Citation : 2023 Latest Caselaw 593 Bom
Judgement Date : 17 January, 2023
908 SA 50.23, ia 457.23.doc
Dusane
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
SECOND APPEAL NO.50 OF 2023
WITH
INTERIM APPLICATION NO.457 OF 2023
Mr. Vinod Manohar Deshpande ...Appellants
(since deceased) through LRs.
Smt. Geetanjali Vinod Deshpande
& Ors.
V/s.
Mr. Satish Eknath Chauhan ...Respondent
Mr. Shailendra S. Kanetkar for Appellants/
Applicants
CORAM: MADHAV J. JAMDAR, J.
DATE: 17th JANUARY, 2023
P.C.:
1. Heard Mr. Kanetkar, learned Counsel appearing for the
Appellants. He submitted that following three substantial
questions of law are involved in the present Second Appeal:
(i) Whether the findings of both the Courts that the
Plaintiff has proved his readiness and willingness is in
accordance with the evidence on record ?
(ii) Whether the suit filed by the Respondent is within
limitation?
908 SA 50.23, ia 457.23.doc
(iii) Whether the Civil Court has jurisdiction to deal with
the Suit?
2. Before considering the substantial questions of law as
submitted by Mr. Kanetkar, it is relevant to note few factual
aspects.
3. Admittedly, the Appellants are the landlords of the
Respondent. As the suit building has become dilapidated, the
Appellants executed Agreement of Sale dated 22 nd October 2001
with the Respondent. The said agreement was executed by the
Appellant in his capacity as owner-developer and the
Respondent in his capacity as purchaser. By the said agreement,
the Respondent agreed to purchase from the Appellant flat
bearing No. C-1 on the 2nd Floor admeasuring about 650 sq.ft.
for total consideration of Rs.4,35,910/-. The said flat is agreed
to be purchased on the ownership basis. Out of the said
consideration, an amount of Rs.65,386/- i.e. 15% of the
consideration was paid by cash and cheque on the date of
execution of the said agreement and balance amount of
Rs.3,70,524/- was to be paid in instalments as set out in Clause-
(2) of the agreement. The said instalments are set out
hereinbelow for ready reference :
908 SA 50.23, ia 457.23.doc
1. 15% at the time of executing this Rs.65,386/-
Agreement
2. Completion of Plinth Rs.94,447/-
3. 22% on 1st Slab Rs.94,447/-
4. 22% on 2nd Slab Rs.94,447/-
5. 20% at the time of completion of Rs.87,183/-
P.M.C.
TOTAL Rs.: 4,35,910/-
4. Clause Nos. 3, 4 and 5 of the said agreement are also
relevant. The said clauses read as under:
"3. The party of the first part hereby agrees to hand over the possession of the flat agreed to be sold/ allotted to the party of second part, on or before 31st May 2003. The party of first part shall complete the construction of the said flat as agreed to herein within a period of 18 months from the date of this agreement and shall hand over the possession thereof to the party of second part after completing all flat amenities and civil work. If the owner developer fails to complete the construction and hand over vacant and peaceful possession within the stipulated time i.e. within 18 months from executing this agreement the owner developer shall pay Rs.5,000/- per month to the purchaser for delayed period. The purchaser shall have right to adjust the said amount in the instalments payable by the party of the second part.
4. The purchaser admit that the grant of completion certificate by the Pune Municipal Corporation in respect of the said flat shall be conclusive proof as to the completion of construction thereof.
5. The party of first part shall communicate to the party of second part on the completion of the said flat and purchaser shall pay the remaining balance out of the outstanding cost to the owner subject to clause No. 4 above and shall shift into the newly completed flat, more particularly described in Schedule 'B'."
(Emphasis added)
908 SA 50.23, ia 457.23.doc
5. The suit notice was issued on 9 th April 2008 and the suit
was filed on 21st August 2008 inter alia seeking specific
performance of agreement of sale dated 22nd October, 2001.
6. The substantial questions of law raised by Mr. Kanetkar,
learned Counsel appearing for the Appellants are required to be
examined in the light of factual position and the evidence on
record.
7. As far as the first substantial question of law that the
Plaintiff has proved his readiness and willingness is concerned, it
is the contention of Mr. Kanetkar that the Plaintiff has failed to
pay as per the instalments agreed in the agreement. Both the
Courts have concurrently found that the Defendant has not
informed the Plaintiff after completion of each stage of
construction and the Defendant has not issued any notice to the
Plaintiff to pay any instalment and therefore, the Plaintiff cannot
be faulted for non-payment of said instalments. In fact, both
the Courts have concurrently held that the Defendant has denied
the execution of agreement of sale itself and therefore noted the
said conduct of the Defendants.
8. The learned Courts have also taken into consideration the
aspect that the Plaintiff has deposited entire balance amount in
the Court after filing of the suit. Both the Courts have
concurrently found that the Plaintiff has proved his readiness
908 SA 50.23, ia 457.23.doc
and willingness.
9. It is also important to note that as per Clauses 3 to 5 of
the agreement, if on or before 31st May 2003, the Appellant fails
to hand over possession of the flat in question with completion
certificate of the Pune Municipal Corporation then the Developer
was under obligation to pay Rs.5,000/- per month to the
Respondent and the Respondent is entitled to adjust the said
amount in the instalments payable by the Appellant to the
Respondent. Admittedly, even till filing of Suit i.e. till August
2008, the flat was not ready. Therefore, the said amount of
compensation towards delay is more than Rs.3,00,000/-. The
Respondent has deposited entire balance payment in the learned
Trial Court after filing of Suit.
10. Mr. Kanetkar has failed to point out that the said finding
regarding readiness and willingness is contrary to the evidence
on record. Therefore, there is no substance in the first
substantial question of law raised by Mr. Kanetkar.
11. As far as second substantial question of law regarding
limitation, Clause 3 provides that the Defendant will handover
possession of the flat to the Plaintiff on or before 31 st May 2003.
It further records that the Defendant shall complete the
construction of the said flat within a period of 18 months. It is
further provided that if owner-developer fails to complete the
908 SA 50.23, ia 457.23.doc
construction and handover vacant and peaceful possession
within the stipulated time i.e. within 18 months from execution
of the agreement, the owner-developer shall pay Rs.5,000/- per
month to the purchaser for delayed period. It is further provided
that the purchaser shall have right to adjust the said amount in
the instalments payable by the party of the second part. Clause
4 provides that the grant of completion certificate of the Pune
Municipal Corporation in respect of the said flat shall be
conclusive proof as to the completion of construction thereof.
Clause 5 provides that the party of the first part shall
communicate to the party of the second part about the
completion of the said flat. It is the admitted position that the
Defendant has never communicated to the Plaintiff about
completion of the said flat and completion certificate as
contemplated under Clause 4 was not issued by the Pune
Municipal Corporation till filing of the suit.
12. Article 54 of the Limitation Act, 1963 specifies three years
as a period for filing suit for specific performance of a contract.
The said period begins to run from the date fixed for the
performance, or, if no such date is fixed, when the Plaintiff has
notice that performance is refused. Although in the agreement,
it is stated that the possession of the flat shall be handed over
on or before 31st May 2003, the agreement further contemplates
908 SA 50.23, ia 457.23.doc
that the owner-developer shall pay Rs.5,000/- per month to the
purchaser for delay in handing over possession. Agreement
further specifies grant of completion certificate by the Pune
Municipal Corporation, as conclusive proof as to the completion
of the construction. The agreement further contemplates that
the Defendant to communicate to the Plaintiff about the
completion of the said flat. Therefore, it cannot be said that the
date mentioned as 31st May 2003 is the last date fixed for
performance.
13. Article 54 further contemplates that if no such date is fixed
for performance then, when the Plaintiff has noticed that
performance is refused, it is the starting point of the limitation.
In the present case, admittedly no completion certificate was
issued by the Pune Municipal Corporation and in any case, the
Plaintiff has never communicated to the Plaintiff about the
completion of the said flat. Admittedly till filing of the Suit, the
flat was not completed. Both the Courts have concurrently held
that the suit is filed within limitation. The said finding is arrived
at on the basis of evidence on record. Mr. Kanetkar, learned
Counsel appearing for the Appellant failed to point out any
perversity in the finding recorded by the Court. Therefore, there
is no substance in the second substantial question of law raised
by Mr. Kanetkar.
908 SA 50.23, ia 457.23.doc
14. As far as third substantial question of law regarding
jurisdiction, Mr. Kanetkar submitted that the suit filed is between
the landlord and tenant and therefore the Civil Court has no
jurisdiction to deal with the said case.
15. Mr. Kanetkar fairly admits that the point regarding
jurisdiction is not raised in the written statement. However,
relying on the judgment of the Supreme Court in the case of
Sushil Kumar Mehta V. Gobind Ram Bohra (Dead) through
His LRs1, he submits that a decree passed by a Court without
jurisdiction over the subject matter or on other grounds which
goes to the roof of its exercise or jurisdiction, lacks inherent
jurisdiction. It is a coram non judice. A decree passed by such a
court is a nullity and is non est. Its invalidity can be set up
whenever it is sought to be enforced or is acted upon as a
foundation for a right, even at the stage of execution or in
collateral proceedings. Therefore, he submits that point of
jurisdiction can be raised even at the stage of Second Appeal.
16. Perusal of the written statement filed by the Appellant
shows that the point of jurisdiction is not at all raised. However,
it is very important to note that the Defendant has come up with
a case that the Defendant was in need of money to execute the
proposal regarding development of the said property and
1 (1990) 1 SCC 193
908 SA 50.23, ia 457.23.doc
therefore the Defendant was collecting funds from available
sources. It is further contended that as the Plaintiff offered to
provide finance of Rs.50,000/- subject to execution of an
agreement of sale of flat showing receipt of Rs.65,386/-, the
agreement was executed. The said contention raised can be
specifically seen from the paragraph 2 of the written statement,
which reads as under:
"2. It is true that this defendant is owner of CTS No. 543A, 543B and 545 Shivaji Nagar, Pune 05. It is also true that the defendant intended to develop above property. This defendant was in need of money to execute the proposal regarding development of above property. He was collecting funds from available sources. The Plaintiff is acquainted with the defendant. The Plaintiff offered to provide finance to the defendant of Rs.50,000/- (Rupees Fifty Thousand only) subject to execution of agreement of sale of flat showing receipt of Rs.65,386/- (Rupees Sixty Five thousand three hundred eighty six only). The agreement had to state price of flat of Rs.4,35,910/- (Rupees Four Lakhs thirty five thousand nine hundred ten only). However, the agreement was to be for security and on return of the advance it was to stand, cancelled. The Plaintiff did not agree to include this condition in the agreement asking the defendant to trust his word. The Defendant was in need of money and therefore executed suit agreement dated 22.10.2001. However, the agreement was not meant for specific performance."
(Emphasis added)
It is further pertinent to note that the Defendant has not entered
into witness box and has not lead any evidence.
908 SA 50.23, ia 457.23.doc
17. The agreement of sale describes the Defendant as owner-
developer and Plaintiff as purchaser. Thus the Suit has been filed
by the Plaintiff in his capacity of the flat purchaser. It is the
contention of the Defendant that the said agreement was
executed as security for the loan advanced by the Defendant.
Thus none of the parties have come up with the case that the
suit is between the Plaintiff and the Defendant in their capacity
as the landlord and tenants. Therefore, there is no substance in
the third substantial question of law raised by Mr. Kanetkar.
18. For the above reasons, the Second Appeal is dismissed
with no order as to costs.
19. In view of dismissal of the Second Appeal, nothing survives
in the Interim Application and the same is also disposed of.
BHALCHANDRA GOPAL DUSANE (MADHAV J. JAMDAR, J.) Digitally signed by BHALCHANDRA GOPAL DUSANE Date: 2023.01.19 18:22:09 +0530
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!