Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Devagirikar Industries Pvt. Ltd, ... vs Maharashtra Industrial Development ...
2025 Latest Caselaw 3455 Bom

Citation : 2025 Latest Caselaw 3455 Bom
Judgement Date : 25 March, 2025

Bombay High Court

M/S. Devagirikar Industries Pvt. Ltd, ... vs Maharashtra Industrial Development ... on 25 March, 2025

Author: A.S. Chandurkar
Bench: A. S. Chandurkar
   2025:BHC-AS:13694-DB
RAMESHWAR
LAXMAN
DILWALE                                                          1       WP-9866-2014.doc



Digitally signed by
                                  IN THE HIGH COURT OF JUDICATURE AT BOMBAY
RAMESHWAR                                 CIVIL APPELLATE JURISDICTION
LAXMAN DILWALE
Date: 2025.03.25
17:11:35 +0530                              WRIT PETITION NO. 9866 OF 2014

                      M/s Devagirikar Industries Pvt. Ltd.                  )
                      Plot No.26, D-III Block, MIDC, Chinchwad,             )
                      Pune-411019 representing through its                  )
                      Managing Director Mr. Venkatesh P. Devagirikar        ) ... Petitioner

                                V/s
                      1]     Maharashtra        Industrial  Development)
                      Corporation,                                     )
                      'Udyogsarthi' Mahakali Caves Road, Marol Indl.   )
                      Area Andheri (E), Mumbai                         )
                                                                       )
                      2]    The Regional Officer,                      )
                      Maharashtra Industrial Development Corporation, )
                      having its office at Jog Centre, Wakadewadi,     )
                      Pune - 411003                                    )
                                                                       )
                      3]    The Principal Secretary,                   )
                      Industries, Energy & Labour Department           )
                      Government of Maharashtra, Mantralaya,           )
                      Mumbai -400 032.                                 )
                                                                       ) ....Respondents
                      4]    The State of Maharashtra                   )

                      Mr. Pralhad Paranjape a/w Mr. Rahul Punjabi & Mr. Yash Tembe,
                      Advocates for the petitioner.

                      Ms. Shyamali Gadre, Advocate i/b Little & Co. for respondent no.1 -
                      MIDC.

                      Mr. N.C. Walimbe, Additional Government Pleader a/w Mrs Reena A.
                      Salunkhe, Assistant Government Pleader for respondent nos. 3 and 4.
                                                      ****

                                                      CORAM : A. S. CHANDURKAR &
                                                              RAJESH S. PATIL, JJ.

                                Date on which the arguments were heard : 17/12/2024
                                Date on which the judgment is pronounced : 25/03/2025

                      BDP-SPS
                                                          1/18


                       ::: Uploaded on - 25/03/2025                  ::: Downloaded on - 25/03/2025 22:42:54 :::
                                                 2              WP-9866-2014.doc




JUDGMENT:

(Per A.S. Chandurkar, J.)

1] The petitioner, a private entity is a lessee of the Maharashtra

Industrial Development Corporation - MIDC having been granted a

lease for a period of 95 years in respect of an industrial plot of land

being Plot No.26, D-III Block, MIDC Chinchwad. It has approached this

Court by filing the present writ petition and seeks the following reliefs:-

"(b) That this Hon'ble Court be pleased to issue a writ of mandamus or a writ in the nature of mandamus or any other appropriate writ order or direction under Article 226 of the Constitution of India directing the Respondent to enter into an Agreement of Lease for a Plot No.F-II-52/3 admeasuring 1387 sq. mtrs at Pimpri for a plot at the rate of 7700/- per sq. mtrs And refund the excess amount to the Petitioner;"

"(c) To hold and declare that the possession of the plot handed over to the petitioner should be reckoned from the date the agreement of Lease is entered into with the Petitioner."

"(C1) To quash and set-aside the demand letter dated 26 June 2019 sent/issued by the Respondent No.1 & 2 asking the Petitioner to make good the amount of Rs 1,16,36,236/- for delay of Petitioner in

BDP-SPS

3 WP-9866-2014.doc

developing the plot from 2014-2020."

2] It is the case of the petitioner that it was undertaking engineering

activities on Plot No.26, MIDC, Chinchwad. It sought to expand its

activities and hence on 03/03/2011, it applied for allotment of Plot

No.52/3-F-II Block admeasuring about 1387 square meters. Pursuant to

a meeting of the Land Allotment Committee on 24/08/2011 its

application was scrutinized and the said Committee decided to allot Plot

No.52/3 to the petitioner subject to conditions laid down in MIDC

Circular dated 18/03/2008 for expansion of its Unit. The MIDC issued

an offer letter to the petitioner on 05/10/2011 stating therein that the

rate of premium payable for the land to be allotted was Rs 8,251/- plus

additional 10% of the said amount, thus totalling Rs 9,077/- per square

meter. The petitioner was called upon to submit its duly completed

application alongwith Demand Draft of Rs 62,94,900/-towards the

earnest amount within a period of fifteen days. The petitioner on

20/10/2011 submitted a Demand Draft for the aforesaid amount to the

MIDC alongwith the requisite "Blue Application" duly filled-in. On the

aforesaid basis, the MIDC on 23/11/2011 issued an order of allotment

in favour of the petitioner subject to various terms and conditions. One

such condition was that the agreement of lease was required to be

BDP-SPS

4 WP-9866-2014.doc

signed within a period of thirty days from receiving the balance

occupancy premium amount. This amount was to be paid by the

petitioner within a period of thirty days from the date of receipt of the

order of allotment. Another condition was that the petitioner was

required to commence production within a period of two years from the

date of possession with a stipulation that no further extension would be

granted. On 18/04/2012, the MIDC issued a communication to the

petitioner stating therein that in terms of the order of allotment the

balance consideration was to be paid within a period of thirty days of

receiving the order of allotment. This amount was however not

deposited. The petitioner was thus called upon to deposit the balance

amount by 15/05/2012.

3] The petitioner on 20/04/2012 preferred an appeal before the

Joint Chief Executive Officer, MIDC raising a grievance that the

premium charged ought to have been at the rate of Rs 7,700/- per

square meter and not Rs 9,077/- per square meter. It sought to rely

upon the Circular dated 18/03/2008 in that regard. On 03/05/2012,

the MIDC informed the petitioner that the last date for depositing the

balance amount was 21/05/2012. Accordingly, on 21/05/2012 the

petitioner deposited an amount of Rs 68,66,400/- with the MIDC.

There being delay of about one hundred and fifty days in depositing the

BDP-SPS

5 WP-9866-2014.doc

balance amount, the MIDC on 23/05/2012 called upon the petitioner

to pay interest of Rs 4,30,330/- at the rate of Rs 15.25% . This amount

was corrected to Rs 4,79,710/- on 01/06/2012. The petitioner

accordingly deposited the aforesaid amount on 21/07/2012. The

petitioner on 07/10/2012 issued a communication to the MIDC seeking

clarification as regards the amount of premium charged from it. On

27/11/2012 the MIDC called upon the petitioner to take possession of

Plot No.52/3 on 06/12/2012. On such possession being taken, a

possession receipt was executed on the said date. The petitioner

thereafter on 10/10/2013 submitted a further proposal for approval of

its plans to the Executive Engineer, MIDC. On 17/10/2013, the MIDC

called upon the petitioner to submit various documents including the

lease agreement. Since the lease agreement was not submitted, the

proposal of the petitioner came to be rejected on 13/11/2013. It

appears that the petitioner in the meanwhile approached the State

Consumer Disputes Redressal Commission by filing a complaint under

the provisions of the Consumer Protection Act, 1986. The complaint

was however withdrawn and the petitioner thereafter has filed this writ

petition.

4] By an order dated 01/08/2018, this Court passed an interim

order directing the MIDC to execute agreement of lease in favour of the

BDP-SPS

6 WP-9866-2014.doc

petitioner by incorporating relevant clauses therein. It was further

directed that after execution of the lease agreement, it would be open

for the petitioner to complete the necessary formalities and seek

sanction of its plans. On the aforesaid basis the agreement of lease

came to be ultimately executed on 20/09/2021. However, in the

meanwhile on 26/06/2019, the MIDC issued a demand note to the

petitioner calling upon it to pay a total amount of Rs 1,16,36,236/-

towards the development charges with penalty. By amending the writ

petition, this communication has been put to challenge.

5] Mr. Pralhad Paranjape, learned counsel appearing for the

petitioner submitted that the petitioner was holding Plot No.26, D-III

Block and had sought to expand its engineering activities. Its

application for seeking allotment of another plot had been favourably

considered by the Land Allotment Committee. In terms of the

expansion policy Circular dated 18/03/2008, it was incumbent upon

the MIDC to apply the prevailing land rate of the industrial area with

10% additional charges for the plot allotted to the petitioner. Being the

only applicant for Plot No.52/3, F-II Block, the petitioner was liable to

pay the prevailing land rate of Rs 7000/- per square meter with 10%

additional charge being Rs 700 and 5% road width charge being Rs

350/-. Thus the petitioner was liable to be charged Rs 8050/- per

BDP-SPS

7 WP-9866-2014.doc

square meter and not Rs 9077/- per square meter as per the offer letter

dated 05/10/2011 and thereafter Rs 9489/- per square meter as per the

subsequent offer letter dated 23/11/2011. Both the offer letters were

contrary to the expansion policy Circular dated 18/03/2008, the Board

decision of the MIDC dated 18/04/2011 and the decision of the Land

Allotment Committee dated 24/08/2011. The MIDC had thus acted

arbitrarily in the matter and had sought to demand higher premium

from the petitioner. Various representations made by the petitioner

were not considered resulting in delay in finalising the premium rates.

It was further submitted that the MIDC failed to enter into the

agreement of lease without any justifiable reason. It was incumbent

upon the MIDC to have called upon the petitioner to have the

agreement of lease executed but no steps in that regard were taken by

the MIDC. It was only on 06/12/2012 that the petitioner was put in

possession. It was further submitted that even after the petitioner

approached the High Court and order dated 30/03/2016 was passed in

the writ petition, the agreement of lease was not entered into. It was

only pursuant to the Court's order dated 01/08/2018 that the

agreement of lease was executed. The subsequent demand raised on

26/06/2019 for an amount of Rs 1,16,36,236/- was also unjust and

arbitrary as the MIDC sought to recover extension charges for the

period from 2014 to 2020 for no justifiable reason. There was no legal

BDP-SPS

8 WP-9866-2014.doc

basis for the MIDC to demand such exorbitant amount. As a result,

grave prejudice as well as financial loss was caused to the petitioner.

Relying upon the decisions in Tata Iron and Steel Company Limited and

Another vs. State of Bihar and Others, (2018) 12 SCC 107, Sharayu

Ashok Gokhale and others vs. Nagpur Municipal Corporation, Nagpur

and others, 2022 (5) ABR 320 and Ramon Distilleries Ltd vs. State of

Maharashtra and Another, 2022 SCC OnLine Bom 11766, it was

submitted that the impugned demand was liable to be quashed as it was

without any legal basis.

On the stand taken by the MIDC that disputed questions were

involved, it was submitted that there was no such dispute on facts.

Since the MIDC was a State entity, the writ petition as filed was liable to

be entertained on merits and the prayers as made ought to be granted.

6] Ms. Shyamali Gadre, learned counsel appearing for the MIDC

relied upon the affidavit-in-reply and opposed the writ petition. She

submitted that the petitioner was an existing lessee of the MIDC and

hence had full knowledge of the policies and Circulars issued by the

MIDC. The demand of premium was made from the petitioner on the

basis of expansion Circular dated 18/03/2008. Since the highest bid

received by the MIDC was at the rate of Rs 8251/- per square meter, the

BDP-SPS

9 WP-9866-2014.doc

same was taken into consideration for determining the amount of

premium payable by the petitioner. The MIDC had acted in accordance

with the offer letter dated 05/10/2011 given to the petitioner. If the

terms mentioned in the offer letter were not acceptable to the

petitioner, it could have refused the allotment. It was further submitted

that the petitioner accepted allotment of Plot No.52/3, F-II Block

without any protest. Hence the terms of the offer letter were binding

on the petitioner. The time limit to complete the construction and also

execute the agreement to lease had been stated in the allotment letter

dated 23/11/2011. The petitioner failed to abide by the time frame

stated therein. Possession of the said plot was also accepted and hence

it was not permissible for the petitioner to thereafter contend that

higher rate of premium was being claimed by the MIDC. It was only

after the building plans submitted by the petitioner were rejected by the

MIDC due to non-submission of an agreement to lease that the

petitioner approached this Court. There was considerable delay in

doing so and hence no discretionary relief be granted to the petitioner.

It was thus submitted that the parties were governed by the terms of the

contract entered into and as those terms were unconditionally accepted

by the petitioner, no relief could be granted to it. To substantiate her

contentions, the learned counsel placed reliance on the decisions in

Suganmal vs. State of Madhya Pradesh and others , AIR 1965 SC 1740,

BDP-SPS

10 WP-9866-2014.doc

Union of India & Others vs. M/s Bhim Sen Walaiti Ram , [1970] 2 S.C.R.

594, Jawahar Lal Burman vs. Union of India , 1961 3 S.C.R. 769,

Punjab National Bank and Others vs. Atmanand Singh and Others ,

(2020) 6 SCC 256 and the judgment of the Supreme Court dated

21/11/2001 in Appeal (Civil) No.7932 of 2001 ( State of Bihar and

Others vs. Jain Plastics and Chemicals Limited ). It was thus submitted

that there was no merit in the writ petition and it was liable to be

dismissed.

7] We have heard the learned counsel for the parties at length and

with their assistance we have perused the documents on record. At the

outset, it may be stated that the petitioner seeks to rely upon the offer

of allotment of Plot No.52/3 which it had sought for expansion of its

engineering activities. The relations between the parties are thus

contractual in nature and keeping the said aspect in mind the

entitlement of the petitioner to the reliefs sought in the writ petition

would be required to be adjudicated. It is not in dispute that pursuant

to the petitioner's application seeking allotment of Plot No.52/3, a

decision to allot the said plot to the petitioner as per the Circular dated

18/03/2008 was taken on 02/09/2011. The petitioner was issued an

offer letter dated 05/10/2011. The rate of premium to be paid by the

petitioner was clearly indicated as Rs 9077/- per square meter. Various

BDP-SPS

11 WP-9866-2014.doc

other terms and conditions were mentioned therein. It is not in dispute

that the petitioner in accordance with the offer had paid an amount of

Rs 62,94,900/- towards the earnest money and had also enclosed its

"Blue Application". This would indicate that the rate at which the offer

was made by the MIDC came to be accepted alongwith other terms and

conditions mentioned therein. As regards payment of the balance

amount, the petitioner did not abide by the time frame as indicated

therein. Hence, the MIDC called upon the petitioner to pay the balance

amount by its communication dated 10/04/2012. It is at that stage that

the petitioner sought to raise a grievance with regard to the rate of

premium charged from it. The MIDC however on 03/05/2012 informed

the petitioner that the last date for paying the balance consideration

was 21/05/2012. On that date, the petitioner deposited an amount of

Rs 68,66,400/-. Though it was urged on behalf of the petitioner that

this deposit was without prejudice to the grievance raised by it in

respect of the rate of premium, the covering letter issued by the

petitioner on 21/05/2012 alongwith the Demand Draft for sum of Rs

68,66,400/- does not indicate the same. It thus becomes evident that

even this amount was deposited by the petitioner without protest.

