Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Classique Associates And Ors vs Kamlakar Motiram Satve And Anr
2023 Latest Caselaw 412 Bom

Citation : 2023 Latest Caselaw 412 Bom
Judgement Date : 11 January, 2023

Bombay High Court
Classique Associates And Ors vs Kamlakar Motiram Satve And Anr on 11 January, 2023
Bench: Sandeep V. Marne
                                                     1 / 27
                                                                    IA-10155-2022-PIL-131-2008+.doc


         rrpillai            IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                    CIVIL APPELLATE JURISDICTION

                                INTERIM APPLICATION NO. 10155 OF 2022
                                                     AND
                                INTERIM APPLICATION NO. 10110 OF 2022
                                                      IN
                             PUBLIC INTEREST LITIGATION NO. 131 OF 2008
                                                     WITH
                             PUBLIC INTEREST LITIGATION NO. 131 OF 2008
                        1.    Classique Associates

                        2.    HGP Community Pvt. Ltd.
                              Both having Registered Office at
                              514, Dalamal Tower, Nariman
                              Point, Mumbai 400 021
                                                                               ... Applicants
                              In the matter between

                        1.    Kamlakar Motiram Satve
                              Age about 49, occupation: service
                              and social worker, residing at Sita
                              Sadan, Opp. I.I.T Main Gate,
                              Tirandaz /village, Powai,
                              Mumbai-400 076

                        2.    Sou Usha Kamlakar Satve
                              Age about 44, occupation:
                              household work and social work,
                              residing at Sita Sadan, Opp. I.I.T
           Digitally
           signed by
           RAJESHWARI
                              Main Gate, Tirandaz /village,
RAJESHWARI RAMESH                                                              ... Petitioners
RAMESH
PILLAI
           PILLAI             Powai, Mumbai-400 076
           Date:
           2023.01.12
           16:19:53
           +0530
                             2 / 27
                                           IA-10155-2022-PIL-131-2008+.doc



                    Vs.
1.   The State of Maharashtra
2.   Department of Revenue & Urban
     Development, Government of
     Maharashtra, Mantralaya,
     Mumbai-400 032

3.   Mumbai Metropolitan Regional
     Development Authority
     Having office at Bandra Kurla
     Complex, Bandra (East),
     Mumbai-400 051
4.   Brihanmumbai Municipal
     Corporation through its
     Commissioner having his office at
     Mahapalika Bhavan, Opposite
     C.S.T., Fort, Mumbai-400 001
5.   Chittaranjan Chandrabhan
     Sharma age about 80, occupation:
     Builder having his office at C-104,
     Prashant Apartment, Opp IIT
     Main Gate, Powai,
     Mumbai 400 076
6.   Narottam Chittaranjan Sharma
     age about 80, occupation: Builder
     having his office at C-104,
     Prashant Apartment, Opp IIT
     Main Gate, Powai,
     Mumbai 400 076
                             3 / 27
                                           IA-10155-2022-PIL-131-2008+.doc



7.   Bhavanishankar (Lallu)
     Harishchandra Sharma
     Age about 60, Occupation :
     Builder, residing at Sharma
     Cottage, Behind Lake Cassel,
     Hiranandani Complex, IIT Powai,
     Mumbai-400 076 having his office
     at Bhavani Industrial Services
     Estate, Powai, Mumbai-400 076

8    Prashant Gopal Sharma
     Builder & Developer, 3rd Floor,
     G.H.P. Corporation,
     MilleniumTower, Near Petrol
     Pump, Powai, Mumbai-400 076

9    M/s. Hiranandani Developers Pvt.
     Ltd. Having its office at 'Olympia'
     Hiranandani Complex, Powai,
     Mumbai-400 076

10   Niranjan Hiranandani
     Age about 55, Occupation: Builder
     Managing Director of M/s.
     Hiranandani Developers Pvt. Ltd-
     the Respondent no. 9 having his
     office at at 'Olympia' Hiranandani
     Complex, Powai,
     Mumbai-400 076                                ... Respondents
                              4 / 27
                                          IA-10155-2022-PIL-131-2008+.doc

                             WITH
         ORDINARY ORIGINAL CIVIL JURISDICTION
       PUBLIC INTEREST LITIGATION NO. 91 OF 2008
                             WITH
            NOTICE OF MOTION NO. 437 OF 2011
                         AND
            NOTICE OF MOTION NO. 441 OF 2011
                          IN
       PUBLIC INTEREST LITIGATION NO. 91 OF 2008

Mr. Rajendra Thacker
Res. At Flat No. D1, Dwarkesh Park Co-
operative Housing Society, Sai Baba
Nagar, Borivali (West)
Mumbai-400 092                             ... Petitioner
                  Vs.
 1.    The State of Maharashtra
       Principal Secretary , Dept. of
       Urban Development Dept,
       Secretary Revenue and Forest
       Department, Mantralaya
       Mumbai-400 032
 2.    Mumbai Metropolitan Regional
       Development Authority
       Having office at Bandra Kurla
       Complex, Bandra (East),
       Mumbai-400 051
 3.    Slum Redevelopment Authority
       Regd Add : 5th floor, MHADA Bldg
       Kalanagar, Bandra (E),
       Mumbai-400 051
                               5 / 27
                                           IA-10155-2022-PIL-131-2008+.doc

 4.    Municipal Corporation of Greater
       Mumbai, Regd Add : Mahapalika
       Bhavan CST,Mumbai-400 001
 5.    Maharashtra Chamber of Housing
       Industry, Regd. Add : Maker
       Bhavan II 4th floor, 18/V
       Thackersey Marry, New Marine
       Lines, Opp. Income Tax Office,
       Mumbai

 6.    M/s. Hiranandani Construction
       Regd. Add: 'Olympia' Central
       Avenue, Hiranandani Gardens,
       Powai, Mumbai-400 076

 6A    Niranjan Hiranandani

 6B    Hiranandani Group of Companies

 6C    Lake View Developers
       All having address at : 'Olympia'
       Central Avenue, Hiranandani
       Gardens, Powai.                             ... Respondents

                        WITH
        ORDINARY ORIGINAL CIVIL JURISDICTION
      PUBLIC INTEREST LITIGATION NO. 21 OF 2010
                        WITH
           NOTICE OF MOTION NO. 442 OF 2021
                         IN
      PUBLIC INTEREST LITIGATION NO. 21 OF 2010
Medha Patkar
National Alliance for Peoples Movement
29-30 Haji Habib Building, Naigaon Cross
Road, Dadar (East), Mumbai-400 014                     ... Petitioner
                            6 / 27
                                        IA-10155-2022-PIL-131-2008+.doc

                 Vs.
1.   The State of Maharashtra
     Through the Secretary, Urban
     Development Department,
     Mantralaya, Mumbai
2.   The Secretary
     Housing and Special Assistance
     Department, Mantralaya,
     Mumbai

3.   Competent Authority
     Urban Land (Ceiling and
     Regulation) Act, 1976, New
     Administrative Building,
     Government Colony, Bandra
     (East), Mumbai-400 051

4.   The Commissioner
     Municipal Corporation of Greater
     Mumbai, Mahapalika Marg
     Mumbai - 400 001
5.   The Metropolitan Commissioner
     Mumbai Metropolitan Region
     Development Authority
     Having office at Bandra Kurla
     Complex, Bandra (East),
     Mumbai-400 051

6.   Shri Niranjan Hiranandani
     Hiranandani Gardens, Powai
     Mumbai                                     ... Respondents
                            7 / 27
                                    IA-10155-2022-PIL-131-2008+.doc

                        WITH
           CIVIL APPLICATION NO. 37 OF 2017
                          IN
      PUBLIC INTEREST LITIGATION NO. 131 OF 2008

M/s.Crescendo Associates and Ors.      ...Applicants
In the matter between
Kamlakar Motiram Satve and Anr.        ... Petitioners
        vs.
The State of Maharashtra and Ors.      ... Respondents

                        WITH
           CIVIL APPLICATION NO. 10 OF 2010
                        WITH
          CIVIL APPLICATION NO. 152 OF 2011
                          IN
      PUBLIC INTEREST LITIGATION NO. 131 OF 2008

Kamlakar Motiram Satve and Anr.        ...Applicants
In the matter between
Kamlakar Motiram Satve and Anr.        ... Petitioners

        vs.
The State of Maharashtra and Ors.      ... Respondents

                        WITH
          CIVIL APPLICATION NO. 153 OF 2011
                          IN
      PUBLIC INTEREST LITIGATION NO. 131 OF 2008

Niranjan Hiranandani and Ors.          ...Applicants
In the matter between
Kamlakar Motiram Satve and Anr.        ... Petitioners
        vs.
The State of Maharashtra and Ors.      ... Respondents
                              8 / 27
                                           IA-10155-2022-PIL-131-2008+.doc

                         WITH
            CIVIL APPLICATION NO. 36 OF 2017
                           IN
       PUBLIC INTEREST LITIGATION NO. 131 OF 2008

M/s. Lake View Developers and Ors.            ...Applicants
In the matter between
Kamlakar Motiram Satve and Anr.               ... Petitioners

         vs.
The State of Maharashtra and Ors.             ... Respondents


Dr. Milind Sathe, Senior Advocate a/w. Mr. Chetan Kapadia,
Ms. Vidisha Rohira, Mr. Parag Kabadi and Ms. Falguni Thakkar
i/b. DSK Legal for the Applicant.

Mr. P. P. Kakade, GP a/w. Mr. M.M. Pabale, AGP for the State.

Mr. Akshay Shinde for MMRDA.

Mr. Mihir Joshi for the Petitioner in PIL/21/2010.

Mr. Latika Kabad i/b. Mr. Rohit Joshi for Respondent nos. 5
and 6 in PIL/131/2008 and IA/10135/2022.

Mr. Akshay Shinde 'B' Panel Counsel a/w. Mr. P.P. Kakade, GP
and Ms. Nisha Mehra, AGP for the State.

Mr. Ramdas Shelke i/b. Mr. S.G.Deshmukh for the Petitioner in
PIL/131/2008.

Mr. Kedar Dighe, AGP for the State of Maharashtra.


                 CORAM : S.V. GANGAPURWALA, ACJ. &
                         SANDEEP V. MARNE, J.

DATED : 11 JANUARY, 2023 9 / 27 IA-10155-2022-PIL-131-2008+.doc

JUDGMENT (Per Sandeep V. Marne, J) :-

1. These three Public Interest Litigations involve the issue

of development of vast lands at Powai in Mumbai known as

"Powai Area Development Scheme" (for short PADS). The

constructions put up by the developer on these lands under

PADS have been challenged in these three Public Interest

Litigations praying inter alia for institution of inquiry in

respect of Tripartite Agreement dated 19 November 1986

executed between State of Maharashtra, Mumbai Metropolitan

Region Development Authority (MMRDA) and the developers.

2. Extensive interim order dated 22 February 2012 came to

be passed in the present Public Interest Litigations holding

that there was breach and non-compliance of the Tripartite

Agreement by the developers. This court therefore proceeded

to pass the following directions:

(a) The petitioners and the developer as also the Metropolitan Commissioner of the MMRDA shall prepare a statement of all the buildings and structures put up by the developer in the Powai ADS alongside their names and description and the numbers and area of the units/flats therein within 4 weeks from today.

(b) The petitioners, the developer and the Metropolitan Commissioner of the MMRDA shall prepare a plan showing the vacant areas of the plot under the Powai ADS, where further buildings may be constructed, within 4 weeks from today.

10 / 27 IA-10155-2022-PIL-131-2008+.doc

(c) If the parties are unable to work jointly they would be entitled to work individually in terms of (a) and (b) above.

(d) The developer shall not put up any further construction of whatsoever nature on the remainder of the plot under the Powai ADS before specifying the vacant lands and the buildings that can be constructed thereupon as per the statement and plan mentioned in clauses (a) and (b) above and shown to Court.

(e) The developer shall be entitled to commence any further construction only after obtaining the specific permission of this Court in that behalf and subject to the sanctioned plans of the MMC.

(f) Such construction shall be only of 1511 flats of 40 sq.mtrs 1593 flats of 80 sq.mtrs without any amalgamation, exception, or further allowance.

(g) No two flats shall be sold to the same person or any member of her/his family, being her/his spouse and children.

(h) The developer shall sell to the State Government from such construction such of the flats or units as would represent 15% of the total FSI of the total plot consumed under the development @ Rs.135/- per sq.ft. And the State Government shall offer those flats to be purchased by the employees of the State Government at the aforesaid rate in a transparent manner.

(i) After constructing and showing the Court the total number of units or flats constructed for residential purpose as initially required under the Powai ADS and after offering to sell the flats as directed in clause (h) above, the developer shall submit a report of such construction and sale to Court with a copy to the Petitioners in all the above Petitions, the MMRDA, the State Government and the MMC.

(j) The Developer shall thereafter be entitled to put any further construction as per law.

11 / 27 IA-10155-2022-PIL-131-2008+.doc

(k) The compensation for the breaches of the tripartite agreement claimed by the MMRDA shall be determined in the appropriate forum.

(l) The petitioners may file any private criminal complaint for any offence committed by the developer or any of the public officers of MMRDA or the State Government in the appropriate Court.

(m) All the writ petitions shall stand over to 29th March 2012 for placing on record the statement and plan as directed in clauses (a) and (b).

3. Thus under the interim order dated 22 February 2012,

this court directed the developers/applicants to complete

construction of 1511 flats of 40 sq.mtrs, 1593 flats of 80

sq.mtrs and to sell to the State Government such of the flats or

units as would represent 15% of the total FSI of the total plot

consumed under the development.

4. Further interim order came to be passed by this court on

3 October 2017 clarifying that the number of flats to be

constructed by the developer would be 1511 flats of 40 sq.mtrs

and 887 flats of 80 sq.mtrs. A timeline came to be set by this

court for completion of construction of such 1511 flats of 40

sq.mtrs and 887 flats of 80 sq.mtrs. In paragraph 22 of the

order, this court directed that in the event of the

developers/applicants failing to comply with any of the terms

and conditions laid down in the order, they would construct 12 / 27 IA-10155-2022-PIL-131-2008+.doc

additional 10% of the remaining flats to be constructed which

remained incomplete as on 1 June 2021.

5. The Interim Application no. 10155 of 2022 has been filed

by the developers/applicants seeking condonation of delay

with the following prayers:

(a) that this Hon'ble Court be pleased to condone the delay by extending time for completing the construction of 'A' & 'B' wings and 'C' wing of Atlantis building comprising of 448 number of flats of 80 sq. mtrs to March 2018 and February 2019 respectively.

(b) that this Hon'ble Court be pleased to extend the timelines for completing the construction of:

i. 'C' & 'D' Wings of Building Castle Rock till 30 th June, 2021 and 'A' & 'B' Wings of Building Castle Rock till 30th January 2022 (instead of December, 2020);

ii. the Building Regent Hill, Wings A & B, C, D & E till 30th January, 2023 (instead of 31st May 2021);

iii. the Building Sorrento till 15th June, 2023 (instead of December, 2020);

(c) for interim and ad-interim relief in terms of prayers (a) and (b) above;

(d) for such other and consequential reliefs as this Hon'ble Court may deem fit; and 13 / 27 IA-10155-2022-PIL-131-2008+.doc

6. When the Interim Application no. 10155 of 2022 came up

before this court on 9 April 2021, this court passed following

order :

I In so far as prayer (a) is concerned, the same stands deferred for consideration at a later stage.

II We allow the prayer clauses (b)(i) and (b)(ii).

III In so far as prayer (b)(iii) is concerned, the applicants shall file a better affidavit explaining the reasons for the delay in commencement of construction.

IV All other conditions imposed by the earlier orders of this Court shall remain intact.

V The Interim Application shall be listed once again on 9 th June 2021.

7. Thus prayer clause (b)(i) and (b)(ii) of the Interim

Application were allowed and while prayer clause (a) was

deferred for consideration at a later stage, the developers

/applicants were granted liberty to file better affidavit with

regard to prayer clause (b)(iii). Accordingly, the

developers/applicants have filed affidavit dated 7 June 2021

setting forth the reasons for delay in construction of flats in the

building 'Sorrento' covered by prayer clause (b)(iii). Further

affidavit dated 19 January 2022, 21 March 2022 and 22 June

2022 have been filed by the developers/applicants putting on 14 / 27 IA-10155-2022-PIL-131-2008+.doc

record progress made by them with regard to construction of

flats from time to time.

8. In the affidavit dated 22 March 2002, the

developers/applicants have put on record that the entire

construction is now complete and the obligation imposed by the

interim order dated 22 February 2022 read with the order

dated 3 October 2017 have been met with. It is stated that the

developers have completed construction of 1511 flats of 80

sq.mtrs and 1593 units of 40 sq. mtrs and have further handed

over 128 flats of 40 sq. mtrs and 128 flats of 80 sq.mtrs to the

State Government on 7 May 2022.

9. After consideration of the above affidavits, this court

constituted a three member committee to verify completion of

construction of 1109 flats of 40 sq.mtrs and 276 flats of 80 sq.

mtrs by its order dated 19 October 2022. The committee

appointed by this court submitted its report dated 1 November

2022 confirming completion of construction of 1109 flats of 40

sq. mtrs and 276 flats of 80 sq.mtrs.

10. Thus as of now the updated status of construction of the

flats by the developers is as follows:-

15 / 27 IA-10155-2022-PIL-131-2008+.doc

Buildings Completion/OC No. of flats O.C. Extension Prayer Present Status estimated date as per 40 sq.mtrs 80 sq.mtrs Received Prayed for Clause the Affidavit dated 24.9.2017 filed in this Hon'ble Court Atlantis-A & December 2017 294 28.03.2018 (a)

B Wings Atlantis-C June 2018 154 13.02.2019 (a)

Wing Hill Grange July 2018 172 172 19.06.2018 Maple September 2018 231 24.07.2018 Castle Rock- December 2020 224 26.11.2020

C & D Wings Castle Rock- December 2020 284 30.01.2022 (b)(i) Full OC for A Wing and Part A & B Wing OC for B Wing till 21st floor received on 14.9.2021 Regent Hill- May 2021 (as per the 1021 30.01.2023 (b)(ii) OC for Wings A and A,B,C,D & E Order dated 3.10.2017) received on 9.3.2022; OC Wings for Wings C, D and E received on 22.4.2022 Sorrento December 2020 88 15.06.2023 (b)(iii) OC received on 13.6.2022 TOTAL 1512 1128

11. Thus, as against direction of this court in interim orders

dated 22 February 2012 and 3 October 2017 for construction of

887 flats of 80 sq.mtrs, the developer/applicants have

constructed 1150 flats of 80 sq. mtrs. However there appears

to be delay in construction of some of the flats. It is evident

from the above chart showing updated status of construction.

So far as 'A' and 'B' wings of 'Atlantis' building is concerned,

294 flats of 80 sq.mtrs which were required to be constructed

by December 2017 are constructed by 28 March 2018. In 'C'

wing of 'Atlantis' building 154 flats of 80 sq. mtrs which were

supposed to be complete by June 2018 are constructed by 13 16 / 27 IA-10155-2022-PIL-131-2008+.doc

February 2019. These flats are covered in prayer clause (a) of

the Interim Application no. 10155 of 2022 which was deferred

by this court by its order dated 9 April 2021. So far as 88 flats

of 40 sq. mtrs in building 'Sorrento' are concerned, the same

were required to be completed by December 2020. However,

the same appears to have been constructed by 13 June 2022.

These flats are covered by prayer clause (b)(iii) of the Interim

Application for which developers/applicants were granted

liberty to file better affidavit by order dated 9 April 2021.

12. We have heard Dr. Sathe, the learned Senior Advocate

assisted by Mr. Chetan Kapadia for the developers/applicants.

Mr. Sathe would take us through the affidavits explaining the

reasons for delay in construction of some of the flats. He would

submit that the delay caused in construction of some of the

flats in the building 'Sorrento' was essentially on account of the

requirement of obtaining environmental clearances, which was

beyond the control of the developers. That the entire obligation

of construction of requisite number of flats and handing over of

requisite area to the State Government being met by the

Developers, they should now be permitted to proceed further

with the development of PADS by lifting all fetters imposed by 17 / 27 IA-10155-2022-PIL-131-2008+.doc

this court in its various interim orders. He would further

submit that the bonafides of the developers are clear from the

fact that they have developed additional flats of 80 sq. mtrs

than the one required under the interim orders of this Court.

Dr. Sathe would further contend that as directed by this court

in paragraph 53(g) of the interim order dated 22 February

2012 developers have scrupulously followed the conditions of

not selling two flats to the same person or any member of

her/his family, being her/his spouse and children.

13. Mr Joshi, the learned counsel appearing for the

Petitioner in PIL/21/2010 would oppose the prayers in the

Interim Application filed by the developers contending that the

justification of delay in obtaining environment clearance for

construction of the building 'Sorrento' is required to be

rejected as the developers always had the knowledge about

mandatory requirement of law for obtaining environmental

clearance. He would submit that on account of inordinate delay

in construction of 88 flats of 40 sq.mtrs in building 'Sorrento',

the direction in paragraph 22 of the interim order dated 22

August 2017 for construction of additional 10% flats would

automatically kick in. He would therefore urge before us to 18 / 27 IA-10155-2022-PIL-131-2008+.doc

direct further construction of 10% additional flats of 80 sq.

mrts. by the developers.

14. We have also heard Mr. Kakade, the learned Government

Pleader who draws our attention to the affidavit dated 19

September 2022 in which the State Government has also

clarified that the developers/applicants have complied with all

the obligations. We would refer to the relevant paragraphs of

the affidavit dated 19 September 2022 in which it is averred in

paragraph 6 to 8 as under:

6. On 7th May, 2022, the Respondent No. 2, MMRDA has taken possession of 128 flats of 40 sq. mtrs and 128 flats of 80 sq.mtrs having area aggregating 17,173.70 sq.mtrs against 17,146.05 sq.mts in the Hill Grange Building. Hereto annexed and marked Exhibit "A" and "A-1" is copy of the said Possession Receipt dated 7 th May, 2022 along with the English translation.

7. Thus, the Applicant has complied with the obligation of handing over 17,146.05 sq.mtrs to State Government as specified in paragraph 53(h) of the said Judgment dated 22nd February, 2012 read with the paragraph (3) of the Order dated 3rd October, 2017.

8. Thus, the Applicants have complied with the paragraph no. 53 (f) of the said Judgment dated 22 nd February, 2012 read with paragraph no. 16 of the Order dated 3rd October, 2017 in respect of construction of 40 sq.mtrs and 80 sq.mtrs flats.

19 / 27 IA-10155-2022-PIL-131-2008+.doc

15. We have also heard Mr. Shinde, the learned counsel for

MMRDA who also does not dispute fulfillment of obligations

under the interim orders of this Court by the

developers/applicants.

16. Having heard the learned counsels for rival parties and

after perusal of previous orders passed by this court and

various affidavits filed by the parties, the undisputed position

that emerges is that the developers/applicants have fulfilled

the entire obligations cast upon them by this Court by its

interim orders. However they have defaulted in respect of

timeline with regard to construction of some of the flats as

detailed above. This court has already granted prayer clauses

b(i) and b(ii) of the Interim Application No. 10155 of 2022 and

has thereby extended the timeline in respect of some the flats

in buildings 'Castle Rock' and 'Regent Hill' to 30 January 2022

(instead of December, 2020) and 30 January 2023 (instead of

31 May 2021) respectively. What remains now is to extend the

timeline/ condone the delay in construction of some of the flats

in buildings 'Atlantis' and 'Sorrento'.

17. In the affidavit dated 7 June 2021, the

developers/applicants have provided justification for delay in 20 / 27 IA-10155-2022-PIL-131-2008+.doc

construction of flats in building 'Sorrento' covered by prayer

clause (b)(iii). We have gone through the affidavit dated 7 June

2021. It appears that the developers/applicants had obtained

Environment Clearance on 10 April 2014 in respect of other

buildings such as Atlantis, Mapple and Hill Grange and since

'Sorrento' was newly proposed after the year 2014, the earlier

Environment Clearance of 2014 did not apparently cover it.

Therefore a common application for environment clearance

was made to the Central Government on 3 August 2017 for

proposed expansion of residential buildings (including

Sorrento) and on account of non-convening of meeting of

Expert Appraisal Committee, the application remained

pending. Due to change in the policy of grant of EC by the State

Environment Assessment Committee, developers/applicants

were required to re-apply for EC on 17 May 2018 at the State

Government level.

18. The State Expert Appraisal Committee (SEAC II) in its

77th meeting held on 16 November 2018 considered

developers'/applicants' application but decided to defer the

same seeking certain clarifications. The clarifications were

provided by the developers on 6 December 2018. Thereafter in 21 / 27 IA-10155-2022-PIL-131-2008+.doc

various meetings of SEAC II the proposal was deferred for

various reasons, details of which are stated in the affidavit.

Ultimately SEAC recommended the proposal to State

Environment Impact Assessment Authority (SEIAA) for

approval on 24 February 2019. SEIAA granted environment

clearance to the developers/applicants on 29 May 2019 subject

to conditions. This is how final environment clearance came to

be granted in respect of various buildings including Sorrento

on 14 June 2019. The affidavit dated 7 June 2021 also states

the reason of delay in issuance of NOC for tree cutting resulted

in delay in issuance of Commencement Certificate from 31

August 2018 to 6 March 2019. Another reason cited is sub

division of plot-layout as per condition 10 of the IOD which

consumed time between 20 November 2018 to 5 July 2019.

Last impediment cited is about the ambiguity regarding

applicability of Development Control & Promotion Regulations,

2034 and its effect requiring amendment of layout and plans.

19. For the above quoted reasons delay, in completion of 88

flats of 40 sq.mtrs in building Sorrento is sought to be justified.

It must however be noted here that in prayer clause (b)(iii),

the developers/applicants sought extension of time upto 15 22 / 27 IA-10155-2022-PIL-131-2008+.doc

June 2023 for completion of those flats, whereas they were

able to complete construction of the building 'Sorrento' on 13

June 2022 itself, i.e. before the extension sought.

20. Having gone through the reasons set forth in the affidavit

dated 7 June 2021 with regard to delay in construction of 88

flats of 40 sq.mtrs in building 'Sorrento', we record our

satisfaction about the justification given therein. Therefore we

are of the view that prayer clause b(iii) sought for in the

Interim Application No. 10155 of 2022 deserves to be granted.

21. In additional affidavits filed on 19 January 2022, 22

March 2022 and 22 June 2022, the developers/applicants

have put on record as to how the construction progressed and

how ultimately the entire obligations of construction of both

categories of flats were finally completed by them.

22. So far as prayer clause(a) of the Interim Application No.

10155 of 2022 is concerned, the delay in construction of 294

flats of 80 sq.mtrs in 'A' and 'B' wing of building 'Atlantis' is

only of three months. They were to be constructed by

December 2017, but have been constructed by 28 March 2018.

So far as 154 flats of 80 sq.mtrs in 'C' wing of building 'Atlantis' 23 / 27 IA-10155-2022-PIL-131-2008+.doc

is concerned, again the delay is about seven and a half months.

They were to be constructed by June 2018 and are actually

constructed by 13 February 2019. Since the delay in

construction of flats covered by prayer clause (a) of the

Interim Application is not significant, we propose to condone

the same. It must be observed here that under the interim

orders of this court, the developers/applicants were under

obligation to construct only 887 flats of 80 sq.mtrs whereas

they have constructed 1150 flats of 80 sq.mtrs i.e more than

the obligation casted by this court. This is yet another factor to

be borne in mind while considering the prayer of the

developers/applicants for condonation of delay in respect of

flats covered by prayer clause (a) of the Interim Application.

23. As observed above, this court has already granted prayer

clause (b)(i) and b(ii) of the Interim Application. As observed

above we are inclined to grant prayer clauses (a) and (b)(iii) of

the Interim Application No. 10155 of 2022.

24. Interim Application No. 10110 of 2022 has been filed

seeking direction to transfer the amount of Rs. 112.35 cores

(approx.) presently lying in the joint account held in the names

of Applicants (Classique Associates and HGP Community Pvt.

24 / 27 IA-10155-2022-PIL-131-2008+.doc

Ltd.) and the Prothonotary and Senior Master of this court

into the bank account maintainable by the applicants in

accordance with the provision of the Real Estate (Regulation

and Development) Act, 2016 in respect of building 'Regent Hill'

to be utilised for the purpose of construction of the building.

Prayer is also made to deposit the considerations received by

the developers/applicants from sale of the balance flats into

their bank accounts. Now that interim orders of this court are

already satisfied by the developer/applicants, the sale proceeds

deposited as per interim order dated 3 October 2017 lying in

the above joint accounts can be permitted to be withdrawn by

the applicants (Classique Associates and HGP Community Pvt.

Ltd.). Thus the Interim Application No. 10110 of 2022 can also

be disposed of permitting withdrawal of such amounts.

25. While hearing the Interim Application nos. 10155 of 2022

and 10110 of 2022, it is noticed that the main Public Interest

Litgations have not yet been disposed of. By the initial

extensive interim order though this court issued various

directions in the main PILs, the same were adjourned to 19

March 2012 seeking compliance. Thereafter various interim

orders appear to have been passed in the PILs. However all the 25 / 27 IA-10155-2022-PIL-131-2008+.doc

three PIL Nos. 131 of 2008, 91 of 2008 and 21 of 2010 continue

to remain pending. The aspect of violation of Tripartite

Agreement on the part of the developers, which is the main

issue in all there PILs, has already been dealt with in the

interim order dated 22 February 2012 and corrective

measures were directed to be undertaken. Thus the main issue

involved in the PILs has already been decided by the interim

order dated 22 February 2012. With complete compliance of all

obligations put on the developers/applicants for construction

of flats and handing over tenements to the State Government,

we observe that no purpose would be served in keeping the

PILs pending any further. Therefore while disposing of the

Interim Application No. 10155 of 2022 and 10110 of 2022, we

propose to dispose of the main PILs as well. Accordingly, we

proceed to pass the following order :

ORDER

(i) Interim Application No. 10155 of 2022 is allowed in

terms of prayer clause (a) and (b)(iii) as well.

(ii) Delay in construction of some of the flats as per the

directives of this court in the interim order dated 22 February

2012 and 3 October 2017 shall stand condoned.

26 / 27 IA-10155-2022-PIL-131-2008+.doc

(iii) It is recorded that the developers/applicants have

completed construction of 1511 flats of 40 sq.mtrs and 887

flats of 80 sq.mtrs as envisaged in the interim orders dated

22 February 2012 and 3 October 2017.

(iv) It is further recorded that the flats having aggregate area

of 17146.05 sq.mtrs have been handed over by the developers/

applicants to MMRDA which has issued possession receipt

dated 7 May 2022.

(v) In view of compliance of all the obligations imposed on

the developers/applicants by interim order dated 22 February

2012 and 3 October 2017, all restraints imposed in paragraph

53 of the order dated 22 February 2012 are vacated and the

developer/applicants shall be at liberty to proceed with

development of PADs land without any embargo/restrictions

including regarding size of tenements or joint use of the

tenements, amalgamation or construction of tenements for

commercial use.

(vi) The amounts of sale proceeds deposited as per order

dated 3 October 2017 lying in the joint accounts held jointly by

applicants (Classique Associates and HGP Community Pvt.

Ltd.) and Prothonotary and Senior Master of this court along 27 / 27 IA-10155-2022-PIL-131-2008+.doc

with interest accrued thereof are permitted to be withdrawn

by the joint applicants and the Prothonotary and Senior

Master is directed to take steps to close the joint accounts. As a

result, Interim Application No. 10110 of 2022 seeking

withdrawal of the amounts stands disposed of.

(vii) The one-man committee headed by Justice S.

Radhakrishnan (Retired) appointed by this court by order

dated 3 October 2017 shall stand discharged.

(viii) It is made clear that all other directions given in the

interim order dated 22 February 2012 and 3 October 2017,

except as modified by the present judgment, shall continue to

operate.

(ix) Public Interest Litigation Nos. 131 of 2008, 91 of 2008

and 21 of 2010 stands disposed of.

(x) In view of the disposal of the Public Interest Litigations

all Interim Applications, Civil Applications and Notices of

Motion stand disposed of.

(xi) There shall be no orders as to costs.

(SANDEEP V. MARNE, J.) (ACTING CHIEF JUSTICE)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter