Citation : 2022 Latest Caselaw 11117 Bom
Judgement Date : 19 October, 2022
P.H. Jayani 18(A) FAST25538.2022.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
INTERIM APPLICATION NO. 16726 OF 2022
IN
FIRST APPEAL (ST.) NO. 25538 OF 2021
Executive Engineer,
Kadava Kadava (Canal) Project,
Nashik .... Applicant
v/s.
Vatsalabai Nathu Bhalerao and anr. .... Respondents
Ms. Chaitrali Deshmukh for the Applicant.
Ms. Tanaya Goswami, AGP for the State.
CORAM: SMT. ANUJA PRABHUDESSAI, J.
DATED : 19th OCTOBER, 2022.
P. C. :-
. By this Application, the Applicant has sought stay of execution
and implementation of the impugned judgment dated 26/07/2018 in
Land Reference No.362/2010.
2. Learned counsel for the Applicant states that entire compensation
as per the impugned judgment and award shall be deposited before the
Civil Judge, Senior Division (Reference Court), Nashik within a period
of four weeks.
3. In the light of said statement, execution and implementation of
the impugned judgment dated 26/07/2018 is stayed till the next date
P.H. Jayani 18(A) FAST25538.2022.doc
of hearing. Issue notice to Respondent No.1, returnable on
06/12/2022. Learned AGP waives service of notice on behalf of
Respondent No.2.
4. Stand over to 06/12/2022.
PREETI H JAYANI (SMT. ANUJA PRABHUDESSAI, J.) Digitally signed by PREETI H JAYANI Date: 2022.10.21 17:16:21 +0530
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!