Thereafter, the petitioner was called upon to pay the interest of a sum of

Rs 4,79,710/- on account of delay of about one hundred and fifty days

in paying the balance amount. On 21/07/2012, the petitioner paid a

BDP-SPS

12 WP-9866-2014.doc

sum of Rs 4,79,710/- without indicating that it was under protest. It is

only for the first time on 07/10/2012 that the petitioner has stated in

its communication that the earlier amounts were deposited under the

protest. In absence of any protest whatsoever being raised while

making such payment, the protest raised on 07/10/2012 after about

five months from making such payment appears to be an afterthought.

We therefore find from the conduct of the petitioner that it

accepted the allotment of the plot in question for the amount of

premium of Rs 9077/- per square meter as stated in the offer letter

dated 05/10/2011 and made the entire payment on that basis. In these

facts therefore we do not find that it would be open for the petitioner to

re-open the issue with regard to the rate of premium charged by the

MIDC from it. Hence no relief can be granted to the petitioner in this

regard.

8] Coming to the challenge as raised to the demand letter dated

26/06/2019 calling upon the petitioner to pay an amount of Rs

1,16,36,236/- on account of delay in developing the plot allotted for the

period from 2014 to 2020, certain factual aspects are required to be

borne in mind. Pursuant to the offer letter issued by the MIDC on

05/10/2011, the earnest amount of Rs 62,94,900/- was paid by the

BDP-SPS

13 WP-9866-2014.doc

petitioner on 20/10/2011. The balance amount of Rs 68,66,400/- came

to be deposited by the petitioner on 21/05/2012. On account of such

delayed deposit, the MIDC called upon the petitioner to pay interest of

an amount of Rs 4,79,710/- which was paid by the petitioner on

21/07/2012. It is thus clear that the entire amount of premium

towards allotment of Plot No.52/3, F-II Block was paid by the petitioner

by 21/07/2012.

In accordance with the offer of allotment dated 05/10/2011, the

MIDC was required to enter into the lease agreement. Same was

however not executed. On 06/12/2012 the petitioner obtained

possession of the plot in question and executed a possession receipt in

that regard. The plans submitted by the petitioner on 10/10/2013

seeking approval to the construction sought to be undertaken came to

be rejected on 13/11/2013 on the ground that the lease agreement was

not executed. In the aforesaid factual backdrop, the petitioner

approached this Court by filing the present writ petition. On

30/03/2016, an interim order was passed directing the MIDC to

consider the petitioner's proposal in the matter of seeking sanction.

Thereafter, on 01/08/2018 a further order was passed in the writ

petition noting that the petitioner had already deposited the lease

premium with the MIDC and that despite such deposit in terms of the

BDP-SPS

14 WP-9866-2014.doc

demand made by the MIDC, the agreement of lease had not been

executed due to pendency of the present writ petition. It was thus

observed that as the petitioner had deposited the lease premium as

computed by the MIDC, there was no impediment for the MIDC to enter

into the lease agreement subject to making appropriate provisions in the

lease deed. A direction was thus issued to the MIDC to execute the

agreement of lease in favour of the petitioner after which the petitioner

could comply with the necessary formalities for seeking sanction of the

plans. The agreement of lease was to be executed within a period of

four weeks from the date the petitioner approached the MIDC.

9] Accordingly, on 28/08/2018 the petitioner approached the MIDC

seeking execution of the agreement of lease. Since there was no

response to the petitioner's request, a reminder was issued on

27/11/2018 to the MIDC. On 01/01/2019 the Regional Manager,

MIDC informed the petitioner that after receiving necessary instructions

from the Head Office, the lease agreement would be executed. Since no

further steps were taken by the MIDC, the petitioner filed Contempt

Petition No.470 of 2019 raising a grievance that the order dated

01/08/2018 passed in the writ petition had not been complied with.

Instead of executing the agreement of lease, the MIDC issued the

impugned communication dated 26/06/2019 calling upon the

BDP-SPS

15 WP-9866-2014.doc

petitioner to pay development charges of Rs 1,16,36,236/- on account

of delay in commencing such development. Thereafter on 24/02/2021

the learned counsel for the MIDC made a statement that the order dated

01/08/2018 directing execution of the agreement of lease would be

complied with by the MIDC within a period of three weeks. It is only

thereafter that on 20/09/2021 was the agreement of lease executed.

From the aforesaid sequence of events, it becomes clear that

despite having paid the entire amount of premium as demanded with

interest by 21/07/2012 and thereafter putting the petitioner in

possession on 06/12/2012, there is no justifiable explanation by the

MIDC for non-execution of the agreement of lease. On account of

absence of the agreement of lease, the development plans submitted by

the petitioner came to be rejected on 13/11/2013. Despite the interim

order passed on 01/08/2018 by which the agreement of lease was to

be executed within a period of four weeks of the petitioner approaching

the MIDC, such agreement was not entered into by the MIDC. It is only

after the order dated 24/02/2021 was passed in the Contempt Petition

that the agreement of lease came to be executed. It is thus clear that no

fault can be found on the part of the petitioner in not having the

agreement of lease executed. The entire amount of premium having

been paid, the MIDC ought to have executed the agreement of lease in

accordance with the offer of allotment. There is no explanation

BDP-SPS

16 WP-9866-2014.doc

forthcoming from the MIDC as to why the agreement of lease was

executed only on 20/09/2021. Issuance of the impugned

communication dated 26/06/2019 demanding further amount from the

petitioner cannot be a justification on the part of the MIDC in not

executing the agreement of lease. It was made clear in the order dated

01/08/2018 that the additional amount claimed by the MIDC would be

subject to adjudication of the present writ petition. We therefore find

from the material on record that the MIDC without any legal

justification failed to execute the agreement of lease in favour of the

petitioner.

10] Having found that the MIDC was responsible for the delay in

execution of the agreement of lease resulting in rejection of the plans

submitted by the petitioner, the demand of development charges from

06/12/2014 till 05/12/2020 in the absence of an agreement of lease

cannot be countenanced. The MIDC refused to approve the plans

submitted by the petitioner as no agreement of lease was entered into.

Despite interim directions given by this Court, the MIDC delayed the

execution of the agreement of lease. The petitioner was required to

invoke the contempt jurisdiction of this Court. Considering these

aspects, in our view, the impugned demand as made in the

communication dated 26/06/2019 does not appear to be justified.

BDP-SPS

17 WP-9866-2014.doc

11] Yet another reason for holding the impugned communication to

be bad in law is that it has been issued in breach of principles of natural

justice. The impugned demand has been issued in response to the

petitioner's communication dated 28/08/2018. This communication

was issued by the petitioner seeking implementation of the interim

direction contained in the order dated 01/08/2018 in the writ petition.

Without granting any opportunity to the petitioner and without

complying with the interim direction, the impugned communication has

been issued. The communication dated 26/06/2019 does not indicate

the basis on which the amount of Rs.1,16,36,236/- has been arrived at.

On this count too, the impugned communication is liable to be quashed

and set aside. We may only observe that if any demand is to be made

from the petitioner, the same has to be done in accordance with law

after giving due opportunity to the petitioner.

12] As a result of the foregoing discussion, we hold as under :-

(i) The petitioner having accepted the offer made by the MIDC on 05/10/2011 demanding premium at the rate of Rs 9077/- per square meter, the same is binding on the petitioner.

             (ii)   The         impugned      communication       dated

BDP-SPS




                                            18           WP-9866-2014.doc


             26/06/2019 issued by the Regional Manager,
             MIDC is quashed and set aside.           The MIDC

however is at liberty to make a claim against the petitioner on the basis of the offer letter dated 05/10/2011 and its prevailing Regulations in case there has been any non-compliance on the part of the petitioner. In case any such claim is made, the observations made/findings recorded hereinabove shall be borne in mind.

13] Rule is made partly absolute in the aforesaid terms leaving the

parties to bear their own costs.

  (RAJESH S. PATIL, J.)                         (A. S. CHANDURKAR, J.)




BDP-SPS




 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter