, PMC, warned
                                        the Societies that obstructing the Nala
                                        development work could cause damage
                                        to life and property, especially during
                                        monsoons.
                                        (ii) However, the Society members have
                                        not relented from their position and
                                        continue obstructing laying the 900 mm
                                        Storm Water Line

                                        Special Civil Suit No. 2012/2024
                                        (i) Due to persistent obstructions, Atria
                                        Constructions filed Special Civil Suit
                                        No. 2012/2024 on November 27, 2024,
                                        against the Societies. The Civil Judge,
                                        Senior Division, Pune, granted an Ad-
                                        Interim Ex-Parte Order on December 2,
                                        2024, restraining the defendants from
                                        obstructing the development and
                                        construction activities.

                                        (ii) Despite the Court Orders, the
                                        obstructions continue unabatedly.

                                  Page 17 of 62
                               21 November 2025



::: Uploaded on - 21/11/2025                           ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC




31.      It is thus the petitioner's case that, the petitioner having completed the

entire construction/development of Wing 'D'/Tower 'D', by December 2023

comprising of 80 tenements, out of which 58 tenements were sold under

registered deeds and 17 tenements were booked, at such crucial stage Wellbuild

started creating hurdles only to shift the burden of completion of amenities of

Wings 'A' & 'B onto the petitioner. It is submitted that all attempts initiated by

Wellbuild had failed, hence the motive to oust the petitioner from the project

(Rajgruhi Residency) when it failed to secure any interim injunction against the

petitioner in the legal proceedings. It is submitted that Wellbuild to overcome

such failures, started making multiple complaints through other methods, namely

through RTI activists, social activists, politicians and residents of Tower 'A' and 'B'

from whom such complaints against the petitioner were generated during the

period April 2024 to 24 December 2024 which were filed with the Municipal

Corporation and with the authorities granting Environmental Clearance (EC).


32.      The petitioner contends that such persons, who are wholly unconnected

with the project and were connected and/or associated with Mr. Yuvraj Dhamale,

Director of Wellbuild. It is the petitioner's case that all such complaints were

intended to withhold issuance of the occupation certificate to be issued in favour

of the petitioner in respect of Tower 'D' to be granted on the petitioner's

application, knowing well that third party rights are created and this would cause

a serious prejudice and losses to the petitioner thereby harming the innocent flats

purchasers of Tower 'D' as also the petitioner's reputation.            It is hence the

                                        Page 18 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                              WP 1022-25CORRECTED.DOC



petitioner's case that the reliefs as prayed for in the writ petition be granted to the

petitioner.


33.       In supporting the petitioner's case for reliefs as prayed for in the writ

petition, Mr. Godbole, learned senior counsel for the petitioner has made the

following submissions:-


i.        The impugned stop work notice is wholly illegal, being contrary to the

record of the completed work. It is in breach of principles of natural justice, high-

handed and issued for extraneous reasons.


ii.       The impugned action on the part of the Assistant Engineer and the

Deputy Engineer of the municipal corporation to issue the impugned stop work

notice dated 10 December 2024, on the grounds inter alia that (i) there is no

consent to establish and operate from MPCB; (ii) that there is a failure to shift the

Nala despite permission dated 25 February 2025 and in respect of which IOD

was issued on 22 February, 2023; and (iii) a revised EC not being obtained on an

alleged variation from the original EC dated 04 October 2017 when compared to

the actual construction at site, were wholly arbitrary reasons, contrary to the clear

factual situation as explained in the chart (supra).


iii.      Respondent no.2-City Engineer exercised undue haste in passing the

impugned order/stop work notice inasmuch as, a notice scheduling a hearing was

issued to the petitioner by the Executive Engineer on 06 December 2024, calling

upon the petitioner to appear before the City Engineer on 09 December 2024 at


                                         Page 19 of 62
                                      21 November 2025



       ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



11.30 a.m. and the impugned order was passed on 10 December 2024. It is thus

submitted that considering such haste and the lack of adequate opportunity being

granted to the petitioner, malafides are necessarily required to be presumed on the

part of such officials of the Municipal Corporation. Further no reasons being set

out in the notice as to the purpose for which meeting was scheduled speaks

volumes of the high-handed and arbitrary approach of the Municipal officials. In

support of such contentions, reliance is placed on the decisions of the Supreme

Court in Dr. S. P. Kapoor vs. State of Himachal Pradesh & Ors. 1, Zenit Mataplast

Private Limited v/s. State of Maharashtra & Ors. 2, Fuljit Kaur vs. State of Punjab

& Ors.3, Rajiv Kumar vs. State of Uttar Pradesh & Anr.4 and Ayaaubkhan

Noorkhan Pathan vs. State of Maharashtra & Ors.5


iv.      No show cause notice was issued to the petitioner, as the basic principles of

law would require, before a hearing being fixed before the City Engineer on 09

December 2024. Also the impugned order/stop work notice was passed not by

the authority, namely, the City Engineer who presided over the hearing, but by

the Assistant Engineer and the Deputy Engineer. This was a novel method, i.e.,

merely on a purported approval by the City Engineer. It is submitted that apart

from the impugned stop work notice, no reasoned order is passed by the City

Engineer, also such order is neither pleaded nor placed on record on behalf of the


1 (1981) 4 SCC 716
2 (2009) 10 SCC 388
3 (2010) 11 SCC 455
4 (2017) 8 SCC 791
5 (2013) 4 SCC 791
                                        Page 20 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                              WP 1022-25CORRECTED.DOC



respondents.         For such reason, the impugned stop work notice dated 10

December 2024 is in breach of the principles of natural justice, high-handed and

void ab initio.


v.        The purported exercise of the statutory power is purely to assist Wellbuild

in the private dispute which the petitioner has against Wellbuild, for the reason,

that only after the order dated 22 November 2024 was passed by the Division

Bench of this Court, dismissing Wellbuild's appeal filed under Section 37 of the

ACA, the said notice dated 06 December 2024 was issued to the petitioner

scheduling a hearing on 9 December 2024 on which the impugned order was

immediately passed on 10 December 2024. Hence, such hasty exercise of powers

is clearly high-handed, arbitrary and malafide.


vi.       The IOD dated 22 February 2023 which was withdrawn by issuing new

IOD dated 26 November 2023 providing for an extra area, had not culminated

into a Commencement Certificate since a revised EC proposal was pending.


vii.      During the hearing which had taken place before the City Engineer, on 9

December 2024, the MPCB resolution dated 14 November 2024 was relied upon

by the petitioner, granting revalidation of Consent to Establish as also Consent to

Operate. Such material was not considered in passing the impugned order and on

the ground of absence of such consent, the stop work notice has been issued. The

impugned stop work notice dated 10 December 2024, only on this count, is

required to be held to be perverse, arbitrary and illegal.



                                         Page 21 of 62
                                      21 November 2025



       ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                               WP 1022-25CORRECTED.DOC



viii.      Passing of the impugned order has amounted to nullifying the injunction

which was granted by the Civil Court against the society formed by the residents

of 'A' and 'B' Wings, who were creating obstruction in the realignment of the

Nala. By any indirect methods of this kind, court orders cannot be defeated. This

amounts to misuse of the machinery of the municipal corporation.

ix.        One of the vital aspects of the matter is to the effect that the construction

being undertaken was under a valid Environmental Clearance and the same was

undertaken as per the sanctioned plan dated 13 October 2021 obtained by

Wellbuild, which provided for construction of an area of more than 81,000 sq.

mtrs. Hence there was no violation of any FSI norms sanctioned for the project.

x.         That such high-handed action on the part of the City Engineer/Assistant

Engineer is apparent as even the Environmental Clearance dated 13 October

2017 provided for total construction area of 72,032.18 sq. mtrs. For 'D' Wing the

Environmental Clearance provided for 4P (4 podiums) + Amenity + 20 Floors

and the construction as presently undertaken by the petitioner, was within the

area as provided under the Environmental Clearance limits and was halted at

68,132 sq. mtrs. It is submitted that the construction of 'D' wing was completed

only till 20 floors and in fact, there is a reduction in height. It is submitted that

the sanctioned plan dated 13 October 2021 provides for 80 flats, hence, the

construction is only of 80 flats, thus, there is no excess construction whatsoever as

alleged.




                                          Page 22 of 62
                                       21 November 2025



        ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                               WP 1022-25CORRECTED.DOC



xi.        It is next submitted that the malafide and high-handedness in the actions

of the municipal officers is writ large, also considering Intervention Application

No. 1309 of 2025. The submission is that the modus operandi of Wellbuild in

connivance with the official machinery of the municipal corporation and private

land parties stands completely exposed, also considering the attempt of the

intervenor coming before this Court supporting Wellbuild's case as the intervenor

is unable to even disclose the source of his knowledge and information or explain

how he had learnt about the project and more particularly about the litigation

inter se between the petitioner and Wellbuild and by the petitioner against the

society more particularly, the ad-interim orders dated 28 May 2024 and 25 June

2024 passed on the Section 9 proceedings, which was purely a matter between the

petitioner and Wellbuild.

xii.       It is submitted that, also the intervenor has miserably failed to disclose the

reasons for not apprising the concerned authorities on the judgment and order

dated 20 September 2024 passed in Civil M.A. No. 544 of 2024 and Civil M.A.

No. 582 of 2024, whereby Section 9 application filed by Wellbuild came to be

rejected and Section 9 application filed by the petitioner was partly allowed. It is

submitted that this shows apparent dishonesty and the intention of Wellbuild to

mislead the authorities.


xiii.      The intervenor has also miserably failed to disclose alleged source of

information i.e., the date of his alleged RTI applications. In such context, it is

submitted that the impugned order has blindly accepted such facts presented by


                                          Page 23 of 62
                                       21 November 2025



        ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



Wellbuild and the intervenor when these parties failed to establish the correctness

of their case. It is submitted that even the alleged Certificates annexed as Exhibit-

G to the Intervention Application dated 13 January 2025 and 10 January 2025

are documents generated much after the passing of the impugned stop work

notice dated 10 December 2024, which clearly demonstrates the role being

played by the intervenor, purely at the behest of Wellbuild. In such context, it is

further submitted that the intervenor has also failed to disclose the source/ details

of receipt of notice for hearing dated 09 December 2024, which came to be

attended by him, as seen from the Attendance Sheet, annexed at page 92 of the

petition. It is, hence, submitted that all these issues completely expose the

complicity and the collusion between Wellbuild and the intervenor. In such

context, reliance is placed on Ayaaubkhan Noorkhan Pathan vs. State of

Maharashtra & Ors. (supra).

34.      It is next submitted that there is no excess construction undertaken by the

petitioner much less contrary to the sanctioned building plans and the petitioner

had already stalled its construction when the construction reached the prescribed

limits under the Environmental Clearance dated 13 October 2017 at 68,132 sq.

mtrs. which is almost 4,000 sq. mtrs. within the approved Environmental

Clearance as granted. It is for such reason that there is no impediment whatsoever

for grant of Occupancy Certificate in regard to the already completed

construction work of Tower 'D' and part of Tower 'C'.




                                        Page 24 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



35.      It is submitted that irreparable prejudice is being caused not only to the

petitioner but also to several flat purchasers with whom registered agreements are

already executed and who are waiting to occupy their respective flats having

parted with valuable money. It is thus submitted that the petition is required to

be allowed.


         Respondent/Wellbuild's reply affidavit:-


36.      A brief reference to the reply affidavit filed on behalf of Wellbuild can be

made, which inter alia contends that the petitioner had applied for revised

Environmental Clearance which is yet to be issued. It is contended that in a

meeting held on 27 February 2025, the State Environment Impact Assessment

Authority ("SEIAA") had rejected the petitioner's application for obtaining

revised Environmental Clearance, which was referred back to the SEAC-III for

investigation and reconsideration. It is stated that thereafter, in a meeting held on

14 May 2025, the SEAC inter alia noted that the petitioner had submitted a

proposal for revision of the EC without first amending the previously granted ECs

to reflect the change in the name from respondent no.5 to the petitioner as the

Project Proponent. In such context, it is contended that the Committee observed

that the Project Proponent was required to submit a separate application in the

prescribed form through the PARIVESH portal for such an amendment. The

petitioner cannot be considered to be the Project Proponent. The Committee has

opined that the proposal could only be considered once the necessary change in

the proprietorship was duly processed and approved by the SEIAA. It is hence

                                        Page 25 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



contended that the petitioner is yet to obtain revised Environmental Clearance

and hence, the reliefs as prayed for in the petition cannot be granted.


37.      The reply affidavit has further set out the nature of the private dispute

between respondent no.5 and the petitioner and in such context, refers to the

various clauses of the Articles of Agreement dated 19 August 2021 and

Development Agreement dated 26 August 2021 entered between respondent

no.5 and the petitioner for construction of Tower 'C', (7 to 28 floors both

inclusive) and for Tower 'D'. Respondent no.5 has also contended that the

amounts had become due and payable to respondent no.5 from the petitioner

under the said agreements. On these contentions, it is prayed that the petition be

dismissed.


38.      Mr. Kamat, learned senior counsel for the respondent-Well Build has made

the following submissions:


         i.       The Environmental Clearance in respect of the project was issued by

         the Pune Municipal Corporation on 13 October 2017 (for short "2017

         EC") incorporating condition no. 5, providing that in case of any deviation

         or alteration in the project from the one already submitted to Pune

         Municipal Corporation (PMC), a fresh application for amendment was

         required to be submitted to the PMC, and the PMC, after assessing the

         adequacy of the conditions imposed, would decide whether any additional

         environmental protection measures were required to be incorporated. It is

                                        Page 26 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                       WP 1022-25CORRECTED.DOC



   his submission that the 2017 EC was issued based on the plan then

   sanctioned by the PMC. It is submitted that when there was an alteration

   in the plans approved by the PMC, the petitioner was required to make a

   fresh application for Environmental Clearance. It is submitted that on such

   backdrop, the earlier sanctioned plans were revised on 13 October 2021,

   which further revised on 22 February 2023. It is hence submitted that

   once the plans stood amended, it was imperative that the petitioner applies

   for a fresh Environmental Clearance prior to construction of any structure

   beyond the scope of the 2017 EC and failure to do so, would amount to

   breach of 2017 EC.


   ii.      It is submitted that as the petitioner has failed to obtain

   fresh/revised Environmental Clearance, which the petitioner had applied

   on 3 November 2023 and when such application was pending and/or is

   yet to be decided, the petitioner cannot claim legitimacy of the

   construction as undertaken in respect of Tower/Wing D.


   iii.     In the context of Environmental Clearance being applied for by the

   petitioner, a meeting was held on 27 February 2025 of the State

   Environment Impact Assessment Authority (SEIAA), which is stated to

   have remanded the petitioner's proposal/application for obtaining revised

   Environmental Clearance back to SEAC-III for investigation and

   reconsideration. Thereafter, a meeting of the SEAC-III was held on 14

   May 2025, in which SEAC-III inter alia noted that the petitioner had
                                  Page 27 of 62
                               21 November 2025



::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                       WP 1022-25CORRECTED.DOC



   submitted a proposal for revision of the Environmental Clearance, without

   first amending the previously granted Environmental Clearances, to reflect

   the change in the name from respondent no. 5/Well Build to that of the

   petitioner as the project proponent. It was hence observed that the project

   proponent is required to submit a separate application in the prescribed

   format through the portal for such amendment. It is submitted that the

   petitioner, hence, was not considered as the project proponent, as the

   Committee noted that the proposal could only be considered once the

   necessary change in proprietorship was duly processed and approved by

   SEIAA. It is hence submitted that the petitioner had not obtained the

   necessary Environmental Clearance for carrying out the work beyond the

   sanctioned construction limits under the 2017 EC.


   iv.      The petitioner has constructed Wing-D/Tower D in contravention

   of the 2017 EC and without obtaining fresh/revised Environmental

   Clearance.      It is submitted that this is clear from the perusal of the

   sanctioned plan of 2017 which would show that the construction as

   sanctioned was of an area of 14599.71 sq. mtrs. for Wing D, which was

   confirmed by the Project Architect Mr. Dilip Kale by his letter dated 10

   January 2025. It is hence submitted that for any construction beyond the

   sanctioned limit, the petitioner was required to obtain fresh Environmental

   Clearance. This contention is also supported by referring to the Minutes

   of meeting of SEIAA held on 27 February 2025, which according to


                                  Page 28 of 62
                               21 November 2025



::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                           WP 1022-25CORRECTED.DOC



       respondent no. 5/Wellbuild, shows that the petitioner has constructed a

       total area of 16095.80 sq. mtrs. for Wing D, which according to Wellbuild

       is beyond the construction area sanctioned under 2017 EC. It is thus

       contended that the petitioner has knowingly and deliberately undertaken

       construction beyond the sanctioned limits and in breach of 2017 EC.

       Thus, the petitioner's contention that there is no construction beyond the

       overall sanctioned limit cannot be accepted. Reliance is placed on the

       decision of the Supreme Court in Vanashakti vs. Union of India 6 and in

       Keystone Realtors Pvt. Ltd. vs. Anil V. Tharthare 7, to contend that the

       Supreme Court has held that an application for fresh Environmental

       Clearance would be required if the project is expanded beyond the

       construction limits for which the prior Environmental Clearance was

       obtained even if the expansion is within the upper limit prescribed. It is

       hence submitted that the petitioner was required to apply for and obtain

       fresh Environmental Clearance before constructing Wing 'D' beyond the

       sanctioned limits. The petitioner was aware of such requirements and

       accordingly had applied for a fresh Environmental Clearance. Hence,

       Wing 'D' could not have been constructed without first obtaining fresh

       Environmental Clearance. It is also submitted that the law would not

       permit grant of Environmental Clearance ex-post facto. It is submitted

       that for such reason, there is no scope for the petitioner to contend that


6 2025 SCC OnLine SC 1139
7 (2020) 2 SCC 66
                                      Page 29 of 62
                                   21 November 2025



    ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                     WP 1022-25CORRECTED.DOC



        Wing 'D' is constructed as per the 2017 EC. In such circumstances, there

        was no question of an Occupation Certificate or Part Occupation

        Certificate being granted to Tower/Wing 'D', which according to

        Wellbuild is illegal.


        vi.      It is next submitted that this is a clear case where the petitioner is a

        wrongdoer, who ought not to be granted any reliefs having knowingly

        constructed Wing 'D' without a fresh Environmental Clearance. The

        petitioner, therefore, cannot take advantage of                  its own wrong.          In

        supporting this submission, reliance is placed on the decision of the

        Supreme Court in the case of Municipal Committee Katra & Ors. vs.

        Ashwani Kumar8.


        vii.     It is next submitted that there cannot be any misplaced sympathy

        towards the flat purchasers of a construction which is illegal. In supporting

        such contention, reliance is placed on the order passed by the Supreme

        Court in Willingdon View Cooperative Housing Society vs. The

        Municipal Commissioner, Brihanmumbai Municipal Corporation & Ors. 9.


        viii.    Thus, no relief under Article 226 of the Constitution of India,

        which is an equitable relief, ought to be granted to the petitioner and the

        petition needs to be dismissed.



8 Unreported judgment dated 9 May 2024 in Civil Appeal Nos. 14970-71 of 2017
9 Unreported order dated 1 August 2025 in Special Leave Petition (C) No. 20175 of 2025.
                                        Page 30 of 62
                                     21 November 2025



     ::: Uploaded on - 21/11/2025                               ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



39.      Mr. Vishwanath Patil, learned counsel appearing for the Municipal

Corporation has supported the impugned order. He has placed reliance on a reply

affidavit of Shri Prashant Waghmare, City Engineer of the Municipal

Corporation, filed on behalf of the Municipal Corporation. It is submitted that

on 12 January 2016, MPCB issued Consent to Establish under Section 25 of

Water (Prevention and Control of Pollution) Act, 1971, under Section 21 of the

Air (Prevention & Control of Pollution) Act, 1981 and Municipal Solid Waste

(Management and Handling) Rules 2000 and E-waste (Management and

Handling) Rules 2011 in favour of Wellbuild for a total built up area of 56950.70

sq. mtrs. which was valid for a period upto commissioning of the unit or five years

i.e. upto 12/01/2021 whichever was earlier. It is submitted that the EC was

granted in favour of Wellbuild dated 13 October 2017, under which the total

project area (FSI + Non-FSI) was 72,032.18 sq. mtrs. Further, on 02 February

2022, MPCB renewal for Consent to Operate under Section 26 of Water

(Prevention and Control of Pollution) Act, 1971, under Section 21 of Air

(Prevention and Control of Pollution) Act and an authorization/renewal of

Authorization under Rule 6 of the Hazardous & Other Waste (Management &

Transboundry Movement) Rules 2016 was granted in favour of Wellbuild. It is

submitted that thereafter on 22 May 2023, the Municipal Commissioner passed

an order granting permission to the petitioner to shift the Drains/Nala. On such

backdrop, it is submitted that on 02 February 2024, a work order was also issued

in favour of the petitioner to carry out shifting of the Drain/Nala, which was not

fully complied with. It is thus submitted that under clause 11 of the work order
                                        Page 31 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                              WP 1022-25CORRECTED.DOC



dated 02 February 2024, it was provided that the petitioner needs to complete the

work of the shifting of the storm water drain (nala) within a period of one year

and that an Occupation Certificate would be issued by the Building Department

only if the certificate of completion of such drain/nala work was issued by the

Drainage Department. It is hence submitted that the Municipal Corporation had

accordingly approved the IOD on 26 December 2023, pursuant to which the

petitioner had made an application to the State Environment Assessment

Committee (for short, "SEAC") for grant of revised environment clearance

certificate, which is pending consideration of the SEAC and on such application, a

revised environment clearance certificate is so far not issued to the petitioner by

the SEAC.


40.      Mr. Patil has also submitted that the Municipal Corporation received

multiple complaints from social workers and NGOs, which were inter alia to the

effect that the petitioner had failed to provide amenities as promised to the

residents of Rajgruhi Residency. It is submitted that in pursuance thereto on 06

December 2024 a notice was issued by the Executive Engineer of Municipal

Corporation to the licensed Architect of the Project, to the developer and to the

members of the cooperative society formed by the flat purchasers of Wings 'A' &

'B', informing them about the scheduled hearing to be held on 09 December

2024 before respondent no.2-City Engineer.              Such hearing was held and

according to the City Engineer, it was revealed that the petitioner had failed to

complete the work of shifting of the drain/nala as per the Work Order dated 02


                                        Page 32 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                       ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                      WP 1022-25CORRECTED.DOC



February 2024, as also the petitioner had failed to produce Consent to Establish,

Consent to Operate and the Revised EC as per the sanctioned IOD dated 22

February 2023. Also, there was a deviation in the actual construction amounting

to a breach of the Environmental Certificate issued in the year 2017. It is

submitted that in pursuance of such hearing granted to all the stakeholders, an

order dated 10 December 2024 was passed ordering the petitioner to stop work.

Some of the relevant averments as made in the reply affidavit filed on behalf of

the Municipal Corporation are required to be noted which read thus:-


         11)     I say that pursuant the above mentioned complaints received by
         the Respondent Corporation, on 06.12.2024 a notice was issued by the
         Respondent Corporation to licensed Architect of the Project though hand
         delivery and to the Developer, members of the society of Rajgruhi
         Residency at S. No. 63/1/1+1/2+2, near Shantinagar Society, Kondhwa,
         Tal. Haveli, Dist. Pune 411048, informing the them about scheduling of
         hearing regarding the construction being carried out on land being Survey
         no. 63/1/1+1/2+2A in village Kondhwa Budruk, Pune at 11:30 hrs. on
         09.12.2024 before the Respondent No. 2.

         12)      I say that on 09.12.2024 hearing was duly conducted and it was
         revealed that the Petitioner had failed to (1) complete the work of shifting
         the nala pursuant the Work Order dated 02.02.2024, that the Petitioner
         failed (2) to produce Consent to Establish, (3) Consent to Operate and
         the (4) revised EC as per sanctioned IOD dated 22.02.2023 and that
         there was deviation in actual construction from the Environmental
         Certificate issued in 2017.

         13)    I say that pursuant hearing on 09.12.2014 before the Respondent
         NO. 2, by order dated 09.12.2024, a stop work notice as issued by the
         Respondent No. 2 to the Petitioner on the grounds mentioned therein."



41.      Mr. Patil would next submit that after the impugned stop work notice

dated 10 December 2024 was issued, the petitioner addressed a letter dated 20

December 2024 informing the municipal corporation that on 19 November

2024, the MPCB issued a revalidation of 'Consent to Establish', for a total built-


                                         Page 33 of 62
                                      21 November 2025



      ::: Uploaded on - 21/11/2025                               ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                   WP 1022-25CORRECTED.DOC



up area of 72,032.18 sq. meters and revalidated 'the Consent to Operate' for the

completed construction area, with built up area of 35,794.6 sq. metrs. Such

revalidated consent to establish with expansion was granted for a period from the

commissioning of the project on 12 January 2016, which was to be valid upto 30

June 2025. It is hence submitted that on such backdrop, it was clear that the

respondent/municipal corporation had granted EC in favour of Wellbuild dated

13 October 2017 and that as per the EC, the total project area (FSI + Non-FSI)

was 72,032.18 sq. mtrs. and thereafter the respondent/Municipal Corporation had

approved a revised Intimation of Disapproval (IOD) dated 26 December 2023

according to which the total project area was 84,131.86 sq. meters. The relevant

averments as made in the reply affidavit are also required to be noted which read

thus:-


         "15) I state that the Respondent Corporation granted Environmental
         Clearance (EC) in favor of Respondent No. 5 vide IEC/Samiti/5 dated
         13.10.2017. As per the said EC, the total project area (FSI + Non-FSI)
         was 72,032.18 sq. mt. Subsequently, the Respondent Corporation
         approved a revised Intimation of Disapproval (IOD) dated 26.12.2023
         sq. mt., according to which the total project area (FSI + Non-FSI) is
         84,131.86 sq. mts The Petitioner has applied for a revised EC, which is
         still pending consideration."



42.      Mr. Patil has further submitted that the Architect of the project Mr. Dilip

Kale and Associates had issued a letter dated 13 January 2025 addressed to the

Municipal Commissioner thereby granting a "certification of area". The said

certificate recorded that according to the EC dated 13 October 2017 granted by

the Municipal Corporation, the total built up area (FSI + Non-FSI) of Wing 'D'

was 14,599.71 sq. meters, while the total built up area (FSI + Non-FSI) of the

                                        Page 34 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                           ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                WP 1022-25CORRECTED.DOC



completed construction on the date of issuance of the said certificate of Wing 'D'

was 16,117.96 sq. meters. It is submitted that as per the said certificate, the

petitioner proceeded with the construction based on the revised IOD without

obtaining the requisite revised EC, making a reference to the EC Notification of

2006 dated 14 September 2006.

43.      On the aforesaid submissions, it is prayed that the impugned stop work

notice does not deserve interference and the writ petition be dismissed.

         Analysis and conclusion :-

44.      We have heard learned counsel for the parties. With their assistance, we

have also perused the record. In the facts and circumstances of the case and more

particularly considering the submissions as advanced at the bar, the following

issues, which in our opinion, would go to the root of the matter arise for

consideration in the present proceedings:-


         i.     Considering the fact that the show cause notice dated 06
         December 2024 was issued by the Executive Engineer whether the
         Designated Officer / City Engineer had jurisdiction to pass the
         impugned order dated 10 December 2024 under Section 267(1) of the
         Maharashtra Municipal Corporation Act, 1949.

         ii.    Whether construction undertaken by the petitioner under the
         Environmental Clearance (EC) dated 13 October, 2017 under which
         construction plans were sanctioned could be considered to be illegal
         merely for the reason that the petitioner had applied for a revised
         Environmental Clearance (EC).


45.      To answer the aforesaid questions, we do not intend to replicate the facts,

suffice it to observe that WellBuild/respondent no.5, on the backdrop of the

previous contractual relations with the petitioner, had admittedly entered into


                                        Page 35 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                         ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                WP 1022-25CORRECTED.DOC



Articles of Agreements dated 19 August 2021 and 26 August 2021 with the

petitioner, under which the petitioner was authorized to execute the construction

work of Tower 'C' and Tower 'D'. It is also not in dispute that plans in regard to

Tower 'C' and 'D' were sanctioned by the Municipal Corporation on 13 October

2017 in respect of an area to be constructed as referred hereinabove namely

16516.14 and 14,599.71 sq. meters. It is also not in dispute that the parties acted

upon such Articles of Agreements in regard to the construction of Tower 'C' and

Tower 'D' to be constructed by the petitioner. Accordingly, it appears to be not in

dispute that construction of Tower 'D' is complete in all respects, which is a

building of 20 floors. It is also not in dispute that Tower 'D' is now at the stage

whereby the occupancy proposal as submitted by the petitioner to the Municipal

Corporation (Planning authority) is to be processed and occupancy certificate

would be required to be granted, so that the "flat purchasers" can be put in

possession of their respective tenements. It is quite clear that at such stage,

disputes and differences have arisen between Wellbuild and the petitioner, which

in our opinion, appear to be purely a monetary dispute i.e. relating to the revenue

being generated from the sale of tenements (Tower 'C' and 'D') by the petitioner,

on which the petitioner is claiming benefit under the terms and conditions of the

Articles of Agreement.             It is in such context, both the parties resorted to

proceedings under Section 9 of the ACA, and as stated hereinabove, the petitioner

succeeded in its application filed under Section 9 of the ACA as also is the

beneficiary of the orders passed by the Civil Court against the Society formed by

the flat purchasers of Wing A and B. Further the orders passed against Wellbuild
                                         Page 36 of 62
                                      21 November 2025



    ::: Uploaded on - 21/11/2025                           ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



in the proceedings filed by the petitioner under Section 9 of the ACA were

confirmed in an appeal under Section 37 of the ACA. At the same time,

Wellbuild could not succeed in its Section 9 ACA proceedings.

46.      Be that as it may, the questions which have fallen for determination of the

Court need to be addressed on such backdrop. The following discussion would

aid our conclusion on such issues.

47.      The residential project 'Rajgruhi Residency' "as a whole", comprises of

construction of 4 towers - A, B, C and D. In regard to Towers 'A' and 'B', there is

no dispute whatsoever as the construction of these towers/wings stands completed

in respect of which an Occupancy Certificate has already been granted. It is also

not in dispute that the construction of Towers 'A' and 'B' was undertaken by the

petitioner in the capacity of being a "contractor" appointed by Wellbuild. The

dispute however has arisen between Wellbuild and the petitioner on the works

being undertaken for Towers 'C' and 'D' and more particularly under the Articles

of Agreement and the documents executed by Wellbuild in favour of the

petitioner. The dispute as seen is more focused in the context of Tower 'D' the

construction of which, according to the petitioner, stands completed.


48.      Having noted the aforesaid factual position, it is seen from the record that

the petitioner had proceeded to execute the work in relation to Towers 'D' and

'C'. Admittedly, the construction work of Tower 'D' was taken up as the first leg

of such construction and as on date has attained completion. It is also not in

dispute that as per terms and conditions of the agreement inter se between the

                                        Page 37 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



petitioner and Wellbuild , the petitioner has entered into agreements with third

party/flat purchasers, who are awaiting possession of their respective flats to be

handed over to them by the petitioner, after Occupation Certificate (O.C.) is

granted to Wing 'D'. It also appears to be not in dispute that the work of Wing

'C' which is taken as second leg has progressed only upto four floors i.e.

construction of 16 habitable floors is yet to be undertaken.


49.      As noted hereinabove, it is at such juncture, disputes and differences have

arisen between the petitioner and Wellbuild, whereunder the parties are asserting

their respective rights on allegations which are certainly matters to be tested on

evidence to be led by the parties in appropriate proceedings. Such conclusions

based on the prima facie findings between the parties were subject matter of the

proceedings filed by both the sides invoking Section 9 of the ACA before a forum

no less than the learned District Judge, who passed orders on the Section 9

proceedings which were assailed in the appeals filed under Section 37 of the ACA

before this Court. The orders passed in the Section 9 proceedings as also in the

appeals clearly go to show that no substantive reliefs could be obtained by

Wellbuild against the petitioner insofar as the execution of the said project under

the Articles of Agreement in question was concerned.


50.      It clearly appears to us, it is on such backdrop, Wellbuild having failed in

the proceedings initiated under the ACA, took a recourse to approach the

municipal machinery, that too in a very peculiar manner, gathering support from

persons who are totally alien to the project and/or the Articles of Agreement
                                        Page 38 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                     WP 1022-25CORRECTED.DOC



entered into between the petitioners and Wellbuild. On such action of the

Wellbuild taken up with the officials of the municipal corporation, a cryptic

notice dated 06 December 2024 was issued to the petitioner, which in our

opinion, possibly breaches all norms of legitimacy, as to on what issues the

petitioners needed to appear at the hearing, much less show cause or for what

purpose such urgent hearing is scheduled on 9 December 2024. No details

whatsoever were set out in such notice issued to the petitioner by the Executive

Engineer of the Building Development Division, Zone-II of the Municipal

Corporation. It is imperative to note the contents of this notice which is the

genesis of the impugned orders, which read thus:-

       "[Official Translation of a xerox copy of a Letter typewritten in Marathi.]

       [LOGO]

                                        Office of the Executive Engineer.
                                        Construction Development
                                        Department,
                                        Savarkar Bhavan, Pune Municipal
                                        Corporation.
                                        O. No. - Zone-2/7240.

       To,
       Shri. Anil Reddy on behalf of M/s. Atria Construction.
       440/441, Nana Peth, PGI Building,
       Pune - 411002.

                Subject - Regarding construction work on the land bearing S.
                No.63/1/1+1/2+2, situated at - Peth Kondhwa Budruk, Pune.

               In connection with the construction work of Rajgruhi Residency
       Project on the land bearing S. No. 63/1/1+1/2+2 located at - Peth
       Kondhwa Budruk, Pune, hearing is scheduled in the Office of the City
       Engineer (Office of the City Engineer, 1 st floor, Pune Municipal
       Corporation, Shivaji Nagar, Pune-05) on Monday, the date 09.12.2024 at
       11:30 a.m.
               Therefore, you should remain present during the course of said
       hearing together with the necessary documents.


                                      Page 39 of 62
                                   21 November 2025



    ::: Uploaded on - 21/11/2025                                ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                  WP 1022-25CORRECTED.DOC



         May this be known.

                                               (Signature Illegible)
                                                     06/12
                                                Executive Engineer
                                           Construction Development
                                            Department (Zone No. 2)
                                           Pune Municipal Corporation"

                                                        (emphasis supplied)



51.      Thus, the vagueness of the aforesaid notice itself raises a serious doubt

about the intention of the Executive Engineer, on the backdrop of what has been

referred hereinabove concerning the disputes between the parties. The said notice

does not in any manner set out as to on what aspects, in relation to the said

project, a hearing was summoned on 09 December 2024 at 11.30 a.m.


52.      What has happened thereafter is quite appalling and in fact it would shock

our conscience. At such hearing, to the surprise of the petitioner, several persons

who are totally unconnected with the project and not even remotely connected

with the contract as entered between Wellbuild and the petitioner, attended the

hearing, which is clear from the roznama dated 09 December 2024 annexed to

the petition. On a query as to how such persons, including the intervenor - Mr.

Vikas Kuchekar, came to be involved, there is no justification whatsoever from the

Executive Engineer or the Municipal Corporation regarding the involvement of

such persons qua the project or even from Mr. Vikas Kuchekar who has

intervened in the present petition, we have passed a separate order rejecting his

intervention.



                                        Page 40 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                           ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                       WP 1022-25CORRECTED.DOC



53.      Be that as it may, the hearing held on 9 December 2024 (for whatever

worth) was held not by the Executive Engineer who issued the notice dated 06

December 2024, but by the City Engineer and the Deputy Engineer, who

immediately on the next day i.e. on 10 December 2024 issued the impugned stop

work notice under Section 267(1) of the Maharashtra Municipal Corporation

Act, 1949 (for short, "MMC Act") read with Section 54 of the Maharashtra

Regional & Town Planning Act, 1966. In the peculiar facts, it is vital to extract

the impugned stop work notice, which reads thus:-


         "(Translation of the Impugned Stop Work Notice, typewritten in Marathi)


                                          Building Development Department,
                                          Zone No. 2,
                                          Pune Municipal Corporation,
                                          Outward No. Zone-2/7327,
                                          Date: 10.12.2024.

                                            NOTICE

              (Under Section 267(1) of the Maharashtra Municipal Corporation
              Act and under Section 54 of the Maharashtra Regional and Town
              Planning Act, 1966).

              To,
              1) M/s. Atria Construction, through Shri Anil Reddy,
                 440/441, Nana Peth, P.G.I. Building, Pune 411 002.

              2) Shri Dilip Kale, Licensed Architect
                 1226, Subhash Nagar, Lane No.4,
                 Shukrawar Peth, Pune 411 030.

                 Whereas, a Building, a description whereof is given hereinbe-
              low, is being constructed on the plot of land bearing Survey No.
              63/1/1+1/2+2 at Peth Kondhva Budruk, Pune, by you or under
              your supervision. As per the provisions made in the said Act, the
              Commissioner of Municipal Corporation has conferred upon me
              the powers under Section 267 of the Maharashtra Municipal
              Corporation Act and under Section 54 of the Maharashtra Regional
              and Town Planning Act, 1966. By this Notice, you are informed to
              immediately stop the said construction work upon receipt of this
              Notice. If you continue carrying out the said construction work or if

                                         Page 41 of 62
                                      21 November 2025



      ::: Uploaded on - 21/11/2025                               ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                              WP 1022-25CORRECTED.DOC



        the said construction work is continued further under your
        supervision, then, in exercise of the powers conferred upon me as
        per the provisions of the aforesaid Act and as mentioned
        hereinabove, the person carrying out the said work will be removed
        therefrom with the help of Police Officers and the expenditure to be
        incurred therefor will be recovered from you.

            You may please note that, as per the provisions of Section 433
        (c) of the Maharashtra Municipal Corporation Act, "Save as
        otherwise provided in this Act, any notice issued, order passed or
        direction issued by the Designated Officer, shall not be questioned
        in any suit or other legal proceedings.

            The Original lay-out in respect of the 'Rajgrushi Residency' on
        the plot of land bearing Survey No. 63/1/1+1/2+2 at Peth -
        Kondhva Bu-druk, Pune, had earlier been sanctioned vide San. Pa.
        No. D.P.O./ 4323/ F/KB/ 62, dated 16.08.2002. Thereafter, the
        revised lay-outs had been sanctioned from time to time and the
        Building Plans had been approved accordingly. The upto date
        revised lay-outs and the Buildings Plans have been approved by the
        San. Pa. No. CC/2042/21, dated 13.10.2021. Similarly, Part
        Occupancy Certificates have been issued to the buildings under the
        said project from time to time.
            The First Environment No Objection Certificate (EC) to the
        said project had been received from SEIAA on the date 10.12.2015
        and as regards the second (Environment No Objection Certificate),
        in view of the Government Resolution No. TPS-1816/M.
        No.443/16/D.S./Pune and Konkan Divisions/U.D.-13, dated
        28.06.2017, the Environment Cell, Pune Municipal Corporation
        examined the proposed project of 'Rajgruhi Residency, on the plot
        of land bearing Survey No. 63/1/1+1/2+2 at Peth -Kondhva
        Budruk, Pune and made recommendation to the Environment
        Committee under Category-III and in the meeting of the
        Environment Committee, held on the date 04.10.2017,
        recommendations for the said project were made subject to
        following the conditions of environment.

            By the Office Order bearing Outward No. MC/ UDCPR- 20/
        SEC/ 3.1.1(ii)/443, dated 22.05.2023, passed by the Municipal
        Commissioner, approval has been granted for shifting of the Nullah.
        Similarly, the Sewage Maintenance and Repairs Department has
        granted permission for carrying out development of Nullah subject
        to the terms and conditions. However, till today, no development in
        respect of the nullah has been carried out at the site. Moreover,
        frequent complaints are being received from the citizens in this
        regard.

           On the date 14.01.2024, the Maharashtra Pollution Control
        Board has granted 'Refusal of Consent to Establish' under section
        27 of the Water (Prevention & Control of Pollution) Act, 1974 and
        Section 21(4) of the Air (Prevention & Control of Pollution) Act,
        1981. Moreover, the 'Consent to Operate' mandatory for each
        project has not been obtained. This issue is serious and the
                                  Page 42 of 62
                               21 November 2025



::: Uploaded on - 21/11/2025                             ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                      WP 1022-25CORRECTED.DOC



              conditions of Environment No-Objection Certificate have been
              violated. Similarly, the Environment No-Objection Certificate (EC)
              as per the Proposed Intimation of Disapproval (IOD) has not yet
              been submitted. Moreover, discrepancy is found between the
              Environment No-Objection Certificate (EC) received on the date
              04.10.2017 for your Project and actual construction work going on
              at the site.

                 You had been asked to submit within the period of 8 days, your
              explanation in writing as to why action should not be taken against
              you for violating the conditions of Environment No-Objection
              Certificate and in pursuance thereof, you have submitted
              explanation.

                 However, as the said explanation does not contain satisfactory
              reply and as the aforesaid issues are serious, the City Engineer, Pune
              M.N.C. has granted approval on the date 10.12.2024 to issue Stop-
              Work Notice under section 267(1) of the Maharashtra Municipal
              Corporation Act, 1949 and under section 54 of the Maharashtra
              Regional and Town Planning Act, 1966 to stop the work that is
              being carried out by you on the property bearing
              S.No.63/1/1+1/2+2 situated at Peth Kondhva Bu., Pune.

                 Therefore, you are directed to immediately stop the work that is
              being carried out by you on the property bearing
              S.No.63/1/1+1/2+2 situated at Kondhva Bu., Pune.

              Current status of the construction work at site:

              Wing 'C' - R.C.C. work of Stilt floor + Upper Park floor + Lower
              Park floor 01 + Lower Park floor 02 + Lower Park floor 03+ upto
              4th floor, has been completed.

              Wing 'D'- Construction work of Stilt floor + Upper Park floor +
              Lower Park floor 01 + Lower Park floor 02 + Lower Park floor 03 +
              upto 20th floor, has been completed.

              May this be known,
                 (Signature )                                      (Signature)
              Designated Officer and
              Junior/Branch Engineer                  Designated Officer and Deputy
              Building Development Department         Engineer Building Development
              Zone No.2,                              Department Zone No.2,
              Pune Municipal Corporation.             Pune Municipal Corporation."
                                                                   (emphasis supplied)


54.      It is thus clearly seen that the construction work of the 'D' Wing as set out

in the notice, is clearly accepted to have been completed. Insofar as Wing 'C' is

concerned, the construction upto 4 floors is stated to have been completed, which

                                         Page 43 of 62
                                      21 November 2025



      ::: Uploaded on - 21/11/2025                               ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



includes R.C.C. work of stilt floor + upper park floor + lower park floor 01 +

lower park floor 02 + lower park floor 03 + upto 4 th floor, the construction of

which is supposed to be upto 20 floors.


55.      As urged on behalf of the petitioner, the challenge to the impugned stop

work notice needs to be considered on two basic legal issues. Firstly, that the

petitioner in the show cause notice was never informed that the petitioner would

be called upon to give explanation on any issues, the consequence of which is set

out in the impugned stop work notice for the first time. As there was no prior

show cause notice issued to the petitioner as the law would mandate, hence, as

rightly urged by the petitioner, without the petitioner being granted an

opportunity of being called upon to show cause and defending any such issues,

which forms the subject matter of the reasons as set out in the impugned stop

work notice, the impugned stop work notice cannot stand the test of law. We find

much substance in this contention as urged by the petitioner. This for the reason

that it is clear from the purported notice dated 06 December 2024 that it does not

set out any details as to on what specific issues a hearing was scheduled on 09

December 2024. The petitioner is, therefore, taken by surprise when the

impugned order records all such issues which were never put for any specific

explanation by the petitioner. It is the settled principle of law that any order to be

passed by a statutory authority which would entail civil consequence whereby

civil rights of a party are likely to be breached by any order passed by such

authority, such order cannot be passed, unless the procedure known to law i.e. of


                                        Page 44 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



issuance of an appropriate show cause notice with adequate grounds being made

out, granting an opportunity to reply to such show cause notice and a hearing

being granted to the affected party, on such show cause notice and thereafter a

reasoned order to be passed, is a sine qua non / the necessary mandate of law.

This on the ground that the soul of natural justice is "fair play in action" which is

held to be important in both the quasi judicial or administrative proceedings. The

rule of natural justice is calculated to secure justice or in other words, to prevent

miscarriage of justice. Hence, it is applicable in any quasi judicial inquiry, this

more particularly when civil rights of the parties are likely to be breached. In

Maneka Gandhi vs. Union of India 10 the Supreme Court held that the law must

now be taken to be well settled that even in an administrative proceeding, which

involves civil consequences, the doctrine of natural justice must be held to be

applicable. Thus, any order/action taken by a quasi judicial authority is required

to satisfy the test of fairness, transparency and non-discrimination. When orders

to be passed by such authorities who enjoy enormous statutory powers, the

authorities are required to be more circumspect in discharging these official

obligations in exercising such powers, so that the orders, which are passed, are not

in any manner in breach of the principles of natural justice, arbitrary, biased

and/or vitiated by non application of mind or are tainted by extraneous

considerations.


56.      This apart, there is much substance in the petitioner's contention that the

impugned order has been passed on extraneous considerations, which is clear
10 1978 AIR SC 597
                                        Page 45 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



from the fact that it is not the officer of the municipal corporation namely the

'Executive Engineer', who issued the show cause notice to the petitioner, but the

City Engineer who heard the petitioner and the other parties. Further quite

surprisingly several persons who were unconnected with the project and who

appear to be supporting the cause of Wellbuild, attended the hearing, as if it was a

public hearing. The impugned order appears to have been thus passed on such

extra legal considerations and with the interference caused by third parties, which

is clearly seen from the appearance of these several unconnected persons as

recorded in the roznama. This more significantly considering the presence of the

intervenor Mr. Vikas Kuchekar.


57.      Thus, in our clear opinion, such illegality in passing the impugned stop

work notice, which is quite gross, appears to have been committed in the absence

of the petitioner being put to a clear notice of the issues, with which, the

petitioner would be required to be confronted or called upon to answer. Notably,

no copies of any complaints received by the Executive Engineer from any person

on the basis of which such show cause notice dated 06 December 2024 (supra)

were supplied to the petitioner, on the basis of which such drastic order was

passed to stop work of the entire project. Such hearing being attended by totally

unconnected persons, itself raises a serious doubt on the fairness of the officials of

the municipal corporation in the proceedings, who passed the impugned order/

notice. In our clear opinion, this fact would demonstrate a gross breach of the

principles of natural justice at the hands of the Executive Engineer, City and


                                        Page 46 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



Deputy Engineer in issuing the impugned stop work notice and on these basic

non-compliances of the mandatory requirement of law, the impugned show cause

notice would be required to be quashed and set aside.


58.      We also cannot overlook the timing at which, the impugned stop work

notice is issued, that is at the time when the proceedings filed by Wellbuild

against the petitioner under the Arbitration and Conciliation Act could not

succeed.      This most importantly, when on the municipal corporation's own

showing the construction of Tower/Wing 'D' is complete and is now required to

be proceeded for grant of an Occupation Certificate. It is thus clear that what

could not be achieved directly by Wellbuild in a manner known to law i.e. in the

legal proceedings, Wellbuild has sought to achieve the same, by utilising the

municipal machinery, and that too by garnering extra legal interference, the

municipal machinery being exploited to its advantage, in getting the impugned

stop work notice issued. Admittedly, Wellbuild could not succeed in its attempts

to secure benefits which otherwise Wellbuild could not secure in the legal

proceedings, having failed in the Section 9 proceedings as also in the Section 37

proceedings under the ACA. This is quite apparent from the facts as set out

hereinabove, which are our considered observations on these issues which touch

the impugned stop work notice.


59.      On such backdrop, we examine the first question (supra), which has fallen

for consideration, which, in our opinion, touches the basic tenets on the settled

principles of administrative law, namely, that a person who hears is required to

                                        Page 47 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                    WP 1022-25CORRECTED.DOC



pass an order. It is clear that the show cause notice was issued by the Executive

Engineer, however, a hearing on the same was held by the City Engineer and the

impugned order/ notice to stop work has been issued by the Deputy Engineer and

the Junior Engineer. Such procedure is wholly unknown to law and can never be

recognized to have any legal sanctity. It is well settled that a person who has not

heard the aggrieved party, has no jurisdiction to pass an order. In the present case,

the impugned stop work notice is a reasoned order, there could not have been any

delegation by the Executive Engineer for such order to be passed by his

subordinates, namely, Deputy Engineer and Junior Engineer. In this context, we

may refer to the decision of the Supreme Court of India in Union of India & Ors.

vs. Shiv Raj & Ors.11 wherein the context of the obligation of a person who hears a

party, would be the only person who can decide, which has been held to be a vital

requirement of the principles of natural justice. Following observations as made

by the Supreme Court are required to be noted, which read thus:

       "17.      This Court in Gullapalli Nageswara Rao(supra), held:

              "Personal hearing enables the authority concerned to watch the
              demeanour of the witnesses and clear up his doubts during the
              course of the arguments, and the party appearing to persuade the
              authority by reasoned argument to accept his point of view. If one
              person hears and another decides, then personal hearing becomes an
              empty formality. We therefore hold that the said procedure followed
              in this case also offends another basic principle of judicial
              procedure."

       18.     This Court in Rashid Javed vs. State of UP, AIR 2010 SC 2275
       following the judgment in Gullapalli(supra), supra held:

              "51.        .... a person who hears must decide and that divided
              responsibility is destructive of the concept of hearing is too
              fundamental a proposition to be doubted."

11 (2014) 6 Supreme Court Cases 564
                                       Page 48 of 62
                                    21 November 2025



    ::: Uploaded on - 21/11/2025                              ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                       WP 1022-25CORRECTED.DOC




         19.      A similar view has been reiterated by this Court in Automotive
         Tyre Manufacturers Association vs. Designated Authority & Ors. , (2011)
         2 SCC 258, wherein this Court dealt with a case wherein the Designated
         Authority (DA) under the relevant Statute passed the final order on the
         material collected by his predecessor in office who had also accorded the
         hearing to the parties concerned. This court held that the order stood
         vitiated as it offended the basic principles of natural justice.

         20.      In view of the above, the law on the issue can be summarised to
         the effect that the very person/officer, who accords the hearing to the
         objector must also submit the report/ take decision on the objection and
         in case his successor decides the case without giving a fresh hearing, the
         order would stand vitiated having been passed in violation of the
         principles of natural justice."


60.       We may also usefully refer to the decision of the learned Single Judge of

this Court in Golden Chariot Airport, Mumbai vs. Airports Authority of India

International Airports Division Chhatrapati Shivaji International Airport,

Mumbai & Another12 wherein in similar context the following observations were

made by the Court:-


         "17.      It is well settled that when a statute calls upon the Authority or
         officer to form an opinion and take a decision he must apply his own
         mind to the situation, consider its various aspects himself and give a
         decision himself. The law does not tolerate an officer who is entrusted
         with the responsibility of taking- a decision referring the case to another
         officer and then verbatim adopting the latter's reasonings and views
         without any effort on his own part. A consideration of the case by officer
         is the live link between the facts and the decision. Such an officer is not
         entitled to refer the matter to any one else for receiving "brief" complete
         analysis and findings and then merely deliver what he receives as his own
         order.

         18.      At this juncture, it may be noted that many arguments were
         made by the learned counsels appearing for the parties on the basis of the
         roznama and the pleadings before the Estate Officer Kaushal. The issue
         agitated by the parties was whether Kaushal had properly closed the
         matter for orders on 23-12-2005 after hearing it on earlier dates, and
         whether the said Estate Officer has wrongly rejected the permission
         sought by the petitioners for examining the Officer of the respondent
         No. 1. Having held that the order is vitiated and void for the reasons
         stated earlier, it is not necessary to deal with this aspect of the matter.

12 2009(3) Mh.L.J. 684
                                         Page 49 of 62
                                      21 November 2025



      ::: Uploaded on - 21/11/2025                               ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                        WP 1022-25CORRECTED.DOC




         19.       ........................ Having regard to the observations above, it
         is clear that the Supreme Court was of the view that the authority must
         himself reach a conclusion which he regards as just and must record the
         ultimate mental process leading from the dispute to its solution. The
         judgment must be supported by reasons that suggest themselves to the
         Judge. It is clearly observed that a mere order deciding the matter in
         dispute not supported by reasons is no judgment at all. It is obvious from
         these observations that what is contemplated is that the Judge or the
         authority empowered to decide, must record the ultimate mental process
         leading from the dispute to its solution. The reference is obviously to the
         mental process of the Judge himself and not the mental process of
         another. It must follow that whether the Judge or the authority has not
         applied his own mind, but has adopted the reasoning applied by another
         and merely acted as rubber stamp, as here, the order passed by the Judge
         must be construed to be an order not supported by any reasons at all. The
         application of the ratio to the facts of the present case clearly lead to the
         conclusion that the impugned order is not a valid order and is void and
         unsustainable.
                                                                     (emphasis supplied)



61.      Although even on the aforesaid basic legal consideration the impugned

order deserves to be set aside, we now proceed to consider the second issue, which

is on merits to consider whether the reasoning as set out in the impugned order in

any manner is sustainable. The following are the primary three considerations on

which the stop work notice is issued:-


         i.      The municipal corporation had issued an order dated 22
         May 2023 permitting the shifting of the existing drain/nala on
         such terms and conditions, however, the said nala has not been so
         far developed and in this regard, complaints are received from the
         citizens from time to time.

         ii.    Secondly, on 14 January 2024, the Maharashtra Pollution
         Control Board has granted 'Refusal of consent to establish' under
         Section 27 of the Water (Prevention & Control of Pollution) Act,
         1974 and under Section 21(4) of the Air (Prevention & Control of
         Pollution) Act, 1981, however, in respect of each and every
         construction, consent to operate have not been obtained. This
         would amount to breach of Environmental Clearance.

         iii.   Thirdly, as per the Intimation of Disapproval (IOD), a
         revised Environmental Clearance (EC) so far has not been

                                         Page 50 of 62
                                      21 November 2025



      ::: Uploaded on - 21/11/2025                                ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



         submitted and the work which is actually undertaken is not in
         consonance with the Environmental Clearance granted to the
         project dated 4 October 2017.


62.      The impugned stop work notice records that petitioner was called upon to

provide explanation within 8 days and the petitioner has submitted explanation,

but such explanation is not satisfactory and therefore, it is necessary that the

construction being undertaken on the said land needs to be stopped. For ordering

the stoppage of the construction, approval has been granted by the Junior

Engineer and the Deputy Engineer on 10 December, 2024, as per the provisions

of Section 267(1) of the Maharashtra Municipal Corporation Act, 1949 and

under Section 54 of the Maharashtra Regional and Town Planning Act, 1966.


63.      Considering the reasons which are set out in the impugned stop work

notice, we are in complete agreement with the contentions as urged on behalf of

the petitioner on two basic counts - firstly, although show cause notice dated 6

December, 2024 was issued to the petitioner, it did not point out any of the

deficiencies. Further the construction of the drain/nala was already underway and

the same is being completed as pointed out by the petitioner to which there

appears to be no dispute.

64.      The reasons in regard to Water and Air Act permissions being not available

with the petitioner, also does not appear to be a correct observation in the

impugned stop work notice, for the reason that the petitioner had submitted a

resolution of the Maharashtra Pollution Control Board dated 14 November 2024

granting revalidation of 'consent to establish' and also 'consent to operate'. Thus,
                                        Page 51 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



such reason as set out in the impugned stop work notice is patently without

application of mind and oblivious of the correct position on record.

65.      As regards the Environmental Clearance dated 13 October 2017, granted

to the project is concerned, it clearly provides for total construction area of

72032.18 sq. meters. It is the petitioner's case, to which we do not find any

effective counter or opposition, that for construction of the 'D' wing

Environmental Clearance was received / granted which provides for 4P +

Amenity +20 floors under which the construction is undertaken and in regard to

which the completion certificate and occupation certificate is being applied for by

the petitioner, is of an area of 68132 sq.meters. The construction of 'D' wing is

completed upto 20 floors, and in fact there is a reduction in height. There is no

explanation from the municipal corporation or Respondent No.5 on such vital

contentions as urged on behalf of the petitioner. This more particularly when such

issue was sought to be raised only after the entire construction upto 20 floors, as

undertaken by the petitioner, is completed. It also appears that the sanctioned

plan dated 13 October 2017 provides for 80 flats and accordingly, 80 flats are

constructed and hence, the case of any excess construction of flats as alleged by

Wellbuild and denied by the petitioner, finds no support.

66.       We may also observe that this is not the case that the entire project which

includes wings/towers A, B, C, D has no Environmental Clearance, inasmuch as

Environmental Clearance was granted to the entire project on 13 October 2017. It

is not the case of the respondents that after such clearance was granted, a separate

and/or independent environment clearance was required to be granted to each
                                        Page 52 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



and every wing / tower even in respect of a minor modification in the area of each

of the towers, it was to be undertaken within the permissible limits under such

Environmental Clearance granted to the entire project. Thus, merely for the

reason that on account of some minor modifications, the petitioner had applied

for revised clearance cannot bring about a situation that the project of which

Wing 'D' is a part, has no Environmental Clearance. For such reason also, the

impugned stop work order, when it observes that there is no Environmental

Clearance, for the petitioner to undertake construction for Wing "D" and "C",

appears to be wholly untenable. Considering the very recent position in law in the

majority decision of the Supreme Court in Confederation of Real Estate

Developers of India (CREDAI) V/s. Vanashkti and Anr. 13, the petitioners

application for modification of the Environment Clearance post facto cannot be

said to be not maintainable.


67.      For the aforesaid reasons, we are not inclined to accept the contentions as

urged on behalf of the Municipal Corporation or Wellbuild, as noted

hereinabove. In our opinion, if in the course of execution of the project, some

incidental changes/ modifications are required to be made which would not be

contrary to the construction as permissible under the Environmental Clearance,

the same would not render the construction to be contrary to the Environmental

Clearance already granted. Thus, considering such changes, if a revised

Environmental Clearance is applied for in a revised application, the same needs to

be considered as per rules.
13 2025 SCC Online SC 2474
                                        Page 53 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



68.      In such context, insofar as Wing 'D' is concerned, it is clearly seen that the

proposed height of the building as granted under the provisions of the

Environmental Clearance was 68.45 meters, the configuration 4P +Amenity +

20FL and the same height and configuration is maintained in the revised

application. So far as the revised construction of the Wing C is concerned, there

is no variation whatsoever in the basic parameters of the area of construction or

the height of the construction. In any event, in the 187 th meeting of the SEAC

held on 29 December 2023, the petitioner's application for revised

Environmental Clearance was to the effect that the petitioner would provide

electric charging facility by providing charging points at suitable places as per

Maharashtra Electric Vehicle Policy, 2021 and the petitioner was to ensure that

the water proposed to be used for construction phase should not be drinking

water, and that recycled water or tanker water be used for proposed construction.

These are not the conditions incapable of being performed so that the City

Officer can come to a conclusion that a stop work notice is required to be issued

to the project.


69.      On the requirement of the Environmental Clearance, in our opinion, Mr.

Kamath's reliance on the decision of the Supreme Court in Vanashakti vs. Union

of India (supra) is not well founded for two fold reasons. Firstly, the present case is

not a case wherein it can be said that there was no Environmental Clearance. In

fact Environmental Clearance was granted on 13 October 2017 and construction

was accordingly undertaken. Hence, it is not the case that the petitioner had


                                        Page 54 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



sought any wholesale ex post facto clearance and/or that the petitioner has

undertaken the construction without obtaining Environmental Clearance. In

Vanashakti vs. Union of India (supra), the Supreme Court was considering the

challenge to the judgment of the Madras High Court which quashed the 2021

Office Memorandum which pertained to Standard Operating Procedure (SOP)

for identification and handling of violation cases under the 2006 EIA

Notification and another Office Memorandum dated 19 February 2021. It is in

such context the Supreme Court held that it was not permissible for the project

proponents to seek ex post facto clearance retrospectively being alien to the

environmental jurisprudence and the EIA notification. However, considering the

recent decision of the Supreme Court in Confederation of Real Estate Developers

of India (CREDAI) V/s. Vanashakti and Anr. (supra), the said decision of the

Supreme Court in Vanashakti (supra) has been recalled. This being the legal

position, the judgment in Vanashakti (supra) would not assist Wellbuild.



70.      This apart, one of the most glaring aspects of the present matter is the

conduct, not only of the officials who have issued the impugned stop work notice,

but also of respondent No.5 to garner extra legal interference of several persons

who have attended the hearing fixed by the Executive Engineer on 9 December

2024. Such persons had no official concern whatsoever in regard to anything to

do between the petitioner and/or Wellbuild/respondent No.5-the owners who

handed over the project to be executed by the petitioner. The official machinery

of the respondents was totally misused by Wellbuild along with such persons,

                                        Page 55 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



more particularly one Mr. Vikas Shravan Kuchekar, who had attended the hearing

and who also filed an Intervention Application. Rejecting such Intervention

Application, we have passed a detailed order, considering the statements of the

intervenor as made before the Court. From the perusal of our order on the

Intervention Application, things get abundantly clear that the intervenor is no

less than a busybody who could not justify his presence in the proceedings before

the City Engineer. He also could not justify from where he obtained the intricate

information which is completely internal to the project and more particularly in

regard to the relation between the petitioner and respondent No.5. It appears that

the intervenor's role is purely on extraneous considerations, who could not have

been involved except to help those who had an axe to grind against the petitioner.

He appears to have been introduced to obtain an unfair advantage by adopting

such pressurizing tactics before the municipal officers, by utilizing the resourceful

nature of intervenor. Similar comments can be made against others, however, they

are not before the Court. The orders passed by this Court in the intervenor's

application, in fact, would speak volumes about the high-handed and arbitrary

manner of the Municipal officials in issuing the impugned stop work notice,

thereby bringing the petitioner's project which is at a stage of grant of occupation

certificate of Wing "D" as also the construction of Tower "C" to a grinding halt.

71.      Such conduct of the municipal officers has also deprived the legitimate flat

purchasers of early occupation of their flats, having purchased the flats in "D"

wing. This more particularly when the construction of "D" Wing' is completed

long back and awaits an occupation certificate. It has also delayed the construction
                                        Page 56 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



of "C" wing in respect of which the plans are also sanctioned. In these

circumstances, in our opinion, this is a clear case where, Wellbuild/ respondent

No.5 by misuse of the official machinery of the Municipal Corporation has

caused or obtained the impugned order of stopping of work, in respect of the

project. Such order otherwise would not have even been passed.

72.      We may observe that this is also a case, where the impugned decision has

been taken in extreme haste, inasmuch as a totally cryptic and unreasoned show

cause notice dated 6 December 2024 was issued to the petitioner calling upon the

petitioner to remain present, without a whisper of details as to why such hearing

was called for, what were the deficiencies, if any, as also no material whatsoever of

any complaints received by the Municipal Corporation was provided to the

petitioner alongwith the notice dated 6 December 2024. The hearing on the said

notice was held on 9 December 2024, and immediately on the next date i.e. on 10

December 2024 the impugned stop work order has been passed. This apart, as

noted above, several persons unconnected with the project who are social workers

attended the hearing. Their presence in the said hearing was totally unjustified

and unwarranted. Also the impugned stop work order clearly appears to have

been passed at their behest. In such context, the settled principle of law is that if a

decision is taken by a statutory authority at the behest or suggestion of a person

who has no statutory role to play, the same is required to be held to be ultra vires.

This is clear from the decision of the Supreme Court in Bahadursinh Lakhubhai




                                        Page 57 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                       WP 1022-25CORRECTED.DOC



Gohil vs Jagdishbhai M. Kamalia And Ors. 14 wherein the Supreme Court has

observed thus:

         "25. In S. P. Kapoor (Dr) V. State of H.P. 15 this Court held that when
         a thing is done in a post-haste manner, mala fide would be presumed,
         stating:(SCC p.739, para 33)
         "33. .....The post-haste manner in which these things have been done
         on 3-11-1979 suggests that some higher-up was interested in pushing
         through the matter hastily when the Regular Secretary, Health and
         Family Welfare was on leave."

         26.     It is also well settled that if any decision is taken by a statutory
         authority at the behest or on the suggestion of a person who has no
         statutory role to play, the same would be ultra vires. (See Commr. Of
         Police V. Gordhandas Bhanji16 and Mohinder Singh Gill V. Chief
         Election Commr.17 )".



73.      Now coming to the decisions which are cited by Mr. Godbole, learned

Senior counsel for the petitioner supporting the proposition that the impugned

decision of the Deputy Engineer and City Engineer, to order stop work of the

project, is arbitrary and high-handed by relying on the decisions in Dr. S. P.

Kapoor Vs. State of Himachal Pradesh & Ors. 18; Zenit Mataplast Pvt. Ltd. Vs.

State of Maharashtra & Ors. 19; Fuljit Kaur Vs. State of Punjab 20; Rajiv Kumar vs.

State of Uttar Pradesh & Anr.21. There cannot be any dispute on the principle of

law as laid down in these decisions. We do not intend to burden the judgment by

discussing these decisions, suffice it to observe that in the present case, the action


14 2004 (2) SCC 65
15 (1981)4 SCC 716
16 AIR 1952 SC 16
17 (1978)1 SCC 405
18 (1981)4 SCC 716
19 (2009)10 SCC 388
20 (2010)11 SCC 455
21 (2017)8 SCC 791
                                        Page 58 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                               ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



on the part of the concerned officials who have issued the impugned stop work

notice, certainly in no manner satisfies the test of law and accordingly, we had

held the impugned stop work notice to be grossly arbitrary, high-handed and

illegal.


74.        We may observe that this is a clear case where Wellbuild appears to have

clearly exceeded its contractual position with the petitioner, as discussed in detail

hereinabove. However, what surprises us is the conduct of the municipal officials

as to how without verifying the records, without any site inspection to identify

any breaches of any building permissions or any other permissions and above all

without issuance of an appropriate show cause notice merely on purported

complaints of busybodies and / or certain unknown persons could have resorted

to exercise powers affecting and prejudicing the civil rights of the petitioner. This

more particularly knowing well that the construction of Wing 'D' was complete

and would be required to be granted an occupation certificate. The municipal

officials could not have acted so casually. They have acted so as their intentions

appear to have been completely taken over by extraneous considerations, by

virtue of which they have decided to discard all norms of legitimacy, legality,

fairness, transparency and non discrimination in their actions as public officials.

The Municipal Commissioner in the facts of the present case needs to investigate

the role of these officials and the object and motive of these officials in taking the

impugned action, and place an action taken report on the record of this Court

within a period of six weeks. After such report is received, the Registrar Judicial


                                        Page 59 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                   WP 1022-25CORRECTED.DOC



shall list the matter after six weeks for recording compliance. This more

importantly keeping in mind the basic principle of legitimate expectations of the

citizens from public officials. A stitch in time save nine.


75.      In the aforesaid circumstances, we have no manner of doubt that the

petition needs to succeed. It is accordingly allowed in terms of prayer clause (b)

which reads thus:

         "(B) This Hon'ble Court be pleased to issue a Writ of
         Mandamus or any other writ, order or direction in the nature of
         mandamus to the Respondent Nos.01 to 04 and declare that the
         issuance of the Impugned Stop Work Notice dated 10 th December
         2024 issued by the Respondent Nos.03 & 04 and
         recommended/approved by Respondent No.02 under section
         267(1) of the Maharashtra Municipal Corporation Act, 1949 r/w.
         Section 54 of the Maharashtra Regional & Town Planning
         Act,1966 is perverse, illegal, improper, invalid, arbitrary, malafide
         and the same deserves to be set aside."


76.      Before parting, as a Constitutional Court we would be failing in our duty, if

we do not deprecate the arbitrary and high handed action on the part of the

concerned        officials    of     the   Pune   Municipal     Corporation        who      were

instrumental/involved in taking the impugned decision. In our clear opinion,

despite judicial orders, including the orders passed by the Division Bench of this

Court (supra) in the Section 37 ACA proceedings, the petitioner was made to

suffer not only on account of delay in completion of the project but also suffer the

pain and agony of the present litigation. Thus, the petition cannot be simplicitor

allowed, it would be required to be allowed by ordering payment of exemplary

costs. If we do not pass an order as to costs, the message would be that despite

such arbitrary and high-handed conduct of the municipal officials which is purely
                                          Page 60 of 62
                                       21 November 2025



      ::: Uploaded on - 21/11/2025                            ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                             WP 1022-25CORRECTED.DOC



at the behest of private parties, these officials can comfortably get away, so as to

indulge in similar high-handed practices in future, in regard to other parties.

When under the law, public officials are conferred such drastic powers, there is an

onerous duty and responsibility cast on them to exercise such powers only in

accordance with law and not on extraneous considerations. The actions of the

public authorities can never be arbitrary, malafide and high-handed. In this view

of the matter, we direct that the concerned officials including the City Engineer

who are directly involved in passing the impugned order/stop work notice shall,

jointly and severally, pay cost of Rs.5,00,000/- (Rupees Five Lakhs only) to the

petitioner. Such cost be paid to the petitioner within two weeks from today. If the

same is not paid, the Municipal Commissioner shall recover the same in

accordance with law.


77.      Further, all the concerned illegalities have taken place at the behest of

respondent No.5-Wellbuild who itself is a developer. Considering our

observations, respondent No.5-Wellbuild has misused the official machinery of

the municipal corporation in the manner which has shocked our conscience

although it had pure contractual relations with the petitioner. It has nullified the

orders passed by the Courts as noted by us hereinabove. Accordingly, respondent

No.5/Wellbuild also has become liable to be ordered to pay exemplary cost to the

petitioner. It is accordingly directed that respondent No.5-Wellbuild shall pay cost

of Rs.25,00,000/- (Rupees Twenty Five lakhs only) to the petitioner within two

weeks from today.


                                        Page 61 of 62
                                     21 November 2025



      ::: Uploaded on - 21/11/2025                      ::: Downloaded on - 21/11/2025 23:03:55 :::
                                                                     WP 1022-25CORRECTED.DOC



78.         Rule is accordingly made absolute in the aforesaid terms.


            WRIT PETITION NO. 10414 OF 2025


79.         Insofar as the companion petition is concerned, as this Court has allowed

the first petition, we are in complete agreement with the contention as urged on

behalf of the petitioners that these petitioners are unwarrantedly suffering private

disputes between the petitioner and respondent No.5/Wellbuild in the earlier

petition.


80.         For the reasons which we have set out in our judgment on the first petition

(Writ Petition No.1022 of 2025), we are inclined to allow this petition in the

following terms:

                                               ORDER

i. Respondent Nos.01 to 04 are directed to issue Completion/Occupancy Certificate in respect of said Tower viz. Rajgruhi Residency Tower 'D' on the application/proposal in that regard made by M/s. Atria Constructions in accordance with law. ii. Rule is made absolute accordingly. No costs.

81. At this stage, Mr. Kamat, learned senior counsel appearing for respondent

no. 5-Wellbuild seeks stay of both these orders. In the facts and circumstances of

the case, request for stay is rejected.

(ARIF S. DOCTOR, J.)                                     (G. S. KULKARNI , J.)



                                      21 November 2025




 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter