Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Patel Engineering Limited vs Acron Developers Private Limited
2025 Latest Caselaw 410 Bom

Citation : 2025 Latest Caselaw 410 Bom
Judgement Date : 14 July, 2025

Bombay High Court

Patel Engineering Limited vs Acron Developers Private Limited on 14 July, 2025

Author: R.I. Chagla
Bench: R.I. Chagla
2025:BHC-OS:10704



                                                                                            1-carbp-26-2021.doc
                       jsn


                                          IN THE HIGH COURT OF JUDICATURE AT BOMBAY
          Digitally
          signed by
                                              ORDINARY ORIGINAL CIVIL JURISDICTION
          JITENDRA
 JITENDRA SHANKAR
 SHANKAR NIJASURE
                                                   IN ITS COMMERCIAL DIVISION
 NIJASURE Date:
          2025.07.14
          14:57:41
          +0530                             COMM ARBITRATION PETITION NO.26 OF 2021
                              Patel Engineering Ltd.                                   ...Petitioner

                                      Versus

                              Acron Developers Pvt. Ltd.                               ...Respondent
                                                                 ----------
                              Mr. Venkatesh Dhond, Senior Counsel with Mr. Rohan Kelkar, Mr.
                              Ravitej Chilumuri, Ms. Muskan Arora and Mr. Kunal Parekh i/b.
                              Khaitan and Co. for the Petitioner.
                              Mr. J.P. Sen, Senior Counsel, Mr. Karl Tamboly with Mr. Hrushi
                              Narvekar, Vivek Vashi, Ms. Shaheda Madraswala, Ms. Rajvi Mehta
                              and Ms. Khushi Dhanesha i/b. Vashi and Vashi for the Respondent.
                                                                 ----------

                                                                 CORAM : R.I. CHAGLA J.

                                                            Reserved on       : 11TH DECEMBER, 2024.
                                                            Pronounced on : 14TH JULY, 2025

                              J U D G M E N T:

-

1. By this Commercial Arbitration Petition, the Petitioner

has sought for quashing and setting aside of the Award dated 1st

February, 2020 of the Majority Arbitral Tribunal ("impugned

Award"). There is a dissenting opinion by Mr. R.G. Kulkarni,

Secretary, Irrigation (Retired) to Government of Maharashtra.

2. A brief background of facts is necessary and referred to

1-carbp-26-2021.doc

as under:-

(i) The Petitioner - Patel Engineering Ltd. had engaged an

agency between January to April, 2010 with Company known as

VCon for carrying out construction work at Smondoville

Residential Apartments at Patel Neo Patel Town, Bengaluru.

(ii) The Petitioner had invited tenders of Civil RCC /

Architectural Finishing work for seven towers at Smondoville

Residential Apartments at Patel Neo Patel Town, Bengaluru

("Project") on 3rd June, 2010.

(iii) The Respondent - Acron Developers Pvt. Ltd. submitted its

final offer on 14th and 15th June, 2010 in respect of the project. A

meeting was held between the parties for finalization of the

Contract in respect of six towers, S9, S10, S14, S15, S16 and S17.

(iv) The Letter of Intent ("LoA") was issued by the Petitioner to

the Respondent in respect of six towers on 23rd June, 2010. The

LoA specified that the contract sum would be as under:-

(a) Rs. 860.40 per Sq.ft. (79.93 Sq. mtrs.) for five towers

i.e. S9, S14, S15, S16 and S17.

1-carbp-26-2021.doc

(b) Rs.823.50 per Sq. ft (76.50 Sq. mtrs,) for Tower S10.

(c) The measurement of the area would be as per Annexure - I

of the LoA.

(d) There is a mention in the LoA that "This is a Contract based

on the measurable on built up area basis. Payment will be made

based on joint measurement of laid quantity at the site after

completion of the total work carried out by the Contractor..."

(e) The duration of contract was for 16 months i.e. till 22nd

October, 2011.

(f) The contract sum would be Rs.34,15,62,096/- and the

measurement of the area would be as per Annexure I.

(v) The second LoA was issued on 26th July, 2010 by the Petitioner to

the Respondent in respect of the 7th Tower i.e. S11. The LoA

specified as under:-

(a) That the terms and conditions would be the same as the

LoA dated 23rd June, 2010.

(b) The contract sum would be Rs.3,59,97,528/- and the

measurement of the area would be as per Annexure - I.

(c) It is mentioned in the second LoA that " This is a contract

1-carbp-26-2021.doc

based on the measurable on built up area basis. Payment will be

made based on joint measurement of laid quantity at the site after

completion of the total work carried out by the Contractor....".

(d) The Respondent would be paid for 'actually executed

quantities at the rates mentioned against payment schedule...'.

(e) Duration of the Contract was for 15 months i.e. till 25th

October, 2011.

(vi) The Respondent mobilized resources for the purposes of

execution of the project in June / July, 2010.

(vii) Good for Construction ("GFC") drawings were issued to the

Respondent by the Development Manager ("DM") periodically / in a

stage-wise manner from July, 2010 onwards.

(viii) The Respondent requested DM on 7th July, 2010 for footing

details in respect of Towers S9 and S14.

(ix) The DM provided Acron with an area statement of the project

on 6th August, 2010.

(x) An email dated 3rd September, 2010 was sent by the

Respondent to the DM seeking details specifications of items of work.

1-carbp-26-2021.doc

(xi) An email was sent on 14th September, 2010 by the Respondent

to the DM informing of the stoppage of work due to third parties.

This was followed by an email dated 30th October, 2010 to the same

effect.

(xii) On 11th November, 2010, the Petitioner and the Respondent

executed the contract in respect of the project. It was provided in the

contract, that "the contract is not an item-rate-contract. The

quantities mentioned in the BOQ are only indicative. The contractor

has to verify the quantities from the drawings provided with the

tender. Only a change in drawing will imply verification. The contract

is a lump sum contract calculated on the rate per total built up area

as quoted by the contractor".

Further, the contract sum for all 7 towers was for

Rs.37,75,59,624/- and a total area of 4,45,443.7 Sq. ft. (41,383.07

sq. mtrs.) was agreed upon.

(xiii) There were email exchanged between Respondent and DM

with regard to the drawings to be forwarded; for electrical contractor

to complete works at the earliest and for providing revised

calculations of the built areas for the project.

1-carbp-26-2021.doc

(xiv) DM by email dated 12th May, 2011 rejected RA Bill 6A issued

by the Respondent on the ground that the work had not yet been

completed.

(xv) The Respondent by email dated 20th May, 2011 responded to

DM's email / letter of rejections stating that the DM can verify the

measurements as provided by it and the parties can also take joint

measurements for the work completed by the Respondent.

(xvi) The DM by email dated 20th May, 2011 sent to the Respondent

stated that payment can be made on the joint measurement of

executed quantities only after the completion of total work. It was

further stated that the stagewise payment based on the actual area

taken by joint measurement will be released after the structure work

completion of each tower.

(xvii) There were further emails exchanged between the Respondent

and DM dated 15th June, 2011, 20th June, 2011 and 2nd July, 2011

regarding delay due to the plumbing and electrical contractors who

are third parties.

(xviii)The Respondent by email dated 25th July, 2011 sent to the DM

resubmitted the detailed calculation of the increase in As Built Area

1-carbp-26-2021.doc

for the Project.

(xix) The DM by email dated 27th July, 2011 sent to the Respondent

requested it to send the concerned person for the area reconciliation

so as to process the Respondent's calculation for additional area.

(xx) By a letter dated 27th July, 2011 the Respondent submitting RA

Bill 9A to the DM for its claim on increase in built up area of the

project.

(xxi) The Respondent by emails sent on 4th and 11th August, 2011

submitted as built calculations and drawings.

(xxii) The Respondent in an email dated 4th October, 2011 sent to

DM stated that the contract needs to be revalidated by extension of

time. The DM in response email dated 4th October, 2011 stated that

contract is work bound and not time bound and therefore, 'a renewal

is not necessary...".

(xxiii)The timeline to complete the project as per the contract came

to an end on 22nd and 25th October, 2011.

(xxiv) The Petitioner terminated the contract vide letter dated 22nd

October, 2011 on inter alia the ground that the Respondent has failed

1-carbp-26-2021.doc

to achieve the milestones to complete the project as stipulated in the

contract.

(xxv) The Respondent responded to the termination letter

dated 25th October, 2011 denying the allegations as contained in

the termination letter and requested for a meeting to amicably

settle the issues.

(xxvi) A Deed of Settlement was executed between the

Petitioner and Respondent on 31st October, 2011. It was recorded

therein as under:-

(a) It was recorded in recital 1 that " However, Acron failed to

fulfil its part of the obligations and PEL was constrained to

terminate the Agreement..." .

(b) It was further recorded in Recital 2 of Deed of Settlement

that "Acron requested for an amicable settlement and further

requested for withdrawal of the termination Notice".

(c) In Clause 2, it was recorded that " the Contract stood

revived subject to the modifications as contained in the Deed of

Settlement".

1-carbp-26-2021.doc

(d) In Clause 5, it was recorded that the Respondent undertook

to complete the project by 31st January, 2012 as per the

milestones set out in Annexure 3.

(e) Further in Clause 9, it was recorded that the Respondent

may raise a bill every 15 days and the Petitioner shall pay the

same within a period of 15 days from the date of submission.

(f) In Clause 11, it was recorded that the Respondent's

fulfillment of its obligations within the time stipulated in the Deed

of Settlement is of the essence.

(g) In Clause 13, it was recorded that, except the modifications

as contained in the Deed of Settlement, all other clauses of the

contract, including the arbitration agreement, shall remain in full

force.

(xxvii) There were emails sent from 3rd January, 2012 to 31st

January, 2012 by the Respondent to DM, regarding the delay due

to third parties i.e. plumbing and electrical contractors.

(xxviii) As per the Deed of Settlement, the timeline to complete

the project came to an end on 31st January, 2012.

1-carbp-26-2021.doc

(xxix) A show cause notice was issued by DM to Acron stating that

the Respondent has not completed the works as per the schedule

and called upon the Respondent to clarify as to why the liquidated

damages ought not to be imposed on it.

(xxx) The Respondent in the response to the Show Cause Notice

on 17th February, 2012 stated that any delay was due to inter alia

non-completion of works by other agencies and non-availability of

kitchen granite slabs which were to be supplied by Patel Realty

(India) Ltd. ("PRIL"). The Respondent requested for extension of

time till 31st May, 2012 for completion of works.

(xxxi) There were further emails exchanged between the

Respondent and DM regarding delay due to aluminum contractor

as well as, delay due to pending work by various other third

parties.

(xxxii) An email dated 17th April, 2012 was sent by the

Respondent to DM referring to a meeting of even date wherein

timelines for completion of the project were agreed between the

parties. The last date of hand over was set to 30th June, 2012.

1-carbp-26-2021.doc

(xxxiii) There were further emails sent from 14th May, 2012 till

27th June, 2012 by the Respondent to the DM regarding the delay

in payment of RA bills 17 to 19.

(xxxiv) A notice dated 16th July, 2012 was issued by the Petitioner

to the Respondent stating that the Respondent had committed to

complete the project by 30th July, 2012 and there continues to be

delay in around 11 activities by the Respondent. The Respondent

was called upon to provide a proper plan as to how it was going to

achieve the final target by 30th July, 2012.

(xxxv) The Respondent responded on 23rd July, 2012 to

Petitioner's notice stating that all commitments made by the

Respondent were based upon reciprocal promises to make timely

payment of the RA Bills by the Petitioner. Further, owing to the

slow progress of work by the other agencies appointed by the

Petitioner, the Respondent's work has been impacted.

(xxxvi) There were emails sent from 28th August, 2012 till 27th

September, 2012 by the Respondent to DM, regarding the delay

due to the plumbing contractor i.e. relatable to third parties.

1-carbp-26-2021.doc

(xxxvii) An email dated 26th October, 2012 was sent by the

Respondent to the Petitioner stating that the final cleaning of

towers S10 and S11 was underway and providing timelines as

agreed at meeting held on even date, for handover of the same.

The last date of hand over was 3rd November, 2012.

(xxxviii) An email was sent by the Respondent to the Petitioner

requesting for release of the delayed payments as the site was just

a few days from handover.

(xxxix) The DM was no longer involved with the project from 30th

November, 2012. According to the Respondent, the project was to

be completed on 31st December, 2012.

(xl) The Respondent handed over the flats to the Petitioner's

representative Arsen Infra Pvt. Ltd. after rectification of the snags

between February to March, 2013.

(xli) The Respondent submitted the final bill to the Petitioner in

respect of the project on 24th August, 2013.

(xlii) An email dated 25th September, 2013 was sent by the

Petitioner to the Respondent requesting the Respondent to send its

1-carbp-26-2021.doc

authorized person to meet with Petitioner's employee for

certification of the final bill.

(xliii) The Petitioner sent email dated 25th October, 2013 to the

Respondent providing it with the joint inspection list and

requesting for the handover document along with the bill. It is the

Petitioner's contention that the Respondent abandoned the site in

August, 2013.

(xliv) On 12th November, 2013, an email was sent by the

Respondent to Arsen and the Petitioner stating that it has rectified

the snags as pointed out by Arsen / Petitioner.

(xlv) The Respondent invoked Arbitration dated 18th November,

2013 owing to the Petitioner's failure to certify the final bill and

take joint measurements.

(xlvi) An Arbitration Petition No.62 of 2014 was filed by the

Respondent under Section 9 seeking relief that the Petitioner be

restrained from invoking the bank guarantees; from selling or

otherwise creating any third party rights in the subject property;

or in the alternative be directed to deposit a sum of approximately

1-carbp-26-2021.doc

Rs.15 Crores before this Court. This Court declined ad-interim

reliefs in the said Petition on 28th November, 2013.

(xlvii) The Petitioner invoked the Bank Guarantees provided by

the Respondent amounting to a total of Rs.2 Crores on 28th

November, 2013.

(xlviii) The Petitioner responded to the invocation notice on 2nd

December, 2013 stating that the Final Bill submitted by the

Respondent is arbitrary and its authenticity needs to be

ascertained and calling upon the Respondent to discuss the matter

so that the dispute can be amicably settled.

(xlix) On 24th December, 2013, Mr. Anil Nagrath, the Architect

appointed by the Respondent provided his computation of the

area constructed by the Respondent.

(l) The defect liability period i.e. 12 months from 31st December,

2012 came to an end on 31st December, 2013.

(li) The Respondent submitted the final bill on 4th January, 2014

and requested the same to be treated as the final bill.

1-carbp-26-2021.doc

(lii) The Petitioner and the Respondent appointed their nominee

arbitrators on 23rd April, 2014 and 27th March, 2014 respectively.

(liii) Statement of Claim was filed by the Respondent on 11th

August, 2014 raising claims of Rs.22,81,23,681/-.

(liv) The Statement of Defence was filed by the Petitioner on 17th

December, 2014.

(lv) The Petitioner filed its counter claim raising claims of

Rs.24,06,73,079/-.

(lvi) The deposit order was passed by this Court on 21st August,

2015 in the Section 9 Petition filed by the Respondent whereby

the Petitioner was directed to deposit a sum of Rs.11 Crores with

the Prothonotary and Senior Master of this Court. It is pertinent to

note that pursuant to several Orders passed, including Contempt

Petition filed by the Respondent, the Petitioner deposited the

amount in tranches with the final deposit made by 1st February,

2019.

(lvii) The issues were framed by the Tribunal on 25th September,

2015.

1-carbp-26-2021.doc

(lviii) The impugned Award was passed by the Arbitral Tribunal

on 1st February, 2020 in terms of which the certain claims of the

Respondent were allowed and the Petitioner's counter claims were

rejected. A dissenting opinion was provided by the Petitioner's

nominee Arbitrator, Shri R.G. Kulkarni.

(lix) The captioned Section 34 Petition was filed by the Petitioner

along with Interim Application (L) No.8620 of 2020 for stay on

10th December, 2020.

(lx) A consent minutes of Order dated 12th February, 2021 was

tendered by the parties in terms of which the award was stayed

subject to the Respondent being permitted to withdraw the

deposited amount of Rs.11 Crores along with interest, without

security. Accordingly, the Interim Application (L) No.8620 of 2020

came to be disposed of. It is pertinent to note that the Respondent

has withdrawn the deposited amount along with accrued interest

amounting to Rs.12,41,80,617/-.

(lxi) The Interim Application (L) No.6786 of 2021 filed by the

Petitioner for amendment of the captioned Section 34 Petition was

allowed by the Order dated 16th March, 2021.

1-carbp-26-2021.doc

3. Mr. Venkatesh Dhond, the learned Senior Counsel

appearing for the Petitioner has submitted that the impugned Award

is patently illegal and / or perverse. It is in manifest disregard of the

facts on record and settled law. It is also contrary to the terms of the

contract which governed the parties.

4. Mr. Dhond has submitted that the Impugned Award's

factual findings, and its legal conclusions are so irrational and

manifestly flawed that no reasonable person properly instructed in

the law and the facts on record, could possibly have arrived at the

same. The majority view on the matter as a whole, travels far beyond

the scope of the reference, and do not represent a possible view.

5. Mr. Dhond has submitted that the findings on the Deed

of Settlement are perverse, inasmuch as only allegations of coercion

(made to avoid said Deed) were those of "lawful act" coercion. He

has further submitted that no evidence in support of such allegations,

or which could clear the high bar for proving such coercion, was led.

He has submitted that not only this, but after the Respondent alleging

coercion, and the Tribunal accepting the allegation, both relied upon

Deed itself to seek and to grant relief. He has submitted that this is

1-carbp-26-2021.doc

unheard of in law.

6. Mr. Dhond has submitted that the original contract

contained a specific provision [General Conditions of Contract

("GCC") of Clause 1/3.20] making time of the essence. It was so

contended even in the Statement of Defence. He has submitted that

the original contract came to an end on 22nd October, 2011 and the

Petitioner terminated the contract on that date.

7. Mr. Dhond has submitted that pursuant to a request by

the Respondent the termination was revoked and a Deed of

Settlement was executed by and between the parties on 31st October,

2011 and it was also agreed before the Tribunal that time was of the

essence under the same.

8. Mr. Dhond has referred to the Recitals and Clauses of the

Deed of Settlement. He has in particular referred to the Recital which

states, "However, Acron failed to fulfill its part of the obligations and

PEL was constrained to terminate the Agreement vide Notice dated

22nd October, 2011". He has further referred to the Recital, " on the

request of Acron to withdraw the letter dated 22nd October, 2011

(termination letter) and for the following settlement in Order to

1-carbp-26-2021.doc

continue the Agreement and to allow Acron to complete all the

unfinished work within the extended period, subject to certain

additional terms and conditions proposed by the PEL and agreed to

by Acron". He has referred to Clauses 6, 11 and 12 of the Deed of

Settlement. He has submitted that the express terms of the Deed of

Settlement (including its recitals) were that; (a) Acron had defaulted

in discharging its obligations under the Original contract; (b) it was

on the express and specific request of Acron to revoke the notice of

termination and revive the original contract and on Acron's solemn

assurances to complete the work within the extended time given to

them, that PEL withdrew the notice of termination, and the original

contract was revived with additional terms as expressly incorporated

in the Deed of Settlement.

9. Mr. Dhond has submitted that despite this the Tribunal

allowed Acron / the Respondent to wriggle out of the consequences

of the Deed of Settlement on the specious plea that it was compelled

to enter into the same under coercion or financial duress. No

evidence whatsoever of such coercion or duress was produced by the

Respondent before the Tribunal. He has referred to the conclusions

on this score which are in paragraphs 82 and 83 of the Impugned

1-carbp-26-2021.doc

Award.

10. Mr. Dhond has submitted that mere averments in

pleadings as such the Statement of Claim do not and cannot

constitute evidence. Nevertheless these form the basis of the

Tribunal's findings on coercion.

11. Mr. Dhond has submitted that perhaps aware that

accepting the plea of economic coercion without any semblance of

evidence in support would render its finding vulnerable, the Tribunal

has referred to paragraph 42 on page 20 of the Affidavit of Evidence

of Mr. Velmurugan (CW2) and records that the contents of the said

paragraph constitute evidence of coercion. He has submitted that

mere perusal of the paragraph shows that all that CW2 referred to

was an alleged overdraft facility availed of not by the Respondent,

but by an alleged sister concern in Goa. The letter of the bankers

dated 9th August, 2011 referred to by the Tribunal is one from the

Citizen Credit Cooperative Bank Ltd. again addressed not to the

Respondent but to one Acron Infra Projects Pvt. Ltd.

12. Mr. Dhond has submitted that in paragraph 42 of the

Affidavit of Evidence of CW2 there is not even an assertion making

1-carbp-26-2021.doc

any grievance against the Petitioner as being the cause for the

Respondent to avail of such overdraft facility.

13. Mr. Dhond has referred to the Respondent's case of

duress and which is unlawful threat of payment by the Petitioner to

one of the Respondent's supplier; unlawfully withholding payment

from the Respondent; the Petitioner's consultant's turning down of

Respondent's request to reduce Bank Guarantee amount for reasons

that were "incorrect and contrary to the contract terms" and

termination of the contract by the Petitioner on 11th November,

2010.

14. Mr. Dhond has submitted that the Respondent

acknowledged that, due to "several issues" between the parties, it

was "contemplating initiating legal proceedings" against the

Petitioner.

15. Further, the Respondent had called for an amicable

settlement and had agreed to complete the work in December 2011

only if a sum of Rs.2 Crore was released at once. It had also said that

it would revalidate Mobilization Guarantees for a lesser amount and

upon the first termination, it had requested for a settlement for

1-carbp-26-2021.doc

"closing and concluding our legal relationship".

16. Mr. Dhond has submitted that the Respondent has relied

upon the Deed of Settlement to support its claims and the Tribunal

relied upon it to grant relief to the Respondent. He has referred to the

Award at paragraphs 40, 55 and 62 to 63 in this context. The

Tribunal itself states that the Deed of Settlement was signed to

"maintain good business relations", "purely out of practical business

sense".

17. Mr. Dhond has submitted that given all of the above, the

findings of the Tribunal refusing to give effect to the Deed of

Settlement are perverse.

18. Mr. Dhond has placed reliance upon the judgment of the

Privy Council in Pao On & Ors. Vs. Lai Yiu Long & Ors. 1 The Privy

Council has held that for coercion which is stated to have resulted

from perfectly lawful acts, the threshold or bar to be cleared to

establish the same is extremely high. There must be present some

factor that could, in law, be regarded as a coercion of his Will

sufficient to vitiate a party's consent. It is material to enquire

1 (1979) 3 WLR 435 at 450-451

1-carbp-26-2021.doc

whether, the person alleged to have been coerced did or did not

protest; whether at the time he was allegedly coerced into making

the contract, he did or did not have an alternative course open to him

such as an adequate legal remedy; whether he was independently

advised; and whether after entering the contract he took steps to

avoid it.

19. Mr. Dhond has submitted that the aforementioned Privy

Council judgment had been relied upon by this Court in Balaji

Pressure Vessel Ltd. Vs. Bharat Petroleum Corporation Ltd 2. at

paragraph 12. The said judgment has not been dismissed though

appealed from and the SLP therefrom before the Supreme Court has

been dismissed on 5th August, 2019. This Court has held that in

considering duress in a contractual situation in simple commercial

pressure is not good enough. The pressure so as to constitute duress

must be such that the victim must have entered the contract against

his will, must have had no alternative course open to him, and must

have been confronted with coercive acts by the party exerting the

pressure. In other words, the pressure exercised by the other party

must be such as the law would not regard legitimate.

2 2014 SCC OnLine Bom 1709

1-carbp-26-2021.doc

20. Mr. Dhond has submitted that the Respondent in the

present case has even relied on the allegedly 'coerced' Deed of

Settlement to obtain relief. This was despite the fact that it was not

its case that only parts of the Deed were the result of coercion. The

whole of it allegedly was. He has submitted that the Arbitral Tribunal

has not only failed to recognize this, it has replicated the

Respondent's approach in making the impugned Award.

21. Mr. Dhond has relied upon the judgment in the case of

S.K. Jain Vs. State of Haryana & Anr. 3 paragraph 8, where it is held

that, the very "concept of unequal bargaining power has no

application in case of commercial contracts".

22. Mr. Dhond has further relied upon the judgment of the

Courts of England in Times Travel (UK) Ltd. and Anr. Vs. Pakistan

International Airlines Corporation4. It has been held therein that the

Common Law doctrine of duress to include lawful act economic

duress by drawing on the rules of equity in relation to undue

influence and treating as 'illegitimate' conduct which, when the law

of duress was less developed, had been identified by equity as giving

3 (2009) 4 SCC 357.

4 (2021) 3 WLR 727 @727.

1-carbp-26-2021.doc

rise to an agreement which it was unconscionable for the party who

had conducted himself or herself in that way to seek to enforce.

23. Mr. Dhond has submitted that in view of the well settled

law on the Common Law doctrine of duress, the factors which

constitute duress have not been met in the present case.

24. Mr. Dhond has submitted that the Respondent has

selectively relied upon Deed of Settlement which is impermissible. He

has placed reliance upon the decision of this Court in Ranjit

Vardichand Jain Vs. Nirmal Gagubhai Chhadwa & Ors.5 at paragraphs

76-78. He has submitted that to allow one party to selectively rely

upon a document and to disallow the other from relying upon the

entirety of the same document, is other than being perversity in itself,

a failure to meet any Tribunal's ingrained obligations; ensuring

'parties shall be treated with equality' and no party is 'otherwise

unable to present his case". He has placed reliance upon Sections 18

and 34(2) (a) (iii) of the Arbitration and Conciliation Act, 1996 in

this context.

25. Mr. Dhond has submitted that the claim of the

5 2023 SCC OnLine Bom 1095.

1-carbp-26-2021.doc

Respondent for additional built-up area has been allowed dehors the

terms of the parties contract, and in the face of several clear

admissions by Respondent's Chief Witness.

26. Mr. Dhond has submitted that there is a distinction

between 'constructed area' and 'built up area'. He has submitted that

the Respondent in the present case was in a position to ascertain (a)

amount of construction and / or (b) what the built up area would be.

The contract itself identified with fair certainty what such built area

would be per building, per floor, apart from other facilities like lifts,

overhead water tanks, lift machine rooms, staircases, balconies etc.

The Respondent was in no element of doubt on two things namely

(a) it would be paid not with the reference to the construction

actually put up i.e. the area actually constructed but with reference to

built up area; and (b) the co-relation between the built up area and

the construction actually put up i.e. the actual area that it was

required to construct. It was in this context that the Respondent was

required to quote a rate. He has submitted that this is akin to a

situation where the gross and net figure are both known, but the

parties quote with reference to the net figure. In such a case, a person

who quotes with reference to a net figure is going to be paid on net

1-carbp-26-2021.doc

basis, and cannot, subsequently, use a rate for net and multiply it

with the gross amount of work.

27. Mr. Dhond has submitted that since there was no

material change between the tender drawings and construction

drawings, the Respondent was only entitled to be paid for the built

up area (which did not materially change).

28. Mr. Dhond has submitted that the Respondent initially

made a claim for work citing that this consisted of new elements that

were absent in the tender drawings. This was demolished in cross

examination. The Respondent then tried to recover the same amount

by referencing it to the area actually constructed without giving any

weightage to the mode of measurement as provided in the contract,

when all that it was entitled to, and did receive, was for the built up

area it actually constructed.

29. Mr. Dhond has submitted that the elements that the

Respondent identified as constituting "excess built up area" were

present in the tender drawings as well. There was no real / material

difference between the tender drawings and the GFC drawings. He

has submitted that as long as the Respondent built as per the tender

1-carbp-26-2021.doc

drawings / GFC drawings it could not demand anything more. It

could only claim more where it could demonstrate that the work it

did was different than that shown in the drawings. He has submitted

that the entire theory propounded with reference to additional built

up area being constructed by reason of elements which materialized

only in the GFC drawing was dishonest.

30. Mr. Dhond has submitted that submissions of the

Respondent on claim for additional built area is contrary to the

Respondent's pleaded case and its evidence and should have been

rejected by the Tribunal at the threshold. The Tribunal in taking

cognizance of this, has committed a grave error which has resulted in

a serious violation of natural justice and / or a miscarriage of justice

that ought to shock the conscious of this Court. He has placed

reliance upon the judgment of the Supreme Court in Ssangyong

Engineering and Construction V/s. National Highways Authority of

India (NHAI)6, paragraphs 35, 70 and 76.

31. Mr. Dhond has submitted that the Tribunal by totally

ignoring and making no reference to the complete change of case of

the Respondent, constitute perversity. The Tribunal has further

6 (2019) 15 Supreme Court Cases 131.

1-carbp-26-2021.doc

committed a serious error in accepting the Respondent's case and

disregarding the terms of the contract, pleadings of the parties, and

evidence before it.

32. Mr. Dhond has further submitted that, the Tribunal's

findings and its acceptance of the Respondent's claim of additional

built up area in the sum of Rs.4,33,60,124.70, plainly constitutes

'patently illegality' within the meaning of Section 34(2) (a) of the

Arbitration and Conciliation Act, 1996. He has placed reliance upon

the judgments of Supreme Court in Patel Engineering Ltd. Vs. North

Eastern Electric Power Corporation Ltd., 7 paragraphs 3, 4, 13 and 16

- 22; State of Chhatisgarth & Anr. V/s. Sal Udyog Pvt. Ltd. 8

paragraphs 1, 4, 6, 14-17, 23 and 24 and judgment of this Court in

Interocean Shipping (India) Pvt. Ltd. Vs. Oil and Natural Gas

Corporation Ltd.9 paragraphs 1-3, 17, 24-26, 30 and 33.

33. Mr. Dhond has submitted that in so far as the other claim

of the Respondents namely for an amount of INR 1,10,59,673/- for

additional work done at site beyond what has been certified by the

Respondent Viz. Claim No.1 (04), the Petitioner admitted to an

7 (2020) 7 SCC 167.

8 (2022) 2 SCC 275.

9 (2022 SCC OnLine Bom 1699.

1-carbp-26-2021.doc

amount of INR 52,41,930/-. The Tribunal has awarded an amount to

the tune of INR 86,10,441/- and thus the disputed difference under

this claim is of INR 33,68,511/-.

34. Mr. Dhond has submitted that the claim of various

additional items of work purportedly executed by the Respondent

which were billed by it under the supplementary final bill dated 4 th

January, 2014, admittedly was not certified by the consultant. He has

submitted that in the absence of that certification by the consultant, it

was incumbent upon the Respondent to prove the exact quantity of

the concerned item of work purportedly executed as well as the rate

that it was claiming in respect of the said work.

35. Mr. Dhond has submitted that the Tribunal while

awarding the claim of Rs. 28,15,413/- for the Respondent using Kota

stone for the staircase, has relied upon evidence of CW4 and rate

analyzing at C-198 (colly) at pages 822-839, Volume C-7. He has

submitted that the observation of the Tribunal in this context is

demonstrably perverse in as much, firstly, no such rate analysis was

produced. The document to which reference has been made by the

Tribunal is a mere statement of calculations set out in tabular form.

1-carbp-26-2021.doc

This is neither been signed, authenticated nor certified by any person,

much less by the Respondent's witness CW4. He has submitted that

even if the Respondent had in fact produced a rate analysis such a

rate analysis could not have constituted evidence by any stretch of

imagination because a rate analysis too is merely a notional breakup

of a rate claimed by the Respondent whereas its individual

components and the costing thereof is still required to be proved by

the requisite bills, invoices, master rolls, invoices for hiring of

machinery, etc.

36. Mr. Dhond has made submissions with regard to Claim

No.5 of the Respondent in the Statement of Claim which is for an

amount of Rs.2,85,21,280/- towards alleged additional expenditure

incurred by it as a result of alleged delay caused by the Petitioner

resulting in overstay of the Respondent at the site beyond the

schedule date of completion viz. 22nd October, 2011. He has

submitted that the Tribunal has relied upon evidence of CW4 which

though having referred to alleged accounts of the Respondent, no

such accounts were produced in evidence. He has submitted that

save and except for reference to Annexure CA - 10 of the Statement

of Claim, CW4 did not make reference to any other documents in

1-carbp-26-2021.doc

support of the Respondents Claim No.5. He has submitted that

insofar Annexure CA-10 to the Statement of Claim is concerned that

even a cursory perusal thereof would show that it was merely a list of

certain items and various amounts claimed against them set out in a

tabulated form not unlike particulars of claim annexed at the end of a

Plaint in a money Suit. He has submitted that such particulars of

Claim as Annexure CA-10 does not and cannot constitute 'evidence'.

He has submitted that the Tribunal in awarding such claim on no

evidence whatsoever, is perversity, as understood in Ssangyong

Engineering and Construction Co. Ltd. (Supra).

37. Mr. Dhond has submitted that the Tribunal has recklessly

granted Respondent's claim No.6 which was for alleged additional

expenditure for alleged prolongation of use of machinery, tools, plant

and other construction equipment beyond the period of deployment

originally contemplated under the contract. An amount of

Rs.74,90,758/- which had been claimed by the Respondent and

awarded in its entirety by the Tribunal.

38. Mr. Dhond has submitted that the Tribunal in awarding

Claim No.6 has relied upon Annexure CA-11, CA-12 and CA-13 which

1-carbp-26-2021.doc

are nothing but notional calculations and particulars put in a

tabulated form and which were unsigned, uncertified and

unauthenticated by any person. He has submitted that the Tribunal

inspite of total absence of evidence has awarded the said claim.

39. Mr. Dhond has submitted that the Tribunal in awarding

Claim No.6 has relied upon paragraphs 43 and 44 of CW-4's Evidence

Affidavit which is in the nature of secondary evidence within the

meaning of Section 63 (5) of the Indian Evidence Act, 1872 and

could only be given under the circumstances that could satisfy

Section 65(g) of the Act. He has submitted that the witness was

wholly incompetent under either of those sections. He has placed

reliance upon the judgments of the Delhi High Court in Fortuna Skill

Management Pvt. Ltd. Vs. Jaina Marketing and Associates 10

paragraphs 30 and 31 and Fortuna Skill Management Pvt. Ltd. Vs.

Jaina Marketing and Associates11 paragraphs 37 and 38.

40. Mr. Dhond has submitted that the Respondent has raised

a claim for interest on alleged delayed payments in respect of the

alleged additional area allegedly constructed. The claim for interest

10 2024 SCC OnLine Del 1972 -SJ.

11 2024 SCC OnLine Del 4685 - DB.

1-carbp-26-2021.doc

on delayed payments was under the two separate heads viz. Claim

No.7 and Claim No.8. Claim No.8 is for interest on delayed payment

against the additional area allegedly constructed. The said claim has

been awarded by the Tribunal for an amount of Rs.64,33,292/-. He

has submitted that for the reasons mentioned regarding additional

built up area, this claim ought to have failed. He has submitted that

the impugned Award to the extent that it awards this claim is in

violation of the terms of the contract and is thus liable to be set aside.

41. Mr. Dhond has referred to the terms of the contract

namely payment will be made based on joint measurements of laid

quantity at site after completion of total work carried out by the

contractor. He has submitted that the terms of the contract further

provided that no claim for interest or damage will be accepted by the

DM with respect to any money, which may be in its possession, owing

to any dispute, difference or misunderstanding between the DM and

the contractor. He has submitted that the terms of the contract were

thus clear and unambiguous inasmuch as firstly, the contractor was to

raise its interim bills in terms of the agreed payment schedule. If the

contractor was desirous of claiming any additional amount towards

construction of any allegedly additional area, the payment regarding

1-carbp-26-2021.doc

the same was to be made only after joint measurements were

recorded after the final completion of work. He has submitted that

the Petitioner was not bound to entertain, much less release any

payment in respect of such bills until the final recording of

measurements after the entire completion of work, as per express

terms of the contract. He has accordingly submitted that the

Respondent could not claim interest from the Petitioner by alleging

that payments of such bills were delayed.

42. Mr. Dhond has submitted that the Claim of interest under

Claim 8 was in respect of amounts which were in dispute between

the Respondents and DM and hence, the claim was barred by the

provisions of Clause 1/6.9.1 of the contract. He has submitted that on

this ground also, the Impugned Award granting such a claim is in

violation of the express terms of the contract between the parties and

liable to be set aside.

43. Mr. Dhond has submitted that the Petitioner has raised a

total of 12 heads of claim in its counter claim before the Arbitral

Tribunal. Out of 12 heads, Nos.1, 2, 9 and 11 were for damages. Each

of these heads have been rejected by the Arbitral Tribunal.

1-carbp-26-2021.doc

44. Mr. Dhond has submitted that in so far as counter claim

1 which was claim for liquidated damages under Clause 1/3.21 of the

Contract, he has submitted that the Petitioner was entitled to recover

a sum of Rs.1,88,77,981/- for the period from 31st July, 2012 to 31st

December, 2012. Out of the said sum, the Petitioner had recovered

Rs.40,00,000/- by making deductions from the Respondent's running

Bill Nos. 22, 23 and 24. This left outstanding a sum of

Rs.1,48,77,981/-.

45. Mr. Dhond has submitted that Clause 11 of the Deed of

Settlement specifically makes time of the essence of the contract. The

Deed of Settlement required the work to be completed on or before

31st January, 2012. The Petitioner had given the Respondent

extension beyond the period specified in the Deed of Settlement i.e.

till 30th July, 2012. No extension beyond 30th July, 2012 was

expressly sought or expressly granted. The Respondent however

continued work till 31st December, 2012 and made promises to

complete the work. The Petitioner however, did not terminate the

contract, nor did the Petitioner call upon the Respondent to stop

work. The Tribunal has found that, after 31st January, 2012 time

ceased to be of the essence and / or was put at large.

1-carbp-26-2021.doc

46. Mr. Dhond has referred to the findings of the Tribunal on

the counter claim 1. He has submitted that the findings are perverse

and patently illegal. The Tribunal has in the first set of findings, held

that there was no lawful notice under Section 55 of the Contract Act.

There is an alternative finding that the Petitioner has waived its right

to levy liquidated damages at the rate of 5% of the contract value as

per Clause 1/3.21. There is a finding that the Petitioner was

responsible for the delay that resulted in the Respondent having to

stay at site until 31st December, 2012 and therefore, cannot claim

damages from the Respondent on that score.

47. Mr. Dhond has submitted that these findings are

untenable. He has placed reliance upon Section 55 of the Indian

Evidence Act, 1872 which provides that effect of failure to perform at

fixed time, in contract in which time is essential. He has submitted

that from a plain language of the Section it means that: (a) in the

case of a contract of which time is intended to be of the essence, a

promisor's failure to perform his promise within the time specified

renders the contract voidable at the option of the promisee; (b) in

the case of a contract of which time is not intended to be of the

essence, the promisor's failure to perform his promise within the time

1-carbp-26-2021.doc

specified does not render the contract voidable, but entitles the

promisee to claim damages for the delay and (c) where the contract

was voidable under (a), and the promisee, rather than avoid it,

[under (a)], accepts performance at a later time, his right to seek

damages [under (b)] is subject to his giving the promisor notice of

his intention to seek such damages at the time that he accepts

performance.

48. Mr. Dhond has submitted that the Tribunal has clearly

misconstrued the requirement noted in paragraph 9(c) as one for a

'notice to make time...as of essence of contract', rather than one

merely notifying the promisor of the promisee's intention to claim

damages. That is all that Section 55's plain terms require and that is

all that the letter dated 16th July, 2012 in fact did. He has placed

reliance upon the judgment of this Court in ONGC Vs. Soconord

OCTG & Anr.12 paragraphs 49 - 53 in this context.

49. Mr. Dhond has submitted that the alternative finding of

the Tribunal on alleged 'waiver' is also equally untenable. He has

relied upon the judgment of the Supreme Court in All India Power

12 2014 SCC OnLine Bom 1277.

1-carbp-26-2021.doc

Engineering Federation & Ors. Vs. Sasan Power Ltd. & Ors. 13 at

paragraph 21, where the Supreme Court has reiterated the oft-stated

principle that waiver is "the intentional relinquishment of a known

right", but that this implies, " unless there is a clear intention to

relinquish a right that is fully known to a party, a party cannot be said

to waive it". He has submitted that applying this principle to the facts

in the present case, the Tribunal's finding on waiver is perverse.

50. Mr. Dhond has submitted that the Tribunal in finding

that the Petitioner was responsible for delay until 31st December,

2012 has relied upon mere ipse-dixit of CW1 on delay in supplying

drawings and contradicts the express provisions of the contract

between the parties. He has submitted that the finding on delay in

making payments is an impossible one, since delay in making

payments makes a payor liable to pay interest, not to be held liable

for the payee's failure to complete its work on time. Further, the

findings on delay due to obstructions also contradict an express term

in the parties' contract. The delay in supply of granite is based on no

evidence whatsoever. He has submitted that the finding that the

Petitioner was responsible for the delay until 31st December, 2012 is

13 2017 1 SCC 487.

1-carbp-26-2021.doc

legally unsustainable.

51. Mr. Dhond has submitted that the Respondent's case on

delay during the original term of the contract was that the delay was

because of the Petitioner and not the Respondent. He has submitted

that the Respondent has alleged that the delay was in issuing

drawings by the Petitioner which has found favour with the Tribunal.

He has submitted that this is legally perverse as the question of

"delay" was not part of the Petitioner's case. The Respondent wished

to prove delay, and in order to prove it, wished to rely upon certain

state of facts. The Petitioner was not asked either by the Respondent

or the Tribunal to produce any old drawings or "details of more

area". There was no suppression by the Petitioner or any "admission"

of delay. The Tribunal's findings on adverse inference against the

Petitioner for not producing the drawings and to hold the delay was

on the Petitioner's account is perverse and contrary to settled law. He

has placed reliance upon the decision of the Supreme Court Standard

Chartered Bank Vs. Andhra Bank Financial Services Ltd. and Ors. 14 at

paragraph 49 - 53 in this context.

52. Mr. Dhond has accordingly submitted that the impugned

14 (2006) 6 Supreme Court Cases 94.

1-carbp-26-2021.doc

Award suffers from perversity and is patently illegal and accordingly

requires to be set aside.

53. Mr. J. P. Sen, the learned Senior Counsel appearing for

the Respondent has submitted that in so far as Claim No.1 (1) on

completion of works, there was no delay attributable to the

Respondent and delay was attributable only to the Petitioner. All

works were duly completed by the Respondent and for which reliance

has been placed on the documents on record. Further, reference is

made to the dates and events. He has submitted that after

considering the evidence and documents on record, the Tribunal

rightly came to the conclusion that the work had been completed by

the Respondent.

54. Mr. Sen has submitted that there is no tenable ground in

the captioned Petition challenging the finding of the Tribunal. The

findings of the Tribunal are arrived at after going through the

evidence before it and the Tribunal has arrived at not only a plausible

but also a correct conclusion. He has submitted that in a Section 34

Petition, the evidence cannot be re-appreciated. He has placed

reliance upon the decision of the Supreme Court in Associate Builders

1-carbp-26-2021.doc

Vs. Delhi Development Authority15, paragraphs 32, 52 and 56;

Maharashtra State Electricity Distribution Co. Ltd. Vs. Datar

Switchgear Ltd.16, paragraphs 45 - 90; Ssangyong Engineering and

Construction Co. Ltd. Vs. National Highways Authority of India

(NHAI)17, paragraphs 36, 37 and 38; State of Jharkhand Vs. HSS

Integrated Sdn.18, paragraphs6 & 7.1; Delhi Airport Metro Express

Pvt. Ltd. Vs. Delhi Metro Rail Corporation Ltd.19, paragraphs 28, 29 to

32 and Netaji Subhash Institute of Technology Vs. M/s. Surya

Engineers & Anr.20 paragraphs 54, 66, 67 & 69.

55. Mr. Sen has submitted that in so far as Claim 1(2) for

non tender items there is no dispute over this claim.

56. Mr. Sen has submitted that regarding Claim No.1 (3) for

additional built up area, the contract itself provided that, the

Respondent was required to construct the area 4,45,443.7 Sq.ft.

(equivalent to 41,383.07 Sq. mtrs.). Further, the contract provided

for certain deductions to be made for the purposes of calculating the

payable area of the contract, as per Annexure III thereof. The contract 15 (2015) 3 Supreme Court Cases 49.

16 (2018) 3 Supreme Court Cases 133.

17 (2019) 15 Supreme Court Cases 131.

18 (2019) 9 Supreme Court Cases 798.

19 (2022) 1 Supreme Court Cases 131.

20 OMP (Comm.) 48 of 2020 and I.A. No.1401 of 2024.

1-carbp-26-2021.doc

also provided for the rates per square feet agreed to be paid to the

contractor.

57. Mr. Sen has submitted that realizing this is a construction

contract and eventually the areas as first stated may increase or

decrease, an omnibus clause was incorporated in the contract which

inter alia provided that the Respondent will be paid at the agreed

rates for the area which is actually constructed. He has submitted

that this is also reflected in the LoA's which LOA's have been

incorporated in the contract by reference.

58. Mr. Sen has submitted that the aforementioned term in

the contract stands to good reason because the Respondent being a

contractor is entitled to receive money for the work actually done. If

the work actually done exceeds the area set out in the tender, then

the Respondent will not be paid for any additional work carried out

by it. Therefore, the Petitioner will be permitted to unjustly enrich

itself.

59. Mr. Sen has submitted that admittedly no joint

measurements were taken by the parties after completion of the

works. Therefore, the evidence had to be led by the parties as regards

1-carbp-26-2021.doc

the quantum of area actually constructed by the Respondent.

60. Mr. Sen has referred to the evidence on record of the

RW-3, Architect in employment of the Petitioner and the Respondent's

Witness (CW-5, Architect) as to the area constructed. The reason for

the difference in the payable area between the two witnesses is due

to the additions and deductions made by them to the profile area.

61. Mr. Sen has submitted that taking into account the

contractual provisions and the evidence led by the parties, the

Tribunal came to the conclusion that the Respondent is liable to be

paid for the (a) additional area of 50,395.31 Sq. ft. (4,681.87 Sq.

mtrs.) which was constructed by it; and (b) at the contractual rate of

Rs.860.40 per sq. ft.

62. Mr. Sen has submitted that the conclusions arrived at by

the Tribunal is on the basis of relying upon the contractual provisions

contained in the Contract which provided that the Respondent would

be paid for actually executed quantities. The Tribunal has relied upon

the letter dated 12th May, 2011 and DMs letter dated 20th May, 2011

to buttress the finding. He has referred to paragraphs 15, 34, 58 (c-3)

to (c-9) to 58(c-10) of the Award in this context.

1-carbp-26-2021.doc

63. Mr. Sen has submitted that the Tribunal has considered

each addition and deduction made by the parties' witnesses to the

constructed area and accordingly arrived at its finding that the

Respondent had constructed an extra area of 50,395.31 sq. ft.

(4,681.87 Sq. mtrs.).

64. Mr. Sen has submitted that the findings are based on

appreciation of evidence on record. It is impermissible for the

Petitioner to question the merits of the findings and seek re-

appreciation of the evidence. He has submitted that the law is well

settled that an Arbitral Tribunal is the master of the evidence and

findings of fact arrived at by an arbitrator is on appreciation of the

evidence on record and are not to be scrutinized as if the Court was

sitting in Appeal. He has submitted that even assuming that the

Section 34 Court may take a view different from that in the Award,

nevertheless that is not a ground for setting aside an Award. He has

placed reliance upon State of Jharkhand (Supra) and Maharashtra

State Electricity Distribution Co. Ltd. (Supra).

65. Mr. Sen has made submissions with regard to Claim No.1

(4) which is for the non-tender items for the project amounting to

1-carbp-26-2021.doc

Rs.1,10,59,673/-, the details of which formed part of the Final

Supplementary Bill dated 4th January, 2014 submitted by the

Respondent to the Petitioner. Out of the claimed amount of

Rs.1,10,59,673/-, the Petitioner admitted to the fact that an amount

of Rs.52,41,930/- stood due to the Respondent for this claim. The

Tribunal awarded a sum of Rs.86,10,441/- to the Respondent

towards this claim.

66. Mr. Sen has submitted that the main disputed item by

the Petitioner is the amount claimed for Kota works for staircase done

by the Respondent amounting to Rs.31,31,493/-. The Petitioner

contended that as per items 4.6 and 4.7 of the BOQ provided with

the contract, the staircase work was to be done in Epoxy Paint and

not Kota. Further, it was due to bad quality work done by the

Respondent that Kota stone was used in lieu of Epoxy Paint.

Therefore this sum according to the Petitioner was not payable.

67. Mr. Sen has submitted that as per Annexure III,

Milestone 2 of the Deed of Settlement, the same provided for 'kota

for steps'. He has submitted that Kota work was carried out at the

instance of the Petitioner, as agreed in the Deed of Settlement. The

1-carbp-26-2021.doc

Petitioner's contention that the Respondent had carried out poor

quality of work due to which kota was provided in lieu of epoxy paint

is belied by the Deed of Settlement and unsupported by any

documentary evidence whatsoever.

68. Mr. Sen has submitted that the Final Bill included with it

measurement sheets which provided the total quantity of Kota used

for the staircase in each tower. He has relied upon the evidence of the

Respondent's witness i.e. CW-4, who has personally verified the

quantities of such works executed and also the rates adopted for its

payment in the final bill submitted by the Claimant. He has submitted

that there was no cross examination by the Petitioner on the evidence

led by CW-4 in this regard.

69. Mr. Sen has submitted that considering evidence on

record, the Tribunal has awarded a sum of Rs.28,15,413/- to the

Respondent for the Kota work done by it after deducting the rate of

Epoxy Paint as provided for in the Contract BOQ.

70. Mr. Sen has submitted that as regards the other non-

tendered items for which claims were allowed by the Tribunal, the

Petitioner had admitted to the fact that such work was executed by

1-carbp-26-2021.doc

the Petitioner but contested either the quantum of work done or the

rate charged by Respondent for the same. He has submitted that the

Tribunal considered evidence on record including documentary

support filed by the Respondent with the final bill and the evidence

of CW-4, whilst granting the same.

71. The Tribunal's conclusions are based on appreciation of

the evidence on record and hence it is impermissible for the

Petitioner to question the merits of these findings and seek re-

appreciation of the evidence. He has submitted that the law is well

settled that an Arbitral Tribunal is the master of evidence and the

same cannot be scrutinized as if the Court was sitting in Appeal.

72. Mr. Sen has submitted that in so far as Claims 1(5) to

1(7) relating to service tax, the Petitioner has not disputed its liability

for payment and there is no ground of challenge in the Section 34

Petition raised as regards the Tribunal's findings on these claims.

73. Mr. Sen has submitted that with regard to claims 1(8) to

1(11) regarding extra over basic rate there is no ground of challenge

in the Section 34 Petition raised as regards the Tribunal's findings on

these claims.

1-carbp-26-2021.doc

74. Mr. Sen has submitted that as regards Claims 1(12) and

1(13) i.e. material supplied by PRIL there is no ground of challenge

in the Section 34 Petition as regards the Tribunal's findings on these

claims.

75. Mr. Sen has submitted that regarding Claims 2 and 4,

these claims were rejected by the Tribunal.

76. Mr. Sen has submitted that Claims 3, 5 and 6 are

regarding delay. He has submitted that, it was the case of the

Petitioner before the Tribunal that the project was delayed by the

Respondent and that this fact has been allegedly admitted by the

Respondent in a recital recorded in the Deed of Settlement dated 31st

October, 2011.

77. Mr. Sen has submitted that it was the case of the

Respondent before the Tribunal that the project was delayed due to

various circumstances beyond its control and for no fault of the

Respondent. He has referred to the main cause of delay attributed by

the Respondent, during the contract period i.e. upto 22nd October,

2011 being delay in issuing of drawings; delay due to obstructions by

third parties and delay by the Petitioner in making payments. He has

1-carbp-26-2021.doc

submitted that the main cause of delay attributed by the Respondent

post execution of the Deed of Settlement was due to delay in supply

of kitchen granite; delay due to obstruction by third parties; delay in

issuance of certain drawings and delay by the Petitioner in making

payments. He has submitted that the Tribunal upon considering the

submissions of the parties and evidence on record came to the

conclusion that the delay in completion of the project was not

attributable to the Respondent.

78. Mr. Sen has submitted that it was in light of the findings

of the Tribunal that it held in paragraph 31 of the Award that "not

much importance should be given to" the recital in the Deed of

Settlement as sought to be so heavily relied upon by the Petitioner as

the same are "formal recitals....which are usually found for

maintaining good relations as long as the work is completed and full

payment is received".

79. Mr Sen has submitted that it is trite law that evidence

can be led to explain any recital of statement in a document. He has

placed reliance upon Hindu Public Vs. Rajdhani Puja Samithee21,

21 (1999) 2 SCC 583.

1-carbp-26-2021.doc

paragraph 20 and Manickathamal Vs. Nallsami Pillai22, paragraphs 5,

6 & 8.

80. Mr. Sen has submitted that in so far as Claim No.(3) is

concerned, as per Clause 3 of the Deed of Settlement, the Respondent

was to furnish four performance guarantees of Rs.50 lakh each

amounting to a total of Rs.2 Crores to the Petitioner. Further, under

Clause 6 of the Deed of Settlement, the Petitioner was conferred a

right to terminate the contract and invoke the Bank Guarantees, if the

Respondent failed to achieve the Milestones set out in Deed of

Settlement.

81. Mr. Sen has submitted that it is an admitted position that

after execution of the Deed of Settlement, the Petitioner did not

terminate contract and time was extended to complete works by the

Respondent from time to time. He has submitted that therefore, the

invocation by the Petitioner of the Bank Guarantees on 28th

November, 2013 i.e. after all the works were completed and snags

were attended to by the Respondent, was unjustified and not in

accordance with the Deed of Settlement.

22 1976 SCC OnLine Mad 32.

1-carbp-26-2021.doc

82. Mr. Sen has submitted that it has therefore, been held by

the Tribunal that the invocation of Bank Guarantees by the Petitioner

was wrongful and the Tribunal has correctly granted this claim to the

Respondent.

83. Mr. Sen has submitted that regarding Claim Nos.5 and 6,

it is the case of the Respondent that due to the delay caused to the

project, for no fault of the Respondent, the Respondent was required

to incur additional expenditure during the extended period of

contract amounting to Rs.2,84,60,550/- as per the details provided in

Annexure C-10 of the Statement of Claim. Further, the Respondent

was required to incur additional expenditures for retaining its

machinery, tools and other construction equipments at the site during

the extended period of Contract, which caused loss to extent of

Rs.74,90,758/- to the Respondent (Claim 6) as per details provided

in Annexures C-11 to C-13 of the Statement of Claim.

84. Mr. Sen has referred to the evidence of CW2 and CW4 on

these claims. He has submitted that there is no cross examination by

the Petitioner on this claim whatsoever. It is settled law that in the

absence of questions being put to a witness, a party cannot seek to

1-carbp-26-2021.doc

discredit the witnesses testimony. He has relied upon Laxmibai Vs.

Bhagwantbuva23, paragraph 40 in this context.

85. Mr. Sen has submitted that considering the evidence, the

Tribunal has correctly granted these claims in favour of the

Respondent; especially given the fact that it came to the conclusion

that the delay was not attributable to the Respondent. He has

submitted that the findings of the Tribunal are not only plausible but

also a correct view of the matter and merits no interference in a

Section 34 Petition.

86. Mr. Sen has submitted that regarding Claims 7 and 8

which are for interest due to delayed payments made by the

Petitioner towards (a) running accounts bills and (b) payments for

additional constructed area, these claims are based on Clause 1/6.6.1

of the Contract and Clause 9 of the Deed of Settlement. These

Clauses provide that RA Bills are required to be paid by the Petitioner

to Respondent within specified time period.

87. Mr. Sen has submitted that the Petitioner has incorrectly

relied upon Clause 1 /7.6.9 of the contract. He has submitted that the

23 (2013) 4 SCC 97.

1-carbp-26-2021.doc

said Clause provides that there would be no claim for interest in

respect of amounts which are lying in the possession of the DM due

to any dispute between the DM and the Contractor. He has submitted

that no instance of any such dispute has been referred to by the

Petitioner. He has submitted that since no amounts were lying in the

possession of DM and the Petitioner having demonstrably failed to

make payment of the RA bill within the stipulated time, the

Respondent was entitled to claim interest on the delayed payment.

88. Mr. Sen has submitted that the Respondent had proved

that it had constructed an additional area beyond what was

contemplated in the Contract but the Petitioner failed to make

payment of the same. Accordingly, the Respondent has rightly claim

for interest, in respect of Claim No.8, on the sum due to it for such

additional constructed area.

89. Mr. Sen has submitted that based on evidence on record,

the Tribunal correctly came to the finding that Claim Nos. 7 and 8

regarding interest ought to be granted. As regards, Claim No.8, the

Tribunal reduced the claim amount proportionately in view of its

findings as to the quantum of the additional area constructed by the

1-carbp-26-2021.doc

Respondent.

90. Mr. Sen has submitted that regarding Claim Nos.9 and

10, namely for (i) pendente lite interest due against outstanding

amounts payable by the Petitioner to the Respondent based on RA

bills and Final Bills, and (ii) future interest on the Award sum, there

are no oral submissions made by the Petitioner contesting the claims.

91. Mr. Sen has submitted that regarding Claim No.11, costs,

there are no oral submissions made by the Petitioner contesting the

claim in the present proceedings.

92. Mr. Sen has submitted that all 12 counter claims have

been rejected by the Tribunal. During the course of arguments in the

present proceedings the Petitioner has only contested the rejection of

one of its Counter Claims i.e. Counter Claim No.1 for liquidated

damages. The Petitioner's Counter Claim No.1 was premised on the

allegation that the Respondent was responsible for delays caused to

the project and the Respondent failing to complete the works at site.

The Petitioner claim damages at the 5% of the contract sum as per

Clause 1/3.21.1 of contract.

1-carbp-26-2021.doc

93. Mr. Sen has relied upon the findings of the Tribunal

concurring with the Respondent's submission that the delays caused

to the project are attributable to the Petitioner and not the

Respondent.

94. Mr. Sen has submitted that in view of such findings the

Tribunal has rightly rejected the Petitioner's claim for liquidated

damages.

95. Mr. Sen has submitted that the Tribunal has found that

the Petitioner failed to produce the best evidence in defense of the

Respondent's allegations that the Petitioner failed to timely provide

GFC drawings. He has submitted that the Tribunal has relied upon

the evidence on record to arrive at such finding. He has submitted

that it is settled law that, if the party fails to produce evidence, which

it could produce to prove a particular fact that it asserts, then the fact

of non production of the same ought to be presumed as the evidence

being unfavourable to it and adverse inference with respect to the

same ought to be drawn. He has relied upon Section 114 (g) of the

Evidence Act in this context.

96. Mr. Sen has submitted that the Tribunal has rightly come

1-carbp-26-2021.doc

to finding that the Respondent has proved its case on delay and that

the Petitioner failed to produce its best evidence to disprove the

same. The findings of the Tribunal cannot be faulted; especially in the

scope of Section 34 Petition.

97. Mr. Sen has accordingly submitted that the present

Commercial Arbitration Petition ought to be dismissed with costs.

98. Having considered the submissions, the Petitioner has

impugned the findings of the Arbitral Tribunal predominantly on the

ground that the Tribunal had refused to give effect to the Deed of

Settlement, where in the Recital it is recorded that the Respondent

had failed to fulfil its part of its obligations. It is further recorded that

the Petitioner was then constrained to terminate the agreement vide

notice dated 22nd October, 2011. It is the Petitioner's contention that

the Tribunal has allowed the Respondent to wriggle out of the

consequences of the Deed of Settlement on a plea that it was made to

execute the said instrument by coercion or under financial duress,

neither of which the Respondent produced even a shed of evidence.

The Petitioner further contends that the findings of the Tribunal

refusing to give effect to the Deed of Settlement is perverse.

1-carbp-26-2021.doc

99. In my view, this ground of challenge to the impugned

award merits non acceptance in view of the Tribunal after

considering the pleadings and the evidence on record coming to the

conclusion that the delay in completion of the project was not

attributable to the Respondent. Although, the Tribunal has referred to

the pleadings of the Respondent / Claimant, wherein it was asserted

by the Respondent had been coerced into entering into the Deed of

Settlement by the Petitioner and there is an assertion of duress /

coercion raised by the Respondent, this was not the basis for the

Tribunal not giving importance to the Recital in the Deed of

Settlement. The Tribunal has considered the aforementioned Recital

in the Deed of Settlement as being a formal recital which is usually

found for maintaining good relations as long as the work is

completed and full payment is received.

100. The Supreme Court in Hindu Public (Supra) relied upon

by the Respondent has held that the evidence can be led to explain

any recital or statement in a document. In the said decision, it has

been held in paragraph 20 as under:-

"20. It is in the evidence of witnesses examined on behalf of the "Hindu Public" before the Assistant

1-carbp-26-2021.doc

Commissioner that para (a) of the aims and objects was introduced along with paragraph (b) so as to ensure that the request for grant of lease of this very land was not rejected by the Government on the ground that land could not be leased exclusively for religious purposes. On this aspect, the Assistant Commissioner rejected the oral evidence as inadmissible as it contradicts the recitals in the deed of registration of the Society in view of Section 91 and 92 of the Evidence Act, 1872. In our view, this is not correct in law. Oral evidence could be adduced to show that the recitals in a deed were nominal or were not intended to be acted upon or that they were not meant to alter the existing state of affairs. Oral evidence could therefore, be adduced to show that the Society's main concern was the celebration of the Durga Puja festivals etc. and that other activities were subsidiary. Therefore, the Deputy Commissioner was right in relying on this part of the oral evidence."

101. The Supreme Court has placed reliance upon Sections 91

and 92 of the Evidence Act, 1872 which provides that oral evidence

could be adduced to show that the recitals in a deed were nominal or

were not intended to be acted upon or that they were not meant to

alter the existing state of affairs.

102. This has also been held in Manickathammal & Ors.

(Supra), relied upon by the Respondent. In paragraph 5, the Madras

High Court has held that "There are cases and cases like the one in

the instant case, whereunder if a genuine doubt is raised about truth

1-carbp-26-2021.doc

of the recital then, Courts are not helpless but they are in a position

to make a further probe into the truth or falsity of the recital and

come to a conclusion".

103. The Tribunal has carried out the aforementioned exercise

of appreciating the evidence on record and thereafter deciding the

issue as to whether the delay in completion of the project was

attributable to the Respondent as recorded in the recital. The genuine

doubt of the Recital was raised by the Respondent in the arbitral

proceedings. It has been the Respondent's contention that the delay

was not attributable to it and was attributable to the Petitioner. It is

after appreciating the evidence on record that the Tribunal has held

in favour of the Respondent on the issue of delay in completion of the

project.

104. The Tribunal has held that the Petitioner had not

considered time to be of the essence of the contract, and this after

considering that the Petitioner had upon execution of the Deed of

Settlement not terminated the contract and instead from time to time

extended the time to complete the works by the Respondent. The

material on record shows that the Respondent completed the work at

1-carbp-26-2021.doc

site after the timeline set in the contract and Deed of Settlement by

attending to all snags pointed out by the Petitioner from time to time.

There were delays which were attributable to third parties and not to

the Respondent as borne out from the material on record.

Accordingly, the Tribunal has held that the invocation of the Bank

Guarantees by the Petitioner was wrongful and granted the Claim of

the Respondent.

105. The Tribunal has also appreciated the evidence on record

whilst granting the Claims in favour of the Respondent regarding

additional expenditure incurred by the Respondent during the

extended period of the contract and additional expenditure incurred

for retaining its machinery, tools and other equipment at site during

the extended period of contract. This upon finding that the delay is

not attributable to the Respondent. There was no cross examination

by the Petitioner on the claim of additional expenditure incurred by

the Respondent. These findings of the Tribunal are not only a

plausible but a correct view and in any event merits no interference

in a Section 34 Petition.

106. It is well settled that in a Section 34 Petition, the

1-carbp-26-2021.doc

evidence cannot be re-appreciated, particularly where the Tribunal

has appreciated the evidence and come to a possible view. In

Associate Builders (Supra) the Supreme Court has held in paragraph

33 that "A possible view by the arbitrator on the facts has necessarily

to pass muster as the arbitrator is the ultimate master of the quantity

and quality of evidence to be relied upon when he delivers his

arbitral award". A similar view has been taken in MSEDCL (Supra) at

paragraph 51 and Ssangyong Engineering (Supra) at paragraph 38 as

well as Delhi Airport Metro Express Pvt. Ltd. (Supra) at paragraph

29, which have been relied upon by the Respondent. The Petitioner

by raising such grounds of challenge to the impugned award is

treating the Section 34 Court as if it is a Court of First Appeal and

which the aforementioned decisions relied upon by the Respondent

militate against.

107. The Claims which have been raised by the Respondent

on completion of works; for additional built up area; for non tender

items; apart from the aforementioned Claim for delay are Claims

which have been considered by the Tribunal after appreciation of

evidence and thereafter finding in favour of the Respondent. Further,

the Tribunal has interpreted the contract and which interpretation is

1-carbp-26-2021.doc

a possible view which in no event can be disturbed by a Section 34

Court. Thus, it is not open for a Section 34 Court to go into the

details of each Claim and / or consider whether the Tribunal has

appreciated the evidence appropriately. This given the settled law

that a Section 34 Court can only disturb the Award where there is a

patent illegality on the face of the Award or perversity in the findings.

This Court finds that neither of the aforementioned have been

established by the Petitioner in their challenge to the Arbitral Award

under Section 34 of the Arbitration and Conciliation Act, 1996.

108. The findings on interest and costs by the Tribunal in

favour of the Respondent is also upon appreciation of the evidence on

record viz. that the delay was not attributable to the Respondent.

Hence these findings also call for no interference by a Section 34

Court.

109. I further find that the Tribunal having come to the

conclusion that the delay was not attributable to the Respondent has

rejected the counter claim of the Petitioner for liquidated damages

and this too after appreciating of evidence and interpretation of

contract which interpretation is a possible view, and hence this Court

cannot interfere with such findings of the Tribunal.

1-carbp-26-2021.doc

110. I am also of the view that the finding on adverse

inference to be drawn against the Petitioner for non production of the

best evidence in defence, by upholding the Respondent's claim that

the Petitioner failed to timely provide the GFC drawings are on an

appreciating of evidence. Further, it is settled law that where a party

fails to produce evidence which could have produced to prove a

particular fact that it asserts then that fact of non production of the

same ought to be presumed as the evidence being unfavourable to it

and an adverse inference with respect to the same ought to be drawn

as per Section 114(g) of the Evidence Act.

111. I find no valid grounds of challenge to the impugned

Award has been raised in the Petition by the Petitioner. This upon

considering that the grounds of challenge do not fit within the

parameters of the Section 34 of the Arbitration and Conciliation Act.

112. Accordingly, the Commercial Arbitration Petition is

dismissed. There shall be no order as to costs.

[ R.I. CHAGLA J. ]

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter