Citation : 2023 Latest Caselaw 360 Bom
Judgement Date : 10 January, 2023
k 1/5 80 wp 10072.22 as.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO.10072 OF 2022
Sreebalajee Consultants ....Petitioner
V/S
Mira Bhayander Municipal Corporation & Ors. ....Respondents
...
Mr. K.P.Anil Kumar a/w Ms. Roshni Viani, Ms. Priyanka Kumar, Mr. Chinmay
Apte for the Petitioner.
Mr. Mayuresh Lagu for Respondent Nos.1 and 2-Corporation.
...
CORAM: S.V. GANGAPURWALA, ACJ &
SANDEEP V. MARNE, J.
DATE : 10 JANUARY 2023.
P.C.:
1 Pursuant to the tender notice the Petitioner had submitted its bid for
construction, maintenance, repair of bus stop, shops in Mira Bhayander
Municipal Corporation area on build-use-and-transfer basis and grant of
rights to the broadcast advertisements on the bus stops. The Petitioner
was held eligible in the technical and financial bid. The Petitioner was found
to be the highest bidder. It is the case of the Petitioner that Petitioner was
called for negotiation and the Petitioner had increased is offer by
Rs.15,00,000/-. The Petitioner agreed also. However, on or about 6 August
2022 the tender was cancelled.
2 The learned Counsel for the Petitioner submits that the entire tender SUDARSHAN RAJALINGAM KATKAM process pursuant to which the Petitioner had filled the tender was Digitally signed by
SUDARSHAN RAJALINGAM KATKAM Date: 2023.01.12 11:02:14 +0530 k 2/5 80 wp 10072.22 as.doc
completed. The Petitioner was found to be the highest bidder and qualified
with each and every terms and conditions of the tender. The Petitioner was
called for negotiation for increasing his offer by Rs.15,00,000/- and it agreed
for the same. Pursuant to the request of the Respondent-Corporation the
Petitioner also constructed the model bus stand and had spent an amount
of Rs.12,00,000/-. It was arbitrary on the part of the Respondent-
Corporation to cancel the tender at such an advanced stage. The entire
process of the tender having concluded, only work order remained to be
issued. According to the learned Counsel, the reason for cancellation of the
tender is erroneous, unreasonable and irrational. The learned Counsel
further submits that thereafter second and third tenders were issued but the
Respondent-Corporation did not get any bidder. The fourth tender was also
issued surreptitiously by increasing the eligibility criteria of turn over of Rs.1
crore per year to turn over of Rs.3 crores. The same was to favour the
contractor in which the Respondent-Corporation was interested. For the
fourth tender a cartel was created and the same entity in two names had bid
in the tender process. According to the learned Counsel, if the decision
making process is arbitrary then this Court can interfere and exercise its
powers of judicial review under Article 226 of the Constitution. The learned
Counsel relies upon the judgment of the Apex Court in case of Food
Corporation of India vs. M/s. Kamdhenu Cattle Feed, reported in AIR
k 3/5 80 wp 10072.22 as.doc
1993 SC 1601. The learned Counsel further submits that it is a legitimate
expectation of tenderer that being highest bidder, would be entitled for the
work order. The learned Counsel further relies upon the judgment of the
Apex Court in the case of B.S.N. Joshi & Sons Ltd. vs. Nair Coal
Services Ltd. & Ors. reported in (2006) 11 SCC 548 to submit that
marginalization by bidding contractor is impermissible. The act of the
Respondent-Corporation is not bonafide and is stated to be malafide.
3 The learned Advocate for the Respondent-Corporation submits that
no work order was issued in favour of the Petitioner. It was found by the
Committee that the price received was too less and therefore a decision
was taken to float fresh tender. The fresh tenders were floated for the
second and third time but no eligible bids were received. However, in the
fourth tender the highest bidder was 30% more than the Petitioner, the
Respondents are benefitted by the better retendering. The Petitioner has
not challenged the decision to proceed with retendering.
4 We have considered the submissions. 5 The jurisdiction of this Court to entertain a Writ Petition in respect of
contractual matters and/or tender is in a narrow campass. This Court would
only concerned with the decision making process and not the decision. This
Court would not sit as an Appellate Authority over the decision taken by the
k 4/5 80 wp 10072.22 as.doc
Respondent-Corporation but is only concerned with a due adherence of the
decision making process.
6 It appears that when the first tender was issued, the Petitioner was
the highest bidder. According to the Petitioner the bid was also raised by
Rs.15,00,000/- and that the model bus stop was also constructed. However,
the same does not find approval from the Respondent-Corporation.
7 The Petitioner was never issued with the work order. No concluded
contract came into existence between the parties. As concluded contract did
not come into existence, the Petitioner did not get the vested right nor any
contractual obligation arose.
8 Be that as it may, the decision was taken by the Committee of the
Respondent-Corporation to cancel the tender process and to go for fresh
bidding as it was observed in the order wherein decision was taken for fresh
tender that though the Petitioner claims to have agreed to enhance the
amount by Rs.15,00,000/- no such communication was given in writing. It
was also observed that considering the growth of the city and that in future
metro would also start running, more income would be derived from the
advertisements and various reasons were given for fresh tender. Thereafter,
second and third tenders were issued but there were no bidders and in the
fourth tender process, two bids were received. The highest bidder was 30%
k 5/5 80 wp 10072.22 as.doc
more than the Petitioner's bid. The Respondent-Corporation would be
benefited by an amount of Rs.2.5 crores in total. The public exchequer
would be benefited. There is no concrete proof of cartelisation as alleged.
9 The Petitioner has also not challenged the decision of the
Respondent-Corporation to go for fresh tender process.
10 Considering all the aforesaid conspectus of the matter, we are not
inclined to exercise our writ jurisdiction under Article 226 of the Constitution.
11 The Writ Petition as such is dismissed. No costs.
12 At this stage, the learned Advocate for the Petitioner submits that the
Respondents be directed to refund the costs incurred in constructing the
model bus stop i.e. Rs.12,00,000/-. The said amount is disputed by the
Respondent-Corporation. The Petitioner may file a civil suit or take
appropriate steps as may permissible in that regard. In that event the
contentions of respective parties are kept open.
(SANDEEP V. MARNE, J.) (ACTING CHIEF JUSTICE)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!