Citation : 2023 Latest Caselaw 4914 Bom
Judgement Date : 5 June, 2023
2023:BHC-AS:14630
6- A.O. 234-23+.DOC
Sayali Upasani
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
APPEAL FROM ORDER NO.- 234 OF 2023
WITH
INTERIM APPLICATION NO. 3262 OF 2023
Kedar Darshan Co-Operative Housing ...Appellant/Org.
Society Ltd Defendant
Vs.
Messrs Nooman Developers ...Respondent/
Org. Plaintiff
Mr. Karl Tamboly, a/w. Ms. Tanya Mehta, Ms. Vaibhavi
Bhalerao and Ms. Sayali Diwadkar i/b DSK Legal, for
Appellant.
Mr. Vishal Kanade a/w Mr. S.P. Trivedi, Ms. Tanaya
Tendulkar, Mr. Sandeep Hirvadekar i/b Bharat T.
Mahubarwala, for the Respondent.
CORAM:- N. J. JAMADAR, J.
RESERVED ON:- 20th APRIL, 2023 PRONOUNCED ON:- 5th JUNE, 2023
6- A.O. 234-23+.DOC
ORDER:-
1) This Appeal is directed against an order dated 4 th
February, 2023, passed by the learned Judge, City Civil Court
in Notice of Motion No.1936 of 2022 in Suit No. 6889 of 2003,
whereby the Notice of Motion came to be partly allowed
restraining the defendants-appellants from creating third party
rights, title or interest or permitting any third party under any
Development Agreement, Assignment Agreement and Sale
Agreement under any rights doing any construction activity on
the suit plot and also from interfering with the plaintiffs rights
in the suit emanating from the agreement dated 7 th July, 1993,
supplemental agreement dated 3rd December, 1996 and the
consent terms dated 20th October, 2000 filed in Suit No.4262 of
2000.
2) For the sake of the convenience and clarity, the parties are
hereinafter referred to in the capacity in which they are arrayed
before the City Civil Court.
3) Though the litigation has chequered history peppered with
sporadic settlements, the background facts can be stated in
brief as under:-
6- A.O. 234-23+.DOC
(a) A building consisting of 40 tenements was situated at a
plot of land bearing CTS No. 229 and 267, admeasuring 1392.12
sq. meters, Nehru Nagar Housing board colony, Kurla (E),
Bombay. It was allotted to the defendant's Society by MHADA.
On 7th July, 1993, the defendant society entered into a
development agreement with the plaintiff for redevelopment of
the suit property. A supplemental agreement dated 3 rd
December, 1996 came to be executed between the plaintiff and
defendant. It was the claim of the plaintiff that the defendant
society and its members committed breach in performance of
the obligations under the development and supplemental
agreement. Proceedings commenced.
(b) In Suit No. 4262 of 2000, instituted in this Court, the
plaintiff asserted that the defendant society failed to pay the
construction costs as agreed under the development agreement
and supplemental agreement and instead threatened to forcibly
take possession of the flats which were entrusted to the
plaintiff. In the said suit, pursuant to the settlement arrived at
between the plaintiff and defendant, a consent order was passed
on 20th October, 2000. In the consent order, the defendant
society confirmed to have executed the development agreement
6- A.O. 234-23+.DOC
dated 7th July, 1993 and supplemental agreement dated 3 rd
December, 1996 and agreed to allow the plaintiff to carry out
the construction work and also accept the prospective
purchasers of the flats sold by the plaintiffs as the members of
the defendant society.
(c) The plaintiff asserts despite the consent order dated 20 th
October, 2000, in Suit No. 4262 of 2000 and having agreed to
pay a sum of Rs.2,00,000/-, per member towards construction
cost the defendant committed default in payment of the
construction cost. Defendant also threatened to dispossess the
plaintiff and obtain the possession of the flats forcibly. The
plaintiff was thus constrained to institute Suit No.5732 of 2001
before the City Civil Court.
(d) Again a settlement was arrived at between the plaintiff and
defendant. Consent terms were executed on 3 rd December, 2001.
Defendant agreed not to disturb the possession of the plaintiff
over the flats, which were delivered on account of the failure on
the part of the defendant to make the payment, and to
surrender the rights of those members in favour of the plaintiff.
(e) Defendant again failed and neglected to perform the
contractual obligations and the undertakings given in the
6- A.O. 234-23+.DOC
consent terms. Plaintiff was forced to institute suit No. 2498 of
2002. In the said suit Minutes of Order were passed on 16 th
May, 2002. The defendant conceded to an order that the
defendant No. 1 and its members be restrained form interfering
with the construction activity to be carried out by the plaintiff
at the suit property by purchasing F.S.I. from MHADA.
(g) Eventually, the plaintiff was constrained to institute the
instant suit with the allegations that the defendant and its
members were in arrears to the tune of Rs.10,30,000/-. The
plaintiff thus prayed for a decree of Specific Performance of the
consent terms dated 20th October, 2000, development agreement
dated 7th July, 1993 and supplemental agreement dated 3 rd
October, 1996 and, in the alternative, a money decree for the
sum of Rs.3,00,000/-, by way of damages and a sum of
Rs.10,30,000/-, towards the balance construction cost along
with interest at the rate of 18% p.a. from 21 st February, 2001 till
payment and/or realisation.
4) During the pendecny of the said suit, the plaintiff took out
the instant Notice of Motion, on 2nd May, 2022, with the
assertion that though the defendant failed to file a written
statement yet, during the pendency of the suit, the defendant
6- A.O. 234-23+.DOC
has entered into a development agreement with some
developers, who have demolished the suit building consisting of
40 flats. Upon being informed by the Secretary of the defendant,
the plaintiff claimed to have visited the suit property and found
that the building had been demolished and further development
was being carried out. The plaintiff claimed to have registered
the lis with Registrar of Assurances and yet instruments were
executed by the defendant and new developer.
5) Hence, to protect the subject matter of the suit till the
decision of the suit, the plaintiff took out the instant Notice of
Motion seeking interim reliefs in the nature of appointment of
the Court Receiver in respect of the suit property and temporary
injunction restraining the defendant from creating third party
interest therein of whatsoever nature.
6) The defendant resisted the Notice of Motion by filing an
affidavit-in-reply. Entitlement of the plaintiff to seek Specific
Performance of the development agreement dated 7 th July, 1993
and supplemental agreement dated 3 rd December, 1996 was put
in contest on the ground that those agreements were for
execution of construction contract only and did not create any
interest in the suit property. The delay in seeking the interim
6- A.O. 234-23+.DOC
reliefs, in view of the subsequent developments, was stated to be
fatal to the tenability of the Notice of Motion. In any event,
according to the defendant, the suit represented a money claim
and the plaintiff was not entitled to seek the injunctive reliefs as
well as appointment of the Court Receiver.
7) By the impugned order, the learned Judge was persuaded
to allow the Notice of Motion holding inter alia, that the
development agreement dated 7th July, 1993 was not a works
contract simplicitor. The development agreement, coupled with
the supplemental agreement, incorporated a contract, which
could be specifically enforced and the plaintiff has been
consistently pursuing the relief of specific performance as well.
Therefore, the suit can not be said to be for recovery of money
simplicitor. Opining that, having entered into the consent terms
with the plaintiff, the defendant consciously entered into
development agreement with a third party and thereby infringed
the contractual obligations, the learned Judge considered it
necessary to restrain the defendant from creating third party
rights in the suit property. Resultantly, the Notice of Motion
came to be partly allowed whilst rejecting the prayer for
appointment of the Court Receiver and a direction for discovery.
6- A.O. 234-23+.DOC
8) Being aggrieved the defendant is in Appeal.
9) I have heard Mr. Karl Tomboly, the learned Counsel for the
appellant-defendant and Mr. Vishal Kanade, the learned
Counsel for the respondent-plaintiff. With the assistance of the
learned Counsel for the parties, I have perused the pleadings,
orders passed in the proceedings hitherto and the material on
record.
10) Mr. Tamboly urged with a degree of vehemence that
impugned order singularly lacks consideration on the aspect of
the balance of convenience and irreparable loss. Though the
plaintiff failed to make out a prima facie case also, according to
Mr. Tamboly, even if it is assumed that the plaintiff succeeded
in making out a prima facie case, yet the defendant could not
have been restrained by order of temporary injunction without
determining the aspects of balance of convenience and
irreparable loss. On this count alone, Mr. Tamboly urged, the
impugned order deserves to be interfered with.
11) Laying emphasis on the fact that the suit came to be
instituted in the year 2003 and the Notice of Motion came to be
moved in the year 2022, Mr. Tamboly would urge this time lag
dis-entitles the plaintiff from claiming any equitable relief. The
6- A.O. 234-23+.DOC
learned Judge, City Civil Court did not adequately consider
these aspects of the matter.
12) Mr. Tamboly further submitted that the learned Judge City
Civil Court recorded an erroneous finding that the suit was also
for specific performance of contract in the face of an order
passed by a learned Single Judge of this Court in Notice of
Motion No. 2159 of 2003 in Suit No. 2328 of 2003, wherein a
categorical statement was made on behalf of the plaintiff that
the claim was restricted to payment of money under the consent
terms dated 20th October, 2000, came to be recorded. Mr.
Tamboly strenuously submitted that the learned Judge, City
Civil Court was not at all justified in restraining the defendant
from creating third party rights, which has severe ramifications
not only qua the defendant but the third parties. It was
submitted that after demolition of the existing structure, the
new construction has reached an advanced stage. Grant of
injunction, at this stage, has the effect stalling the entire project
for recovery of a sum of Rs.10,30,000/- i.e. the Suit claim.
13) Mr. Kanade, the learned Counsel for the plaintiff joined
the issue by stoutly submitting that the learned Judge, City
Civil Court has recorded a justifiable finding that instant suit is
6- A.O. 234-23+.DOC
also for a decree for Specific Performance of contract. Taking the
Court through the recitals of the development agreement and
the supplemental agreement as well as the consent orders, Mr.
Kanade would submit that the agreement in question can not be
said to be a mere construction contract. On the contrary, those
agreements, coupled with the consent order, according to Mr.
Kanade, unmistakably indicate that interest had been created in
the suit land in favour of the plaintiff. The act of defendant
society in surreptitiously demolishing the building, which stood
over the suit property, and entering into a development
agreement with a new developer per se reflects the oblique
motive. In such circumstances, the learned Judge, City Civil
Court was justified in restraining the defendant from creating
further third party rights in the suit property, lest the plaintiff
would be left in the lurch, urged Mr. Kanade.
14) Mr. Kanade would further urge that having regard to the
history of litigation between the parties and the fact that the
suit is ripe for hearing, it may be appropriate to expedite the
hearing of the suit instead of interfering with a discretionary
order.
6- A.O. 234-23+.DOC
15) To start with, it may be apposite to note the circumstances
in which the jural relationship between the plaintiff-defendant
emerged. The suit property was in a dilapidated condition.
Defendant floated tender. The bid of the plaintiff to construct
the building to house 40 members of the defendant society came
to be accepted, leading to execution of the development
agreement dated 7th July, 1993. The primary agreement was to
construct the building to be paid for by the defendant at the rate
of 375 per square. It was specifically agreed by and between the
parties that the plaintiff would construct the building for and on
behalf of the defendant after dismantling then existing old
dilapidated building as per the building plan prepared by the
Society's Architect M/s. Ranjit Naik and Associates. Certain
provisions for sale of the area, which might become available,
after accommodating 40 tenants/members were also made. In
the event of sale of such additional area, which might become
available, the society was to get credit at the specified rates. Yet,
the development agreement was predominantly a contract to
build.
16) Supplemental agreement dated 3rd December, 1996, came
to be executed between the parties whereby and whereunder the
6- A.O. 234-23+.DOC
plaintiff was authorised to accept surrenders from those
members who had no money to pay to the developer for
construction of their tenement. The defendant also agreed to
accept the incoming members to whom the plaintiff would
transfer the surrendered tenement, as members of the
defendant society without charging transfer fees. The plaintiff
was granted right to sale balance un-utilised F.S.I. and sale
newly constructed flats to the prospective purchasers. The
defendant agreed to pay for the construction at the rate of
Rs.511/- per square feat instead of Rs.375/-as originally agreed.
17) In the wake of the controversy, noted above, the plaintiff
instituted Suit No. 4268 of 2000 and consent terms were
executed on 20th October, 2000. Under the consent terms, the
defendant acknowledged that the agreement for development
dated 7th July, 1993, supplemental agreement dated 3 rd
December, 1996 and the power of attorney dated 30 th June,
1997 executed by the defendant in favour of the plaintiff were
valid, subsisting and binding. Defendant agreed to allow the
plaintiff to carry out the reconstruction work as per the terms of
the said agreement. Defendant agreed to make payment of
balance consideration within a period of four months therefrom.
6- A.O. 234-23+.DOC
On account of the non-compliance of the said consent terms,
two more suits came to be instituted.
18) In substance, what emerges from the material on record
is that, by the year 2000, the plaintiff completed the entire
construction work and claimed to have performed its part of
contract. On account of the failure on the part of the defendant
to comply with the obligations under the agreements and
consent terms, the plaintiff was constrained to institute instant
Suit No. 2328 of 2003, inter alia, seeking a sum of
Rs.10,30,000/-, towards balance construction cost and
Rs.3,00,000/- towards damages and interest thereon at the rate
of 18% p.a. Undoubtedly, the plaintiff also prayed for a direction
against the defendant to specifically perform the consent terms
dated 20th October, 2000, development agreement dated 7 th July,
1993 and supplemental agreement dated 3rd December, 1996.
19) The pivotal question that arose for consideration was
whether the suit still retained the character of a suit for the
specific performance of the contract contained in development
agreement dated 7th July, 1993 and supplemental agreement
dated 3rd December, 1996. The learned Judge, City Civil Court
6- A.O. 234-23+.DOC
was of the view that the suit was also for Specific Performance
of the said contract.
20) The aforesaid question assumes significance. If the
contract is construed as a contract to build simplicitor,
ordinarily such a contract is not specifically enforceable. On the
contrary, if the contract envisages creation of interest in the
property to be developed, the Court would be justified in passing
a decree for specific performance, if certain conditions are
fulfilled.
21) A profitable reference, in this context, can be made to a
judgment of the Supreme Court in the case of Sushil Kumar
Agarwal Vs. Meenakshi Sadhu and Others1, wherein the
Supreme Court considered the question as to whether the
Section 14(3) (c) of the Specific Relief Act, 1963, constitutes a
bar to a suit by a developer for specific performance of a
development agreement between the developer and the owner of
the property. After adverting to the provisions contained in
Section 14 of the Act, 1963 and the judgments which dealt with
the enforceability of a development agreement, the Supreme
Court expounded the various facets of development agreement,
the conditions in which the development agreement may become
1 (2019) 2 SCC 241
6- A.O. 234-23+.DOC
enforceable and the principles which govern the exercise of
discretion in granting the specific performance of development
agreement, as under:
18. When a pure construction contact is entered into, the contractor has no interest in either the land or the construction which is carried out. But in various other categories of development agreements, the developer may have acquired a valuable right either in the property or in the constructed area. The terms of the agreement are crucial in determining whether any interest has been created in the land or in respect of rights in the land in favour of the developer and if so, the nature and extent of the rights.
.............
24. Various High Courts have interpreted the requirements under Section 14(3)(c) of the Act and opined on the maintainability of a suit by the developer for Specific Performance against the owner of the property for a breach in the conditions of the development agreement. A common thread that runs through the analysis in decided cases is the following:
24.1. The courts do not normally order Specific Performance of a contract to build or repair. But this rule is subject to important exceptions, and a decree for Specific Performance of a contract to build will be made only upon meeting the requirements under law;
24.2. The discretion to grant Specific Performance is not arbitrary or capricious but judicious; it is to be exercised on settled principles; the conduct of the plaintiff, such as delay, acquiescence, breach or some other circumstances outside the contract, may render it inequitable to enforce it;
24.3. In order to determine the exact nature of the agreement signed between the parties, the intent of the parties has to be construed by reading the agreement as a whole in order to determine whether it is an
6- A.O. 234-23+.DOC
agreement simpliciter for construction or an agreement that also creates an interest for the builder in the property. Where under a development agreement, the developer has an interest in land, it would be difficult to hold that such an agreement is not capable of being specifically enforced; and
24.4. A decree for Specific Performance of a contract to build will be made if the following conditions are fulfilled:
24.4.1. the work of construction should be described in the contract in a sufficiently precise manner in order for the court to determine the exact nature of the building or work;
24.4.2. the plaintiff must have a substantial interest in the performance of the contract and the interest should be of such a nature that compensation in money for non-performance of the contract is not an adequate relief; and
24.4.3. the defendant should have, by virtue of the agreement, obtained possession of the whole or any part of the land on which the building is to be constructed or other work is to be executed.......... "
(emphasis supplied)
22) Mr. Kanade would urge that in the case at hand not only
the agreements provide for the right of the plaintiff to construct
additional floors and sale the units but the defendant has
incurred a decretal obligation. Attention of the Court was invited
to consent order dated 16th May, 2002, passed in S.C. Suit No.
2498 of 2002. In the said suit, on the basis of the Minutes of
Order it was recorded that the defendants have no objection if
6- A.O. 234-23+.DOC
prayer clause "a" of the said Suit was granted in favour of the
plaintiff. The suit thus came to be decreed in terms of the prayer
Clause "a". It was submitted that in view of the aforesaid
consent decree in Suit No. 2498 of 2002, it can not be disputed
that interest was created in the suit property.
23) Mr. Tamboly countered by submitting that under the said
consent decree, the defendant had agreed not to restrain the
plaintiff from utilising the F.S.I., at the suit property, which the
plaintiff may acquire. However, the plaintiff never acquired
additional F.S.I. nor performed the rest of the contractual
obligations, and, therefore, the defendant had terminated the
contract by notice dated 18th June, 2002.
24) Prayer Clause "a" in Suit No. 2498 of 2002, reads as
under:-
"a) For permanent injunction order restraining the defendants, their servants or agents or any one claiming through them from obstructing the plaintiff from using the F.S.I. on the suit property Viz. Building No. 45, situated on plot of land bearing S. No. 229 and 267, C.T.S. No. 12(part) at Nehru Nagar Housing Board Colony, Kurla (E) Mumbai-400 024 from the adjoining plot of land belonging to MHADA authorities on his complying with requisite conditions of the MHADA Authorities...."
25) Evidently, the suit was instituted to restrain the defendant
from causing obstruction to the plaintiff from using F.S.I. on the
6- A.O. 234-23+.DOC
suit property from adjoining plot of land belonging to MHADA
Authorities. It clearly implied that the plaintiff had to first
acquire additional F.S.I./T.D.R. and then load the same on the
suit property.
26) At this juncture, the fact that by notice dated 18 th June,
2002, the defendant terminated the development agreement and
supplemental agreement assumes importance. Ordinarily, a suit
for Specific Performance without seeking a declaration that the
termination of the contract is illegal and bad in law, does not
deserve to be entertained. Since the contract can not be said to
subsist, in view of the termination, a declaration that contract is
still subsisting and binding on the parties is necessarily
required to be sought, if a prayer for Specific Performance is to
be sustained. In the instant suit, there is no prayer for a
declaration that the termination is illegal and bad in law and
the suit agreements still subsist.
27) What was the nature of the suit claim, in the
contemplation of the plaintiff himself, also assumes significance.
In Notice of Motion No. 2159 of 2003 in the instant Suit, while
the suit was still on the file of this Court on Original Side, the
plaintiff had purportedly moved for attachment before judgment.
6- A.O. 234-23+.DOC
On 8th December, 2005, this Court was persuaded to dismiss
the said Motion. The order reads as under-
"1. The learned counsel for the plaintiff states that the only relief which the plaintiff claims is payment of money under the Consent Terms dated 20.10.2000. No case for attachment before judgement is made out. It is submitted that under the Consent Terms, the plaintiff is entitled to the same. That is a money claim which must be decided at the final hearing of the suit.
2. The Notice of Motion is, accordingly, dismissed. This order will not prejudice the plaintiff's rights to apply for execution of the Consent Terms, in accordance with law...."
28) It thus appears that, even in the contemplation of the
plaintiff, the suit was primarily for recovery of the amount
which under the terms of the contract and the consent terms
dated 20th October, 2002, the defendant and its members were
enjoined to pay to the plaintiff. The fact that there was a
stipulation in the contract that in future the plaintiff would
acquire additional development rights and construct additional
floors was clearly in the nature of an executory contract. Prima
facie such a stipulation can not operate in infinity.
29) At this stage, the time lag comes into play. The jural
relationship between the plaintiff and defendant started when
the original building was in a dilapidated state. After another 20
years of construction of the building by plaintiff, the building
6- A.O. 234-23+.DOC
again warranted re-development (in the contemplation of the
defendant society). Admittedly, the building erected by the
plaintiff has since been demolished. A development agreement
with another developer has been executed. A multi-story
structure has already been erected.
30) It is in the context of the aforesaid developments, the
prayer for grant of interim reliefs deserves to be appreciated. The
parameters for grant of temporary injunction are well settled. In
the case of Seema Arshad Zaheer and Others Vs. Municipal
Corporation of Greater Mumbai and Others 2, the essential
requirements to be satisfied by the plaintiff for grant of
temporary injunction were postulated by the Supreme Court as
under:-
"(i) Existence of a prima facie case as pleaded, necessitating protection of plaintiff's rights by issue of a temporary injunction;
(ii) When the need for protection of plaintiff's rights is compared with or weighed against the need for protection of defendant's right or likely infringement of defendant's right, the balance of convenience tilting in favour of plaintiff; and
(iii) Clear possibility of irreparable injury being caused to plaintiff if the temporary injunction is not granted. In addition, temporary injunction being an equitable relief, the discretion to grant such relief will be exercised only when the plaintiff's conduct is free from blame and he approached the court with clean hands."
2 (2006) 5 SCC 282
6- A.O. 234-23+.DOC
31) If the facts of the case are appraised on the aforesaid
touchstone, it would be difficult to draw an inference that the
plaintiff has succeeding in making out a prima facie case,
especially in the context of the nature of the suit claim. In any
event, the time of 20 years, which has elapsed, seems to have
taken a toll on the plaintiffs case.
32) A profitable reference in this context can be made to a
judgment of a learned Single Judge of this Court in the case of
Ambalal Maganlal Patel and Another Vs. Indumati Narayan
Mohile and Others3, wherein, in the facts of the case, the
learned Judge had observed as under:-
".... Interim reliefs such as those claimed in the present motion by the plaintiffs are basically in the discretion of the Court. Though discretion is expected to be exercised fairly and reasonably, this, in my judgment, is not a case for exercising the same in favour of the plaintiffs. Even assuming that the plaintiffs had initially, when the suit was filed, made out a case for interim relief, the same stood virtually destroyed by their utter silence all these long years. Third party rights have intervened. The old building has been demolished. A new construction has come up to third floor level....."
(emphasis supplied)
33) Reliance placed by Mr. Tamboly on a Division Bench
judgment of this Court in the case of Ferani Hotels Private
3 AIR 1990 Bombay 187
6- A.O. 234-23+.DOC
Limited and Others Vs. Nusli Neville Wadia and Others 4 also
appears to be well founded. In the said case, the aspect of delay
in seeking the interim relief on the entitlement for interim relief
was adverted to by the Division Bench. It was observed that the
fact that the equities have intervened and third party rights
have been created and the work under the project was continue
must weigh with the Court in deciding to grant stay on
construction at the interim stage.
34) The aforesaid factor also bears upon the determination of
the balance of convenience. As noted above, the suit
predominantly represents a money claim. The building which
the plaintiff had constructed has already been demolished and
given way to a multi-storey structure housing far more units
than the tenements in the original building. Equities and third
party rights have incontrovertibly intervened. Restraint of the
nature ordered by the learned Judge City Civil Court, in the
circumstances of the case, would not balance the equities
between the parties.
35) I am, therefore, persuaded to hold that the learned Judge,
City Civil Court did not adequately advert to the parameters of
4 2013 (3) Bom.C.R.669
6- A.O. 234-23+.DOC
balance of convenience and irreparable loss. The exercise of
discretion by the learned Judge thus deserves to be corrected.
36) Undoubtedly, the interest of the plaintiff also deserves to
be protected. Having regard to the nature of the suit claim, in
my view, restraining the defendant-appellant from alienating
and/or otherwise creating third party rights in three 2BHK flats
till the disposal of the suit would meet the exigency of the
situation and also equip the Court to work out the equities at
the stage of determination of the suit.
37) The Appeal thus deserves to be partly allowed.
38) Hence, the following order.
-:ORDER:-
(i) The Appeal stands partly allowed.
(ii) The Notice of Motion No. 1936 of 2022
stands dismissed, subject to the defendant and
the developer furnishing an undertaking, on an
affidavit, before the City Civil Court that they
would keep aside three 2BHK flats (to be
described with reference to number, area, floor
and wing, if any) and would not dispose of and/or
6- A.O. 234-23+.DOC
alienate and otherwise create third party rights in
those three flats till the final decision of the suit.
(iii) The undertaking be filed within a period of
two weeks from today.
(iv) The impugned order shall continue to
operate as an ad-interim order till the filing of
such undertaking.
(v) Upon filing the undertaking this order will
come into force and the impugned order shall
stand quashed and set aside.
(vi) In view of the disposal of the Appeal, the
Interim Application also stands disposed.
(vii) No costs.
[N. J. JAMADAR, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!