Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Godrej And Boyce Mfg Co Ltd And Anr vs Bmc And Ors
2024 Latest Caselaw 25851 Bom

Citation : 2024 Latest Caselaw 25851 Bom
Judgement Date : 19 September, 2024

Bombay High Court

Godrej And Boyce Mfg Co Ltd And Anr vs Bmc And Ors on 19 September, 2024

Author: M.S.Sonak

Bench: M.S.Sonak

2024:BHC-OS:14332-DB                                        Godrej & Boyce Mfg. Co.Ltd. and Anr. v The
                                                     Municipal Corporation of Greater Mumbai and Ors.
                                                                                 WP-1507-2005-F.docx




                                                                                                Darshan Patil




                              IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                    ORDINARY ORIGINAL CIVIL JURISDICTION
                                          WRIT PETITION NO. 1507 OF 2005


                       1.    GODREJ & BOYCE MFG. CO. LTD.,
                             a Public Limited Company having its
                             Registered Office at Pirojshanagar
                             Vikhroli, Mumbai 400 079
                       2.    NAYAN A. SHAH,
                             through MAYFAIR HOUSING its
                             partner of Mumbai, Indian
                             Inhabitant, having his office at 272,
                             Prabhu Prabhu, 9th & 11th Junction
DARSHAN                      Road, Khar (West), Mumbai - 400
PRAKASH
PATIL                        052                                                       ...PETITIONERS
Digitally signed by
DARSHAN PRAKASH
PATIL
Date: 2024.09.20
                               ~ VERSUS ~
11:26:57 +0530


                       1.    THE MUNICIPAL CORPORATION OF
                             GREATER MUMBAI,
                             a statutory Corporation constituted
                             under the Bombay Municipal
                             Corporation Act, 1988, having its
                             office at Mahapalika Marg,
                             Mahapalika Bhavan, Mumbai - 400
                             001
                       2.    THE MUNICIPAL COMMISSIONER,
                             having his office at Mumbai
                             Municipal Corporation of Greater
                             Mumbai, Mahapalika Bhavan,
                             Mahapalika Marg, Mumbai - 400
                             001




                                                          Page 1 of 9


                      ::: Uploaded on - 20/09/2024                         ::: Downloaded on - 27/09/2024 05:45:24 :::
                                       Godrej & Boyce Mfg. Co.Ltd. and Anr. v The
                               Municipal Corporation of Greater Mumbai and Ors.
                                                           WP-1507-2005-F.docx




 3.    THE EXECUTIVE ENGINEER,
       Water Works (Planning & Research)
       Room No.33, 3rd Floor, "B" Ward
       Municipal Office, 121, Ramchandra
       Bhatt "X" Lane, Opposite J.J.
       Hospital, Byculla, Mumbai-400009
 4.    THE DEPUTY CHIEF ENGINEER
       (ROADS),
       Easter Suburbs, Pant Nagar, Garage
       Bldg, 5th Floor, Behind BEST Depot,
       Ghatkopar (East), Mumbai - 400
       075                                                     ...RESPONDENTS

 A PPEARANCES
 FOR THE PETITIONERS                 Mr Surel Shah, Senior Counsel,
                                          with Mr Amrut Joshi, Yazad
                                          Udwadia, Mr Arun Panickar,
                                          Vinay Nair, i/b Arun
                                          Panickar.
 FOR THE RESPONDENT-BMC Mr A Y Sakhare, Senior Counsel,
                             with Mr Kunal Waghmare,
                             i/b Mr S K Sonawane.


                                      CORAM : M.S.Sonak &
                                              Kamal Khata, JJ.
                               RESERVED ON : 12 September 2024
                           PRONOUNCED ON : 19 September 2024
 JUDGMENT (Per MS Sonak J):

-

1. Heard learned counsel for the parties.

2. The petitioners, by instituting this petition, have sought the following substantive relief in this petition:-

Godrej & Boyce Mfg. Co.Ltd. and Anr. v The Municipal Corporation of Greater Mumbai and Ors.

WP-1507-2005-F.docx

"(a) That this Hon'ble Court be pleased to issue a Writ of Mandamus or a Writ in the nature of Mandamus or any other appropriate, Writ direction or order in exercise of its Power under Article 226 of the Constitution of India calling for the records of the case and after examining the legality and propriety of the case under which the demand towards road opening and back filing charges for excavation work (Reinstatement charges) by Demand Notice dated 10th May 2005 (Exhibit "F") for Rs.48,36,150/- towards reinstatement charges and Rs.50,000/- towards penalty and the stop work notice dated 28th March 2005 (Exhibit "E") issued by the Respondent No.4 be quashed and set aside."

3. The learned Vacation Judge (Coram: R.S. Mohite J.), on 18 May 2005, made the following order granting limited interim relief to the petitioners:-

"1. The Advocate for the petitioners states that he is willing to continue to lay down the water mains in accordance with the permission and terms contained in the permission dated 10.5.2005 except Condition No.10. He makes a statement that an amount of Rs.12/-lacs are lying with the Corporation. In so far as Condition No.10 is concerned, he will give bank guarantee of Rs.36/- lacs in favour of the Prothonotary and Sr. Master of this court within a period of one week from today. He further states that he will complete the aforesaid work within 20 days from today. In view of this, list the matter on 8.6.2005. It is directed that the B.M.C will not obstruct for laying down the water mains. The bank guarantee will be without prejudice to the rights and contentions of the parties.

2. All concerned to act on the copy of this order duly authenticated by the Court Stenographer of this court."

4. After that, the rule was issued in this petition on 18 April 2006, and the petitioners were directed to keep the bank guarantee they had furnished alive pending the final disposal of the petition.

Godrej & Boyce Mfg. Co.Ltd. and Anr. v The Municipal Corporation of Greater Mumbai and Ors.

WP-1507-2005-F.docx

5. Mr Shah learned Senior Advocate for the petitioners submitted that Brihanmumbai Mahanagar Palika ("BMC") had earlier issued an NOC for laying water mains. However, a stop work order was issued after the petitioner commenced the work. He submitted that later, on 10 May 2005, formal permission was granted by the BMC subject to 10 conditions. Mr Shah submitted that one of the conditions was that the petitioners should backfill the trenches with granular material to cover up the water pipelines. Since the petitioners were directed to reinstate the trenches with backfilling, there was no question or justification for levying reinstatement charges of Rs.48,36,150/- and a penalty of Rs.50,000/- as the 10th condition in the permission dated 10 May 2005.

6. Mr Shah submitted that there was no statutory provision based upon which the above levy towards reinstatement charges or penalty could be justified. He submitted that the condition was absurd and illogical, given that the petitioners were directed to reinstate the trenches and restore the road to its original condition. Mr Shah submitted that the petitioners furnished the necessary bank guarantee and completed laying the water mains. He submitted that since the 10th condition was arbitrary, absurd and illogical, the BMC should not be permitted to enforce the same and insist upon payment of reinstatement charges and penalty. He submitted that even the principles of natural justice and fair play were not complied with before levying the above amount on the petitioners.

Godrej & Boyce Mfg. Co.Ltd. and Anr. v The Municipal Corporation of Greater Mumbai and Ors.

WP-1507-2005-F.docx

7. For the above reasons, Mr Shah submitted that the rule in this petition may be made absolute and the bank guarantee furnished by the petitioners discharged or returned to them.

8. Mr Sakhare, the learned Senior Advocate for the BMC, submitted that the petitioners commenced laying of water mains without obtaining any permission from the BMC. He submitted that even the works were not undertaken or completed in terms of the permission dated 10 May 2005. Mr Sakhare submitted that letters were written to the petitioners from time to time, pointing out the defaults and deficiencies. Still, no cognisance was taken of such defaults and deficiencies. He submitted that even the work was not completed within the prescribed period. He submitted that as a result of such delays, defaults, and deficiencies, other BMC projects suffered.

9. Mr Sakhare relied upon the policy guidelines to grant permissions to utility and municipal agencies for excavation and reinstatement after that. In particular, he relied upon the schedule for penalties and submitted that there was provision for recovery of actual costs where there were damages to Municipal Utility or other Utilities. He submitted that clause 10 of the permission, dated 10 May 2005, was consistent with such policy guidelines that were binding upon the petitioners.

10. Mr Sakhare submitted that in the above circumstances, the BMC was justified in demanding reinstatement charges or levying a penalty of Rs.50,000/-- on the petitioners.

Godrej & Boyce Mfg. Co.Ltd. and Anr. v The Municipal Corporation of Greater Mumbai and Ors.

WP-1507-2005-F.docx

11. Mr Sakhare submitted that this petition involves disputed questions of fact. He submitted that the petitioners had pleaded a false case, even though the record shows that the petitioners delayed and defaulted on the execution of works, thereby causing severe damage to the BMC and public interest.

12. The rival contentions now fall for our determination.

13. The petitioners have pleaded that they commenced the work of laying the water mains after obtaining permission from the BMC. Prima facie, this may not be entirely correct. The stop work orders were issued after the work commenced, and the petitioners did stop the work and apply for permission.

14. The permission was granted on 10 May 2005. The Petitioners do not quarrel with 9 out of the 10 conditions in the permission dated 10 May 2005. However, the petitioners have a serious objection to the 10th condition, which reads as follows:-

"10) The necessary R.I. charges of Rs.48,36,150/- and a penalty of Rs.50,000/- shall be paid in the office of Dy.

Chief Engineer (Roads) Eastern Suburbs, Pant Nagar Garage Bldg., 5th Floor, Behind B.E.S.T. Depot, Ghatkopar (East), Mumbai -400 075."

15. The BMC has justified the 10th condition by contending that the petitioners commenced works without permission and, further, even the works were not completed within the assigned time or by following all the conditions (excluding the 10th condition).

Godrej & Boyce Mfg. Co.Ltd. and Anr. v The Municipal Corporation of Greater Mumbai and Ors.

WP-1507-2005-F.docx

16. There are assertions on either side supporting their respective versions. Photographs have also been produced by both parties in support of their respective versions. There are seriously disputed questions of fact as to whether petitioners commenced work after obtaining permission, whether the petitioners completed the works within the prescribed period, whether the petitioners complied with conditions subject to which permissions were granted to them and so on. Some decision would be necessary on all these questions of fact before we can rule upon the validity or otherwise of the BMC's impugned demand. We cannot decide on all these questions exercising our extraordinary but summary jurisdiction under Article 226 of the Constitution of India. Decisions on such issues may be necessary, but we cannot adjudicate such questions under the summary proceedings.

17. Accordingly, it would not be appropriate for us to decide all such disputed questions in this petition even though the rule was issued on 18 April 2006. Such questions are best adjudicated in a Suit, where both parties can lead evidence supporting their respective versions. Therefore, we decline to adjudicate upon this petition's disputed questions of fact. This petition will, hence, have to be dismissed by granting the petitioners liberty to institute a Suit, inter alia, to question the levy of R.I. charges of Rs.48,36,150/- and penalty of Rs.50,000/-.

18. If the petitioners institute a suit within two months from today, then the trial court must consider the period spent by the petitioners bona fide in pursuing this petition. This

Godrej & Boyce Mfg. Co.Ltd. and Anr. v The Municipal Corporation of Greater Mumbai and Ors.

WP-1507-2005-F.docx

petition was instituted on 13 May 2005 and is now being disposed of on 19.09.2024. The petitioners spent This entire period in bona fide pursuing their claims. Therefore, the trial court must give due credence to this significant circumstance. Mr Sakhare, learned Senior Advocate for the BMC, also, quite reasonably, admitted that the petitioners were bona fide pursuing this matter before this court.

19. As noted earlier, this court granted ad-interim relief in this matter on 18 May 2005. Based on this ad-interim relief, the petitioners were permitted to proceed with the works upon furnishing the bank guarantee. The rule was issued in this matter on 18 April 2006 with directions to the petitioners to keep the bank guarantee alive pending the final disposal of this petition. Mr Shah submitted that the bank guarantee has been kept alive.

20. Accordingly, though we are disposing of this petition and as a consequence of such disposal, we would have had to permit the BMC to encash the bank guarantee, we direct the petitioners to keep such bank guarantee alive but restrain the BMC from encashing such bank guarantee for three months from today. Meanwhile, if the petitioners institute a suit and obtain ad-interim or interim orders, there will be no question of the BMC encashing such bank guarantee. However, if no suit is instituted with prior notice within two months from today and no ad-interim or interim order is obtained within three months, the BMC would be entitled to encash the bank guarantee.

Godrej & Boyce Mfg. Co.Ltd. and Anr. v The Municipal Corporation of Greater Mumbai and Ors.

WP-1507-2005-F.docx

21. The observations, if any, in this judgement and order or in the interim order made by the learned Vacation Judge on 18 May 2005 should not influence the trial Court in deciding the suit if instituted by the petitioners. The suit must be decided based on the evidence laid by the parties and by following the law. All contentions of all parties are left open.

22. This petition is disposed of in the above terms without any orders for costs. All concerned to act on an authenticated copy of this judgment.

 (Kamal Khata, J)                                            (M. S. Sonak, J)








 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter