Citation : 2022 Latest Caselaw 10617 Bom
Judgement Date : 13 October, 2022
2939.17-wp.docx
Digitally IN THE HIGH COURT OF JUDICATURE AT BOMBAY
signed by
BASAVRAJ ORDINARY ORIGINAL CIVIL JURISDICTION
BASAVRAJ GURAPPA
GURAPPA PATIL
PATIL Date: WRIT PETITION NO. 2939 OF 2017
2022.10.13
20:34:08
+0530
Safex Chemicals India Ltd.
807, Crown Heights,
Plot No.3B1, Twin District Centre,
Sector 10, Rohini,
New Delhi - 110085, India ..... Petitioner
Versus
1 The Controller of Patents & Designs,
Baudhik Sampada Bhawan,
Antop Hills, Near Head Post Office,
Wadala, Mumbai - 400037
2 Deepak Pranjevandas Shah,
501/502, Vandana Apartments,
Janki Kutir, Juhu Church Road,
Juhu, Mumbai - 400053 ..... Respondents
Mr. J. P. Sen, Senior Advocate with Mr. Alankar Kirpekar, Mr. S. K.
Bansal, Mr. Ajay Amitabh Suman, Mr. Shekhar Bhagat I/b. MAG
Legal for the Petitioner
Mr. Neel G. Helekar a/w. Mr. kanhaiya S. Yadav, Mr. Govind Prajapati
a/w. Mr. Dushyant Kumar for Respondent No.1
Mr. Venkatesh Dhond, Senior Advocate a/w. Mr. Rohan Kadam,
Mr. Shriraj Dhruv, Mr. Mitesh Naik and Mr. Ronak Shah I/b. Dhru &
Co. for Respondent No.2.
CORAM: S.V.GANGAPURWALA &
MADHAV J. JAMDAR, JJ.
JUDGMENT RESERVED ON : AUGUST 20, 2022
JUDGMENT PRONOUNCED ON : OCTOBER 13, 2022
Basavraj 1/29
2939.17-wp.docx
JUDGMENT (PER : S.V. GANGAPURWALA, J.)
1 The Petitioner challenges the order passed by the Controller of
Patents dated 11th April 2017 thereby dismissing the pre grant
opposition Applications filed by the Petitioner and other opponents
and has allowed Respondent No.2's Application for patent titled a
"Novel Agricultural Composition" that increases crop yields.
2 Mr. Sen, the learned Senior Advocate for the Petitioner
eruditely canvassed the following submissions:
According to Mr.Sen, the learned Senior Advocate, the
amendment Application filed by Respondent No.2 was allowed and
the Petitioner was not intimated about the allowance of the
amendments. The Petitioner was not given an opportunity to file an
appropriate pre grant opposition to the amended claims and to
advance oral arguments. This constitutes blatant denial of natural
justice. The learned Controller of Patents allowed the 5 th
amendment Application filed on 26th July 2016 vide order dated 9 th
September 2016. The said order ought to have been informed to the
Petitioner thereby directing them to file amended pre grant
opposition. The learned Controller of Patents nor Respondent No.2
informed the Petitioner that the Controller of Patents had already
allowed the amendment Application on 9th September 2016 till the
Basavraj 2/29 2939.17-wp.docx
date of hearing on 24th February 2017. Even on that day, no copy of
the order allowing the amendment Application was furnished to the
Petitioner. It was only during pendency of the Writ Petition, the
Petitioner could get a copy of the said order. The original patent
Application was filed by Respondent No.2 in the year 2007. The
Petitioner had filed its pre grant opposition Application in the year
2013. The allowance of the 5th amendment Application of
Respondent No.2 ought to have been informed to the Petitioner so as
to file an amended pre grant opposition. The Petitioner was deprived
of the opportunity. The same is in flagrant violation of principles of
natural justice. The order, as such, granting patent is bad in law and
deserves to be set aside.
The learned Senior Advocate further submits that the
Petitioner requested the learned Controller to decide the amendment
Application first and then allow the Petitioner to advance its
arguments on the basis of final claims as found satisfactory by the
Controller of Patents. It was always a case of the Petitioner that the
Petitioner shall be informed about the final amended Application if
the amendment is allowed by the Controller in order to enable the
Petitioner to file amended pre grant opposition and argue the matter.
The learned senior Advocate submits that, initially, the patent
Application was filed on 8th January 2007 with 1 to 15 claims by
Basavraj 3/29 2939.17-wp.docx
Respondent No.2. On 6th May 2008 first amendment Application was
filed in response to the examiner report with 13 claims. On 9 th June
2008 second Application was filed with 11 claims. On 17th July 2009,
third amendment Application was filed with 10 claims. Initially, on
24th October 2009, the Controller of Patents allowed the pre grant
opposition. The same was confirmed by the IPAB under its order
dated 4th April 2012. On 23rd August 2013 the Petitioner filed a
Notice of Opposition. On 13th April 2016 this court set aside the
orders of the IPAB on the ground of violation of principles of natural
justice. Thereafter on 21 st April 2016 the IPAB set aside the order of
the Controller and the matter was remanded back to the Controller
of Patents. On 5th July 2016 fourth amendment Application with 9
claims was filed. On 26th July 2016 fifth amendment Application
with 9 claims was filed. Under letter dated 6 th September 2016 the
Controller of Patents informed the Petitioner that in view of the
hearing held on 22nd August 2016, with mutual consent of the
parties, the matter got adjourned for arguments on amendment
Application on Form 13 and Opposition, both. Under letter dated 7 th
September 2016 the Petitioner informed the Controller of Patents
that it was never agreed that the amendment Application and the
pre grant opposition be decided together. The Petitioner always
insisted for adjudication of amendment Application first. On 8 th
Basavraj 4/29 2939.17-wp.docx
September 2016, interlocutory petition was filed by the Petitioner
vide email seeking disposal of the amendment Application first. On
9th September 2016 the Controller allowed the amendment
Application of Respondent No.2. On 24 th February 2017 hearing of
the Petitioner's pre grant opposition was held by the Controller of
Patents. On the said date, the Petitioner insisted for disposal of its
interlocutory petition and requested the amendment Application be
decided first. On the said date, the Petitioner was never informed
that the amendment Application has already been allowed vide
order dated 9th September 2016. Even copy of the said order was not
given to the Petitioner. The Petitioner, again on 28 th February 2017
requested for hearing and disposal of the amendment Application
first, as he was not aware that the amendment Application was
allowed on 9th September 2016. On 11 th April 2017 the Controller
rejected the pre grant opposition and granted impugned patent. The
Petitioner, on 24th February 2017 submitted that it was unclear as to
which amendment Application was being argued. The Controller of
Patents approbated and reprobated at the same time in the
impugned order by saying that the amendments are already allowed
and there is no point in making submissions on amended claims,
while in the said order, the Controller says that the Petitioner has
been directed by the Controller to argue the pre grant opposition on
Basavraj 5/29 2939.17-wp.docx
the basis of original patent Application as filed in the year 2007,
original pre grant opposition as filed by the Petitioner in the year
2013 and the amendment is allowed by the Controller on 9 th
September 2016 but never informed about the same to the
Petitioner. The Controller observed that he had allowed the
amendment Application, hence directed the Petitioner to argue the
pre grant opposition without allowing the Petitioner to carry out the
amendments subsequent to the amendment of patent Application.
The order impugned dated 11th April 2017 was passed on
interlocutory Application and the Petitioner's request for hearing
the amendment Application is pending. The Petitioner was never
given an opportunity to argue its case on amendment Application
nor was given an opportunity to prosecute its amendment
Application for pre grant opposition with respect to the already
allowed alleged amendment Application. The impugned order is in
clear violation of principles of natural justice, as such, deserves to be
set aside.
The learned Senior Advocate for the Petitioner further submits
that the post grant opposition under section 25(2) is not an
alternate remedy to the proceedings under section 25(1), if the
order of pre grant opposition is challenged by way of Writ Petition.
Reliance is placed by the learned Senior Advocate on the Division
Basavraj 6/29 2939.17-wp.docx
Bench judgment of this Court in the case of Neon Laboratories Pvt.
Ltd. Vs. Troikaa Pharma Ltd. 1 The learned Senior Advocate for
the Petitioner further relies on the judgment of the Division Bench of
the Madras High Court in the case of Indian Network of People
living with HIV/AIDS Vs. Union of India 2 to submit that pre grant
opponent is entitled to a hearing and in the event the patent
Application is allowed, then on the claims as amended. It is also
settled law that post grant hearing is no substitute for a pre grant
hearing and an opportunity to file a post grant opposition under
Section 25(2) is not an alternate remedy that would affect in any
way the maintainability of the Writ Petition filed by the opponent
challenging the dismissal of his pre grant opposition under Section
25(1). The learned Senior Advocate also relies upon the judgment
on similar legal proposition in case of the Glochem Industries Ltd.
Vs. Cadila Healthcare Ltd. & Ors. 3 and judgment of this Court in
the case of TATA Chemicals Ltd. Vs. Union of India & Ors. 4. The
learned Senior Advocate also relies on the judgment of the apex
court in the case of Whirlpool Corporation Vs. Regsitrar of
Trademarks, Mumbai & Ors. 5 to contend that the availability of
alternate remedy would not be a bar for this Court to entertain the
1 2011 (45) PTC 357 2 2009 (39) PTC 468 3 2010 (44 ) PTC 363 (Bom) 4 Judgment dated 08-10-2013 in Writ Petition No.6561 of 2013 5 1998 (8) SCC 1
Basavraj 7/29 2939.17-wp.docx
Writ Petition .
The learned Senior Advocate further relies upon the judgment
of the learned single Judge of Delhi High Court in case of Best Agro
Life Ltd. Vs. Dy. Controller of Patents 6 and submits that in the
said Writ Petition it has been held that pre grant opposition can
never be equated with the post grant opposition or revocation
petition under Section 64 of the Patent Act, 1970. The impugned
judgment deserves to be set aside.
3 Mr.Dhond, learned Senior Advocate for Respondent No.2 in his
usual lucid style put-forth the following submissions:
The Petitioner has suppressed that it has already availed of an
alternate and efficacious remedy by filing the post grant opposition
proceedings under section 25(2) of the Patents Act, 1970. Having so
elected and availed of remedy, thereafter suppressed the same from
this Court. The Petitioner has no right to invoke this Court's
discretionary jurisdiction under Article 226 of the Constitution of
India. The Petitioner vigorously prosecuted those post grant
opposition proceedings whilst this petition remained pending for
admission. It is only when the Petitioner learnt that the technical
report of the Board who is to advise the Controller was adverse to it,
that the Petitioner has revived this petition. The proceedings before
6 Judgemnt dated 07.07.2022 in W.P.(C) IPD 11/2022
Basavraj 8/29 2939.17-wp.docx
the Controller are ripe for final hearing. Hearings were scheduled
and deferred at the Petitioner's instance citing the pendency of the
present Writ Petition.
The learned Senior Advocate submits that the Petitioner was
intimated well in advance that Respondent No.2's amendment
Application and the merits of Respondent No.2's Application for
grant would be heard together. The Petitioner communicated its
acceptance of these directions and then in volte face has attempted
to reprobate and resile from the same. The Controller granted full
opportunity of hearing on the amendment Application and upon
merits of its pre grant opposition Application. The Petitioner was
even granted liberty to file additional written statement in the main
matter. Despite having been given full and fair opportunity, the
Petitioner deliberately refused to argue on merits. The Petitioner did
not avail of the liberty granted by the Controller to file written
submissions and on its own accord confined its argument only to the
amendment Application made by Respondent No.2. In these
circumstances, the Petitioner cannot submit that the principles of
natural justice are violated. The conduct of the Petitioner dis-
entitles it from invoking this Court's jurisdiction under Article 226
of the Constitution.
Basavraj 9/29
2939.17-wp.docx
The learned Senior Advocate submits that the Petitioner
already instituted post grant opposition proceedings five months
before filing of the present Writ Petition. It has even vigorously
pursued the post grant opposition proceedings. The Petitioner could
raise all these grounds in the post grant opposition proceedings. The
fact that five months before filing of the Writ Petition the Petitioner
filed its post grant opposition proceedings, is suppressed by the
Petitioner in the present Writ Petition. The Petition deserves to be
dismissed on the ground of suppression of facts. Moreover, in a post
grant opposition proceedings, the opposition Board issued
recommendation on the present Respondent No.2's patent upholding
its validity and rejecting all the grounds of post grant opposition
proceedings on 6th November 2019. On 19th February 2020, the
Petitioner and other opponents filed interlocutory petition seeking
constitution of a new Opposition Board. On 8th July 2021, the
Controller allowed the Petitioner and other opponent's Application
constituting a new Opposition Board. On 14th June 2022, the new
Opposition Board issued fresh recommendation on Respondent
No.2's patent. On 27th June 2022, the Controller fixed final hearing
dates. It is submitted that once the post grant opposition
proceedings have proceeded further this writ now may not be
entertained. Even after losing in post grant opposition proceedings,
Basavraj 10/29 2939.17-wp.docx
the party can file an appeal under Section 11A of the Patents Act to
the High Court. It is not only the case that the Petitioner has
alternate remedy but in fact it has availed of the alternate efficacious
remedy and thereafter has filed the Writ Petition. The learned
Senior Advocate relies upon the judgment of the Apex Court in the
case of Alloys Wobben Vs. Yogesh Mehra 7. In the said case, the
Apex Court held that the person who availed of and elected the
remedy of post grant opposition proceedings under section 25(2)
was precluded by his election from availing the remedy of revocation
petition and/or counter claim under section 64. The fundamental
principle of law that the apex court laid down was that in patent
cases, objectors had to elect their choice of remedies and where they
did so, they would be held to their election. The same principle
applies here. The Petitioner's conduct of prosecuting the post grant
opposition proceedings evidences purposeful availment and active
election. The Petitioner, now, cannot abandon the post grant
opposition proceedings at the fag end. In a post grant opposition
proceedings, the Petitioner even sought and obtained the
reconstituted Opposition Board because it was unhappy with the
findings of the earlier Board. Now, to its discomfiture, the new Board
has also given findings which it does not like. If, now, these post
grant opposition proceedings are to be abandoned, the same would
7 2014 15 SCC 360
Basavraj 11/29 2939.17-wp.docx
amount to abuse of process of law which this Court would not
entertain. The judgments relied on by the Petitioner to contend that
the remedy to challenge the order in the pre grant opposition
proceedings can still be availed of with the remedy of post grant
opposition proceedings, may not apply in the present case. In the
present case, the Petitioner has already availed of the post grant
opposition proceedings and has vigorously pursued it. Five months
thereafter has filed the Writ Petition.
It is submitted that apart from the Petitioner one Jaishil
Sulphur and Chemicals (Jaishil) filed pre grant proceedings against
Respondent No.2, so also, one Vilas Shetty (Shetty). The Controller
allowed Jaishil's pre grant proceedings on 24th October 2009.
Respondent No.2 filed an appeal against the said order to IPAB. The
IPAB on 4th April 2012 dismissed the appeal of Respondent No.2.
Respondent No.2 filed Writ Petition No.7384/2012 in this court
against the order of IPAB. During pendency of the Writ Petition, the
Petitioner filed pre grant opposition proceedings on 23 rd August
2013. Eventually, the order was set aside and the matter was
remanded to the Controller. The IPAB directed the Controller to
dispose of the matter within three months. These directions were
passed in the proceedings emanating from the Jaishil's Application.
The Controller was bound to decide the objections of Shetty and
Basavraj 12/29 2939.17-wp.docx
Jaishil. He could not have decided Jaishi's and Shetty's opposition
without formally allowing the amendment. The amendment
Applications were reducing the scope of Application. The Controller,
thus, acted lawfully and within jurisdiction.
The learned Senior Advocate submits that the amendment
Applications of the Patent Act are not akin to the proceedings
seeking leave to amend filed in suit before the civil court and/or
under the CPC. The Petitioner cannot claim to have legal vested
right to have heard on the amendment Application made prior to the
grant of patent. In Patent Act, under Sections 57 to 59 the Applicant
seeking to amend can only subtract and not add. By amendment he
can only restrict his claim and not broaden them. Under section 57,
an amendment can be sought either before a patent is granted or
after the patent is granted under section 57(3). If an amendment is
sought after the grant of patent, different considerations apply. In
such a case the controller is bound to publish the Application
seeking leave to amend the Application for a patent and procedure is
prescribed under section 57(4). Further, under Section 57(1) which
provides for pre grant scenario does not envisage granting a hearing
to the opponent for an amendment Application made prior to the
grant of patent. In a pre grant scenario an opponent, thus, has no
right of hearing of an amendment Application. Under Rule 81 also
Basavraj 13/29 2939.17-wp.docx
hearing is contemplated to an opponent in a post grant scenario.
The learned Senior Counsel submits that in respect of the
present patent itself the Delhi High Court in the case of Sulphur
Mills Ltd. Vs. Dharmaraj Crop Guard Ltd. & Anr. 8, prima facie,
found that the Respondent No.2 had restricted its claim and not
broaden them. The Court also found that the amended claims were
well within the originally filed claims. In fact, the Petitioner has not
suffered any prejudice. On 26th July 2016, Respondent No.2 filed its
final amendment Application. This Application narrowed its claims
to 9 claims. This Application superseded four previous amendment
Applications. Respondent No.2 restricted its claims and did not
broaden them. On 22nd August 2016 the hearing took place in the
Petitioner's pre grant opposition Application.
At this hearing, the Petitioner claimed ignorance of
Respondent No.2's final amendment Application. The Controller
directed Respondent No.2 to serve this amendment Application and
the accompanying amended claims upon the Petitioner and the
matter was adjourned for hearing the amendment Application and
the Petitioner's pre grant opposition Application on 14 th September
2016. On 23rd August 2016, Respondent No.2 served final
amendment Application along with amended claims upon the
8 (2021) 282 DLT 658
Basavraj 14/29 2939.17-wp.docx
Petitioner. On 6th September 2016, the Controller addressed an
email to the parties. By this email, the Petitioner was reminded that
the matter had, by consent, been stood over to 14th September 2016.
The Controller, further informed the Petitioner, it would argue the
amendment Application along with main pre grant amendment
Application. The Petitioner was, thus, put to notice that it was to get
ready to argue the merits of the amendment Application. On 6th
September 2016 the Petitioner responded to the Controller and had
intimated the Controller that it had received final amendment
Application (and final claims). It communicated it's acceptance of
the Controller's joint hearing direction since it conveyed that it
would be a complete response in the matter and that it would attend
the hearing on 14th September 2016. The fact that the Petitioner
had sent this email was suppressed by it in its pleadings. Thereafter
on 7th September 2016 the Petitioner attempted a volte face to resile
from its acceptance of the Controller's decision to have a joint
meeting. In spite of having no vested legal right, the Petitioner
insisted on the amendment Application being heard, contrary to the
Controller's decision. On 8th September 2016, 17th December 2016
and 8th February 2017 the proceedings were repeatedly adjourned at
the Petitioner and its Advocate's instance and thereafter the matter
was stood over to 24th February 2017. On 24th February 2017 the
Basavraj 15/29 2939.17-wp.docx
Controller finally conducted the hearing in the petitioner's pre grant
opposition proceedings and Respondent No.2's amendment
Application. The Controller recorded the Petitioner's arguments on
the amendment Application and thereafter gave substantive and
detailed reasons rejecting the same. After recording the Petitioner's
arguments on the amendment Application in detail and substantive
reasons for rejecting the same the Controller called upon the
Petitioner to argue its pre grant opposition. The Petitioner refused
to do so. The Controller further recorded that in spite of granting
liberty to the Petitioner it had not filed written submissions for
opposing the grant of patent in Respondent No.2's favour. It was in
these circumstance that, the Controller thereafter decided the
Petitioner's pre grant opposition proceedings on its merits. The
Petitioner on its own accord chose not to argue on merits of the main
matter. The Petitioner is guilty of suppression of facts and has
weaponized the delays and to frustrate Respondent No.2's legal right
of entitlement. Its conduct dis-entitles it from invoking this Court's
jurisdiction under Article 226 of the Constitution.
The learned Senior Advocate for Respondent No.2 submits that
the Petitioner had filed Writ Petition No.2606/2017 before the Delhi
High Court for a direction restraining the Controller from proceeding
with the matter. The High Court did not grant interim relief. Same
Basavraj 16/29 2939.17-wp.docx
was filed on 10th March 2017. On 11th April 2017 the Controller
dismissed pre grant opposition filed by the opponent and granted the
patent. On 1st May 2017 the Petitioner withdrew the Writ Petition
bearing No.2606 of 2017 filed before the Delhi High Court. The Delhi
High Court dismissed the Writ Petition as withdrawn. Thereafter on
19th May 2017 the Petitioner filed post grant opposition proceedings
(Form 7) under Section 25(2) of the Patents Act.
The learned Senior Advocate submits that the matter does not
require interference of this Court. The post grant opposition
proceedings are at the final stage. The Writ Petition may not be
entertained.
4 We have considered the submissions canvassed by the learned
Senior Advocates for the parties.
5 Following dates and events placed on record by the
Respondent No.2 does not seem to be a matter of debate:
Sr. Date Event No. 1 08.01.2007 2nd Respondent filed the patent Application
No.40/MUM/2007 (being Complete Specification (Form
2) along with claims 1-15 dated 06.01.2007) for a Novel Agricultural Composition before the Controller of Patents.
2 08.01.2007 2nd Respondent filed a request for examination by filing Form No.18 bearing Request No.42/RQ-MUM/2007
Basavraj 17/29 2939.17-wp.docx
3 02.02.2007 Application published in the Patent Office under Section 11(A) of the Patents Act having Journal Issue No.05/2007.
4 17.05.2007 Patent Office issued the First Examination Report wherein 2nd Respondent was requested to comply with the requirements of the report within 12 months. 5 15.06.2007 1st Opposition u/s. 25(1) of the Patents Act is filed by Jaishil Sulfur & Chemicals Industries (Jaishil) with a request for a hearing.
Additionally, another Opposition was filed by Vilas Shetty (Shetty).
6 06.05.2008 Pursuant to the observations of the FER issued by the Patent Office, 2nd Respondent filed a response to FER along with 1st amendment Application to amend the claims via letter of Mr. C. M. Joshi dated 05.05.2008 along with Claims No.1 - 13 dated 06.01.2007.
7 06.06.2008 Reply statement filed by 2nd to the pre grant opposition filed on filed by Jaishil with amended claims dated 6th January 07.06.2008 2007.
8 09.06.2008 2nd amendment Application filed by 2 nd Respondent along with Claims No.1-11.
9 24.04.2009 Hearing held on Jaishil's pre grant opposition. 10 08.05.2009 Written note of arguments submitted by Jaisheel. 11 25.05.2009 Intermediate reply filed by 2nd Respondent in the matter of the Pre Grant Opposition filed by Jaisheel. 12 20.07.2009 2nd Respondent filed affidavit dated 17.07.2009 to overcome the objections raised by the Examiner.
3rd Amendment Application filed by 2nd Respondent along with Form 13 dated 17th July 2009 with Claims No.1 - 10.
13 20.07.2009 Final reply filed by 2nd Respondent in the matter of the pre grant opposing filed by Jaisheel.
Basavraj 18/29
2939.17-wp.docx
14 24.10.2009 The Assistant Controller allowed the Opposition and
decided not to proceed with the grant of the patent Application No.40/MUM/2007 15 23.01.2010 2nd Respondent filed an appeal before the Intellectual Property Appellate Board (IPAB) bearing No.OA/13/2011/PT/MUM challenging the Assistant Controller's Order dated 24.10.2009.
16 04.04.2012 By order No.76 of 2012, the IPAB dismissed the Appeal No.OA/13/2011/PT/MUM.
17 Writ Petition No.7384 of 2012 filed by the 2nd Respondent in this Hon'ble Court challenging the Order dated 04.04.2012 passed by the IPAB.
18 23.08.2013 Petitioner filed pre grant opposition as per Section 25(1) of the Patent Act against the Patent Application. 19 07.10.2013 Haryana Pesticides Manufacturers Association filed pre grant opposition as per section 25(1) of the Patent Act against the patent Application.
20 13.04.2016 This Hon'ble Court set aside the order dated 4 th April 2012 passed by the IPAB. The matter was remanded to the IPAB and the IPAB was directed to hear the matter afresh expeditiously on merits and in accordance with law.
21 21.04.2016 IPAB set aside the order of the Assistant Controller dated 24.10.2009 and remanded the matter back to the Patent Office.
22 05.07.2016 2nd Respondent filed reply statement to Safex's pre grant opposition.
23 05.07.2016 2nd Respondent filed 4th amendment Application to amend the claims while responding to pre grant opposition filed by the Haryana Pesticides and other opponents along with Claim Nos.1-9.
24 26.07.2016 2nd Respondent filed 5th Amendment Application to amend the claims by filling Form-13 along with claims
Basavraj 19/29 2939.17-wp.docx
1-9.
25 26.07.2016 Swati Petrochem Pvt. Ltd. filed pre grant opposition as per section 25(1) of the Patent Act against the Patent Application.
26 27.07.2016 Pre grant oppositions under Section 25(1) filed by
& Jaisheel and Shetty were heard
29.07.2016
27 28.07.2016 Petitioner filed written statement dated 26.07.2016 to
the reply statement dated 05.07.2016 of 2 nd
Respondent.
28 30.07.2016 Jailakshmi Sulphur and Chemical Industries filed pre
grant opposition as per Section 25(1) of the Patent Act against the patent Application.
29 19.08.2016 Excel Crop Care Ltd. filed pre grant opposition as per Section 25(1) of the Patent Act against the patent Application.
30 22.08.2016 Hearing took place in the matter of Petitioner's pre grant opposition. The matter was adjourned to 14 th September 2016 and the 2nd Respondent was directed to furnish the amendment Application.
31 23.08.2016 In compliance with the direction of 1 st Respondent passed on hearing held on 22nd August 2016, by his email, the 2nd Respondent forwarded the following to the Petitioner :
(i) Final Amendment Application dated 26 th July 2016 (Form 13) along with amended claims No.1-9 dated 26.07.2016.
(ii) Form 3 dated 6th January 2007, 8th January 2007 and 3rd May 2010 and 22nd June 2016 respectively along with Petitions dated 23rd June 2016 and 28th July 2016 for condoning a delay in filing Form 3.
32 06.09.2016 Email addressed by the Dy. Controller of Patents and
Basavraj 20/29
2939.17-wp.docx
Designs addressed to the Petitioner informing that, by consent, the next date of hearing was scheduled on 14th September 2016. The Petitioner was directed to argue the main opposition along with amendment Applications.
33 06.09.2016 Email addressed by Petitioner's Advocate to the Dy.
Controller of Patents and Designs informing that :
a. the Petitioner shall attend the hearing on 14.09.2016.
b. the Petitioner received pleadings;
c. the Petitioner shall file complete response. 34 07.09.2016 The Petitioner's Advocate addressed an email to the Dy. Controller of Patents and Designs contending that;
a. it was never decided that the matter would be heard and argued simultaneously on the main opposition Application and amendments thereto;
b. it was their submission that the issue of amendments in the claims be decided first;
c. the Petitioner did not receive all the amendments from the 2nd Respondent.
35 08.09.2016 Interlocutory petition filed by the Petitioner before the Controller of Patents and Designs praying that the Controller to first decide on the amendment Application filed by 2nd Respondent.
36 09.09.2016 Controller of Patents disposed of two pre grant oppositions filed by Jasihil Sulphur (Opposition No.1) and Villas Shetty (Opposition No.2). However, the final decision on patent Application was not taken as other
Basavraj 21/29 2939.17-wp.docx
oppositions were still pending hearing.
Whilst disposing these oppositions, the Controller also allowed the 2nd Respondent's final amendment. 37 14.09.2016 Since the Petitioner filed the interlocutory petition, the hearing was adjourned to 22nd December 2016.
38 10.10.2016 2nd Respondent filed reply to the Petitioner's interlocutory petition.
39 The Controller then fixed up a hearing on 22 nd December 2016, 40 17.12.2016 Petitioner's Advocate filed a request before the Controller to adjourn the hearing which was scheduled on 22nd December 2016 by at least 30 days as he was occupied with a marriage ceremony of a close relative in the family in Aligarh, Uttar Pradesh. The hearing was adjourned to 13th February 2017.
41 08.02.2017 Petitioner's Advocate again requested for an adjournment of a hearing which was scheduled on 13th February 2017 as he was unavailable due to a prescheduled family function for Advocate's daughter. 42 13.02.2017 Notice issued by the Controller of Patents and Designs adjourning the hearing to 24.02.2017.
43 24.02.2017 Hearing held before the Controller of Patents and Design.
The Petitioner's Advocate argues the amendment Application but did not address the Controller on the opposition Application.
The Controller gave an opportunity to the Petitioner to file their written submissions in 10 days.
44 28.02.2017 The Petitioner addressed a letter for issuance of notice & for hearing of the interlocutory Petition.
Basavraj 22/29
2939.17-wp.docx
45 10.03.2017 The 2nd Respondent replied to the above letter dated
28th February 2017.
46 10.03.2017 The Petitioner filed Writ Petition (C) No.2606 of 2017
in the Hon'ble Delhi High Court for a direction restraining the Controller from proceeding with the matter.
47 11.04.2017 Respondent No.1 dismissed pre grant oppositions filed by the Opponents and granted patent.
48 01.05.2017 After the grant of patent by the Controller of Patents, the Hon'ble Delhi High Court dismissed the Writ Petition (C) No.2606 of 2017 as withdrawn.
49 19.05.2017 Post grant opposition (Form 7) filed by the Petitioner under Section 25(2) of Patents Act.
50 27.10.2017 The Petitioner filed this Writ Petition.
It had filed a post grant opposition before the Patent office challenging the order dated 11 th April 2017 which is impugned in this Writ Petition .
6 It would appear that the litigation between the parties is a
chequered one. Respondent No.2 had filed the Patent Application on
8th January 2007 along with 15 claims for Novel Agricultural
Composition before the Controller of Patents. Amendment
Applications were made reducing the claims. The fifth amendment
Application superseded all the earlier amendment Applications
restricting to 9 claims. The first opposition Application was filed on
15th June 2007 by the Jaishil under Section 25(1) of the Patents
Act. Subsequently, another opposition was filed by one Mr. Shetty.
The opposition application of Jashil and Shetty came to be allowed
Basavraj 23/29 2939.17-wp.docx
on or about 24th October 2009. At that time the third amendment
Application was already filed. The order of the Assistant
Commissioner dated 24th October 2009 allowing the opposition
Application was assailed by Respondent No.2 before the IPAB. The
appeal was dismissed. Respondent No.2 filed Writ Petition bearing
No.7384 of 2012. During pendency of the said Writ Petition filed by
Respondent No.2 challenging the order of IPAB, the present
Petitioner filed opposition Application on or about 23 rd August 2013
resorting to Section 25(1) of the Patents Act. Subsequently, on 7 th
October 2013 Haryana Pesticides Manufactures Association also
filed pre grant opposition. On or about 13th April 2016, this Court set
aside the order of IPAB remitting the matter. The IPAB, in turn,
allowed the Appeal and again remanded the matter to the Assistant
Controller on or about 21 st April 2016. On 5th July 2016, Respondent
No.2 filed reply to the pre grant opposition and also the fourth
amendment Application. Subsequently, on 26 th July 2016
Respondent No.2 filed 5th amendment Application to amend the
claims by filing Form No.13 and restricting the claims to 9. On or
about the same time i.e. on 26th July 2016 one Swati Petrochem Pvt.
Ltd. filed pre grant opposition.
7 The pre grant opposition filed under Section 25(1) by Jashil
and Shetty were heard on 27 th and 29th July 2016. There were other
Basavraj 24/29 2939.17-wp.docx
pre grant oppositions filed by other companies / persons. It would
appear that there were many pre grant oppositions filed and
eventually, Respondent No.1 on 11th April 2017 dismissed the pre
grant oppositions filed by the opponents and granted Patent on 11 th
April 2017.
8 It appears from the record that the Petitioner was served with
fifth amendment Application on or about 23rd August 2016. On the
said date, Respondent No.2 forwarded to the Petitioner final
amendment Application dated 26th July 2016 (Form 13) along with
amended claims 1 to 9. The Petitioner was informed through email
by the Dy. Controller of Patents on or about 6th September 2016 that
the hearing in the matter was adjourned to 14 th September 2016 by
consent and the Petitioner was directed to argue the main opposition
along with the amendment Application. It appears that on 6th
September 2016 the Petitioner forwarded email to the effect that the
Petitioner shall attend the hearing on the scheduled date and that
the Petitioner received pleadings and would file response in the
matter. On the subsequent date i.e. 7th September 2016 another
email was sent by the Petitioner's advocate to the Dy. Collector of
Patents stating that it was never decided that the matter would be
heard and decided simultaneously on the main Application and the
amendment Application.
Basavraj 25/29
2939.17-wp.docx
9 Be that as it may, from the facts on record it would appear that
opportunity was given to the parties. The controversy raised by the
Petitioner is that it was not given opportunity to argue the pre grant
opposition and that it was made aware that the fifth amendment
Application was already allowed on 9th September 2016. On 9th
September 2016 the Controller of Patents also disposed of two pre
grant oppositions filed by one Jaishil and Shetty. However, the
patent Application was not decided finally as other oppositions were
pending hearing. Under the amendment Application Respondent
No.2 had narrowed the claims to 9 from the original 15.
10 We may have considered the submissions of the Petitioner of
not being given opportunity of hearing as contended or otherwise,
however, the facts on record would dis-entitle the Petitioner from
invoking the writ jurisdiction under Article 226 of the Constitution
of India.
11 It would appear that during pendency of the hearing on the pre
grant opposition Application the Petitioner filed Writ Petition (C)
No.2606 of 2017 before the Delhi High Court seeking restraint order
against the Controller from proceedings with the matter. The said
Writ Petition was filed on 10th March 2017. The Petitioner could not
get orders from Delhi High Court and the matter before Respondent
Basavraj 26/29 2939.17-wp.docx
No.1 proceeded further. Respondent No.1 dismissed the pre grant
opposition filed by the Petitioner and others on 11 th April 2017. In
view of that the Petitioner withdrew the Writ Petition filed in Delhi
High Court and the same was dismissed as withdrawn. On or about
19th May 2017, the Petitioner filed post grant opposition (Form 7)
purportedly under Section 25(2) of the Patents Act and the same
was prosecuted by the Petitioner. After about five months the
present Writ Petition is filed challenging the rejection of pre grant
opposition Application. Before instituting the present Writ Petition
invoking writ jurisdiction of this Court under Article 226 of the
Constitution, the Petitioner had already availed of remedy under
Section 25(2) of the Patents Act raising post grant opposition. For
five months the said proceedings are prosecuted by the Petitioner
and thereafter has filed the present Writ Petition challenging the
rejection of the pre grant opposition Application. The Petitioner has
chosen the remedy under Section 25(2) of the Patents Act.
12 The availability of the remedy under Section 25(2) of Patents
Act certainly would not be a bar to challenge the rejection of the pre
grant opposition Application by filing the present Writ Petition, as
has been observed and held in the various judgments relied upon by
the learned Senior advocate for the Petitioner viz. the judgment of
the Division Bench of Madras High Court in the case of Indian
Basavraj 27/29 2939.17-wp.docx
Network of People living with HIV/AIDS (supra), in the case of
Glochem Industries Ltd. (supra) and in the case of TATA Chemicals
Ltd. (supra).
13 As a general rule, the availability of an alternate remedy is not
a bar to invoke the writ jurisdiction of this Court under Article 226
of the Constitution, as has been conceptualized by the apex court in
the case of Whirlpool Corporation (supra). However, in the present
case, the Petitioner has already availed of the alternate remedy by
resorting to Section 25(2) by filing an Application for the post grant
opposition prosecuted the alternate remedy for five months and
thereafter has chosen to avail the present remedy under Article 226
of the Constitution.
14 We would have appreciated the present Writ Petition, had the
Petitioner approached this Court challenging the rejection of the pre
grant opposition Application before resorting to any remedy under
Section 25(2).
15 In proceedings initiated by the Petitioner under Section 25(2)
by filing post grant Application the matter is at the concluding stage.
On 6th November 2019, the Opposition Board issued
recommendations on Respondent No.2's patent upholding its
validity and rejecting all the grounds of post grant opposition.
Basavraj 28/29
2939.17-wp.docx
Thereafter on 19th February 2020 the Petitioner and other
opponents filed interlocutory petitions seeking constitution of new
opposition board. On 8th July 2021 the Controller allowed the
Petitioner and other opponent's Application and constituted new
opposition board. On 14th June 2022 the new opposition board
issued fresh recommendation on Respondent No.2's patent. The
matter is now fixed for final hearing before the Controller.
16 From the aforesaid, it would appear that the proceedings filed
by the Petitioner under Section 25(2) challenging post grant
opposition Application is at the final stage. Passing any orders in the
Writ Petition at this stage would be preempting the decision by the
Controller. Even after remedy under section 25(2), the Petitioner
still has remedy to approach this Court. The Petitioner, in all
fairness ought to have disclosed about the availing the remedy under
section 25(2) while filing the present Writ Petition.
17 In light of the aforesaid facts and circumstances, we are not
inclined to exercise our writ jurisdiction under Article 226 of the
Constitution.
18 The Writ Petition, as such, stands disposed of. No costs.
(MADHAV J. JAMDAR,J.) (S.V. GANGAPURWALA, J.) Basavraj 29/29
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!