Citation : 2025 Latest Caselaw 3957 Bom
Judgement Date : 13 June, 2025
2025:BHC-AS:23698-DB
903-aswp-5650-2025-J.doc
HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 5650 OF 2025
Prakash Laxmanrao Adke
A sole proprietor of M/s. P. L. Adke having
his address at 02-AB, Adgaonkar Plaza,
near ABB Circle, Trimbak Road,
Mahatma Nagar, Nashik-07 .....Petitioner
Vs.
1. The Maharashtra Jeevan Pradhikaran,
Division Yavatmal
A statutory authority established
under the Maharashtra Water Supply
and Sewerage Board Act, 1976
having its address at 4th Floor,
Express Towers, Nariman Point,
Mumbai-400 021
2. Member Secretary
Member Secretary of the Maharashtra
Jeevan Pradhikaran, Division Yavatmal
having address at 4th Floor,
Express Towers, Nariman Point,
Mumbai-400 021
3. Superintendent Engineer
of the Head Quarter, Maharashtra
Jeevan Pradhikaran,
having address at 4th Floor, Express Towers,
Nariman Point, Mumbai-400 021
4. Chief Engineer
of the Maharashtra Jeevan Pradhikaran,
having address Tapovan Region Amravati .....Respondents
Shivgan 1/17
903-aswp-5650-2025-J.doc
Mr. Virag Tulzapurkar, Senior Advocate with Mr. Ashish Kamat,
Senior Advocate, Mr. Prathamesh Kamat (through V/C), Ms. Ankita
Sen and Ms. Arpeeta Panvelkar, i/b Renata Partners, for the Petitioner.
Mr. Ajit Ram Pitale, with Mr. Siddharth Pitale, for Respondent Nos.1
to 4.
CORAM : REVATI MOHITE DERE &
DR. NEELA GOKHALE, JJ.
DATE : 13th JUNE 2025.
JUDGMENT :
- (Per Dr. Neela Gokhale, J.)
1. Rule. Rule made returnable forthwith. With consent of
parties, the Petition is taken up for final hearing.
2. By this Petition, the Petitioner seeks to quash and set aside
order dated 5th March 2025 issued by the Respondent No.2 and
restrain the Respondents through their agents, servants or assigns, etc.
from taking any action or acting in furtherance of the impugned order.
Interim relief is also sought in terms of the aforesaid prayer.
3. The Petitioner is a sole proprietary concern and is a
Government recognized Class-1 contractor. The Respondent No.1 is a
statutory body established under the Maharashtra Water Supply and
Sewerage Board Act, 1976. The Respondent No.2 is its Member
903-aswp-5650-2025-J.doc
Secretary and the Respondents No.3 and 4 are its Superintendent
Engineer and Chief Engineer, respectively.
4. The brief facts of the Petition are as under:
4.1 Pursuant to the Petitioner's bid, being accepted, by the Respondents, a formal contract was executed by and between them on 12th April 2017. The contract involved carrying out various works related to the Yavatmal Water Supply Scheme of the Government of Maharashtra under Amrit Phase-I and II.
Amongst other things, the scope of the work included construction of pump house, repairs to the existing water supply pipes, laying new pipes, construction of RCC platforms for substations, etc. The work was to be completed by the Petitioner within thirty months from the date of issuance of work order which was 29th April 2017.
4.2 A tripartite agreement dated 2 nd February 2018 was executed by and between the Petitioner, the Respondent No.1 and one Jai Balaji Industries Private Limited ('JBIL') whereby it was agreed that in order to expedite the work of laying of pipes, the Petitioner shall procure the pipes from JBIL and the Respondent No.1 shall pay the consideration of the pipes to JBIL directly. JBIL was one of the companies appearing in its list of approved manufacturers and the tripartite agreement involving JBIL was done at the instance of the Respondents themselves.
903-aswp-5650-2025-J.doc
4.3 During the testing of the pipes supplied by JBIL, the said pipes were found to be defective and damaged. JBIL replaced the same and the work continued but in the process there was delay in execution of original contract.
4.4 On 11th January 2022, the Petitioner was issued a show-cause notice by the Respondent No.2 calling upon the Petitioner to show cause as to why his proprietary concern should not be recommended for black-listing. The reasons in the show-cause notice related to delay of the Petitioner in completing the work assigned to his concern in terms of the work order.
4.5 The Petitioner sent a reply dated 24 th May 2022 to the show-
cause notice and gave a detailed point-wise explanation to the allegations of the Respondent in the said show-cause notice. There was no action on the basis of this show-cause notice taken by the Respondents for a period of two years. In the meantime, the contract stood executed as the Petitioner completed the work on 11th July 2022. A certificate certifying that the work was commissioned and completed by the Petitioner on 11 th July 2022 was issued by the Executive Engineer of the Respondent No.1 on 29th December 2023.
4.6 On 6th August 2024, another show-cause notice was issued to the Petitioner, once again calling upon the Petitioner to explain the delay caused in performance of the contract. He was also called to attend a meeting with the Respondent No.2 to be convened on 20th August 2024.
903-aswp-5650-2025-J.doc
4.7 The Petitioner attended the said meeting and gave his written explanation. There were other meetings held as well where the matter was discussed among the parties. Even earlier to these meetings, the Respondents held meetings with JBIL regarding the issue, even without the presence of the Petitioner. There are minutes of one of such meeting held on 31 st May 2019 where the issue of defective pipes supplied by the JBIL was discussed and certain directions were given to JBIL. There were also communications exchanged by and between the parties relating to the allegations of delay and the Petitioner's explanation to the same.
4.8 Finally, the Respondent No.2, after a period of another 7 months, passed an order dated 5 th March 2025 directing that the Petitioner's registration with the Respondent No.1 shall not be renewed for a period of one year from the date of the order and the Petitioner will not be allowed to participate in any tendering process of the Respondent No.1 for a period of one year from the date of the order. Penalty and compensation was also imposed against the Petitioner, subject to the final decision of an Arbitration Appeal pending before this Court. It is this order, assailed before us in the present Petition.
5. Mr. Virag Tulzapurkar, learned Senior Counsel appeared
for the Petitioner and Mr. Ajit Pitale, learned counsel represented the
Respondent Nos.1 to 4.
903-aswp-5650-2025-J.doc
6. Mr. Tulzapurkar raised the following objections:
(a) The impugned order refers to an opinion of the technical officers
of the Respondent No.1 as well as an advocate establishing delay
on the part of the Petitioner in completion of work. The said
opinion was never part of the show-cause notice nor was any such
allegation even mentioned in the show-cause notice dated 6 th
August 2024. It is thus, submitted that since the reasons forming
the basis of the impugned order were not put to the Petitioner in
the show-cause notice, the Petitioner was deprived of replying
adequately to the same.
(b) Principles of natural justice require fairness to furnish all material
to the Petitioner and afford an opportunity to him to offer his
explanation.
(c) The Petitioner has been wrongly blamed for supply of
substandard pipes by JBIL especially when in the Minutes of the
Meeting dated 6th August 2018, the responsibility of JBIL is
specifically recorded.
(d) The first show-cause notice dated 11th January 2022 was replied
903-aswp-5650-2025-J.doc
by the Petitioner on 24th May 2022 and the said show-cause
notice was not acted upon for a period of more than two years.
Suddenly, a second show-cause notice dated 6 th August 2024 was
issued, bereft of any specific allegation against the Petitioner. The
impugned order lists various reasons against the Petitioner, which
were never part of the show-cause notice dated 6 th August 2024.
Thus, the principles of natural justice are totally ignored by the
Respondents.
(e) The conduct of the Respondent No.2 indicates that it was pre-
determined to pass the impugned order against the Petitioner.
(f) The Respondent No.2 failed to appreciate that administrative
proceedings entailing significant civil consequences must be
consistent with the principles of natural justice.
(g) The Respondent has acted in exercise of arbitrary authority
against the Petitioner.
7. Mr. Tulzapurkar placed reliance on the following decisions
of the Supreme Court:
(1) Gorkha Security Services v. Government (NCT of Delhi)
and Others1
1 (2014) 9 SCC 105
903-aswp-5650-2025-J.doc
(2) UMC Technologies Private Limited v. Food Corporation of
India And Another2
8. Mr. Pitale, learned counsel appearing for the Respondents
brought to our attention nine grounds finding place in the impugned
order forming the basis of the said order. He defended the said order
by saying that continuous water supply to the residents of Yavatmal
was largely dependent on the expeditious execution of the work
assigned to the Petitioner and delay caused in completing the work
directly caused hardship to the residents of Yavatmal. The prestige and
integrity of the Respondent No.1 came under a cloud. He states that
there was delay on the part of the Petitioner right from the start of the
contract. The Petitioner was not able to procure the required pipes,
raise necessary funds to execute the work and that the progress of the
work was extremely slow. There were many communications
exchanged between the parties and the Respondents had brought the
slow progress of the work to the notice of the Petitioner from time to
time. There were various meetings held in which the Petitioner was
directed to complete the work expeditiously and within the period as
agreed.
2 (2021) 2 SCC 551
903-aswp-5650-2025-J.doc
9. The Petitioner was also found to be negligent in
commissioning the work inasmuch as there was a fatal accident on site
leading to the death of a laborer. Over and above the delay on the part
of JBIL, for which the Respondent did not hold this Petitioner
responsible, there were delays in completing the other work apart
from that related to JBIL. The work ultimately was completed by 11 th
July 2022 and the Respondents suffered great financial loss as well as
loss of goodwill and reputation in the eyes of the residents of
Yavatmal.
10. Mr. Pitale also brought to our notice that penalty was
imposed on the Petitioner's concern for delay in completion of the
work however, by order dated 19 th December 2019 passed by the
Single Judge of this Court in an Interim Application No.1 of 2019 in
Arbitration Appeal (St) No.30511 of 2019, the Respondents were
restrained from deducting any amounts from the RA Bills raised by the
Petitioner towards penalty levied on him, during the pendency of the
Appeal. The said Arbitration Appeal is pending before this Court. For
all the above reasons, Mr. Pitale submitted, that the impugned order is
well-reasoned and requires no interference. He thus, urged us to
dismiss the Petition.
903-aswp-5650-2025-J.doc
11. We have heard the parties and perused the record with
their assistance.
12. The short point that arises for our consideration today is
whether the impugned order can be sustained when passed pursuant
to a show-cause notice, bereft of any allegations against the Petitioner,
forming the basis of the said order, thereby violating the principles of
natural justice.
13. The course of the actions taken by the Respondents
commence with the show-cause notice dated 11 th January 2022 calling
upon the Petitioner to show-cause as to why recommendation of
black-listing the Petitioner's firm should not be forwarded to the
higher authorities of the Respondents on the ground that there was
much delay in discharge of the contract and work order. The
Petitioner replied to this notice in detail, giving a point-wise
clarification to each allegation raised by the Respondents. There was
no action taken in pursuance of the said show-cause notice for a
period of more than two years. Admittedly, in the meantime, the
Petitioner was permitted to continue with the work and the contract
was commissioned and completed by the Petitioner on 11 th July 2022.
903-aswp-5650-2025-J.doc
Accordingly, a completion certificate was also issued by the Executive
Engineer of the Respondent.
14. For various counter monetary claims, the Petitioner filed
an application under Section 9 of the Arbitration & Conciliation Act,
1996 seeking interim order against penalties levied against him. This
Court in an Arbitration Appeal preferred by the Petitioner against
rejection of his Section 9 Application by the District Court, stayed the
deduction of penalties from RA Bills due to the Petitioner. The order is
in effect till date. Surprisingly, the Respondent No.1, a statutory
authority established under Maharashtra Water Supply and Sewerage
Board Act, 1976 has till date neither initiated any claim against the
Petitioner before an arbitrator or any Court of competent jurisdiction
nor has appealed against the said Order passed in the Arbitration
Appeal.
15. It is only after two years that the Respondents have woken
up from their slumber and issued another show-cause notice dated 6 th
August 2024 calling upon the Petitioner to show-cause as to why
action should not be taken against him for delaying the Yavatmal
Water Supply Scheme of the Respondent by refusing to adhere to
agreed timelines. We have gone through the show-cause notice dated
903-aswp-5650-2025-J.doc
6th August 2024. There is not a whisper of any specific allegation in
the said show-cause notice. There is no mention of the fact that the
work has already been completed by the Petitioner in July 2022 itself.
There is nothing in this notice to indicate that this notice is a
continuation of the earlier show-cause notice dated 11 th January 2022.
Considering the admitted fact that the work was completed in July
2022 and a certificate of completion duly issued by the Respondent
and no action was initiated against the Petitioner pursuant to the first
notice dated 11th January 2022, it can be presumed that the
Respondents were satisfied with the explanation given by the
Petitioner in his reply to the same.
16. The law is settled in respect of circumstances in which
black-listing as a penalty can be imposed. The Supreme Court in its
decision in the Blue Dreamz Advertising Pvt. Ltd. v. Kolkata Municipal
Corporation3 while quashing and set aside the blacklisting order, in
almost identical facts, referring to its earlier decision in Kulja
Industries Ltd vs Chief General Manager Western Telecom Project
BSNL & Ors4, in which it has set out the legal position governing
black listing/debarment in USA and UK, observed as under:
3 2024 INSC 589 4 (2014) 14 SCC 731
903-aswp-5650-2025-J.doc
"25. What is significant is that while setting out the guidelines prescribed in USA, the Court noticed that comprehensive guidelines for debarment were issued there for protecting public interest from those contractors and recipients who are non-responsible, lack business integrity or engage in dishonest or illegal conduct or are otherwise unable to perform satisfactorily. The illustrative cases set out also demonstrate that debarment as a remedy is to be invoked in cases where there is harm or potential harm for public interest particularly in cases where the person's conduct has demonstrated that debarment as a penalty alone will protect public interest and deter the person from repeating his actions which have a tendency to put public interest in jeopardy. In fact, it is common knowledge that in notice inviting tenders, any person blacklisted is rendered ineligible. Hence, blacklisting will not only debar the person concerned from dealing with the concerned employer, but because of the disqualification, their dealings with other entities also is proscribed. Even in the terms and conditions of tender in the present case, one of the conditions of eligibility is that the agency should not be blacklisted from anywhere.
26. In other words, where the case is of an ordinary breach of contract and the explanation offered by the
903-aswp-5650-2025-J.doc
person concerned raises a bona fide dispute, blacklisting/debarment as a penalty ought not to be resorted to. Debarring a person albeit for a certain number of years tantamounts to civil death inasmuch as the said person is commercially ostracized resulting in serious consequences for the person and those who are employed by him.
27. Too readily invoking the debarment for ordinary cases of breach of contract where there is a bona fide dispute, is not permissible. Each case, no doubt, would turn on the facts and circumstances thereto."
17. The Apex Court in its decision in Techno Prints v.
Chhattisgarh Textbook Corporation and Another 4, in paragraph 30
held as under:
"30. Therefore, the Authority is expected to be very careful before issuing a show cause notice. It is expected to understand the facts well and try to ascertain what sort of violation is said to have been committed by the contractor. As noted above, there is always an inherent power in the Authority to blacklist a contractor. But possessing such inherent power and exercising such power are two different situations and connotations. There may be a power but there should be reasonable ground to exercise such power."
4 2025 SCC OnLine SC 343
903-aswp-5650-2025-J.doc
18. It is thus, well settled that if a contractor is to be visited
with punitive measures of black-listing on account of any breach of
contract, the nature of his conduct must be so deviant or aberrant
which requires imposing the said punishment. A mere breach of
contract without anything more cannot be used to black-list a
contractor. The Apex Court while dealing with such matters has
observed that the negative effects of black-listing plague the business
of the de-barred entity for a very long time and is viewed as a
punishment so grave which results in sounding a civil death for the
said business.
19. In the case at hand, there are no reasons mentioned in the
show cause notice dated 6th August 2024, which are so grave as to
justify blacklisting the Petitioner for a period of one year from the date
of the order and from participating in any tendering process held by
the Respondents. We say this also because the contract has already
been discharged by execution by the Petitioner in the year 2022 itself.
Moreover, the said show-cause notice does not contain any allegation
on the basis of which the impugned order is passed and hence, the
Petitioner was never afforded an opportunity to meet the said
903-aswp-5650-2025-J.doc
allegation. The principles of natural justice were therefore, totally
ignored.
20. Considering the aforesaid discussion, we have no
hesitation in setting aside the impugned order. Mr. Tulzapurkar
informs us that the registration of the Petitioner's concern with the
Respondent No.1 stands suspended till date and an application
seeking its renewal has been made to the Respondent No.1. However,
since the Petitioner has a valid registration in other State
Government's organizations, the Respondent No.1 itself had assigned
other contracts to the Petitioner's concern, which contracts have also
been completed satisfactorily.
21. Accordingly, we pass the following order:
ORDER
(i) The impugned order dated 5th March, 2025, passed by the
Member Secretary, Maharashtra Jeevan Pradhikaran,
Mumbai, i.e. the Respondent No.2 is quashed and set aside.
(ii) This order shall not be construed to mean that the
registration of the Petitioner's registration with the
903-aswp-5650-2025-J.doc
Respondent No.1-Pradhikaran is renewed. The Respondent
No.1 shall be at liberty to decide the Petitioner's Application
for renewal of his registration on its own merits.
(iii) Needless to state, that all contentions of all parties are kept
open.
22. We also make it clear that we have not dealt with the penal
action imposed against the Petitioner relating to the levy of penalty
and compensation in paragraph 1 of the operative part of the
impugned order since the same is a subject matter of the Arbitration
Appeal (St) No.30511 of 2019 pending before this Court.
23. We also grant liberty to the Respondent No.1 to issue a
fresh show cause notice to the Petitioner, if found necessary and if
they so desire, strictly in accordance with law.
24. The Petition is thus, allowed. Rule is accordingly made
absolute.
25. There will be no order as to costs.
26. All parties to act on an authenticated copy of this
judgment.
(DR. NEELA GOKHALE, J.) (REVATI MOHITE DERE, J.)
Signed by: Raju D. Gaikwad Designation: PS To Honourable Judge Date: 17/06/2025 12:34:53
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!