Citation : 2023 Latest Caselaw 5048 Bom
Judgement Date : 6 June, 2023
2023:BHC-OS:4569
1/49 CARBP-264-22 GRP.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
COMM. ARBITRATION PETITION NO.264 OF 2022
Rajesh Sharma & Anr. .. Petitioners
Versus
Uma Constructions & Ors. .. Respondents
WITH
COMM. ARBITRATION PETITION NO.185 OF 2022
Deepa Sharma & Anr. .. Petitioners
Versus
Uma Constructions & Ors. .. Respondents
WITH
COMM. ARBITRATION PETITION (L) NO.16413 OF 2022
Deepa Sharma & Anr. .. Petitioners
Versus
Uma Constructions & Ors. .. Respondents
WITH
COMM. ARBITRATION PETITION (L) NO.7131 OF 2022
Shakan Lalchand Surtai & Ors. .. Petitioners
Versus
Uma Constructions & Ors. .. Respondents
Niti/M.M.Salgaonkar
::: Uploaded on - 09/06/2023 ::: Downloaded on - 10/06/2023 01:11:07 :::
2/49 CARBP-264-22 GRP.odt
WITH
CONTEMPT PETITION (L) NO.6695 OF 2022
Sunny Mukesh Ramani .. Petitioner
Versus
Rajesh Gaurishankar Sharma & Ors. .. Respondents
WITH
ARBITRATION PETITION (L) NO.8860 OF 2020
Kishan Hukumchand Kappor & Anr. .. Petitioners
Versus
Uma Constructions & Ors. .. Respondents
WITH
ARBITRATION PETITION (L) NO.8861 OF 2020
Hema Amarlal Ahuja .. Petitioner
Versus
Uma Constructions & Ors. .. Respondents
WITH
ARBITRATION PETITION (L) NO.8869 OF 2020
Srichand Waduram Ahuja & Anr. .. Petitioners
Versus
Uma Constructions & Ors. .. Respondents
...
Niti/M.M.Salgaonkar
::: Uploaded on - 09/06/2023 ::: Downloaded on - 10/06/2023 01:11:07 :::
3/49 CARBP-264-22 GRP.odt
Mr Rohan Cama, a/w Mr Piyush Raheja, Mr. Akash Menon, Mr
Vishal Pattabiraman, Ms. Bency Ramkrishanan, Mutahhar
Khan i/b Mr Veer Kantariya, Advocates for the Petitioner in
CARBP No.264/20, CARBP No. 185/2022 and for the
Respondent No.2 & 3 in CARBP(L) No.7131/2022, ARBP(L)
No.8860/2020, ARBP(L) No.8861/2020, ARBP(L)
No.8869/2020 and for the Respondent No. 3 & 4 in CARBP
(L)No.16413/2022.
Mr Sharan Jagtiani, Senior Advocate a/w Minal Jaiwant
Chandnani, Advocates for the Petitioner in CARBP
(L)No.16413/2022.
Dr. Birendra Saraf Senior Advocate a/w Ms. Naira Jeejeebhoy
a/w Ms Pooja Gera i/b Nitin Parkhe, Advocates for the
Respondent No. 4 in CARBP(L) No.7131/2022, ARBP(L)
No.8860/2020,ARBP(L)No.8861/2020,ARBP(L) No.8869/
2020 and for the Respondent No. 2 in CARBP
No.264/2022,CARBP No. 185/2022,CARBP (L)No.16413/2022
.
Mr.Pratik Jani a/w Ms. Princee Vaishnav i/b Prime Legem for
the Petitioner in ARBP(L) No.8860/2020, ARBP(L)
No.8861/2020, ARBP(L) No.8869/2020.
...
CORAM: BHARATI DANGRE, J.
RESERVED ON : 02nd DECEMBER, 2022 PRONOUNCED ON : 06th JUNE, 2023
JUDGMENT :-
1. The dispute involved in the three Commercial Arbitration Petitions being fled as petition numbers CARBP No.264/2022, CARBP No.185/2022 and CARBP No.16341/2022, revolve around the affairs and assets of the partnership frm M/s. Uma Constructions (hereinafter referred to as 'the frm'). The frm
Niti/M.M.Salgaonkar
4/49 CARBP-264-22 GRP.odt
presently comprises of three partners, Mr Rajesh Sharma, Mr Sunil Sharma and Mr Sunny Ramani. Mr Rajesh Sharma and Mr Sunil Sharma (hereinafter referred to as Sharmas/Sharma brothers) stake interest to the tune of 25% in the said frm whereas Mr Sunny Ramani (hereinafter referred to as 'Ramani') claim to have 50% share in the profts and loss of the frm.
The frm is a single venture partnership constituted to redevelop a building - Hamrahi Co-operative Housing Society Limited (Hamrahi) located at 15th Road, Khar Pali Road, Khar (West), Mumbai.
2. The dispute between the partners arises out of the redevelopment of the said building and the three distinct petitions cumulatively challenge two orders passed by the sole Arbitrator in form of interim orders, pending the arbitration proceedings, which was made over to the Arbitrator by order dated 06.11.2020, while dealing with the counter petitions fled by the petitioners, i.e. the two Sharma brothers on one hand and Mr Ramani on the other, which was alleged to be a counterblast to the petitions fled under Section 9 of the Arbitration and Conciliation Act, 1996. By order dated 06.11.2020, this Court directed the Arbitral Tribunal to adjudicate the disputes between the petitioners on one hand and the respondent no.2, Ramani, on the other.
3. Pursuant to the said order appointing the arbitral Tribunal the Commercial Arbitration Petition fled by the
Niti/M.M.Salgaonkar
5/49 CARBP-264-22 GRP.odt
Sharma brothers and that by the respondent no.2 were converted into application under Section 17 of the Arbitration and Conciliation Act, 1996 and the interim orders came to be passed in sequence, the frst being passed on 31.03.2021 by which the learned Arbitrator issued certain directions to the Sharmas and Ramani, which included a direction to disclose certain information on oath and extend their cooperation to the Chartered Accountant in drawing of accounts for a particular period. A restraint order was imposed, which restrained both parties from dealing with selling, transferring, alienating, disposing of, encumbering and/or creating third-party rights in respect of the assets of the frm and particularly in respect of certain fats including fat no.1301 in Hamrahi Building. A further direction restrained the respective wives of the Sharma brothers from using, occupying, carrying out any ftout work or selling, transferring, alienating, disposing of, encumbering or creating third-party rights in fat no.1301.
The Sharmas were cast with the income tax liability as refected in the income tax notice to be discharged within a period of four weeks and they were directed to fle an affdavit to that effect.
The application of Ramani, for appointment of Receiver and in the alternative relief for attachment of the frm's assets came to be rejected.
4. The second order which is subject to challenge through two petitions is the order dated 17.05.2022, which comes by
Niti/M.M.Salgaonkar
6/49 CARBP-264-22 GRP.odt
way of a subsequent development and its genesis lies in the alleged breach of the order dated 31.03.2021 by the Sharmas and it was premised before the Tribunal on behalf of Ramani that subsequent to the passing of the earlier order by the Tribunal there is a complete breakdown in the affairs of the frm and it has become necessary to safeguard the interest of the frm by appointing a Receiver for the entire building and also to ensure completion of the balance civil works/conduct the affairs of the frm including obtaining the balance MCGM permissions, selling the remaining units, handing over of fats to the third party purchasers and ensuring that the proper accounts are maintained.
After a serious contest to the said reliefs by the Sharmas, the Tribunal granted the relief as prayed by Ramani, by appointing a private Receiver to safeguard and protect the disputed fats and directing the Receiver to complete the balance/unfnished work in the disputed fats through the current contractor and/or by appointing a new contractor. The Receiver was directed to continue to be in possession of the disputed fats pending the arbitration proceedings and take all necessary steps to ensure that no further third-party rights are created in respect of the said fats.
5. Before I adjudicate the legality and propriety of the two impugned orders, it is necessary to consider the background facts in detail, since the dispute now at this time is not only restricted to the partners of the said frm but has also brought within its sweep several purchasers of the respective fats in
Niti/M.M.Salgaonkar
7/49 CARBP-264-22 GRP.odt
the said building, whose construction work is now complete and even the Occupation Certifcate is received on 14.03.2022.
6. Through the learned Counsel Mr Rohan Cama appearing for the Sharma brothers in Commercial Arbitration Petition No.264/2022 and Mr Sharan Jagtiani, who represents the petitioners in Commercial Arbitration Petition No.185/2022 and 16413/2022 fled by the wives Mrs Deepa Sharma and Mrs Sangeeta Sharma and upon also hearing Ms Naira Jeejeebhoy representing Ramani, the facts are assimilated from distinct proceedings and the necessary facts are set out in the following paragraphs.
7. By a Deed of Admission, Retirement and Continuation of Partnership executed on 01.04.2011, by Mr Rajesh Gaurishanker Sharma, in his capacity as continuing partner, Mr Sunny Ramani came to be inducted as a partner upon one Mr Chandru Chugani retiring from the existing partnership carrying business through the frm named and styled as M/s. Uma Constructions in terms of the Agreement of Partnership dated 07.04.2008 and supplementary Deed of Partnership dated 01.04.2010.
The continuing partners and retiring partners agreed to an incoming partner in the partnership business with effect from 01.04.2011 on the basis of certain terms and conditions mutually agreed between the parties. Upon the retirement of the "retiring partner" the continuing partners mutually agreed to carry on running the partnership business as a going
Niti/M.M.Salgaonkar
8/49 CARBP-264-22 GRP.odt
concern as per book values of all the assets, and liabilities of the said partnership business as on the close of business hours on 31.03.2011. The continuing partners agreed to continue the partnership frm M/s. Uma Constructions and take over the existing partnership business with all its assets, liabilities and obligations, if any, at their respective book values as on 31.03.2011. The retiring partner was permitted to retire with no rights, titles, claims and/or interest of whatsoever nature, in or against the partnership business.
The continuing partners and the incoming partners were conferred with full rights and liberty to collect the assets of the partnership business and to settle all the accounts, matters and things relating to the partnership business. The continuing partners and the retiring partners also agreed by the said Deed to get completed all the pending Income Tax and Sales Tax Assessments and all allied matters relating to the partnership business and agreed to bear their respective income tax liabilities, if any, including a share in the registered frm tax payable up to the date of the retiring partner, that is up to 31.03.2011.
8. The above Partnership Deed provided for the share of remuneration to the extent of 50.00% for Mr Rajesh Sharma and 50.00% for Mr Sunny Ramani.
The Deed also provided for dissolution of the partnership by mutual consent of the parties and it also prescribed that after payment of liabilities, the assets of the partnership would
Niti/M.M.Salgaonkar
9/49 CARBP-264-22 GRP.odt
be mutually distributed amongst the partners according to their respective proft-sharing ratio.
9. The Deed comprised of an arbitration clause which contemplated that the differences, if any, between the partners shall be resolved through mutual discussion but if they could not be settled, the dispute shall be referred for arbitration to the sole Arbitrator and the decision and order of the Arbitrator shall be binding on both the parties.
10. A Memorandum of Understanding was further executed on 06.05.2011, between Mr.Rajesh Sharma and Mr.Baldev Sharma, his brother as a part of the frst and second part and Mr.Sunny Ramani, which incorporated that family members of Sunny Ramani had purchased foors in the building Hamrahi to be developed by M/s. Uma Constructions and a total amount of ₹6.24 crores was paid for the purchase of the said fats and it was distributed to the members buying shares of retiring partners. The said Deed also confrmed that fat nos.2,7 and 12 are owned by Rajesh Sharma and his family.
Another Declaration is signed between the three partners parties on 15.12.2012 declaring the liability of the frm and the Declaration was signed by Rajesh Sharma, Sunil Sharma and Sunny Ramani referring to a Development Agreement dated 03.09.2009 entered with Hamrahi Co-operative Housing Society for the redevelopment of a plot of land bearing C.T.S. No.F/68, Plot no.608, 15th Road, Khar West, Mumbai. In terms of the said Development Agreement, M/s. Uma Constructions
Niti/M.M.Salgaonkar
10/49 CARBP-264-22 GRP.odt
became the absolute owner of the 6 th to 13th foors in the new building whereas the society was allotted 1st to 5th foors in the new building to be constructed on the said plot. The frst party to the declaration Mr Rajesh Sharma, agreed to bring the capital of ₹7.00 crores in the frm and transferred his half share out of his 50% share in the frm in favour of party no.3 to the declaration, Mr Sunil Gaurishanker Sharma, who agreed to bring the capital of ₹7.00 crores to clear the liability of the frm which was tentatively estimated as ₹27,52,00,000/- (Rupees twenty-seven crores ffty-two lakhs only) as of date.
By the said Declaration, it was agreed between the parties that the two Sharma brothers will hold a 25% share each whereas Mr Ramani would hold 50% share in the frm. It was also mutually agreed between the parties that the amount of ₹7.00 crores being contributed by the two Sharma brothers each and an amount of ₹14.00 crores to be contributed by Ramani would bring the collection to ₹28.00 crores, which shall be utilised for clearing the liability of the frm.
The Declaration also recorded that the 6th and 7th foors in the new building being constructed will be sold by the frm, and the consideration received shall be utilised for the construction/completion of the building. All the future expenses for completion of the building, and for obtaining of Occupancy Certifcate were agreed to be borne in the ratio of 25% and 50% by the signatories to the Declaration respectively respectively.
Niti/M.M.Salgaonkar
11/49 CARBP-264-22 GRP.odt
11. The understanding arrived between the parties was recorded as under:
"e. The entire 8th, 9th and 10th foors of the new building shall belong to deponent no.2 (Ramani),
f. The entire 11 th, 12th and 13th foors of the new building shall jointly belong to deponent nos.1 and 3 (Sharma brothers),
g. The 6th and 7th foors will be sold..
It was also agreed that none of the partners, without consent of the other, shall forgo the whole or any part of any debt or sum due to the partners or trade or dispose of by loan pledge, sale or otherwise of any part of the partnership property or assign or charge their interest in the frm.
It was again agreed that if any dispute arises between the parties, it shall be made over to the sole Arbitrator.
12. A separate Deed of Admission and Continuation of Partnership was executed on 05.02.2013, thereby admitting Sunil Sharma as a 25% partner in M/s. Uma constructions with effect from 24.01.2013 and he was assigned a sharing ratio of 25%.
13. In this background, when the redevelopment of the Hamrahi building progressed, the disputes surfaced arose between the partners.
Niti/M.M.Salgaonkar
12/49 CARBP-264-22 GRP.odt
Some free-sale fat purchasers fled petitions before the High Court to protect their rights in their respective fats. This resulted in the passing of several orders by the High Court including the appointment of a monitoring committee to complete the redevelopment work. The monitoring committee was disbanded by an order dated 21.01.2020 in one of the petitions, upon the construction work being completed.
14. The Sharmas fled a Section 9 petition, which was followed by a petition fled by Ramani under Section 9 and on 06.11.2020 an ad interim order was passed by this Court, protecting the assets of the frm including the fats under redevelopment. A sole Arbitrator was appointed to adjudicate the dispute arising between parties under the Deed of Admission, Retirement and Continuation of Partnership dated 05.02.2013. Section 9 petitions fled by them were converted into Section 17 application and the ad interim reliefs were continued by the Arbitrator, who subsequently recused himself upon an objection being raised by the Sharmas.
At this juncture, it is necessary to note that in the order dated 20.01.2021 passed by the sole Arbitrator, it was recorded that Mrs Deepa Rajesh Sharma and Mrs Sangeeta Sunil Sharma had consented to the terms of reference and they agreed to be parties to the arbitration proceedings. The terms of reference were signed by all the concerned parties on 23.01.2021 and that is how the Sharma wives were introduced in the arbitration proceedings.
Niti/M.M.Salgaonkar
13/49 CARBP-264-22 GRP.odt
15. The Tribunal had before it the two applications fled by the Sharma brothers on one hand and Ramani on the other.
It was the contention of the Sharmas that, Ramani who was to bring initial capital of ₹6.24 crores had failed to do so and has brought only ₹5.81 crores whereas Sharmas themselves had invested an aggregate amount of ₹14.81 crores.
The Sharmas projected that prior to the induction of Ramani they had acquired rights in respect of some fats in the old building, that is fat no.202, 601 and 1301. It was alleged that Ramani avoided executing documents and/or registering deed in favour of the Sharmas in respect of fat no.1301. It was submitted that in the year 2013, an agreement was executed by M/s. Uma Constructions, which was even signed by Ramani in favour of the Sharmas, that is the two Sharma brothers and their wives and it was recorded in the said document that the purchasers had paid to the promoter an amount of ₹4.00 lakhs as part consideration before the execution of the document and agreed to pay to the promoters the balance of the sale price which would be followed by execution of a written agreement of sale of premises to the purchasers under Section 4 of MOFA Act. The consideration was agreed as ₹3.20 crores , but the said document is undated and unstamped. However, Ramani resiled and retained the original document and despite persistent persuasion, the said document was not made available for registration, despite an assertion that consideration of ₹3.20 crores having paid by the purchasers i.e. the Sharmas between 2015-17 by bank transfer into the frm's account. The Sharmas
Niti/M.M.Salgaonkar
14/49 CARBP-264-22 GRP.odt
supported the said statement by furnishing the details of the bank statement and the date when the transfers happened.
16. On failure to release the 2013 agreement, the two Sharma brothers on behalf of the frm executed another document on 30.07.2020 in favour of Mrs Deepa Rajesh Sharma and Mrs Sangeeta Sunil Sharma under which they were held entitled to residential fat no.1301 on the 13 th foor, the fat being specifcally described in the said sale agreement with a specifc mention of a sum of ₹3.20 crores being paid by the purchasers to the promoters before its registration and the receipt of the amount being admitted and acknowledged on behalf of the frm.
The said agreement also comprised of a clause which declared that the possession of fat no.1301 has been handed over by the promoter/s to the purchaser/s on registration of agreement and the possession of the purchasers is absolute and shall not be revoked/challenged and they were entitled to occupy the said premises and use any part thereof and permit the same to be used for the purpose of residence.
The agreement bears the signature of Mr Rajesh Sharma and Mr Sunil Sharma as the "promoters. of M/s. Uma Constructions, the purchasers being shown to be Mrs Deepa Rajesh Sharma and Mrs Sangeeta Sunil Sharma.
17. The Sharma brothers claim that as partners of the frm, it is permissible for them to execute the said document as even originally as per the agreement of the year 2013, the fat was to
Niti/M.M.Salgaonkar
15/49 CARBP-264-22 GRP.odt
go to the Sharmas but under the 2020 document it has been shown to be sold to their wives for a consideration of ₹3.20 crores and this consideration was consumed by the frm in its business venture.
Apart from this, the Sharmas also claim their entitlement to rent/compensation for their three fats being fat nos.2,7 and 12 but the same was refused to them.
18. In the application fled it was also alleged that it is Ramani who is responsible for delaying the redevelopment process resulting in proceedings being fled before the Bombay High Court seeking specifc performance of the agreement executed with the individual members.
Thus, Sharmas claimed relief of handing over the original agreement of fat no.1301. A direction was sought against Ramani to render true and correct accounts of the frm, in the background that no accounts were maintained by the frm in 2011 nor any tax returns were fled and, therefore, it had become necessary to draw the partnership account through an independent Chartered Accountant. Sharmas ensured their cooperation in undertaking the said exercise. The accounts were prayed to be drawn from 01.04.2011 since Ramani came to be inducted as a partner from the said date.
19. On the other hand, Ramani in his application under Section 17 placed before the Tribunal the messy affairs of the Sharmas. His case before the Tribunal is, prior to Ramani being
Niti/M.M.Salgaonkar
16/49 CARBP-264-22 GRP.odt
inducted as a partner three of his family members had purchased the 11th, 12th and 13th foor in the old building sought to be redeveloped and a consideration of ₹6.24 crores was parted as a part payment and even allotment letters were issued by the frm in their favour. This payment was adjusted towards Ramani's contribution towards the frm and the allotments made in favour of the family members stood cancelled.
As per Ramani, the MOU dated 01.04.2011 clearly recorded that a sum of ₹6.24 crores is adjusted towards buying shares of the retiring partner Mr Chughani. Ramani specifcally pleaded that the Sharmas behind his back executed an agreement on 30.06.2020, purportedly transferring fat no.1301 in favour of their wives. This conduct of the Sharmas led the applicant to believe that their wives would create further third-party interest in fat no.1301 and/or other assets of the frm and, therefore, he prayed for a restraint order for either creating third-party rights or otherwise dealing with or disposing of the assets of the frm.
In terms of MOU, it was argued that the sale of consideration of ₹10.03 crores was to come to Ramani's accounts from the sale of fats from the 8 th, 9th and 10th foors along with 50% of sale proceeds for fat no.401 to be added towards contribution from Ramani. It was specifcally denied that they did not bring in the decided contribution into the frm.
Niti/M.M.Salgaonkar
17/49 CARBP-264-22 GRP.odt
The manner in which fat no.1301 was alleged to have been transferred by executing an agreement to sale in favour of their wives by the Sharma brothers without any consideration being paid towards the same, an apprehension was expressed that they may create further third-party interest and jeopardize the position of the frm and, therefore it is necessary to appoint a Receiver to safeguard the project of the frm.
20. The two reliefs were primarily sought by Ramani, i.e. appointing a Receiver on the entire project and restraining the Sharmas and their wives from dealing with the assets of the frm in any manner. Another relief was sought for deposit of the amount due and payable as income tax dues for Assessment Year 2011-12 for which the Sharmas were solely liable.
21. In this background, the Tribunal was called upon to adjudicate the rival contentions.
A consensus was reached between the parties about drawing up all the accounts of the frm through an individual Chartered Accountant and, accordingly, the Tribunal appointed an independent Chartered Accountant for drawing of the accounts from 01.04.2009 till 31.03.2021 and both the parties were directed to render their cooperation by preferring a joint application to the concerned banks and disclosing on oath the statement of all bank accounts of the frm as well as disclosing the list of assets/properties and all transactions executed by the frm during the said period. The parties were also directed
Niti/M.M.Salgaonkar
18/49 CARBP-264-22 GRP.odt
to give the list of all payments received by the frm during the said period towards the sale of each fat.
Though the direction to draw the accounts from 01.04.2009 is frowned upon by the Sharmas, and it is one of the grounds raised in the appeal fled by them, I fnd the order of the arbitral Tribunal is perfectly justifed in refecting drawing the accounts from the said date, as it will be necessary to ascertain the position of the frm prior to induction of Mr.Ramani from 01.04.2011 and, therefore, there is no merit in the submission that the accounts ought to have been directed to be drawn from 01.04.2011. In any case, prior to the induction, Ramani is not expected to discharge any liability of the frm, which is the complete responsibility of Sharmas and upon the accounts being drawn from 01.04.2009, the position of the frm as on 01.04.2011 would be clearly refected.
22. A challenge was raised before the Tribunal, as refected in the impugned order dated 31.03.2021, as regards the tax liability and has fastened the Sharmas with the income tax liability of ₹1,64,89,451/- recorded in the income tax notice dated 11.03.2020.
The income tax authorities raised a demand for its dues of the Assessment Year 2011-12 (Financial Year 2010-11) to the tune of ₹1,64,89,451/- with interest.
23. The sole Arbitrator referred to the Court appointed Administrator's report which referred to the income tax notices
Niti/M.M.Salgaonkar
19/49 CARBP-264-22 GRP.odt
and he also made a reference to the High Court's order dated 21.01.2020 which recorded that there are no income tax dues to be recovered from the project building Hamrahi. However, it is clarifed by the Arbitrator that once again a demand notice was issued on 11.03.2020 to pay the arrears of ₹1.64 crores and there is also a garnishee notice by the Income Tax Department calling upon a customer Mr Pravin Talreja to pay the amount payable by him to the frm.
24. Sharmas deny the demand-cum-liability by the Income Tax Department and even before me, it was vehemently argued and strongly disputed that the Income Tax Department had ever issued such a notice. The Arbitrator clearly recorded a fnding that the frm despite its registration never fled any income tax returns or statutory returns since its formation. The learned Arbitrator has also offered justiciable explanation for drawing the accounts from 01.04.2009, which would in fact in the interest of the frm to ascertain whether Ramani has paid an amount of ₹6.24 crores which in the MOU dated 01.04.2011 came to be adjusted towards the share of Ramani. However, if there is a demand for arrears of tax, it amounts to a liability and the frm must clear the same.
Despite Sharmas' denial about the liability, the Arbitrator after making reference to the garnishee notice deemed it appropriate to direct the Sharmas to satisfy the demand in the notice dated 11.03.2020.
Niti/M.M.Salgaonkar
20/49 CARBP-264-22 GRP.odt
25. Since the demand in the said notice is prior to induction of Ramani, with effect from 01.04.2011, and it was agreed in the Deed of Admission, Retirement and Continuation of Partnership that the continuing partner shall continue the partnership frm M/s. Uma Constructions and take over the existing partnership business as a going concern with all its assets and liabilities at their respective book values on the close of business hours on 31.03.2011, it is imperative for Sharmas to discharge the said liability. It is also agreed by the very said document that the continuing partner and the retiring partner shall get completed all the pending income tax and sales tax assessments and alleged matters relating to said partnership business and agree to bear their respective income tax liability, if any, including a share in the registered frm, tax payable up to the date of retirement of the retiring partner, that is up to 31.03.2011. Necessarily, since Ramani walked into the said venture with effect from 01.04.2011, the liability of whatsoever nature including that of the income tax must fall upon the Sharmas. There cannot be any iota of doubt in my mind that the said liability shall be discharged by the Sharmas subject to the rider that it is open for the Sharmas to dispute the liability fastened or take any appropriate steps for questioning the burden cast upon the frm. However, this will be completely for the Sharmas to take appropriate steps with no involvement of Ramani since the liability is imposed for a period which is prior in the point of time when Ramani joined M/s. Uma Constructions.
The direction of the Arbitral Tribunal on 31.03.2021 to clear the arrears of income tax demanded in the notice dated
Niti/M.M.Salgaonkar
21/49 CARBP-264-22 GRP.odt
11.03.2020, through the Sharmas, therefore, does not warrant any interference and the direction is upheld.
26. This takes me to another point which is the bone of contention between the parties and this is in respect of the allocation of fats.
The building Hamrahi comprises of 13 foors along with a stilt plus a podium. Undoubtedly, in terms of the understanding between the parties, both Sharmas and Ramani are entitled to some of the fats. The said understanding between the parties in MOU dated 01.04.2011, on the basis of Ramani being inducted as a 50% of the partner of the frm record that family members of Ramani had purchased foors in the building and paid some token amount. As per Ramani, fats were purchased on the 8th, 9th and 10th foors. The MOU record that fat nos.12,7 and 2 are owned by Rajesh Sharma and his family. Admittedly, there is no reference to fat no.1301.
27. The declaration signed by the Sharmas and Ramani on 15.12.2012 clearly recorded the understanding reached between the partners of the frm which even included Sunil Sharma, the 25% partner whose Deed of Admission was to be executed on a subsequent date. The capital amount to be brought by the parties was clearly defned so as to clear the liability of the frm on the said date. It is clearly agreed between the parties that the 6th and 7th foor of the new building shall be sold by the frm and the consideration received shall be utilised for construction/completion of the building whereas the
Niti/M.M.Salgaonkar
22/49 CARBP-264-22 GRP.odt
8th, 9th and 10th foors shall belong to Ramani and 11 th, 12th and 13th foors would jointly belong to the Sharma brothers.
28. There is no clarity on the amount of capital being brought by Ramani as the Sharmas had contended before the learned Arbitrator that Ramani has failed to bring the agreed amount. As on the date of the declaration, that is 15.12.2012, the liability of the frm was tentatively assessed at ₹27.52 crores and, therefore, it was an arrangement worked between the partners of M/s. Uma Constructions to pump in a sum of ₹28.00 crores, in the proportion of 50% to be brought by Ramani and the remaining to be contributed by Sharmas in equal portions. However, after a decade of arriving at such an arrangement, one is not sure of the estimated liability, which may have accrued in the years subsequent to 2012 on account of non- payment of income tax and other statutory liabilities.
The sole Arbitrator has rightly recorded that he is unable to verify the actual contribution towards the capital involvement and the further understanding about the entitlement of the fats to the partners, in proportion of their capital contributions, could not be ascertained. The Arbitrator specifcally record that the correctness of the claim staked by the contesting parties could not be ascertained at that stage and it would be determined at the time of trial. However, in order to ensure that the assets are protected, he deemed it appropriate to continue the status quo order operating from 06.11.2020 as the Occupancy Certifcate was yet to be obtained and as such fats cannot be used or occupied by any person and
Niti/M.M.Salgaonkar
23/49 CARBP-264-22 GRP.odt
if any amount was received towards consideration, the same was to be deposited in the frm's account. He dealt with fat no.601, 201, 102, 202, 802, 1001 and 1002 and recorded that the order of status quo deserves to be continued in respect of the said fats as they form the subject matter of certain proceedings, as some of them form part of the pending proceedings.
29. The controversial fat being fat no.1301 was dealt with separately by the Arbitrator in the backdrop of the rival contentions about it being validly transferred to Sharmas. It is the case of Sharmas that an agreement was executed in respect of the said fat in the year 2013 without the date being mentioned and though it is not registered it came to be signed by Ramani as one of the partners of M/s. Uma Constructions/the promoters in favour of the purchasers, the Sharma family. But since this document was kept away and not offered for registration despite the entire consideration of ₹3.25 crores having been transferred, the two Sharma brothers executed an agreement for sale in respect of the said fat in their capacity as partners of the said frm on a subsequent date, that is 30.07.2020 conveying fat no.1301 in favour of their respective wives.
30. The High Court by its order dated 06.11.2020, injuncted the Sharmas and their wives from creating any third-party rights till the decision of the Tribunal and this ad interim injunction is continued by the sole Arbitrator by his order dated 31.03.2021. The relief sought by the Sharmas to deposit the
Niti/M.M.Salgaonkar
24/49 CARBP-264-22 GRP.odt
agreement in respect of the fat executed in the year 2013, stands on shaky ground about the placing of the agreement with the Advocate by way of escrow but in the fairness of the things, the Tribunal directed Ramani to contact the Advocate and obtain the original documents and submit it to the Tribunal within two weeks, as Ramani had failed to demonstrate any right to hold on the documents either directly or through someone else. The relief prayed by Ramani that the Sharma wives should execute the Deed of Cancellation in respect of the document dated 31.07.2020 was however declined at an interim stage.
31. Subsequent to the order dated 31.03.2021, on 14.03.2022, the MCGM granted Occupancy Certifcate (OC) for the entire building. Sharmas continued with the process of completing the fnishing works to hand over the fats pursuant to the Occupancy Certifcate being granted.
32. On 15.03.2022, this Court, by an order passed in a batch of appeals fled by the third-party fat purchasers and the litigating parties, issued a direction for the appearance of the concerned parties before the Tribunal so that appropriate directions can be passed in protecting the disputed fats pending the award.
33. This also resulted in an application being fled by Ramani under Section 17 of the Arbitration and Conciliation Act on 20.03.2022, seeking directions to safeguard the frm's assets, that is the disputed fats and also for the appointment of a
Niti/M.M.Salgaonkar
25/49 CARBP-264-22 GRP.odt
private Receiver or in the alternative for handing over of the keys in respect of the disputed fats of Ramani.
In this application, it was alleged that Sharmas had misrepresented that fat nos.2,7 & 12 belong to them and, in fact, it was realised that fat no.7 is an asset of the frm as it was purchased in the name of the frm and it was never transferred to the Sharmas. The application highlighted the status of the fats in the Hamrahi building and it was specifcally averred that the frm had sold fat nos.802, 1101 and 1102 to Hema Ramani, Sheena Ramani and Neha Ramani for consideration of ₹3,91,80,000/- and as per the Sale Agreement, the possession ought to have been handed over to them but despite receiving consideration, steps were not taken to hand over the possession. It was also stated that the Sharmas did not have any interest in the said fats, which clearly fell to the share of Ramani but they unilaterally and wrongfully purported to cancel/terminate agreements in relation to the aforesaid fats by issuing a letter from the Advocate. Ramani disputed the cancellation of the said agreements in respect of the three fats and contended that they continue to be valid purchasers of the three fats and the agreement being binding on the frm itself.
34. It was also projected by Ramani that Sharma brothers are obstructing the completion of the project and wrongfully claiming rights in the assets of the frm and attempting to act in a unilaterally high-handed manner to his prejudice and also prejudicially affecting the interest of the frm. It was alleged that the frm had to exchange fats due to the wrongful act of
Niti/M.M.Salgaonkar
26/49 CARBP-264-22 GRP.odt
the Sharmas and they are now purporting to unilaterally cancel valid agreements and foist liability on the said frm and, therefore, Ramani apprehended that Sharmas will unilaterally and wrongfully attempt to deal with and create third party rights in respect of the said fats purchased by distinct purchasers and also third party purchasers, contribution from whom has formed part of the partnership assets.
A restraint order was, therefore, sought to restrain Sharmas from dealing with the fats in any manner, i.e. either by selling, transferring, alienating, disposing or encumbering and/or creating third-party rights in respect of the assets of the frm.
35. The basis of the application seeking the appointment of Receiver over the entire building was purportedly the breach of the earlier order passed by the learned Arbitrator on 31.03.2021 and a specifc allegation is levelled that the breach was intentional. The change of circumstance was pressed into service for granting the relief of appointment of Receiver which was refused, on 31.03.2021 and it was projected that the action of the Sharmas has resulted in a failure to secure the assets of the frm and it was highlighted that in respect of the three fats which were sold in the year 2013, that is fat no.801, 901 and 902 by way of registered agreements under MOFA to one Talreja, the frm had received ₹6.10 crores, which amounted to approximately 90% of the consideration for the three fats. Though there was no consensus as to what was the balance amount remaining unpaid as according to Ramani and Talrejas,
Niti/M.M.Salgaonkar
27/49 CARBP-264-22 GRP.odt
an amount of ₹66.38 lakhs is due and payable against the three fats, Sharma brothers claimed that the outstanding amount was to the tune of ₹96.18 lakhs.
36. It was specifcally submitted that by order dated 31.03.2021 passed by the Tribunal, Ramani and Sharmas were restrained from "dealing with" in any manner in respect of the assets of the frm which would include selling, alienating, creating third party rights in respect of the said assets. It was alleged that despite this injunction on 06.07.2021, Sharmas sought to unilaterally terminate the three registered agreements and this unilateral termination amounted to a breach of the order dated 31.03.2021 passed by the Tribunal. Ramani alleged that there was no valid or contractual basis for terminating the agreement with Talreja. As such, termination has now resulted in the frm expending money on litigating. A heap of correspondence was relied upon with the justifcation being offered from Sharmas, the contention of Ramani before the Tribunal was to the effect that the fats will revert back as assets of the frm, should be safeguarded by the appointment of a Receiver who shall prevent repetition of such action in respect of these fats as well as any other fats.
37. Another breach attributed to the Sharmas is in respect of the directions issued in the order dated 31.03.2021, which had resulted in a delay in drawing of the accounts of the frm so as to avoid the actual fnancial picture of the frm coming on record as well as their failure to discharge the liability towards the tax obligation.
Niti/M.M.Salgaonkar
28/49 CARBP-264-22 GRP.odt
38. The learned Counsel Ms Jeejeebhoy, representing
Ramani, who argued before the Tribunal and even before me, would invite my attention to another fagrant breach of the earlier order passed by the Tribunal in respect of the fat no.301, as an asset of the frm.
She would submit that the Sharmas had attempted to deal with the said fat despite an injunction being passed by unilaterally executing an agreement on 30.06.2020, which was without consent of her client. She would submit that the parties were directed to maintain the status quo in respect of the said fat by order dated 31.03.2021 and the Sharma wives were restrained from using, occupying, carrying out any ft-out works or alienating or creating any third-party rights for the said fat but by submitting ample proof it was pointed out to the Tribunal that they are in possession of the said fat and are illegally occupying and using the same. They had obtained an electric meter and the bills revealed heavy consumption and it was even demonstrated that Air Conditioners were installed in the said fats. It was apparent from a notice of disconnection issued by the service provider due to non-payment of the charges that the fat no.1301 was being put to use. When the MCGM conducted the site inspection Sharma wives were not found in possession of the fats and when Ramani attempted to have an inspection of the building on 24.02.2022, the main gate of the building was locked and the inspection was avoided and after the Tribunal's intervention when the inspection was granted, there appeared to be shifting of furniture from fat no.1301 to 1201 and on the basis of the said report it is sought
Niti/M.M.Salgaonkar
29/49 CARBP-264-22 GRP.odt
to be argued that despite an injunction and restraint order, the fat has been put to use.
39. The allegation about the breach of the Tribunal's order dated 31.03.2021 is specifcally denied by the Sharmas including their wives and the argument advanced on their behalf is to the effect that they were in possession of the fat subsequent to the agreement dated 30.06.2020 and their possession is prior in point of time of passing of any interim orders. But a distinction is drawn by them between, being in "possession" and being in "occupation". The use of electricity was sought to be explained, that the electricity meter for fat no.1301 was utilised for completing the common building work so that the Occupancy Certifcate can be granted for the entire building. It is pointed out that the fat is inhabitable and none of the members of the Sharma family is in occupation of the said fat.
40. The Tribunal, thereafter, dealt with the alleged change in circumstance pointed out by Ramani and as regards the undisputed fats in the building, since the Occupation Certifcate was now received, it referred to the understanding recorded by it during the course of hearing on 21.03.2022 when it referred to fat nos.101, 501, 502, and 701 possession of which was already handed over to the respective purchasers. In respect of fat nos.102, 301, 302, 401, 402, 1101 and 1102 the locks of which were found to be broken and the keys of which were with Sharmas, an undertaking was submitted not to deal with the said fats by creating any third party rights over them. It was
Niti/M.M.Salgaonkar
30/49 CARBP-264-22 GRP.odt
also undertaken that the fats in which the ongoing cleaning/fnishing work was ongoing for the parties of handing over to the fat purchaser, they would complete the work and hand over the fats to the respective fat purchasers. This covered fat nos.301, 302, 401, 402, 1101 and 1102.
41. A consensus was recorded by the Tribunal in respect of handing over of these fats. Thus, out of 23 fats in the newly constructed building, 10 fats were undisputed whereas fat no.602 was reserved for the society's offce and since the consensus was recorded in respect of these fats there is no dispute among the parties in respect of these 10 plus 1 fats.
42. The following fats, which are in dispute, are as below :
(i) Flat nos.102, 201, 202, 601 - belong to the partnership frm or certain third-party claimants,
(ii) Flat nos.802, 1101, 1102 - Ramani fats,
(iii) Flat nos.801, 901, 902 - the purported Talreja fats,
(iv) Flat nos.1201, 1202 - Sharmas' fats
(v) Flat no.1301 - the fat belongs to the Sharma wives.
43. The fats in above fve categories are sought to be bifurcated into distinct categories; item nos.(i),(ii) & (v), covering 8 fats are projected to be accounting for change in the circumstances. As far as the third category is concerned, that is the fats belonging to Talreja though it was not initially in dispute, they have come into the disputed category since it is alleged that Sharmas terminated the agreement with Talreja on account of non-clearance of dues and it is sought to be projected
Niti/M.M.Salgaonkar
31/49 CARBP-264-22 GRP.odt
that, in any case, the fats will come back to the frm and the ffth category is in respect of the fat no.1301 where the Sharmas argue that they were already in possession of the said fat and were not occupying the same. As far as category (iv) is concerned, that is fat no.1201 and 1202, though an injunction order operated in respect of the said fats, Sharmas attempted to settle Bedi and my attention is invited to the consent terms presented to this Court in Commercial Suit No.448/2019 fled by Rajendra Bedi against M/s. Uma Constructions on a Notice of Motion (L) no.1037 of 2019.
The order passed by this Court on 03.05.2019 records that parties have entered into consent minutes of an order signed by the plaintiff as well as the defendant, who were the partners of M/s. Uma Constructions and these consent of minutes which bear the signature of Ramani as well as the Sharmas record that Sharmas, i.e. defendants nos.2 & 3 were paying an amount of ₹22.50 lakhs to the plaintiff Bedi, by way of interest for an extension being granted and due to the assertion of the plaintiff that there is a breach of an order passed in his favour. It was agreed that in the event the full payment of ₹5.00 crores is made prior to 31.07.2019, Sharmas will be entitled to get a proportionate reduction.
The consent terms record that pending the payment of the entire sum, fat nos.1201 and 1202 belong to the Sharmas on the 12th foor and the building shall remain injuncted and would offer as a security for satisfaction of the claim of the plaintiff. Upon payment of the entire sum, the security shall be
Niti/M.M.Salgaonkar
32/49 CARBP-264-22 GRP.odt
released and the plaintiff shall withdraw the said suit. Defendant nos.2 & 3, the Sharmas reserved the liberty to bid for the said security fat or bring a new buyer for the same.
44. As far as Ramani is concerned the consent terms clearly record that he being a partner impleaded as defendant no.4 to the suit shall not have any right, title and interest in respect of the secured fat, that is fat nos.1201 and 1202. It is thus argued that Ramani had given up his claim over the said fats. Thus as far as fat nos.1201 and 1202 are concerned since the same is pending adjudication in the suit, it is by way of security and that is why not subjected to arbitration.
45. I fnd suffcient justifcation in keeping the said fats aside since Ramani did not stake any claim in respect of the said fat and the understanding drawn in the form of the consent terms amounted to an order which was purely between the Sharmas and Bedi, who had already instituted a suit, which is pending.
46. In this background, the Arbitrator dealt with the alleged breach asserted by Ramani, on each count.
The frst allegation faced is dealing with Talreja's fats that is fat nos.801, 901 and 902.
Admittedly, the order dated 31.03.2021 restrained Ramani and Sharmas from dealing with, selling, transferring, disposing of encumbering and/or creating third-party rights in respect of the assets of the frm and in particular fat nos.102,
Niti/M.M.Salgaonkar
33/49 CARBP-264-22 GRP.odt
201, 202, 601, 802, 1001, 1002 and 1301. The said order restricted the parties from dealing with the assets of the frm.
The Tribunal attributed the broadest possible meaning to the word "dealing with" and held that the purpose of passing an injunction restraining the parties on both sides, that they do not deal with the assets of the frm thereby prejudicially affecting the rights of the other partner. The termination of the agreement in respect of the said fat unilaterally was held to be a breach of an order, by which a restraint was imposed for "dealing with. the said fats.
47. I concur with the view expressed by the Arbitral Tribunal where the Tribunal has returned a fnding, rejecting the broad argument that, in any case, if the agreement with Talreja is cancelled, it would restore the fats to the frm, was no justifcation for the alleged breach.
In any case, the underlying spirit of the order dated 31.03.2021 was to restrain the parties from creating any third- party interest in the fats, pending the arbitration proceedings and if at all any decision was to be taken for terminating the existing agreement, the Tribunal should have been kept for in the loophole or by seeking consent from the other partner, with the permission of the Tribunal the exercise ought to have been undertaken. But admittedly, there is no such step taken and, hence, the Tribunal rendered a fnding that cancellation of the agreement in respect of the fat nos.1201 and 1202, has defnitely resulted in the breach of the order.
Niti/M.M.Salgaonkar
34/49 CARBP-264-22 GRP.odt
48. Dealing with the breach of the directions directing the parties to produce their accounts so that they can be certifed through the Chartered Accountant, admittedly there is no compliance with the order and specifcally the direction issued in para 58(ii)(a), 58(iii) read with paragraph 33 of the order dated 31.03.2021. The Tribunal recorded that Sharmas were once again directed to furnish the details but the information was submitted on a piecemeal basis and they dragged their feet in submitting the relevant information which would have enabled the expert in drawing up of the accounts. In fact, Sharmas were in charge of the frm for the relevant period before the induction of Ramani and, therefore, it was imperative for them to submit the necessary information. The learned Arbitrator has therefore rightly recorded that Sharmas are not extending cooperation to the expert in drawing the accounts and their non-cooperation has also delayed the statutory compliances of the frm. There is also suffcient justifcation for recording a conclusion that the breach is deliberate and intended to delay the drawing up of accounts by the expert and prevent the correct facts from coming to light.
I fnd no infrmity in the fnding recorded by the Tribunal that the breach is deliberate.
49. As regards fat no.1301 where certain evidence has been tendered before the Tribunal by Ramani to demonstrate that the Sharmas are in occupation of the fat, I have dealt withwith the counter affdavits fled by both parties. Prior to the Occupancy Certifcate of the building being received, the
Niti/M.M.Salgaonkar
35/49 CARBP-264-22 GRP.odt
Sharmas claim that they were put in possession of the said fat and this they claim on the basis of an agreement executed on 30.07.2020, in favour of their Sharma wives by them, in their capacity as promoters/ the partners of M/s. Uma Constructions. This agreement in clause no.12 has recorded as under:
"12. The possession has been handed over by the promoter/s to the purchaser/s on the registration of this agreement hereof. The possession of the purchaser has been absolute..
Admittedly, this document itself is the bone of contention between the parties as it is strongly argued on behalf of Ramani that this document could not be executed behind his back as it was only executed by the two Sharma brothers in favour of their own wives, when allegedly there was a refusal to produce the agreement executed in the month of April 2013 transferring fat no.1301 in favour of Sharmas.
50. In any case, the fate of the document dated 30.07.2020 though in the form of a registered Sale Agreement is the subject matter of the arbitration proceedings and its legality and propriety will have to be determined during the course of the arbitration proceedings. The argument of the Sharmas that they were put in possession by the said agreement from the date of execution of the registered Sale Deed, is an argument to be tested by the Arbitrator.
51. As regards the occupation of the said fat, the learned Arbitrator has rightly recorded that the photographs of the dish antenna, electricity consumption, A/c installation, and the
Niti/M.M.Salgaonkar
36/49 CARBP-264-22 GRP.odt
lights being on at night cannot be considered as fndings of its usage and therefore the Sharmas deserve the beneft.
The Sharmas have also categorically defended in their affdavit that they may be in possession of fat no.1301 but they are not in occupation of the said fat. The learned Arbitrator has, therefore, rightly directed the Sharmas and their wives to hand over the keys of the said fat within a period of one week.
52. The moot question that arises for consideration and which is vehemently argued by the learned Senior Counsel Mr Sharan Jagtiyani, as well as Mr Cama, is about the power exercised by the Arbitrator, in appointment of the Receiver and whether merely alleging breach of an earlier order passed by the Tribunal would justify the appointment of a private Receiver.
Ms Jeejeebhoy appearing for Ramani and supporting the second impugned order dated 17.05.2022 passed by the Arbitral Tribunal appointing the Receiver to take possession of the entire premises, would submit that the said order was necessitated in the background facts in order to safeguard the interest of both the parties, pending the hearing and determination of the arbitration proceedings. She would submit that it is a settled position of law that the appointment of a Receiver is justifed in the peculiar circumstances where it appears to the authority exercising discretion that the assets and properties of the partnership frm should be prevented from being wasted and be kept in the custody of an impartial person.
Niti/M.M.Salgaonkar
37/49 CARBP-264-22 GRP.odt
Relying upon the precedent as laid down in the case of Iqbalnath Premnath Anand V/s. Rameshwarnath Premnath Anand and Anr.1, Ms Jeejeebhoy would submit that in the said case before the Court, in view of the approach of the defendants, with a clear fnding being recorded that the defendants had effectively kept the plaintiff out and are arrogating to themselves from the ownership of the partnership business, the Court had deemed it necessary to appoint a Receiver.
She would specifcally submit that in order to protect and safeguard the business of the partnership frm, pending the winding up of its affairs and settlement of accounts between the partners, it is necessary, that the Receiver is appointed for such business and this is a normal relief which would be granted in such a scenario and, in this case, the scenario being particularly worst since Sharmas have acted in utter dereliction of the earlier orders passed by the Tribunal and their approach would spell out a possibility, that they will deal with the property of the frm and, if they do so, at the end point, when the frm is to be dissolved, the frm may not be in a position to meet its debts and liabilities, which otherwise are mounting on account of delay in the project.
53. Per contra, Mr Jagtiani, learned Senior Counsel for Sharma wives and Mr Cama representing Sharma brothers are extremely critical about the exercise of power by the learned Arbitrator, which though being a discretionary relief did not justify the appointment of an Arbitrator. They would invite my
1 1976 SCC OnLine Bom. 68
Niti/M.M.Salgaonkar
38/49 CARBP-264-22 GRP.odt
attention to the settled proposition of law as set out by various precedents revolving around Order 40 Rule 1 of CPC, which would justify the power to appoint a Receiver not only on the ground that it is just and convenient for the parties but also in a situation of eminent danger and/or waste of the property. It is submitted by Mr Jagtiani that a fnding being rendered by the Tribunal that the Sharmas are not in occupation, as no proof has been tendered to establish the said aspect, the Tribunal could not have exercised the discretion in favour of Ramani, by appointing a Receiver over the entire property. The submission advanced on behalf of the Sharmas is, the Tribunal has arrived at a decision to appoint a Receiver, on the basis of its own assumption and there is a gross error in the order of the Tribunal, which deserved to be rectifed by this Court by exercising it's power under Section 37 of the Arbitration and Conciliation Act.
54. It is no doubt true that the scope of the power to be exercised by this Court under Section 37 is limited, as it is a settled position of law that the Arbitral Tribunal is the fnal. Tribunal on facts as well as in law and not every error, factual or legal which falls short of perversity would permit interference by the Court either under Section 34 or 37 of the Act. It is equally well settled that the ultimate view of the Tribunal on any issue concerned, so long as the view is plausible and not merely possible, the Court would loath to interfere therewith. But it is equally well settled that when the fnding by the Tribunal is either contrary to the terms of the contract between the parties or ex-facie perverse, interference
Niti/M.M.Salgaonkar
39/49 CARBP-264-22 GRP.odt
by the Court is warranted and also justifed. True it is that the Court will not substitute the view of the Arbitrator but in a case where it is demonstrated that the view is so thoroughly implausible, that it would constitute perversity and patent illegality, then defnitely the Court would exercise its power under Section 37 and it is always permissible to pass a workable order.
The settled position of law as regards the exercise of discretion vested in the Court is clearly spelt out in Wander Ltd. & Anr. V/s. Antax India Pvt. Ltd. 2, where the position of law has been clarifed to the effect that the appellate Court will not interfere with the exercise of discretion by the Court of frst instance and substitute its discretion except when the discretion has been shown to have been exercised arbitrarily, capriciously or perversely or where the Court has ignored the settled principles of law. Though the appellate Court may not reassess the material and seek to reach a conclusion different from the one reached by the Courts below, solely on the ground that if it had considered the matter at the trial stage, it would have come to a different conclusion, and if discretion by the Trial Court is exercised reasonably and in a judicial manner the fact that the appellate Court could have taken a different view may not justify interference with the exercise of discretion.
55. The impugned orders dated 31.03.2021 and 17.05.2022 will therefore have to be tested on the aforesaid parameters.
2 1990 (Sup) SCC 727
Niti/M.M.Salgaonkar
40/49 CARBP-264-22 GRP.odt
By the frst order dated 31.03.2021, the Tribunal though restrained the Sharmas as well as Ramani from creating any further interest in the fats and this obligation was cast upon both of them, also in respect of fat no.1301, which was claimed by the Sharma wives on the basis of a registered document signed by the Sharma brothers, under which the said fat was conveyed to them, when the other partner Sunny Ramani was not kept in the loophole, it was directed that they shall not use, occupy or carry out any ft-out works or sell, transfer, alienate, dispose of, encumber and/or create third party rights in respect of the said fat.
On the change in circumstances, the Tribunal however granted the relief prayed by Ramani for the appointment of a Receiver and the Tribunal by its order dated 17.05.2022, in the form of an interim order appointed a private Receiver to safeguard and protect the disputed fats, which were listed along with the application under Section 17. The Sharmas were directed to hand over the keys of all the disputed fats and the Receiver was directed to complete the balance/unfnished work in the disputed fats through a contractor and he was also entrusted with the work of testing the amenities, plumbing and electrical system and ensure that the MCGM obligations are all discharged so that the premises shall be made ready for occupation.
56. This order being passed on 17.05.2022, the fats came under the control of the Receiver and in respect of the undisputed fats (10 fats plus 1 fat), the possession was
Niti/M.M.Salgaonkar
41/49 CARBP-264-22 GRP.odt
handed over in respect of fat nos.101, 501, 502 and 701. Upon the Occupancy Certifcate being issued from the planning authority, it was agreed that the possession of fat nos.301, 302, 401, 402, 1101 and 1102 will be handed over to the respective fat purchasers.
Flat nos.102, 201, 202, 601 belonging to the partnership frm, fat nos.802, 1001 and 1002 claimed by family members of Ramani as bonafde purchasers, fat nos.801, 901 and 902 purported to be Talreja fats, fat nos.1201 and 1202 handed over by Bedis to the Sharmas and fat no.1301 claimed to be in possession of Sharma wives are the fats in dispute.
57. The exercise of power to appoint a Receiver is well settled and in case of T. Krishnaswamy Chetty V/s. C. Thangavelu Chetty & Ors.3, which is considered to be a classic authority on the law pertaining to the appointment of a Receiver, the broad principles are culled out to the following effect.
"(1) The appointment of a receiver pending a suit is a matter resting in the discretion of the Court. The discretion is not arbitrary or absolute: it is a sound and judicial discretion, taking into account all the circumstances of the case, exercised for the purpose of permitting the ends of justice, and protecting the rights of all parties interested in the controversy and the subject-matter and based upon the fact that there is no other adequate remedy or means of accomplishing the desired objects of the judicial proceeding;
(2) The Court should not appoint a receiver except upon proof by the plaintiff that prima facie he has very excellent chance of succeeding in the suit;
(3) Not only must the plaintiff show a case of adverse and conficting claims to property, but, he must show 3 AIR 1955 Madras 430
Niti/M.M.Salgaonkar
42/49 CARBP-264-22 GRP.odt
some emergency or danger or loss demanding immediate action and of his own right, he must be reasonably clear and free from doubt;
(4) ....... It would be different where the property is shown to be 'in medio', that is to say, in the enjoyment of no one, as the Court can hardly do wrong in taking possession: it will then be the common interest of all the parties that the Court should prevent a scramble as no one seems to be in actual lawful enjoyment of the property and no harm can be done to anyone by taking it and preserving it for the beneft of the legitimate who may prove successful. Therefore, even if there is no allegation of waste and mismanagement the fact that the property is more or less 'in medio' is suffcient to vest a Court with jurisdiction to appoint a receiver.
(5) The Court, on the application of a receiver, looks to the conduct of the party who makes the application and will usually refuse to interfere unless his conduct has been free from blame. He must come to Court with clean hands and should not have disentitled himself to the equitable relief by laches, delay, acquiescence etc..
58. In the wake of the aforesaid enunciation of law as well as the law laid down by the highest Court of the Country, it is well settled that the power to appoint a Receiver must justify it's existence. Merely because there is disobedience of an order passed by the Arbitrator, in my considered opinion, would not justify its exercise. The allegations against the Sharmas in respect of breach of an earlier order to the following effect as justifed, in particular, the following instances have formed the basis for the exercise of discretion by the Tribunal in its second impugned order:
(a) Preventing Ramani from accessing the site although Sharma members were in a position to visit the fats;
Niti/M.M.Salgaonkar
43/49 CARBP-264-22 GRP.odt
(b) Unilateral and surreptitious correspondence by Sharmas regarding undisputed fats even during the pendency of the present application;
(c) Change in circumstances since the frst order passed by the Tribunal.
59. When the second impugned order passed by the Tribunal on 17.05.2022 is carefully perused, I can only observe that the prime factor of change in circumstances was based on contradictory stands adopted by the consenting parties and the Arbitrator has clearly recorded in the impugned order that the argument advanced by Ramani as regards fat no.1301 being put to use by the Sharmas was not of conclusive nature and he deemed it ft to grant beneft of the doubt in favour of the Sharma wives but the learned Arbitrator however denied that argument advanced on behalf of Sharmas that the wives were in possession of the fat though not occupation and the fnding is rendered that they were neither in possession nor in occupation of fat no.1301 and until the Occupancy Certifcate was obtained there was no question of anyone being in possession or occupation, even for ft-out works. The Occupancy Certifcate being granted on 14.03.2022, it is held by the Tribunal that thereafter no possession is made over to the wives.
60. As regards the notices being issued unilaterally to Talreja in respect of fat nos.801, 901 and 902, though it is held by the Tribunal that issuing the termination notices to Talreja amounted to "dealing with. the said fats and a peculiar situation was noticed by the learned Arbitrator, where one
Niti/M.M.Salgaonkar
44/49 CARBP-264-22 GRP.odt
partner was objecting to the termination and other partner claimed that the termination is valid, as the dispute was in respect of the balance amount to be paid. The difference between the amounts staked by the two contenders is barely of some lakhs as against the admitted consideration paid by Talreja as against the fats. Whether the termination of Talreja is valid or invalid or whether a partner could unilaterally terminate the registered agreement is a question which was left open by the learned Arbitrator and the learned Arbitrator rejected the relief of handing over the fats of Talreja against the deposit as may be considered by the Tribunal to be appropriate. The Tribunal refused to hand over the possession of fats to either of the partners and recorded that the possession of these fats will have to be protected pending the arbitration proceedings.
61. Undoubtedly, the Tribunal recorded the breaches committed by Sharmas, in not abiding by it's earlier direction of giving the accounts, as a result of which the statement of accounts of the frm could not be drawn by the Chartered Accountant.
However, only for the aforesaid reason, the Arbitrator could not have exercised his discretion in appointing the Court Receiver, which relief was refused in the earlier round of litigation, in the given facts. When the frst order was passed by the Tribunal on 31.03.2021, fat no.1301 was already alleged to have been conveyed in favour of the Sharma wives by the Sharma brothers and when the Tribunal deemed it appropriate
Niti/M.M.Salgaonkar
45/49 CARBP-264-22 GRP.odt
to impose a condition upon the Sharmas not to occupy the said fats, that served the purpose and interest of the frm, as ultimately whether the registered agreement for sale without approval from Ramani had really conveyed the property in favour of Sharma wives is a question required to be determined by the Arbitrator during the proceedings pending before him for adjudication.
62. The exercise of discretion to appoint an Arbitrator must be a judicial exercise, which would necessarily be justifed in the given circumstances for protecting the rights of the parties and for meeting the ends of justice. The two terms are not a mere projection but the conditions must be made out to justify the exercise of the power. The allegation that Ramani was excluded from partnership business and the Sharmas are not willing to share any information, documents and data that may pertain to the frm cannot be a ground for the appointment of a Receiver. The deadlock in the frm defnitely cannot be resolved by appointing a Receiver and merely because one of the parties has allegedly committed a breach of the earlier order passed by the Tribunal would also not justify the appointment of a Receiver, which power will have to be exercised only when it appears that the property or the assets of the frm are being wasted or mismanaged. The partnership between Ramani and Sharmas was restricted to the development of one building and now on 14.03.2022, the Occupancy Certifcate is also received. The undisputed fats are already handed over to the prospective purchasers and as regards the fats under dispute, independent petitions are also fled by the purchasers, who claim
Niti/M.M.Salgaonkar
46/49 CARBP-264-22 GRP.odt
appointment of a Receiver for the purpose of carrying out the work of completion of the building.
63. The aforesaid circumstances in my considered opinion do not justify the appointment of a Receiver. Ramani can always take recourse to the appropriate remedies available to him by moving an application before the Tribunal as and when the circumstances arise and seek appropriate directions. The appointment of the Receiver need not be further continued as the Receiver has served the purpose by ensuring that the construction of the building is completed and now the Occupancy Certifcate is also granted. The undisputed fats are already delivered to the purchasers and as regards the disputed fats the Arbitrator is expected to resolve the dispute at the earliest as it is not only the Sharmas and Ramani, the two partners who are the parties to the dispute but because of their dispute, the other petitioners, who are the purchasers of the distinct fats are also facing serious concern as despite they having parted with different considerations towards the purchase of the fat, the fats cannot be handed over to them.
The Receiver, till date, has also exercised his control over the disputed fats, but now since they are identifed, both the parties shall maintain status-quo as regards the disputed fats and shall not create any third party interest or any encumbrances therein, as directed by the frst order passed by the Tribunal on 31.03.2021. Though the other reliefs sought by Ramani are rejected, no proceedings are fled by Ramani, challenging the said order.
Niti/M.M.Salgaonkar
47/49 CARBP-264-22 GRP.odt
64. As a result of the aforesaid discussion, by continuing the frst order passed by the Arbitrator on 31.03.2021, continuing the restraint upon the Sharmas and Ramani from dealing with, selling, transferring, alienating, disposing off, encumbering and/or creating third party rights in respect of the assets of the frm and in particular, fat nos.102, 201, 202, 601, 802, 1001, 1002 and 1301 in Hamrahi building, the order dated 31.03.2021 is upheld.
As a result, Comm.Arbitration Petition No.185 of 2022 is dismissed.
Comm.Arbitration Petition No.262 of 2022 and Comm. Arbitration Petition (L) No.16413 of 2022 stand allowed by setting aside the impugned order dated 17.05.2022, appointing the Receiver in respect of "Hamrahi Building., including fat no.1301 in possession of the Sharmas.
65. Comm.Arbitration Petition No.7131 of 2022, which is connected with the above proceedings is fled by the three petitioners, who claim that they are entitled for the fats in the redeveloped "Hamrahi Building. under the original "Development Rights Agreement. dated 03/09/2009 and they allege that respondent no.1-Uma Constructions alongwith it's partners have failed to complete the redevelopment work and have neglected their statutory duty by not registering themselves with Maharashtra Real State Regulatory Authority.
Niti/M.M.Salgaonkar
48/49 CARBP-264-22 GRP.odt
The petitioners refer to the arbitration clause contained in the "Development Rights Agreement. dated 03/09/2009 and have approached the Court, seeking appointment of Court Receiver in respect of the suit property and/or the premises, including fat nos.802, 1001, 1002, 1301 in the premises of the new Hamrahi Building, which is in direct or indirect possession of M/s. Uma Constructions and it's partners. They also seek a restraint order against the frm and it's partner from creating any third party interest/rights in the suit fats.
The petitioners allege that during the pendency of the redevelopment project the Sharmas and Ramani executed a Deed of Transfer on 26.04.2016 with respect to the Hamrahi Building and the respondent nos.2 & 3, that is the Sharmas and Ramani, accrued the development rights under the original agreement to which M/s. Uma Constructions was a confrming party. It is the specifc case of these purchasers that fats of the original members of Hamrahi building were acquired by the partners of the frm and by creating a charge on these fats to be attached and sold under the supervision of the Court Receiver and moneys to be utilised for completion of Hamrahi Building and for compensating the petitioners and other members of the Hamrahi Cooperative Housing Society.
66. Since I have set aside the direction of the Arbitrator in appointing the Court Receiver, in respect of the suit property, I am not inclined to grant prayer clause (a) in the above petition fled by the respective petitioners, but I deem it appropriate to restrain the respondent nos.1 to 4 in the said petitions from
Niti/M.M.Salgaonkar
49/49 CARBP-264-22 GRP.odt
dealing with, disposing of, selling, transferring, alienating, encumbering or creating any third party rights in respect of the unsold fats which include the disputed fat nos.802, 1001, 1002 and 1301 in the newly constructed "Hamrahi Building".
67. Conferring the liberty upon the respective parties to move the Arbitrator in case of any exigency arising in future, the learned Arbitrator is directed to conclude the arbitration proceedings expeditiously and, in any case, within a period of 6 months from today or on or before 31.12.2023 whichever is earlier. The Commercial Arbitration Petition Nos.264/22, 185/22 and Comm.Arbitration Petition (L) Nos.16413/22 and 7131/22 stand disposed of.
68. Commercial Arbitration Petition Nos.8869/2020, 8860/2020 and 8861/2020, which seek a relief of payment of rent/compensation are separated and directed to be listed for hearing on 12.06.2023.
69. As far as Contempt Petition bearing CPCUL No.6695/2022 is concerned, I deem it appropriate to issue notice to the respondents, who shall fle the responses within a period of 8 weeks from today and the Contempt Petition is de-tagged from the bunch of Arbitration Petitions, which are disposed of by the present order.
( SMT.BHARATI DANGRE, J. )
Niti/M.M.Salgaonkar
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!