Citation : 2024 Latest Caselaw 2734 Bom
Judgement Date : 30 January, 2024
2024:BHC-AUG:2803-DB
WP-933-2024.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO.933 OF 2024
Samarth Infra-Tech Services Pvt. Ltd.
Registered Office : Office No.40 and 41,
5th Floor, Lokmanya House,
Lokmanya Colony, Opp. Kothrud Police
Station, Paud Road, Kothrud,
Pune - 4011038
Through its General Manager .. PETITIONER
VERSUS
1. The State of Maharashtra,
Through its Principal Secretary,
Water Resources Department,
Mantralaya, Mumbai-32.
2. Godavari Marathwada Irrigation
Development Corporation,
Sinchan Bhavan, Jalna Road,
Chh. Sambhajinagar 431005,
Through the Executive Director.
3. The Executive Engineer,
Minor Irrigation Division No.1,
Sinchan Bhavan, Jalna Road,
Chhatrapati Sambhajinagar-431005.
4. Shri Ashish s/o Shirish Waghchaure,
Age: Major, Occu.: Contractor,
R/o. Deogiri Keshardeep,
Near Bhagatsingnagar, Harsul,
Chhatrapati Sambhajinagar-431008. .. RESPONDENTS
...
Mr. S. T. Shelke, Advocate for petitioner.
Mr. P. S. Patil, AGP for Respondent No.1 - State.
Mr. Hemant Dhage, Advocate for Respondent Nos.2 and 3.
Mr. S. G. Bhalerao, Advocate for Respondent No.4.
...
[1]
WP-933-2024.odt
CORAM : SMT. VIBHA KANKANWADI AND
S. G. CHAPALGAONKAR, JJ.
DATE : JANUARY 30, 2024.
ORDER (Per Smt. Vibha Kankanwadi, J.) :
-
. By invoking the constitutional powers of this Court under Article
226 of the Constitution of India, the petitioner has prayed for following
relief :-
"B) Quash and set aside the decision of respondent No.3 of holding the petitioner as disqualified and the respondent No.4 as qualified as per Exhibit-B and the consequent Work Order dated 27.12.2023 at Exhibit-C issued by respondent No.3 in favour of respondent No.4 and thereafter, further direct the respondent No.3 to open the Tender (Financial Bid) of the petitioner holding him as qualified in Technical Bid and for that purpose issue a necessary writ or order."
2. The facts leading to the present petition are that the petitioner is
a private limited company. Respondent No.3 published the B-1 Tender
Notice thereby inviting the tenders from the competent bidders
through E-Tender System (Online) for the work of preparation of
detailed construction plan for pipe distribution network system
including necessary command survey, linear survey for pipe laying,
chak planing, designing of pipe network and preparation of estimate
for Canal No.1 RD to 37 km of Bramhagavhan L.I.S. Part-II, Taluka
WP-933-2024.odt
Paithan, District Chhatrapati Sambhajinagar. The estimated cost of this
work is Rs.94,12,755/- (Work Portion - Rs.79,09,878/- + GST and
Insurance Rs.15,02,877/-). It is mentioned in the tender notice that
all the information regarding the E-tender is available on the
Government Website and on the notice board of the Divisional Office.
The tender documents were to be uploaded from the Government
Website. It is further mentioned that the contractor/bidder has to
ensure that the First Envelope (Technical Bid) shall contain the
documents as enlisted in the tender notice. It is further mentioned
that all the photocopies submitted in connection with tender shall be
attested by the Gazetted Officer, otherwise their tender will not be
considered and Envelope No.2 will not be opened. Further, it is
mentioned that the first envelope (Technical Bid) was to accompany
the documents which are stated in paragraph No.3 of the present writ
petition. Thereafter, as per the scheduled program, E-tenders were
opened on 07.12.2023 and it appears that only four bidders have
submitted their tenders. The petitioner and one Arun Idhate came to
be disqualified and respondent No.4 and one Sandip Gore came to be
qualified in the technical bid on 22.12.2023. Thereafter respondent
No.3 issued the work order dated 27.12.2023 to respondent No.4,
which was uploaded on the website on 29.12.2023. The petitioner
thereafter made representations to all the authorities bringing to their
notice that the petitioner has been erroneously declared as disqualified
WP-933-2024.odt
in the technical bid and respondent No.4 has been held eligible for the
tender. It is the case of the petitioner that respondent No.4 had not
submitted the copies of the documents duly attested by the Gazetted
Officer as was asked for and, therefore, his technical bid could not
have been considered and opened. So also the respondent No.4 had
not submitted the certificate regarding machinery items. It is the
further case of the petitioner that the respondent No.4 has not
submitted the EPF Clearance Certificate. It is also contended that the
respondent No.4 had not submitted the work certificates of the
quantity and magnitude of Grid Survey of at least 7393 Hectare of
land issued by the Executive Engineer as mentioned in the documents
list clause No.l of Envelope No.1, but submitted the certificate of a
private entity. It is contended that two reasons have been assigned
for rejection of the technical bid of the petitioner i.e. Empanelment
certificate was not submitted and the documents are not digitally
signed. Further, it is contended that the petitioner has submitted
registration certificate of Maharashtra Public Works Department. All
the tender documents submitted by the petitioner are signed by the
petitioner and all the certificates submitted by the petitioner are
signed by the Executive Engineer of Maharashtra Jeevan Pradhikaran,
who is a Gazetted Officer. In view of this it was not necessary to sign
the documents digitally and the so called defect is not of substantial
nature. The petitioner contends that his tender was complete in all
WP-933-2024.odt
respects and has been rejected mala fide by respondent No. 3 only
with a view to favour repsondent No.4. Hence, this petition.
3. Heard learned Advocate Mr. S. T. Shelke for the petitioner,
learned AGP Mr. P. S. Patil for respondent No.1 - State, learned
Advocate Mr. Hemant Dhage for respondent Nos.2 and 3 and learned
Advocate Mr. S. G. Bhalerao for respondent No.4.
4. Learned Advocate for the petitioner submits that respondent
No.4 had not complied with the mandatory requirement clause No.'k'
in Envelope No.1 i.e. scanned copy of Employees Provident Fund
registration and its clearance, still respondent No.4 has been held to
be qualified and the work order has been issued. The petitioner was
holding the requisite certificate of empanelment. He relies on the
Government Resolution dated 18.10.2023 and submits that necessary
time ought to have been given in view of the said Government
Resolution. He has also produced on record the circular issued by
Maharashtra Jivan Pradhikaran dated 08.04.2021 in which the work
distribution was made and thereby Panel of Administrative Advisors
were fixed for Aurangabad. They had appointed the petitioner. He has
also filed the other letters/orders showing that the petitioner was
appointed as consultant/advisor. The petitioner was also appointed as
advisor by other States. Therefore, it cannot be said that the petitioner
was not qualified. The disqualification of petitioner is improper. So
WP-933-2024.odt
also, holding respondent No.4 as qualified is also improper and
deserves to be set aside.
5. The learned Advocate for respondent No.4 submitted that the
work order has been issued and 90% of the work is completed. He
relied on M/s. N.G. Projects Limited Vs. M/s. Vinod Kumar Jain, [2022
LiveLaw (SC) 302] and M/s. Tirupati Construction Vs. The State of
Maharashtra and Others, [2021 (3) ALL MR 258].
6. As aforesaid, the petition is on two counts, firstly to challenge
the petitioners own disqualification and secondly, to challenge the
qualification of respondent No.4. We would like to rely on the decision
in M/s. N.G. Products Limited (Supra), in which the earlier decisions
have been taken note of and it has been observed that :-
"23. In view of the above judgments of this Court, the Writ Court should refrain itself from imposing its decision over the decision of the employer as to whether or not to accept the bid of a tenderer. The court does not have the expertise to examine the terms and conditions of the present-day economic activities of the State and this limitation should be kept in view. Courts should be even more reluctant in interfering with contracts involving technical issues as there is a requirement of the necessary expertise to adjudicate upon such issues. The approach of the Court should be not to find fault with magnifying glass in its hands,
WP-933-2024.odt
rather the Court should examine as to whether the decision-making process is after complying with the procedure contemplated by the tender conditions. If the Court finds that there is total arbitrariness or that the tender has been granted in a mala fide manner, still the Court should refrain from interfering in the grant of tender but instead relegate the parties to seek damages for the wrongful exclusion rather than to injunct the execution of the contract. The injunction or interference in the tender leads to additional costs on the state and is also against public interest. Therefore, the State and its citizens suffer twice, firstly by paying escalation costs and secondly, by being deprived of the infrastructure for which they present-day Governments are expected to work."
7. We are aware of the decision in Jagdish Mandal Vs. State of
Orissa, (2007) 14 SCC 517, wherein Hon'ble Supreme Court has held
that :-
"22. Judicial review of administrative action is intended to prevent arbitrariness, irrationality; unreasonableness, bias and mala fides. Its purpose is to check whether choice or decision is made "lawfully"
and not to check whether choice or decision is "sound". When the power of judicial review is invoked in matters relating to tenders or award of contracts, certain special features should be borne in mind. A contract is a commercial transaction. Evaluating tenders and awarding contracts are essentially commercial
WP-933-2024.odt
functions. Principles of equity and natural justice stay at a distance. If the decision relating to award of contract is bona fide and is in public interest, courts will not, in exercise of power of judicial review, interfere even if a procedural aberration or error in assessment or prejudice to a tenderer, is made out. The power of judicial review will not be permitted to be invoked to protect private interest at the cost of public interest, or to decide contractual disputes. The tenderer or contractor with a grievance can always seek damages in a civil Court. Attempts by unsuccessful tenderers with imaginary grievances, wounded pride and business rivalry, to make mountains out of molehills of some technical/procedural violation or some prejudice to self, and persuade courts to interfere by exercising power of judicial review, should be resisted. Such interferences, either interim or final, may hold up public works for years, or delay relief and succour to thousands and millions and may increase the project cost manifold. Therefore, a Court before interfering in tender or contractual matters in exercise of power of judicial review, should pose to itself the following questions :
(i) Whether the process adopted or decision made by the authority is mala fide or intended to favour someone;
or Whether the process adopted or decision made is so arbitrary and irrational that the court can say: "the decision is such that no responsible authority acting reasonably and in accordance with relevant law could
WP-933-2024.odt
have reached";
(ii) Whether public interest is affected.
If the answers are in the negative, there should be no interference under Article 226. Cases involving blacklisting or imposition of penal consequences on a tenderer/contractor or distribution of State largesse (allotment of sites/shops, grant of licences, dealerships and franchises) stand on a different footing as they may require a higher degree of fairness in action."
8. Thus, taking into consideration the well settled law on this point,
we have limited scope. Since the petition requires attention on two
counts i.e. the petitioner's own disqualification and qualification of
respondent No.4, as aforesaid, we would like to deal with the
disqualification point first, for discussion.
9. Perusal of the tender notice would show that it was stated that
Envelope No.1 should contain the list of documents given thereunder.
Point 'q' was in respect of, Empanelment Certificate in the name of
sole bidder as a working consultant/Independent Engineer with any
Government Department for survey, hydraulic design and consulting
works is mandatory. It is stated that no such certificate was attached.
The petitioner has not produced any such document, which he has
now tendered across the bar i.e. the certificate showing that he was
WP-933-2024.odt
empaneled consultant with various authorities including Maharashtra
Jivan Pradhikaran, Government of Bihar, Uttar Pradesh State Industrial
Development Authority, Gujarat Urban Development Mission,
Government of Jharkhand, Madhya Pradesh Jal Nigam, Environmental
Planning and Coordination Organization. In spite of having documents
with him if those were not produced, then the petitioner will have to
blame itself. Condition No.23 of the tender notice reads thus :-
23. fufonk dkxni= lkscrps udk'ks da=kVnkjkus Lok{kfjr d#u lknj u dsY;kl [kkyhy vk'k;kps ca/ki= n~;kos- "ladsrLFkGkojhy udk'ks eh ikfgys vkgsr rh fufonk dkxni=pkp Hkkx vlqu ;k loZ ckchapk fopkj d#u eh fufonk Hkjyh vkgs- ek>h fufonk eatqj >kY;kl lqj{kk jDde Hk#u dk;kZjaHk vkns'k ?ks.;kiwohZ] udka'kkoj eh lg~;k d#u miyC/k d#u nsbZu-"
Therefore, the petitioner ought to have shown that this condition
is also complied with by him. The said tender was in respect of
preparation of detailed construction plan for pipe distribution network
system and now it is said that respondent No.4 has completed 90% of
the work. At this stage, the same cannot be disturbed and interfered
with. The petitioner would be at liberty to agitate in an appropriate
proceeding that respondent No.4 ought not to have been granted bid
by showing as to what damages the petitioner has suffered. When the
petitioner himself was unsuccessful, he cannot raise the objection in
respect of qualification of another bidder, unless it is shown that his
WP-933-2024.odt
disqualification has resulted in the damages.
9. In view of the above, we are of the opinion that no case is made
out for exercising the constitutional powers of this Court under Article
226 of the Constitution of India.
10. Hence, the Writ Petition stands dismissed.
[ S. G. CHAPALGAONKAR ] [ SMT. VIBHA KANKANWADI ]
JUDGE JUDGE
scm
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!